QAQC DOCUMENT
DOCUMENT NO.
8 Pages
KLD-I-PRC-0010
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 2 of 8
REVISION TABLE
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 3 of 8
REVISION NOTE
Implementasion
Rev Section Pages Comment Description
(Y/N)
KLD FIELD DEVELOPMENT PROJECT
BID PACKAGE NO. S34H18002A
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 4 of 8
DAFTAR ISI
1. INTRODUCTION ................................................................................................................ 5
1.1 General ............................................................................................................................ 5
2. DEFNITIONS ....................................................................................................................... 6
3. OBJECTIVES...................................................................................................................... 7
4. ABBREVITIONS ................................................................................................................. 7
5. LEGEND OF INSPECTION LEVEL ................................................................................ 7
6. NOTES ................................................................................................................................. 8
7. ITP TABLE .......................................................................................................................... 8
KLD FIELD DEVELOPMENT PROJECT
BID PACKAGE NO. S34H18002A
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 5 of 8
1. INTRODUCTION
1.1 General
Company has undertaken Front End Engineering Design (FEED) for new KLD Field
Development Project in the COMPANY’s operated Offshore North Wes Java (“ONWJ”) Block.
KLD Field Development facilities are required to sustain oil and gas production of
COMPANY.
KLD Field Development Project will be consisted of new KLD NUI Platform, subsea pipline,
and brownfield modification at KLB and KLA Plaform.
KLD NUI platform will be located at approximately 3,5 km east of existing KLB Platform, 2,9
km northwest of existing KLA Platform, please refer to below figure:
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 6 of 8
Doble-stringed well are wells consist of “S” string and “L” string where “S” string for well gas
sources and “L” string for well oil sources.
From 3 (three) wells that will be installed at this stage, only KLD_WH-003 will be utilized as
gas lift well.
1.2
The KLD NUI Platform will be connected to existing KLB Platform through 10” dia subsea
pipeline that will be installed with approximate 3.5 km length.
The Brownfield Modification shall cover
2. DEFNITIONS
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 7 of 8
May/ Can Verbal form used to indicate a course of action permissible within the
limit of the specification.
3. OBJECTIVES
This document showing the sample the Inspection and Test Offshore Pipeline Installation
activities to be perfomed throught out the project execution in accordance with PHEONWJ
project specification, standard & code.
4. ABBREVITIONS
Following abbreviations have been used where applicable throughout this document.
All other abbreviations will in the first occurrence include a full description.
Abb. Description
PHE ONWJ PERTAMINA Hulu Energy – Offshore North West Java
ITP Inspection and Test Plan
MPS Manufacturing Procedure Specification
PQT Pre-Production Quality Testing
QA Quality Assurance
QC Quality Control
TBA To be Advised
Date : 17/07/2018
DOCUMENT NO
Rev. A ITP for Offshore Pipeline Installation
KLD-I-PRC-0010 Page 8 of 8
(d) “V” means the Verification being performed by the responsible parties as indicated in
the attached ITP.
(e) “SW” means the Spot Witness being undertaken by the responsible parties as
indicated in the attached ITP.
(f) “W” means a Witness Point.
“Witness Point” is defined as critical steps in the installation and testing process, in
respect of which the Contractor is obligated to agree a time with the Company in
advance of the operation so that it may be witnessed by Company’s authorized
representatives and, where indicated in the Procedure, by representatives from PJIT
and/or MIGAS. If the Company advises the Contractor that the indicated witnesses
cannot attend, then the Contractor may proceed the witness point.
(g) “H” means a Hold Point.
Hold Points” is defined as critical steps in the installation and testing process, in
respect of which the Contractor is obligated to advise the Company by an agreed time
period in advance of the operation so that it may be witnessed by the Company’s
authorized representatives, and, where applicable, by PJIT and/or MIGAS
representatives. The Contractor may not proceed the such operation with the hold
point without it being witnessed by the requisite representative(s), except by prior
written agreement from the Company
6. NOTES
7. ITP TABLE