PRE- INSTALLATION SITE CHECKLIST_ Globe Wireless Expansion

SITE DU ID: SUBCON NAME:


SITE DU NAME: RECEIVER NAME:
NLZ
PROJECT TECHNOLOGY: RECEIVER SIGNATURE:
GT FO NAME: DATE:
Note: * Checklist information must be completed during Material Receiving on site by Subcon Representative
* Information will be based on Approved TSSR vs Actual site scenario
1. PRE-REQUISITE OK NOT OK REMARKS
a. TSSR During Receiving
b. PHONE for ISDP
c. SITE SIGNED

2. TSSR SOLUTION OK NOT OK REMARKS


a. Proposed TMC LOCATION
b. Proposed BBU LOCATION
c. Proposed Tapping RECTIFIER BREAKER
d. Proposed CABLE ROUTE
e. Proposed ANTENNA LOCATION
f. Proposed RRU LOCATION
g. Proposed DCDU LOCATION
h. Proposed New AMB LOCATION
i. Other ISSUE's (pls. specify in Remarks)

3. DELIVERED CABLE LENGHT OK NOT OK REMARKS


a. JUMPER CABLE from ANT to RRU Location
b. CPRI CABLE from RRU to BBU Location
c. RRU POWER CABLE from RRU to DCDU Location
d. 16mm POWER CABLE from DCDU to RECTIFIER
e. 16mm GROUNDING CABLE from Equipment's to Busbar's
f. TRANSMISSION CABLE from BBU to IDU RADIO
g. Other's (pls. specify in Remarks)
4. MINI-CIVIL WORKS NEEDED QTY UNITS REMARKS
a. BUSBAR (6holes) pcs
b. BUSBAR (16holes) pcs
c. TOWER GROUNDING (38mm) meter
d. ARRESTER GROUNDING (38mm) meter
e. LADDER meter
f. FTP (PORT HOLE) pcs
g. AMB REFURBISHMENT Sector
h. CABLE GLAND pcs
i. CABLE STOCKING EXTENTION meter
j. LTC (Liquid Tight Conduit) meter
k. Other's (pls. specify in Remarks) meter

5. MAJOR CIVIL WORKS (if needed) QTY UNITS REMARKS


a. New Ladder Support pcs
b New Basepad lot

6. HT LACKING MATERIAL's NOT DELIVERED (Discription) QTY UNITS REMARKS


a.
b.
c.

7. OTHER's or ADDITIONAL WORKS Requested by GT FO Not in TSSR (pls specify)


a.
b.
c.