DNV-DSS-315
The electronic pdf version of this document found through http://www.dnv.com is the officially binding version
© Det Norske Veritas
If any person suffers loss or damage which is proved to have been caused by any negligent act or omission of Det Norske Veritas, then Det Norske Veritas shall pay compensation to
such person for his proved direct loss or damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in question, provided that
the maximum compensation shall never exceed USD 2 million.
In this provision "Det Norske Veritas" shall mean the Foundation Det Norske Veritas as well as all its subsidiaries, directors, officers, employees, agents and any other acting on behalf
of Det Norske Veritas.
Service Specification DNV-DSS-315, October 2010
Changes – Page 3
Background
The experience gained from past projects specific to onshore LNG and Gas installations is incorporated in this
Service Specification.
Introduction
The suit of inter-related DNV-OSS documents consist of a general description of the verification systematics
(DNV-OSS-300) and object specific documents. This DNV-OSS-315 offers the reader the application of the
common framework and overview of processes in risk verification, to process facilities.
This Service Specification:
— Introduces a levelled description of verification involvement during all phases of an asset's life.
— Facilitates a categorisation into risk levels High, Medium and Low, assisting in an evaluation of the risk
level.
— Assists in planning the verification through the making of a Verification Plan, and describes the DNV
documentation of the process throughout.
— Provides an international standard allowing transparent and predictable verification scope, as well as
defining terminology for verification involvement.
Changes
Two new DNV service document types have been introduced as from October 2010 to be used for services that
are not limited to offshore and/or not to be considered as DNV Rules for classification of Ships or HSLC/NSC.
The documents have been named; DNV Service Specifications (DSS) and DNV Standards (DS).
This service specification; DSS-315: “Verification of Onshore LNG and Gas Facilities” replaces the previous
version of the document with short name; DNV-OSS-315. There are no changes in content, only how the
document is referred to, as OSS now will be used for Service Specifications intended for Offshore use.
CONTENTS
A. General .......................................................................................................................................................................... 24
A 100 General principles ............................................................................................................................................... 24
B. Trigger Questions.......................................................................................................................................................... 24
B 100 Overall project objective and goals..................................................................................................................... 24
B 200 Assessment of risk .............................................................................................................................................. 24
B 300 Technical innovation........................................................................................................................................... 25
B 400 Contractors’ experience ...................................................................................................................................... 25
B 500 Quality management systems ............................................................................................................................. 25
App. B Generic Detailed Verification Scopes of Work Tables ................................................................. 26
A. Purpose.......................................................................................................................................................................... 26
A 100 Introduction......................................................................................................................................................... 26
B. Critical Elements........................................................................................................................................................... 26
B 100 Critical Elements and Components..................................................................................................................... 26
App. C Examples of Verification Documents ............................................................................................. 69
A. Verification Documents ................................................................................................................................................ 69
A 100 Validity of verification documents ..................................................................................................................... 69
A 200 Statement of Compliance ................................................................................................................................... 69
A 300 Verification Reports............................................................................................................................................ 69
A 400 Verification Comments ...................................................................................................................................... 69
A 500 Audit report......................................................................................................................................................... 69
A 600 Survey Reports.................................................................................................................................................... 70
B. Use of quality management systems ............................................................................................................................. 70
B 100 General................................................................................................................................................................ 70
B 200 Quality plans ....................................................................................................................................................... 70
B 300 Inspection and test plans ..................................................................................................................................... 71
B 400 Review of quality management programme ....................................................................................................... 71
C. Document forms............................................................................................................................................................ 71
C 100 Introduction......................................................................................................................................................... 71
C 200 Statement of Compliance.................................................................................................................................... 73
C 300 Verification comments sheet............................................................................................................................... 74
C 400 Survey report....................................................................................................................................................... 75
SECTION 1
GENERAL
A. General
A 100 Introduction
101 This Service Specification (DNV-DSS-315) gives the criteria for and guidance on verification of the
integrity (safety, environmental and reliability) of parts of onshore LNG (both import and export) and gas
receiving facilities during various phases of new developments and modifications.
102 This document is an object-specific Service Specification conforming to the philosophy defined in the
top level document DNV-OSS-300 Risk Based Verification.
A 200 Objectives
201 The objectives of this specification are to:
— describe DNV’s verification services for onshore LNG and gas receiving facilities during design,
construction, and commissioning,
— provide guidance for the Client and other parties for the selection of the level of involvement of those
carrying out verification activities, whether quantitatively as a result of a quantitative risk assessment or
qualitatively by simple trigger questions.
— provide a common platform for defining and manage the scope and extent of verification activities.
A 300 Scope of application for verification
301 This specification may be adopted for the verification of parts of onshore liquefied natural gas and gas
receiving facilities during the project development phase starting from detailed design up to and including
commissioning and start-up.
302 The LNG and gas facilities covered in this specification comprise the following critical systems:
— support structures and foundations
— non-cryogenic critical vessels, piping and equipment
— cryogenic critical vessels, piping and equipment (including transfer piping)
— LNG storage tanks
— open hazardous drains
— pressure relief systems
— ignition prevention and control systems
— emergency shutdown system
— blowdown system
— fire and gas detection system
— fire and blast protection
— emergency power supply
— escape and evacuation means
— emergency communication systems
— environmental control.
which are applied in various configurations and tailored to each particular project’s specific requirements.
The specification does not cover the following:
— Jetty, Mooring and Marine related facilities (with the exception of the shore based transfer systems and
associated safety equipment. Jetty structures are covered by DNV-OSS-304).
— the import and export pipelines within plant battery limits (this is covered under DNV-OSS-301)
303 Compliance to CE Marking Directives such as Pressure Equipment Directive (PED/97/23/EC),
Machinery Equipment Directive 98/37/EC and Explosion Proof Devices ATEX 94/9/EC which are applicable
in the European Community are not covered in this specification.
304 This DSS describes the principle of a levelled verification involvement, where the extent of verification
involvement is linked to the risks associated with part or all of the facility.
305 The primary scope of DNV’s verification work is the verification of the integrity of gas facilities and the
safety of its personnel and those in close proximity to it. Other aspects, such as the verification of the
environmental safety of the facility, or its ability to meet the Client’s business objectives, may be included in
DNV’s scope of work if desired by the Client.
306 Statutory verification (or certification) of onshore gas facilities to the requirements of National
Authorities is not included specifically in the scope of application of this DSS. Such verification (or
certification) shall be governed by the regulations of the relevant Authority. However, if detailed procedures
are not given by these Authorities, this DSS shall be used by DNV as a guideline for its work.
A 400 Structure of this document
This document consists of three sections and 3 appendices:
— Section 1 explains the relationship between this document and DNV’s overall risk-based verification
process.
— Section 2 explains the principles of DNV’s verification process with its risk-based levels of involvement,
and how the level of involvement for a particular project is defined.
— Section 3 describes the verification process and the activities for each of the project phases.
— Appendix A gives guidance on the selection of verification level, preferably as the result from a quantitative
risk assessment or alternatively, qualitatively as a result of the posing of trigger questions.
— Appendix B gives a generic detailed scope of work tables for all phases and all levels of involvement. These
tables are the basis for the development of project-specific scopes of work tables.
— Appendix C gives example verification documents and describes the documents issued during and as a
result of the verification process. The use of quality management systems is addressed here also.
Guidance note:
Risk can be evaluated based on safety, environmental impact, business, schedule, public relations, reputation or other
criteria set by the Client.
The generic scopes of work tables are generated based on safety and integrity risks. Where other risks, such as
environment or business, are required by the Client to be considered during the verification process, the principles set
out in this document may be used to modify the generic scopes of work tables given in Appendix C.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
303 In view of the complexity of many gas facilities, DNV recommends strongly that the verification level
be derived from the results of risk assessments of the facility.
Guidance note:
Only for simple natural gas facilities, with consequently lower levels of risk would DNV consider that simplified
verification planning using the trigger questions and generic Verification scope set out in Appendices A and B to be
justifiable.
For novel technology for which there are no applicable standards to verify against, Technology Qualification
according to procedures as defined in "DNV-RP-A203 Qualification Procedures for new Technology" can be used as
input for Verification.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
As s e t Pla n n e d
As s e t S p ec ific a tio n
in clu d ing o ve ra ll co m p a n y ac c ep ta n c e c rite ria ,
p e rfo rm an ce re qu ire m e nts a n d
ve rific a tio n o b je cti ve s
R is k As s e s sm e n t
in c lu din g id e ntific a tio n o f h a za rd s an d
ra n king o f h a z ard s b a se d o n risk e valu a tio n
A s s e t C o m ple te d
Figure 1
DNV risk based verification Flow-Chart
404 A Statement of Compliance is issued in all other instances where Certificate of Conformity is not
applicable. See Appendix C for further details.
418 Risk Reduction Measures: Those measures taken to reduce the risks to the operation of onshore facilities
and to the health and safety of personnel associated with it or in its vicinity by:
— reduction in the probability of failure
— mitigation of the consequences of failure.
Guidance note:
The usual order of preference of risk reduction measures is:
— inherent safety
— prevention
— detection
— control
— mitigation
— emergency response.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
419 Project Objectives: The safety, integrity and business goals for the design, construction, operation and
decommissioning of the gas facilities including acceptance criteria for the level of risk acceptable to the Client.
420 Safety Objectives: The safety goals in terms of functionality, reliability/availability and survivability for
the design, construction and operation of the natural gas facility including acceptance criteria for the level of
risk acceptable to the Client.
421 Statement of Compliance: A statement or report signed by a qualified party affirming that, at the time of
assessment, the defined onshore installation phase, or collection of activities, met the requirements stated by
the Client.
422 Verification: An examination to confirm that an activity, a product or a service is in accordance with
specified requirements.
Guidance note:
The examination shall be based on information, which can be proved true, based on facts obtained through
observation, measurement, test or other means.
It should be noted that there is a distinct difference between verification and certification.
The scope of work for verification is ultimately decided by the customer, while the scope of work for certification is
ultimately decided by DNV (or the national authorities when DNV issues certificates on their behalf).
ISO 8402: 1994 definition: Verification: Confirmation by examination and provision of objective evidence that
specified requirements have been fulfilled.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
423 Verification Plan: A plan which defines the scope of the work (sow) for verification. It includes;
verification objectives, elements to be verified, performance requirements, level of involvement by party and
type of verification activity. (ref. DNV-OSS-300 Sec.2 C)
D. References
D 100 List of Internal References
— DNV-OSS-300 Risk Based Verification, 2004, Det Norske Veritas
— DNV-OSS-301 Certification and Verification of Pipelines, 2000, Det Norske Veritas
— DNV-OSS-304 Risk Based Verification of Offshore Structures, 2006, Det Norske Veritas
— DNV-OSS-307 Verification of Process Facilities, 2004, Det Norske Veritas
— DNV-OSS-309 Verification, Certification and Classification of gas export and receiving terminals, 2009,
Det Norske Veritas
— DNV-RP-A203 Qualification Procedures for New Technology
D 200 List of External References
— A Guide to Hazard and Operability Studies, 1979, Chemical Industries Association Limited, London
— ISO 8402 Quality – Vocabulary, 1994, International Organization for Standardization, Geneva
— BS 4778 Quality Vocabulary, Part 2 Quality Concepts and Related Definitions, 1991, British Standards
Institute, London
— EN 45011 General Criteria for Certification Bodies Operating Product Certification, 1998, European
Committee for Standardization, Brussels
D 300 List of Technical Specifications
Relevant technical specifications which can be used as references are given in Appendix B.
The main standards for LNG facilities addressed in this document are:
— EN1473 Installation and equipment for liquefied natural gas - Design of Onshore Installations
— NFPA 59A Standard for Production, Storage and handling of Liquefied Natural Gas.
SECTION 2
PRINCIPLES OF RISK BASED VERIFICATION
A. Purpose of Section
A 100 Objectives
101 The objectives of this section are to provide:
— an introduction to the principles of verification the safety and integrity of onshore LNG and gas receiving
facilities
— an introduction to the principles of risk-based levels of verification activity and
— guidance on the selection of levels of verification.
B. Verification Principles
B 100 Purpose of Verification
101 Verification constitutes a systematic and independent examination of the various phases in the life of a
natural gas facility to determine whether it has sufficient integrity to meet its safety objectives.
102 Verification activities are expected to identify errors or failures or non-compliance to agreed
performance requirements in the safety and integrity-related work associated with the natural gas facility and
to contribute to reducing the risks to its operation and to the health and safety of personnel associated with it
or in its vicinity.
103 Verification is primarily focused on integrity and human safety, but business risk (cost and schedule)
may be addressed also if required by the Client.
B 200 Verification as a Complementary Activity
201 Verification shall be complementary to routine design, construction and operations activities and not a
substitute for them. Therefore, although verification will take into account the work, and the assurance of that
work, carried out by the Client and its contractors, it is possible that verification will duplicate some work that
has been carried out previously by other parties involved in the natural gas facility.
202 The verification plan shall be developed and implemented in such a way as to minimise additional work,
and cost, to maximise its effectiveness. The development of the verification plan shall depend on the findings
from the examination of quality management systems, the examination of documents and the examination of
project activities.
B 300 Risk-based Levels of Verification
301 To achieve a DNV Certificate of Conformity for a natural gas facility a verification of the activities
described by the scope of work defined within this DSS first shall take place.
302 The level of verification activity is differentiated according to the overall risk to the facility and to
individual parts of it. If the risk to the facility (or a particular part) is higher, the level of verification
involvement is higher. Conversely, if the risk to the facility (or a particular part) is lower, the level of
verification activities can be reduced, without any reduction in their effectiveness.
303 The extent of verification of gas facilities is categorised into Low, Medium and High. A summary of the
levels of involvement is given in Table 2-1.
304 It is the prerogative of the Client of the natural gas facility to decide the level of verification. The
selection should consider the factors given in Sec.2 C. The selection of the most suitable verification level may
be guided by using the information gained from a Quantitative Risk Assessment, or alternatively qualitatively
by trigger questions, as described in Appendix A. Further guidance is provided in DNV-OSS-300 Risk Based
Verification.
305 Where DNV is issuing the Certificate of Conformity for the facility, DNV will decide on the appropriate
scope and use the same type of questions to evaluate the suitability of the selected level.
306 Different levels of verification can be chosen for different phases of the natural gas facility’s design,
construction or commissioning, or even within the same phase if necessary. For example, the design of a
particular component or unit may be innovative and considered high risk whereas the construction and
installation methods are well-known and considered low risk. The converse might be true also.
307 The level of verification can be reduced or increased during a phase if the originally chosen level is
considered too rigorous or too lenient, as new information on the risks to the natural gas facility becomes
available.
308 Verification should be planned in close co-operation with the Client and each of its contractors, to
provide a scope of work that is tailor-made to the schedule of each production process or activity, i.e. to make
the verification activities, surveillance and hold points, an integrated activity and not a delaying activity.
Guidance note:
Many contractors have adequate quality control systems and quality control departments, with competent personnel
to perform, for example, inspection at pressure vessel manufacturers.
In that case, not all verification work need be done by DNV personnel. Where applicable, the various inspections may
be carried out by competent persons other than DNV personnel.
In that situation DNV’s verification activities may comprise:
— reviewing the competence of the contractor’s personnel
— auditing their working methods and their performance of that work
— reviewing the documents produced by them.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
309 Verification will direct greatest effort at those elements of the natural gas facility whose failure or
reduced performance will have the most significant impact on safety and integrity.
310 The degree of confidence placed in a certificate by its users depends on their degree of confidence in the
verification carried out. Therefore, the level of verification will be stated on the Certificate of Conformity for
the facility.
311 If more than one verification level has been used for a phase, then the lowest level will be reported on
the facility’s certificate, and the additional verification activities will be identified and described in the
verification report.
Note:
High, Medium Low Verification Involvement refers to the degree or intensity of verification involvement.
Completion schedules affect verification involvement in an indirect but important way. The effect of a tight completion
schedule is pressure on the project team to take less time to carry out the various tasks. Tight completion schedules are
more prone to run late, thus adding more pressure on the project team. Problems which have been encountered in this
situation in the past have included:
— design reviews not carried out
— incomplete welding
— non-destructive testing incomplete
— missing structural members
— commissioning incomplete.
Inc re as ing
High R isk
HIGH
Probability M EDIUM
of Failure
L OW
Low
Consequence of Failure High
Figure 1
Selection of the Required Level of Verification
D. Communications
D 100 Notification of Verification Level
101 An assessment of the required level of verification for a project should be made by the Client before
preparing tender documents for design and construction activities. The Client can then specify this level in
Invitations to Tender. This will give contractors clear guidance and reference when estimating the extent and
cost of efforts associated with verification activities.
102 The required level of verification can be assessed by the Client using this DSS. However, if the Client
requires the Contractor to carry out this assessment as part of his response to an Invitation to Tender the Client
should provide the necessary information to enable the Contractor to carry out this work. This information
should include overall safety objectives for the natural gas facility as well as particulars, such as temperatures,
pressures, contents and environmental criteria, commonly contained in a design brief.
D 200 Obligations
201 To achieve the purpose and benefits of verification the involved parties shall be mutually obliged to share
and act upon all relevant information pertaining to the verification scope.
202 The Client shall be obliged to:
— Inform DNV about the basis for selecting the level of verification and the investigations and assumptions
made in this context.
— Give DNV full access to all information concerning the verification scope for the natural gas facility and
ensure that clauses to this effect are included in contracts for parties acting on behalf of the Client and
parties providing products, processes and services covered by the verification scope. If information is
proprietary and not available, exclusion from verification shall be mutually agreed with DNV.
— Ensure that DNV is involved in the handling of deviations from specified requirements within the
verification scope.
— Act upon information provided by DNV with respect to events or circumstances that may jeopardise the
safety or integrity of the facility and/or the purpose and benefit of verification.
— Ensure that the Safety Objective established for the facility is known and pursued by parties acting on
behalf of the Client and parties providing products, processes and services covered by the verification
scope.
203 Second parties shall be obliged to:
— Perform their assigned tasks in accordance with the safety objectives established for the project.
— Provide the Client and DNV with all relevant information pertaining to the verification scope.
204 DNV will be obliged to:
— Inform the Client if, in the opinion of DNV, the basis for selecting the level of verification or the
assumptions made in this respect are found to be in error or assessed incorrectly.
— Inform the Client of events or circumstances that, in the opinion of DNV, may jeopardise the safety or
integrity of the facility and/or the purpose and benefit of verification.
— Effectively perform all verification work and adjust the level of involvement according to the actual
performance of parties providing products, processes and services covered by the verification scope.
SECTION 3
SERVICE OVERVIEW
A. General
A 100 Objectives
101 The objectives of this section are to provide:
— an overview of the verification activities
— details of DNV’s verification services for onshore LNG and Gas facilities during design, construction and
commissioning phases.
B. Service Process
B 100 General Principles
101 The description of the process of DNV’s verification of LNG and gas receiving onshore facilities is based
on distinct project phases and the recognition of key milestones.
102 Verification performed by DNV normally progresses through one or more of these project phases and
may include all or selected aspects of the project. Prior to commencement of work, the scope shall be defined
in terms of the facilities to be verified (battery limits to be specified), applicable codes and standards and
performance requirements, the agreed verification levels and phases to be covered in the Verification Plan.
103 Credit may be given in the Verification Plan, in terms of reduction in the Verification scope, for
compliance to National regulations for example EC Pressure Equipment, Machinery Directive and ATEX
Directives certified by a Notified Body. This is relevant for projects in the European Union in which the EC
Directives are applicable.
104 The risk based verification process is described in relation to the normal project phases:
Project initiation:
— conceptual design.
Project Execution:
— project Management
— detail design
— construction
— manufacturing of process facilities
— manufacturing and fabrication of process facilities components and assemblies
— site assembly and integration
— project completion (pre-commissioning)
— commissioning
— issue of as-built and as-installed documentation,
— issue of operation manuals.
B 200 Simplified verification planning
201 The steps in the simplified verification planning are as follows:
— Use trigger questions to assess the overall risk level of the project (or manageable elements thereof).
— Evaluate the risk against the relevant project acceptance criteria (often this can be directly tied to the
Client’s core values, objectives or a sub-set of these) and decide whether the general verification
involvement shall be Low, Medium or High.
— Use the example detailed scope of work tables in Appendix B to make a first draft of a Verification Plan.
— Generate the project specific Verification Plan by including a project specific engineering judgment or risk
analysis to adjust the table to suit the project.
— Perform the verification execution according to the Verification Plan, making revision to the plan if and
when necessary.
— Report the verification.
202 The trigger questions are included in Appendix A.
203 Generic scopes of work for verification are suggested at the three levels of verification:
— low (L)
— medium (M)
— high (H).
These are given in the tables in this section.
204 Project specific detailed scope of work descriptions should be made identifying all relevant activities to
be verified. Examples of the level of detail are given in Appendix B.
205 It is the tables in this Sec.3 that give the principle difference between the levels of verification
involvement. The detailed example tables in Appendix B are to be treated as examples only. They shall not be
used without a project specific confirmation of their completeness based on an assessment of the prioritised
risks.
206 The project specific scope of work definition, derived from the tables in Appendix B (or similar), shall
be part of the final DNV verification report.
B 300 Selection of level of verification
301 The selection of the level of verification for the simplified verification planning is facilitated by the
trigger questions included in Appendix A.
B 400 Codes, standards and reference documents
401 The verification process described in this DNV-DSS is not tailored to a specific technical standard, code
or reference document.
402 It is recommended to use internationally recognised codes or standards. Where combinations of
standards and external criteria are used the exact terms of reference and documents to be issued shall be agreed
at the beginning of the project and formally defined in the contract.
403 It is strongly recommended not to mix standards due to the possible differences in safety philosophies.
The use of European standards (EN) is required for compliance to EC directives.
Guidance note:
Most standards are a coherent collection of requirements for all the relevant aspects of a process system. These
aspects, e.g. load and resistance, are normally among themselves adjusted to give an overall acceptable safety level.
To pick requirements from different standards can then easily result in unpredictable (low) levels of safety and non-
uniform level of safety.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
C. Project Initiation
C 100 Verification during conceptual design
101 Verification during the conceptual and or feasibility studies of a project and in the early stages of a
project can reduce the need for verification during the design and construction phases, and can reduce costs
during the long term operation, inspection and maintenance phases.
D. Project Execution
D 100 General
101 All design, construction and commissioning aspects, relevant to an onshore LNG and Gas Facility, shall
be covered by a verification process.
102 In this specification the split in the scope of work between design and construction is made between sets
of performance requirements developed during design and a description of the steps necessary to satisfy the
specification (procedures) showing how construction verification activities will be implemented.
Guidance note:
The split between design and construction phases may vary, but it is useful to spend some time on the definition to
reduce interface problems later.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
Guidance note:
Materials may be ordered with certificates of varying degrees of independent 3rd party verification (e.g. 3.2 according
to EN 10204). This can this be integrated in the overall verification activities, so as not to duplicate work.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
Table 3-4 Scope of work for verification of manufacturing and fabrication of critical equipment
Table 3-5 Scope of work for verification of manufacturing and fabrication of non-critical components
Verification activity Level
L M H
Review of the manufacturing & fabrication process
— Review of manufacturing and fabrication management systems x x
Review of manufacturing & fabrication procedures
— Review manufacturing, fabrication and inspection procedures for confirmation of compliance
x x
with the manufacturing specification
Review of qualification process
— Review the Manufacturing Procedure Specification, (MPS), Manufacturing Procedure
Qualification Test (MPQT), if applicable x x x
— Full time attendance during MPQT, if applicable, or first day production x
Surveillance during manufacturing and fabrication activities
— Visit-based attendance during testing, to ensure, based on spot checks, that the delivered
x x
products have been produced in accordance with the manufacturing specification
— Visit-based attendance during manufacturing and fabrication to ensure, based on spot checks,
that the delivered products have been produced in accordance with the manufacturing x
specification
Review of final documentation x x x
Table 3-7 Scope of work for verification of site commissioning and start-up
Verification activity Level
L M H
Review of the commissioning process
Review of commissioning management systems x x x
Audit of the quality management system x x
Review of commissioning procedures
Spot check of commissioning procedures x x x
For critical operations (identified from the FMEA and HAZOP studies or QRA) review the method
x x
statements
Surveillance during commissioning activities
Visit-based attendance during start of each critical operation x x x
Full time attendance during each critical operation x x
Full time attendance for all commissioning operations x
Review of final documentation x x x
Table 3-8 Scope of work for verification of final testing for operation, including as-built survey and
project completion
Verification activity Level
L M H
Review of procedures
Review of the procedures for commissioning tests to ensure that the procedure adequately covers the
system in accordance with the design requirements x x x
E. Verification Documents
E 100 General
The hierarchy of verification document is given in DNV-OSS-300 Appendix C. The descriptions of the content
of these documents as well as examples of Reporting templates are given in Appendix C to this specification.
APPENDIX A
SELECTION OF VERIFICATION LEVEL
A. General
A 100 General principles
101 The selection of the level of verification depends on the risk level of each of the elements that have an
impact on the management of risks to the asset.
102 Verification shall direct greatest effort at those elements of the asset where the risk is highest and whose
failure or reduced performance will have the most significant impact on the project objective and goals, e.g.:
— safety risks
— environmental risks
— business risks.
103 Suitable selection factors include, but are not limited to, the:
— overall safety and other objectives for the asset
— risks associated with the asset and the measures taken to reduce these risks
— degree of technical innovation in the asset
— experience of the contractors
— quality management systems for the Project and its contractors.
104 Due to the diversity of various installation facilities, their contents, their degree of innovation, the
geographic location, etc, it is not possible to give precise guidelines on how to decide what level of verification
is appropriate for each particular LNG and gas receiving onshore facility.
105 Therefore, guidance is given as a series of questions that should be answered when deciding the
appropriate level of verification for an onshore gas facility. This list is not exhaustive and other questions
should be added to the list if appropriate for a particular onshore gas facility.
106 It must be emphasised that the contribution of each element should be judged qualitatively and/or
quantitatively. Wherever possible quantified risk assessment data should be used to provide a justifiable basis
for any decisions made.
107 Depending of the stage of the project, the activities may not have taken place yet in which case the
questions can also be posed in another form, i.e. “Is …. planned to be?”
B. Trigger Questions
B 100 Overall project objective and goals
a) Does the overall verification objective address the main project objectives?
b) Does the verification objective establish acceptance criteria for the level of risk acceptable to the Client?
c) Is this risk (depending on the onshore LNG and gas facility and its location) measured in terms of safety,
as well as environmental, economic and reputation consequences?
B 200 Assessment of risk
a) Has a systematic review been carried out to identify and evaluate the probabilities and consequences of
failures in the onshore gas facilities?
b) Has this review judged the contribution of each element qualitatively and or quantitatively and used, where
possible, quantified risk assessment data to provide a justifiable basis for any decisions made?
c) Does the extent of the review reflect the risk level of the (onsite and offsite) onshore gas installation, the
planned operation and previous experience with similar facilities?
d) Does this review identify the risk to the operation of the onshore gas facilities and to the health and safety
of personnel associated with it or in its vicinity?
e) Has the extent of the identified risks been reduced to a level as low as reasonably practicable by means of
one or both of:
— reduction in the probability of failure?
— mitigation of the consequences of failure?
f) Has the result of the systematic review of the risks been measured against the Client’s safety (or other)
objective?
g) Has the result of this review been used in the selection of the appropriate verification activity level?
B 300 Technical innovation
a) Has the degree of technical innovation in the onshore gas facilities been considered?
b) Has it been considered that risks to the onshore gas facilities are likely to be greater with a high degree of
technical innovation than with an onshore gas facility designed, manufactured and installed to well-known
criteria in well-known locations?
c) Have factors been considered in the selection of the appropriate verification level such as:
— Degree of difficulty in achieving technical requirements.
— Knowledge of similar onshore LNG and gas facilities
— Effect of the new onshore LNG and gas facility on the surrounding area.
B 400 Contractors’ experience
a) Has the degree of risk to the onshore LNG and gas facilities been considered where design, construction or
installation contractors are inexperienced?
b) Has the degree of risk been considered where the contractors are experienced but not in similar work?
c) Has the degree of risk been considered where the work schedule is tight?
B 500 Quality management systems
a) Have all parties involved in the onshore LNG and gas facilities implemented an adequate quality
management system to ensure that gross errors in the work are limited?
b) Do these parties include the:
— client?
— design contractor?
— construction contractors?
— installation contractor?
— operator?
c) Do the factors being considered when evaluating the adequacy of the quality management system include:
— Whether or not an ISO 9000 or equivalent certified system is in place?
— Results from external audits?
— Results from internal audits?
— Experience with contractors’ previous work?
— Project work force familiarity with the quality management system?
APPENDIX B
GENERIC DETAILED VERIFICATION SCOPES OF WORK TABLES
A. Purpose
A 100 Introduction
101 This appendix gives the format of the generic detailed scope of work tables for onshore LNG and Gas
facilities.
102 The Verification Plan shall be developed based on the tables provided in this Appendix. The Tables shall
be supplemented and updated by input from Project Risk Assessments when developing the Plan.
103 The appropriate level of verification involvement based on the principles outlined in Sec.3, is further
defined in the Verification Plan.
104 For gas facilities with aspects or components not covered in this Appendix, similar tables, with the same
degree of detail, shall be developed.
B. Critical Elements
B 100 Critical Elements and Components
101 Based on the results of the HAZID, HAZOP or other risk assessments, gas facilities are likely to have
many or most of the critical elements listed in 104 below.
102 Verification of design is broken down into consideration of these critical elements and components in
isolation but the many interactions between them must not be forgotten.
103 Typical Critical Elements for an onshore LNG and gas facilities are shown in Table B-1. These Critical
Elements shall be modified to suit a specific facility and the Project Objectives.
Table B-1 Onshore LNG and Gas facilities - Typical Critical Elements and associated components
Function Critical Elements Component
Layout Area classification
Inherent Safety
Measures Hydrocarbon Inventory/
All
Leak Source Minimisation
Ship-Shore Interface
Offloading and Loading Loading Arms and Transfer Facilities
Facilities Integrity LNG Transfer Pipelines
Jetty and Moorings
Support Structures and Foundations
Hazard
Prevention Relief Valves and Relief System
Measures Process Systems
Process Facilities Integrity
Cryogenic Pressure Vessels, Piping and Equipment
Non-Cryogenic Pressure Vessels, Piping and Equipment
LNG Storage Tanks
Dropped Object and Impact
Critical components
Protection
Bunding and Drains
Fired Heaters, Hot Surfaces and Exhaust
Control of Ignition Electrical items (explosion proof rating, electromagnetic
compatibility,
ingress protection)
Hazard
Detection and Lightning Protection, Static and Earthing
Control Smoke and Gas Detection for Site Buildings
Measures Fire and Gas Detection - External Areas
Fire and Gas Detection
Fire and Gas Detection - Machinery Enclosures
Fire and Gas Control System
Control Room Control Systems
HVAC Ventilation System, Fire Dampers pressurised enclosures
Table B-1 Onshore LNG and Gas facilities - Typical Critical Elements and associated components
Function Critical Elements Component
Fire Water Storage
Firewater Pumps
Firewater Distribution Ring main
Active Fire Fighting Systems
Firewater and Foam Supply
Hazard Gaseous Fire Fighting Systems
Mitigation Fire-fighting Vehicles
Measures Blast and Passive Fire Protection Critical components
Bunding and Drainage Closed drains, open drains, tank bunds
Blowdown & Flare System Flare, Blowdown valves, knock-out drum, relief valves
Emergency Shutdown System ESD Control System
(ESD) Emergency Shutdown Valves (ESDVs)
Personnel Protection, Breathing Apparatus
Egress and Evacuation System
Escape Routes
Emergency Muster Area
Response
Measures Emergency Lighting
Emergency Services
Emergency Power, uninterruptible power supply
Emergency Communications and Alarms
Emission and Waste Control Emission and Discharge Controls
Environmental Systems
Protection
Waste Heat Recovery Waste Heat Recovery Units
104 The following Tables P1 to P7, C1 to C4, M1, E1 to E3 and N1 provide a template of verification
activities which can be used for Verification activity planning. These give generic performance requirements
and verification activities for typical Critical Elements:
— P1 Support Structures and Foundations
— P2 Installation Layout
— P2 Non-Cryogenic Pressure Vessels and Equipment
— P4 Cryogenic Pressure Vessels and Equipment
— P5 LNG Tanks
— P6 Open Hazardous Drains
— P7 Pressure Relief Systems
— C1 Ignition Prevention and Control System
— C2 Emergency Shutdown System
— C3 Blowdown System
— C4 Fire and Gas System
— M1 Fire and Blast Protection Systems
— E1 Emergency Power System Supply
— E2 Emergency Escape and Evacuation
— E3 Emergency Communications
— N1 Environmental Protection
RELEVANT SPECIFICATIONS
- project specific documents
- Regulatory requirements
- International standards
Pressure Vessels:
— ASME VIII
— PD5500
Heat Exchangers:
— API 660 Shell and Tube Heat Exchangers for General Refinery Service
— API 661 Air Cooled Heat Exchangers for General Refinery Service
— API 662 Plate Heat Exchangers for General Refinery Service
— ASME VIII
— TEMA
Rotating Equipment:
— API 610 Centrifugal Pumps for Petroleum, Petrochemical and Natural Gas Industries
— API 611 General Purpose Steam Turbines for Petroleum, Chemical and Gas Industry Services
— API 616 Gas Turbines for the Petroleum, Chemical and Gas Service Industries
— API 617 Centrifugal Compressors for Petroleum, Chemical and Gas Service Industries
— API 618 Reciprocating Compressors for Petroleum, Chemical and Gas Service Industries
— API 672 Packaged Integrally Geared Centrifugal Air Compressors for Petroleum, Chemical and Gas Service
Industries
Tanks:
— API 620 Design and Construction of Large, welded, Low pressure storage tanks
— API 650 Welded Steel Tanks for Oil Storage
API RP 686 Recommended Practices for Machinery Installation and Installation Design
API 2510 Design and Construction of LPG Installations
Piping Systems: ASME B31.3
Relief Systems: API 14C
ASME B31 Standards of Pressure Piping
EN13480 Metallic Industrial Piping
The LNG storage tanks and recognised code or standard for the project.
shall safely contain all Adequacy of following items shall be checked:
hydrocarbons at the
maximum and minimum — Materials:
foreseeable pressures (as General for all materials: Strength, fire resistance, behaviour at cryogenic temperature if relevant,
defined for this type of durability
tanks), design
temperatures, normal and Design basis/ — Loads and load combinations for normal and abnormal loading condition: It shall be checked that
App.B – Page 44
— Loads, to be combined in accordance with applicable standards
— Reliability of analysis tools shall be documented
— Analysis simplifications shall be conservative related to actual behaviour
— Seismic analysis: Methodology, effects of soil-structure interaction (if relevant), damping, response
spectra reflecting site conditions, load combination. Check of sloshing and adequacy of freeboard.
Page 45 – App.B
Service Specification DNV-DSS-315, October 2010
Performance Document Types: Phase Verification Activity
Requirement
Specification
— Design:
— Foundation: Covered in a separate checklist.
— Wall: Access openings, closure pours between precast elements (if relevant), connection to
foundation, pre-stressing (losses, anchorages, etc), liquid/vapour tightness, embedment loads, design
for heat flux loadings due to fires, construction joints, and wall penetrations shall be checked. Walls
shall be designed for missile impact. Requirements for liquid/vapour tightness are different for
primary and secondary containments, if applicable. Buckling resistance considering pressure from the
insulation when tank is emptied/heated shall be checked.
— Roof: Composite members, liner, sufficient thickness to provide adequate buckling resistance, design
for missile impact, and thermal resistance to heat flux due to fire
— Floor: Heating system shall be designed to avoid permafrost.
— Insulation: Shall be designed to avoid permafrost and to meet boil-off requirements
— Special considerations for earthquake design: Secondary containment structure shall be designed for
1) SSE 2) SSE aft and spill, and 3) OBE
— Special considerations for steel design: The “elephant’s foot” should be checked for earthquake
loadings. When non-linear analyses methods are used to determine the ultimate strength of a structure
DET NORSKE VERITAS
App.B – Page 46
Service Specification DNV-DSS-315, October 2010
App.B – Page 47
PA/GA system shall provide a means of Telecommunications Review amplifier loading to ensure
alerting all personnel to the existence of Schematics / that the number of speakers on a
an emergency situation, provide the Diagrams Design speaker ring does not exceed the
means to communicate additional Telecommunications amount which the amplifier can drive,
information to personnel during an Specification
emergency and shall be capable of Confirm by witness test that the GA
operating without impairment for the System provides clear communication
minimum time required to escape to between the Control Room and all
muster locations and then to evacuate to PA/GA Layouts / Installation areas to alert personnel of
a place of safety after the start of a major Arrangement potential hazardous or emergency
accident. drawings conditions.
The provision and minimum alarm System architectural The PA/GA system shall be in
noise level above local ambient shall be drawings accordance with the project
in accordance with project System block Commissioning requirements. The minimum alarm
requirements. In areas with greater diagrams noise level above local ambient shall
ambient noise levels, visual alarms shall System specification meet the project requirements.
also be provided. Noise study and
Layouts
Guidance: Audible alarms should be ITPs
provided in all areas with minimum of
+6dBA above local ambient and visual
alarms in high noise areas (>85 dBA)
Confirm by review of the vendor data
pertaining to the GA system that it
will not be adversely affected by, nor
Emergency communications equipment adversely affect, the operation of
shall not be adversely affected by the nearby equipment.
operation of other devices/equipment in Design Guidance: Review of vendor
close proximity (electromagnetic technical file, EC Declarations of
compatibility). Conformity and associated technical
file for individual equipment as well
as data pertaining to the compatibility
of all nearby equipment
Confirm by review of the vendor data
Emergency communications equipment pertaining to the emergency
shall not create additional hazards Design communication system that it can be
during an emergency situation operated in situations where a
flammable gas mixture is present.
GA control systems to be protected Confirm by design review that GA
against fire, blast and credible accident Control System shall be protected by
events, by location or otherwise, such location or otherwise, such that its
Design ability to function is not impaired.
that its ability to function is not
impaired for the time taken to muster Note: Secondary method is hand held
after a major accident event. radios or fixed intercom system.
Confirm by review of the cable
specification, cable requisition,
Safety Concept
vendor data sheets and cable schedule
Cable specification that all cables associated with the PA
Cable schedule Design / GA system are fire resistant.
Cable requisition and
PA / GA cables should be located so Cable supports / racks shall offer
vendor data equal rating as a minimum to maintain
that they are protected against
accidental loads as far as possible and availability of the system.
shall be fire resistant to specifications Confirm by sample survey that the
cables installed are fire resistant and
Cable specification are protected against accidental loads
Construction
Cable certification as far as possible. Cable markings and
certification shall be verified as being
compliant.
Table N1 – Environment
HSE CRITICAL SYSTEM: ENVIRONMENT HAZARD MANAGEMENT
Environmental Control Systems Prevention Control Mitigation Emergency Environment
OBJECTIVES: To limit the emissions to the air, limit the discharge to water, limit the generation of waste and spill
prevention.
SCE LIMITS and BOUNDARY:
Complete Gas Installation or Process Plant
RELEVANT SPECIFICATIONS
Project and National Regulations
ISO 14001 (environmental management system)
Council Directive 96/61/EC (Integrated Pollution Prevention and Control)
NORSOK S-003
APPENDIX C
EXAMPLES OF VERIFICATION DOCUMENTS
A. Verification Documents
A 100 Validity of verification documents
101 Verification documents are, in principle, documents confirming that an examination has been carried out,
and are valid only at the time of issue.
A 200 Statement of Compliance
201 A Statement of Compliance can be issued on completion of each particular project phase, or natural part
thereof, and shall be based on a dedicated verification report.
202 A Statement of Compliance shall be issued as a formal statement confirming that verification of
documents and or activities, has found that the onshore gas installation, a part thereof, or a verification activity,
complies with the requirements applicable for that particular project phase.
203 The technical information on a Statement of Compliance shall contain:
— onshore gas installation description and item number, if relevant
— application (operational limitations and conditions of use) for which the onshore gas installation is intended
— codes and standards with which the onshore installation has been found to comply
— level of verification
— an appendix containing the accompanying dedicated verification report.
204 A Statement of Compliance shall be signed by the DNV Project Manager.
An example of a typical Statement of Compliance is shown at the end of this appendix.
A 300 Verification Reports
301 Verification Reports are issued to confirm that the relevant product or service has been completed in
accordance with specified requirements.
302 The report shall include information such as:
— product or service description and item number, if relevant
— application (operational limitations and conditions of use) for which the product or service is intended
— codes and standards with which the product or service has been verified against
— safety objectives and performance requirements
— clear statement of the conclusion from the verification (does it or does it not meet the specified
requirements)
— codes and standards used as reference
— documentation on which the verification report is based (documents, drawings, correspondence, including
revision numbers)
— project-specific scope of work tables
— any comments
— identification of any non-conformances.
303 The Verification Report shall always be dated and have two signatures, the originator and the DNV
internal verifier.
A 400 Verification Comments
401 Reviews of documents shall be reported using Verification Comment Sheets (often called VerComs).
These documents give details to the client of aspects of onshore installation design and construction that DNV:
— considers do not meet the specified requirements
— does not have enough information to make a decision
— offers advice based on its own experience.
402 Only in the first two instances does DNV expect a response from the Client or its contractors.
403 An example of a typical Verification Comment sheet is shown at the end of this appendix.
A 500 Audit report
501 Audit reports are issued to confirm that a company’s quality management system has been reviewed to
confirm compliance (or not) with the nominated standard and project requirements. In addition, the audit
reports confirm compliance with the documented procedures and that these procedures are effective.
502 Audit reports shall contain information such as whether:
602 A survey report shall contain enough information to identify clearly the product or service that has been
examined, the operating conditions or specifications to which it has been examined and the conclusion reached
by DNV.
603 The survey report shall be printed on the relevant form and shall contain as much information as possible
in accordance with the standard headings in the form. In addition, the report number shall be shown.
604 An example of a typical Survey Report is shown at the end of this appendix.
C. Document forms
C 100 Introduction
101 The end of this appendix includes example forms for use by DNV in verification.
Folder:
Cert. No.:
SURVEY REPORT
Client :
Order/Project. No. :
Item Description :
Survey Location :
Date: :
SURVEY SCOPE
SUPPORTING DOCUMENTS
Specifications:
Drawings:
VERIFICATION COMMENTS
NON-CONFORMITIES
Report Ends
Name:
Title:
Date:
If any person suffers loss or damage which is proved to have been caused by any negli
gent act or omission of Det Norske Veritas, then Det Norske Veritas shall pay compensation to such person for his proved direct loss or
damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in quest ion, provided that the maximum compensation shall never exceed USD 2 million.
In this provision "Det Norske Veritas" shall mean the Foundation Det Norske Veritas as well as all its subsidiaries, directors, officers, employees, agents and any other actingn obehalf of Det Norske Veritas.
DET NORSKE VERITAS AS, Veritasveien 1, NO-1322 Høvik, Norway, Telephone: +47 67 57 99 00, Telefax: +47 67 57 99 11, Org.No. NO
945 748 931 MVA
Form No.: 40.91a Issue: January 2008 Page 1 of 1