RESUMEN DE METRADOS DE CERCO PERIMETRICO

: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO


Proyecto - JUNIN"

Entidad : CHAUPIS Región : Junin

Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro

ITEM DESCRIPCION UND METRADO TOTAL


1.00 CERCO PERIMETRICO Y ENTRADA PRINCIPAL
1.01 MOVIMIENTO DE TIERRA
01.01.01 EXCAVACION PARA CIMIENTOS EN TERRENO NORMAL, HASTA m3 20.86 20.86
01.01.02 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL m3 21.76 21.76
01.01.03 ACARREO DE MATERIAL EXCEDENTE HASTA UNA DISTANCIA P m3 53.28 53.28
1.02 OBRAS DE CONCRETO SIMPLE
01.02.01 SOLADO DE CONCRETO F´c = 140 Kg/cm2, e=4", PARA ZAPATAS m2 21.76 21.76
01.02.02 CONCRETO PARA CIMIENTOS CORRIDOS C:H 1:10 + 30% P.G m3 20.86 20.86
01.02.03 CONCRETO PARA SOBRECIMIENTOS C:H 1:10 + 30% P.G. 1:8 + 2 m3 4.48 4.48
1.03 OBRAS DE CONCRETO ARMADO
01.03.01 ZAPATAS
01.03.01.01 ZAPATAS CONCRETO F´C = 210 Kg/cm2 m3 15.23 15.23
01.03.01.02 ZAPATAS, ACERO DE REFUERZO FY = 4,200 Kc/cm, GRADO 60 kg 240.33 240.33
01.03.02 COLUMNAS
01.03.02.01 COLUMNAS, CONCRETO F´C = 210 Kg/cm2 m3 5.95 5.95
01.03.02.02 COLUMNAS ENCOFRADO Y DESENCOFRADO m2 95.20 95.20
01.03.02.03 COLUMNAS, ACERO DE REFUERZO FY = 4,200 Kg/cm2, GRADO kg 1,004.66 1,004.66
01.03.03 VIGAS
01.03.03.01 VIGAS, CONCRETO F´C = 210 Kg/cm2 m3 5.32 5.32
01.03.03.02 VIGAS ENCOFRADO Y DESENCOFRADO m2 456.77 456.77
01.03.03.03 VIGAS, ACERO DE REFUERZO FY = 4,200 Kg/cm2, GRADO 60 kg 403.83 403.83
1.04 MUROS Y TABIQUERIA DE ALBAÑILERIA
1.04.01 MUROS DE ALBAÑILERIA
01.04.01.01 MURO DE SOGA LADRILLO KK 24X14X9CM ACABADO TAR m2 227.92 227.92
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro
DIMENSIONES METRADO
CODIGO DESCRIPCION UNID CANT VECES
LARGO ANCHO ALTO PARCIAL TOTAL
1.00 CERCO PERIMETRICO
1.01 MOVIMIENTO DE TIERRA
01.01.01 EXCAVACION PARA CIMIENTOS EN TERRENO NOR m3 20.86
TRAMO EJE A-A
EJE 1-2 1.00 1.00 3.36 0.50 0.40 0.67
EJE 2-3 1.00 1.00 3.36 0.50 0.40 0.67
EJE 3-4 1.00 1.00 3.36 0.50 0.40 0.67
EJE 4-5 1.00 1.00 3.36 0.50 0.40 0.67
EJE 5-6 1.00 1.00 0.35 0.50 0.40 0.07
EJE 6-7 1.00 1.00 3.36 0.50 0.40 0.67
EJE 7-8 1.00 1.00 3.36 0.50 0.40 0.67
EJE 8-9 1.00 1.00 3.36 0.50 0.40 0.67
EJE 9-10 1.00 1.00 3.36 0.50 0.40 0.67
TRAMO EJE J-J
EJE 1-2 1.00 1.00 3.36 0.50 0.40 0.67
EJE 2-3 1.00 1.00 3.36 0.50 0.40 0.67
EJE 3-4 1.00 1.00 3.36 0.50 0.40 0.67
EJE 4-5 1.00 1.00 3.36 0.50 0.40 0.67
EJE 5-6 1.00 1.00 0.35 0.50 0.40 0.07
EJE 6-7 1.00 1.00 3.36 0.50 0.40 0.67
EJE 7-8 1.00 1.00 3.36 0.50 0.40 0.67
EJE 8-9 1.00 1.00 3.36 0.50 0.40 0.67
EJE 9-10 1.00 1.00 3.36 0.50 0.40 0.67

TRAMO EJE 1-1


EJE A-B 1.00 1.00 3.11 0.50 0.40 0.62
EJE B-C 1.00 1.00 3.11 0.50 0.40 0.62
EJE C-D 1.00 1.00 3.11 0.50 0.40 0.62
EJE D-E 1.00 1.00 3.11 0.50 0.40 0.62
EJE E-F 1.00 1.00 0.35 0.50 0.40 0.07
EJE F-G 1.00 1.00 3.11 0.50 0.40 0.62
EJE G-H 1.00 1.00 3.11 0.50 0.40 0.62
EJE H-I 1.00 1.00 3.11 0.50 0.40 0.62
EJE I-J 1.00 1.00 3.11 0.50 0.40 0.62
TRAMO EJE 10-10
EJE A-B 1.00 1.00 3.57 0.50 0.40 0.71
EJE B-C 1.00 1.00 3.57 0.50 0.40 0.71
EJE C-D 1.00 1.00 3.57 0.50 0.40 0.71
EJE D-G 1.00 1.00 3.57 0.50 0.40 0.71
EJE G-H 1.00 1.00 3.57 0.50 0.40 0.71
EJE H-I 1.00 1.00 3.57 0.50 0.40 0.71
EJE I-J 1.00 1.00 3.57 0.50 0.40 0.71

01.01.02 EXCAVACION PARA ZAPATAS EN TERRENO NORM m3 21.76


ZAPATA 1
TRAMI EJE A-A
ENTRE EL EJE 1 - 10 10.00 1.00 0.80 0.80 1.00 6.40
TRAMI EJE J-J
ENTRE EL EJE 1 - 10 10.00 1.00 0.80 0.80 1.00 6.40
TRAMI EJE 1 - 1
ENTRE EL EJE A -J 8.00 1.00 0.80 0.80 1.00 5.12
TRAMI EJE 10 - 10
ENTRE EL EJE A -J 6.00 1.00 0.80 0.80 1.00 3.84

01.01.03 ACARREO DE MATERIAL EXCEDENTE HASTA UNA m3 53.28


Material de Cimiento 1.00 1.00 Volumen 20.86 1.25 26.08
Material de Zapatas 1.00 1.00 Volumen 21.76 1.25 27.20

1.02 OBRAS DE CONCRETO SIMPLE


01.02.01 SOLADO DE CONCRETO F'c=140 Kg/cm2, e=4'', PA m2 21.76
Zapata 1 34.00 1.00 0.80 0.80 21.76
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro
DIMENSIONES METRADO
CODIGO DESCRIPCION UNID CANT VECES
LARGO ANCHO ALTO PARCIAL TOTAL
01.02.02 CONCRETO PARA CIMIENTOS CORRIDOS C:H 1:10 m3 20.86
TRAMO EJE A-A
EJE 1-2 1.00 1.00 3.36 0.50 0.40 0.67
EJE 2-3 1.00 1.00 3.36 0.50 0.40 0.67
EJE 3-4 1.00 1.00 3.36 0.50 0.40 0.67
EJE 4-5 1.00 1.00 3.36 0.50 0.40 0.67
EJE 5-6 1.00 1.00 0.35 0.50 0.40 0.07
EJE 6-7 1.00 1.00 3.36 0.50 0.40 0.67
EJE 7-8 1.00 1.00 3.36 0.50 0.40 0.67
EJE 8-9 1.00 1.00 3.36 0.50 0.40 0.67
EJE 9-10 1.00 1.00 3.36 0.50 0.40 0.67
TRAMO EJE J-J
EJE 1-2 1.00 1.00 3.36 0.50 0.40 0.67
EJE 2-3 1.00 1.00 3.36 0.50 0.40 0.67
EJE 3-4 1.00 1.00 3.36 0.50 0.40 0.67
EJE 4-5 1.00 1.00 3.36 0.50 0.40 0.67
EJE 5-6 1.00 1.00 0.35 0.50 0.40 0.07
EJE 6-7 1.00 1.00 3.36 0.50 0.40 0.67
EJE 7-8 1.00 1.00 3.36 0.50 0.40 0.67
EJE 8-9 1.00 1.00 3.36 0.50 0.40 0.67
EJE 9-10 1.00 1.00 3.36 0.50 0.40 0.67
TRAMO EJE 1-1
EJE A-B 1.00 1.00 3.11 0.50 0.40 0.62
EJE B-C 1.00 1.00 3.11 0.50 0.40 0.62
EJE C-D 1.00 1.00 3.11 0.50 0.40 0.62
EJE D-E 1.00 1.00 3.11 0.50 0.40 0.62
EJE E-F 1.00 1.00 0.35 0.50 0.40 0.07
EJE F-G 1.00 1.00 3.11 0.50 0.40 0.62
EJE G-H 1.00 1.00 3.11 0.50 0.40 0.62
EJE H-I 1.00 1.00 3.11 0.50 0.40 0.62
EJE I-J 1.00 1.00 3.11 0.50 0.40 0.62
TRAMO EJE 10-10
EJE A-B 1.00 1.00 3.57 0.50 0.40 0.71
EJE B-C 1.00 1.00 3.57 0.50 0.40 0.71
EJE C-D 1.00 1.00 3.57 0.50 0.40 0.71
EJE D-G 1.00 1.00 3.57 0.50 0.40 0.71
EJE G-H 1.00 1.00 3.57 0.50 0.40 0.71
EJE H-I 1.00 1.00 3.57 0.50 0.40 0.71
EJE I-J 1.00 1.00 3.57 0.50 0.40 0.71

01.02.03 CONCRETO PARA SOBRECIMIENTOS C:H 1:10 + 30%m3 4.48


TRAMO EJE A-A
EJE 1-2 1.00 1.00 3.36 0.15 0.30 0.15
EJE 2-3 1.00 1.00 3.36 0.15 0.30 0.15
EJE 3-4 1.00 1.00 3.36 0.15 0.30 0.15
EJE 4-5 1.00 1.00 3.36 0.15 0.30 0.15
EJE 6-7 1.00 1.00 3.36 0.15 0.30 0.15
EJE 7-8 1.00 1.00 3.36 0.15 0.30 0.15
EJE 8-9 1.00 1.00 3.36 0.15 0.30 0.15
EJE 9-10 1.00 1.00 3.36 0.15 0.30 0.15
TRAMO EJE J-J
EJE 1-2 1.00 1.00 3.36 0.15 0.30 0.15
EJE 2-3 1.00 1.00 3.36 0.15 0.30 0.15
EJE 3-4 1.00 1.00 3.36 0.15 0.30 0.15
EJE 4-5 1.00 1.00 3.36 0.15 0.30 0.15
EJE 6-7 1.00 1.00 3.36 0.15 0.30 0.15
EJE 7-8 1.00 1.00 3.36 0.15 0.30 0.15
EJE 8-9 1.00 1.00 3.36 0.15 0.30 0.15
EJE 9-10 1.00 1.00 3.36 0.15 0.30 0.15
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro
DIMENSIONES METRADO
CODIGO DESCRIPCION UNID CANT VECES
LARGO ANCHO ALTO PARCIAL TOTAL
TRAMO EJE 1-1
EJE A-B 1.00 1.00 3.11 0.15 0.30 0.14
EJE B-C 1.00 1.00 3.11 0.15 0.30 0.14
EJE C-D 1.00 1.00 3.11 0.15 0.30 0.14
EJE D-E 1.00 1.00 3.11 0.15 0.30 0.14
EJE F-G 1.00 1.00 3.11 0.15 0.30 0.14
EJE G-H 1.00 1.00 3.11 0.15 0.30 0.14
EJE H-I 1.00 1.00 3.11 0.15 0.30 0.14
EJE I-J 1.00 1.00 3.11 0.15 0.30 0.14
TRAMO EJE 10-10
EJE A-B 1.00 1.00 3.57 0.15 0.30 0.16
EJE C-D 1.00 1.00 3.57 0.15 0.30 0.16
EJE D-G 1.00 1.00 3.57 0.15 0.30 0.16
EJE G-H 1.00 1.00 3.57 0.15 0.30 0.16
EJE H-I 1.00 1.00 3.57 0.15 0.30 0.16
EJE I-J 1.00 1.00 3.57 0.15 0.30 0.16

1.03 OBRAS DE CONCRETO ARMADO


01.03.01 ZAPATAS
01.03.01.01 ZAPATAS CONCRETO F'C=210 KG/CM2. m3 15.23
Zapata 1 34.00 1.00 0.80 0.80 0.70 15.23

01.03.01.02 ZAPATAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRADO kg 240.33


VER CUADRO DE METRADOS 1.00 1.00 240.33 240.33

01.03.02 COLUMNAS
01.03.02.01 COLUMNAS CONCRETO F'C=210 KG/CM2. m3 5.95
TRAMO 01, 02 Y 03
C-1 34.00 1.00 0.25 0.25 2.80 5.95

01.03.02.02 COLUMNAS ENCOFRADO Y DESENCOFRADO m2 95.20


TRAMO 01
C-1 34.00 1.00 PERIM. 1.00 2.80 95.20

01.03.02.03 COLUMNAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRA kg 1004.66


VER CUADRO DE METRADOS 1.00 1.00 1004.66 1004.66

01.03.03 VIGAS
01.03.03.01 VIGAS CONCRETO F'C=210 KG/CM2 M3 5.32
TRAMO EJE A-A
EJE 1-2 1.00 1.00 3.36 0.25 0.20 0.17
EJE 2-3 1.00 1.00 3.36 0.25 0.20 0.17
EJE 3-4 1.00 1.00 3.36 0.25 0.20 0.17
EJE 4-5 1.00 1.00 3.36 0.25 0.20 0.17
EJE 5-6 1.00 1.00 0.35 0.25 0.20 0.02
EJE 6-7 1.00 1.00 3.36 0.25 0.20 0.17
EJE 7-8 1.00 1.00 3.36 0.25 0.20 0.17
EJE 8-9 1.00 1.00 3.36 0.25 0.20 0.17
EJE 9-10 1.00 1.00 3.36 0.25 0.20 0.17
TRAMO EJE J-J
EJE 1-2 1.00 1.00 3.36 0.25 0.20 0.17
EJE 2-3 1.00 1.00 3.36 0.25 0.20 0.17
EJE 3-4 1.00 1.00 3.36 0.25 0.20 0.17
EJE 4-5 1.00 1.00 3.36 0.25 0.20 0.17
EJE 5-6 1.00 1.00 0.35 0.25 0.20 0.02
EJE 6-7 1.00 1.00 3.36 0.25 0.20 0.17
EJE 7-8 1.00 1.00 3.36 0.25 0.20 0.17
EJE 8-9 1.00 1.00 3.36 0.25 0.20 0.17
EJE 9-10 1.00 1.00 3.36 0.25 0.20 0.17

TRAMO EJE 1-1


EJE A-B 1.00 1.00 3.11 0.25 0.20 0.16
EJE B-C 1.00 1.00 3.11 0.25 0.20 0.16
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro
DIMENSIONES METRADO
CODIGO DESCRIPCION UNID CANT VECES
LARGO ANCHO ALTO PARCIAL TOTAL
EJE C-D 1.00 1.00 3.11 0.25 0.20 0.16
EJE D-E 1.00 1.00 3.11 0.25 0.20 0.16
EJE E-F 1.00 1.00 0.35 0.25 0.20 0.02
EJE F-G 1.00 1.00 3.11 0.25 0.20 0.16
EJE G-H 1.00 1.00 3.11 0.25 0.20 0.16
EJE H-I 1.00 1.00 3.11 0.25 0.20 0.16
EJE I-J 1.00 1.00 3.11 0.25 0.20 0.16
TRAMO EJE 10-10
EJE A-B 1.00 1.00 3.57 0.25 0.20 0.18
EJE B-C 1.00 1.00 3.57 0.25 0.20 0.18
EJE C-D 1.00 1.00 3.57 0.25 0.20 0.18
EJE D-G 1.00 1.00 3.57 0.25 0.20 0.18
EJE G-H 1.00 1.00 3.57 0.25 0.20 0.18
EJE H-I 1.00 1.00 3.57 0.25 0.20 0.18
EJE I-J 1.00 1.00 3.57 0.25 0.20 0.18

01.03.03.02 VIGAS ENCOFRADO Y DESENCOFRADO M2 456.77


TRAMO EJE A-A
EJE 1-2 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 2-3 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 3-4 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 4-5 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 5-6 2.00 1.00 0.35 0.20 0.14
1.00 1.00 0.35 0.10 0.04
EJE 6-7 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 7-8 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 8-9 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 9-10 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
TRAMO EJE J-J
EJE 1-2 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 2-3 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 3-4 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 4-5 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 5-6 2.00 1.00 0.35 0.20 0.14
1.00 1.00 0.35 0.10 0.04
EJE 6-7 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 7-8 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 8-9 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
EJE 9-10 2.00 1.00 3.36 0.20 1.35
1.00 1.00 3.36 0.10 0.34
TRAMO EJE 1-1
EJE A-B 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE B-C 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO Distrito : Rio Negro
DIMENSIONES METRADO
CODIGO DESCRIPCION UNID CANT VECES
LARGO ANCHO ALTO PARCIAL TOTAL
EJE C-D 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE D-E 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE E-F 2.00 1.00 0.35 0.20 0.14
1.00 1.00 0.35 0.10 0.04
EJE F-G 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE G-H 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE H-I 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
EJE I-J 2.00 1.00 3.11 0.20 1.25
1.00 1.00 3.11 0.10 0.31
TRAMO EJE 10-10
EJE A-B 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE B-C 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE C-D 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE D-G 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE G-H 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE H-I 2.00 1.00 3.57 0.20 1.43
1.00 1.00 3.57 0.10 0.36
EJE I-J 2.00 1.00 3.57 0.20 1.43
2.00 1.00 3.57 0.10 0.71

01.03.03.03 VIGAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRADO 60 KG 403.83


VER CUADRO DE METRADOS 1.00 1.00 403.83 403.83
HOJA DE METRADOS
Proyecto
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"

Entidad : CHAUPIS Región : Junin


: ING. JESUS POL VICENTE LOPEZ CIP N°:
Responsable Provincia : Satipo
214954
Componente : CERCO PERIMETRICO Distrito : Rio Negro

CODIGO DESCRIPCION UND CANT VECES DIMENSIONES METRADO


LARGO ANCHO ALTO PARCIAL TOTAL
1.04 MUROS Y TABIQUERIA DE ALBAÑILERIA
01.04.01 MUROS Y TABIQUES DE ALBAÑILERIA
01.04.01.01 MURO DE SOGA LADRILLO KK 24X14X9CM A m2 227.92
TRAMO EJE A-A
EJE 1-2 1.00 1.00 2.99 2.50 7.48
EJE 2-3 1.00 1.00 3.11 2.50 7.78
EJE 3-4 1.00 1.00 3.11 2.50 7.78
EJE 4-5 1.00 1.00 2.99 2.50 7.48
EJE 6-7 1.00 1.00 2.99 2.50 7.48
EJE 7-8 1.00 1.00 3.11 2.50 7.78
EJE 8-9 1.00 1.00 3.11 2.50 7.78
EJE 9-10 1.00 1.00 2.99 2.50 7.48
TRAMO EJE J-J
EJE 1-2 1.00 1.00 2.99 2.50 7.48
EJE 2-3 1.00 1.00 3.11 2.50 7.78
EJE 3-4 1.00 1.00 3.11 2.50 7.78
EJE 4-5 1.00 1.00 2.99 2.50 7.48
EJE 6-7 1.00 1.00 2.99 2.50 7.48
EJE 7-8 1.00 1.00 3.11 2.50 7.78
EJE 8-9 1.00 1.00 3.11 2.50 7.78
EJE 9-10 1.00 1.00 2.99 2.50 7.48

TRAMO EJE 1-1


EJE A-B 1.00 1.00 2.74 2.50 6.85
EJE B-C 1.00 1.00 2.86 2.50 7.16
EJE C-D 1.00 1.00 2.86 2.50 7.16
EJE D-E 1.00 1.00 2.74 2.50 6.85
EJE F-G 1.00 1.00 2.74 2.50 6.85
EJE G-H 1.00 1.00 2.86 2.50 7.16
EJE H-I 1.00 1.00 2.86 2.50 7.16
EJE I-J 1.00 1.00 2.74 2.50 6.85
TRAMO EJE 10-10
EJE A-B 1.00 1.00 3.32 2.50 8.30
EJE C-D 1.00 1.00 3.32 2.50 8.30
EJE D-G 1.00 1.00 3.32 2.50 8.30
EJE G-H 1.00 1.00 3.32 2.50 8.30
EJE H-I 1.00 1.00 3.32 2.50 8.30
EJE I-J 1.00 1.00 3.32 2.50 8.30
HOJA DE METRADOS
: "CONSTRUCCION DEL CERCO PERIMETRICO, DISTRITO DE RIO NEGRO, PROVINCIA DE SATIPO - JUNIN"
Proyecto

Entidad : CHAUPIS Región : Junin


Responsable : ING. JESUS POL VICENTE LOPEZ CIP N°: 214954 Provincia : Satipo
Componente : CERCO PERIMETRICO - ACERO Distrito : Rio Negro
DISEÑO DE N° DE LONG. DEL LONGITUD POR Ø EN M.L.
PARTIDA DESCRIPCION Ø CANTIDAD
FIERRO ELEMENTOS ELEMENTO 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm
01.03.01.02 ZAPATAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRADO 60

Zapata 1 Ø 1/2" 34 10 0.66 224.40

Diametro 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm


peso en kilos por M.L: 0.25 0.58 1.02 1.6 2.26 4.04 0.4
Long. Total por Ø en ML. 0.00 0 224.4 0 0 0 0
Unidades de Varilla de 9 ml 0.00 0.00 24.93 0.00 0.00 0.00 0.00
Total Kilos por Ø 0.00 0.00 228.89 0.00 0.00 0.00 0.00
Total Kilos 240.33

DISEÑO DE N° DE LONG. DEL LONGITUD POR Ø EN M.L.


PARTIDA DESCRIPCION Ø CANTIDAD
FIERRO ELEMENTOS ELEMENTO 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm
01.03.02.03 COLUMNAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRADO 60

TRAMO 1, 2, 3, 4 C-1 Ø 1/2" 34 4 4 544.00


estribos Ø 3/8" 30 22 1.05 693

Diametro 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm


peso en kilos por M.L: 0.25 0.58 1.02 1.6 2.26 4.04 0.4
Long. Total por Ø en ML. 0.00 693 544 0 0 0 0
Unidades de Varilla de 9 ml 0.00 77.00 60.44 0.00 0.00 0.00 0.00
Total Kilos por Ø 0.00 401.94 554.88 0.00 0.00 0.00 0.00
Total Kilos 1,004.66

DISEÑO DE N° DE LONG. DEL LONGITUD POR Ø EN M.L.


PARTIDA DESCRIPCION Ø CANTIDAD
FIERRO ELEMENTOS ELEMENTO 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm
01.03.03.03 VIGAS, ACERO DE REFUERZO FY=4,200KG/CM2, GRADO 60
TRAMO EJE A-A
EJE 1 -10 Ø 3/8" 8 4 3.1125 99.60
estribos Ø 1/4" 8 22 0.95 167.20
TRAMO J-J
EJE 1 -10 Ø 3/8" 8 4 3.1125 99.60
estribos Ø 1/4" 8 22 0.95 167.2
TRAMO EJE 1-1
EJE A - J Ø 3/8" 8 4 2.8625 91.60
estribos Ø 1/4" 8 22 0.95 167.20
TRAMO EJE 10-10
EJE A - J Ø 3/8" 7 4 3.3225 93.03
estribos Ø 1/4" 7 22 0.95 146.3

Diametro 1/4" 3/8" 1/2" 5/8" 3/4" 1" 8mm


peso en kilos por M.L: 0.25 0.58 1.02 1.6 2.26 4.04 0.4
Long. Total por Ø en ML. 647.90 383.83 0 0 0 0 0
Unidades de Varilla de 9 ml 71.99 42.65 0.00 0.00 0.00 0.00 0.00
Total Kilos por Ø 161.98 222.62 0.00 0.00 0.00 0.00 0.00
Total Kilos 403.83