1) A kind of substation
2) Electrical equipment details of AIS substation
3) Electrical equipment details of GIS substation
4) Preliminary operation before preventive maintenance
5) Preventive maintenance operation details of AIS substation
and GIS substation
10
11
Electrical Test
- Insulation Resistance Test
Insulation resistance test of each pole
to ground by energize voltage 2500 Vdc for 1 min
with switch open, shall be exceed than 100,000 MΩ
- Contact Resistance Test
It will be made across the main contact
with switch close by energize 100 Adc, and value
compare by factory test should be very less.
- Operating Interlocking Check
When ground bar is closed, It should
not operate to close with mechanic interlocking.
12
Electrical Test
- Insulation Resistance Test
Insulation resistance test of primary
winding and secondary winding with respect to
ground at voltage 2,500 Vdc for 1 min. The value shall
be exceed more than 1,000 MΩ
- Turn Ratio Test
Verification check by voltage method,
measure a turn ratio of each phase and each tap by
energize current following nameplate (such as 1000 A
for CT, 150 A for VT) between HV and LV in every core
Then, read the ratio value from a test instrument in A.
analyze the value of turn ratio in the every core, the
different value should be very less comparing by
nameplate shall not deviate more than 0.5%
14
Electrical Test
- Winding Resistance Test
Measure a secondary winding resistance of
each phase by energize DC current ( 1 A or 5 A follows its
nameplate) between HV and ground in every core at full
tap. Receive the value of V and calculate to R from a test
instrument in Ω and analyze the value, the different value
should be very less and/or comparing by factory test
15
Electrical Test
- Insulation Resistance Test
Insulation resistance test at 5000 Vdc
between top and middle, and between middle and
case for 1 min, shall be exceed than 100,000 MΩ
- Contact Resistance Test
It will be made between the upper
fixed contact through the GCB to the lower contact
points (top to middle) with GCB close at 100 Adc,
the different value should be very less comparing by
factory test
- Operating Timing Test
Energize 125 Vdc at coil for operate
GCB to change position to close and open and catch
that time in use for compare with factory test.
16
Electrical Test
- Contact Resistance Test
It will be made between the upper fixed contact
through the CB at 100 Adc (at the terminal box), the different
value in µΩ should be very less comparing by factory test
- Operating Timing Test
Energize 125 Vdc at coil (in the terminal box) for
operate CB to change position to close and open and catch
that time in use for compare with factory test.
- Insulation Resistance Test
It test between current transformer secondary and
ground usually checked by use of megger test at 1000 Vdc (500
Vdc if required) for 1 min shall be exceed than 100,000 MΩ
- Winding Resistance Test
Test with multi-meter, measure in Ω.
- Alarm Circuit Check 18
MΩ at 10 mins
PI=
MΩ at 1 min
19
20
21
- Oil/Winding Temp.
See a winding temperature at a gauge, shall be in
the length of setting
* Normally Setting Fan : 70 C | Alarm : 95 C | Trip : 105 C
- Tr. Fan (Motor/Fan)
See fan working by simulate all functions refer by
temperature (on/off/work at high temp.), shall work by its setting 22
Visual Inspection
- Seal and Body
- Setting Relay Recording
- Cleaning
- Relay Feature (Operation) Check
- Digital Multi-meter Check
Relay in testing
27/59 – Under/Over Voltage Relay
50/51G – Instantaneous/Inverse Time Overcurrent Relay
21 – Distance Relay
87 – Differential Relay
23
Visual Inspection
- Support Structure
- Seal and Body
- Bus Bar Connection
- Cleaning
- Motor Charging (VCB)
- Terminator (Power Cable)
- Record Setting Relay (Relay)
24
Visual Inspection
- Bushing, Tank and associated device
- Oil Level Check
- Cleaning
Electrical Test
- Winding Insulation Resistance Test
Perform insulation resistance and/or
polarization index on each winding to ground.
Recommended minimum DC test voltage at 2500 Vdc
for primary and 500 Vdc for secondary.
- Oil Transformer Test
By IEC 60156 (ASTM if any) including
Dielectric Breakdown Test.
26
- Visual Inspection
- Cleaning
- Communication System Test
27
- Visual Inspection
- Cleaning
- Insulation Resistance Test (Panel)
Test for 1 min on each bus, phase to
ground and phase to phase with input/output off.
28
29
30
31
32