Anda di halaman 1dari 8

July/August 1996

INDEPENDENT

ENERGY
T H E P O W E R I N D U S T R Y ’S B U S IN E S S M A G A Z IN E

A PennWell Publication
1996-07 Power Shift by
Mr. Vishvjeet Kanwarpal CEO GIS-ACG Global InfraSys - Asia Consulting Group
Published: July/Autus 1996 by
Independent Energy A PennWell Publication

IPPs IN ASIA:
Success Stories & Lessons Learned
Plus: S pecial India S ection
INDEPENDENT

ENERGY Volume 26, No. 6 / July/August 1996

Power Markets

Solicitation
Strategies
Asian markets are moving into the next stage of
maturity: competitive procurement. Industry players are
teaming up to maximize their competitiveness.

The 720 MW Kuala Langat power station entered service in


By Michael T. Burr 8
Malaysia in May. ABB Power Generation built the project in 24
months under turnkey contract with Genting Sanyen Power.

10 Scaleup In 56 Cross-Border
Shandong Marketing
To keep up with economic Despite challenges, Canada’s
growth, Shandong Electric Power competitive power market is
Corp. is pursuing an aggressive beginning to expand through
plan for adding generating and several cross-border transactions
transmission network capacity in with U.S. buyers.
the coming years.

By Mr. Zhou Yongxin


34 Bigger Barges By David Bright
and Stephen Salaff
The 450 MW Port Qasim
combined-cycle project takes
14 Promising barge-mounted power to a new Financial
level.
Prospects 65 Sound Structures
By Michael T. Burr
Opportunities for privatization and Two successful international deals
new projects make the Philippines continue to demonstrate financing
one of Asia’s most promising 38 INDIA structures and partnerships that
markets. work in today’s expanding market.
SPECIAL SECTION
By Michael T. Burr By John Anderson
40 Power Shift
India’s vast power market
24 Project Security appears ready to continue as
China’s Guarantee Law provides a economic growth and reform
Independent Energy
better environment for project continue to move forward. Is Moving!
sponsors.
By Vishvjeet Kanwarpal Effective July 1, 1996, Independent
By Mark H.F. Kuo Energy’s editorial and advertising
52 PFC’s Power offices are relocating to Tulsa, Okla.
27 Progressive Change The new address is:
Australia continues to offer
Funding Independent Energy
The Power Finance Corp. of India PennWell Publishing Co.
investors many opportunities as
privatization continues. is continuing its part in the power 1421 Sheridan Road
sector by expanding its role as a Tulsa, OK 74112
By Kenneth L. Norton financier. Tel: (918) 835-3161
and Noela Cain Fax: (918) 831-9776
By I.M. Sahai

July/August 1996 / INDEPENDENT ENERGY 1


IN D EPEN D EN T THE POWER INDUSTRY'S BUSINESS MAGAZINE 1421 S. Sheridan Rd.
Tulsa, OK 74112

ENERGY
ESTABLISHED IN 1971
Ph.: (918) 835-3161; Fax: 918-835-9776
A PENNWELL PUBLICATION Publisher Emeritus, Donald Marier
Publisher, Margaret Shake
Managing Editor, John L. Anderson
Senior Editor, Michael T. Burr
Associate Editor, Timothy L. Hennagir
Regulatory 82 Contract Updates Contributing Editors
70 Competitive Jeffery C. Bodington, Scott Gawlicki,
Hydropower Paul Gipe, Christopher Hocker, Richard Hunt,
Vision Judith Mohsberg Hunt, Eric Jeffs, George Lagassa,

FERC’s Order 888 lays the


86 Sichuan’s River Jeannie Mandelker, William Meade, Patricia Lloyd
Williams, Michael J. Zimmer
cornerstone for competition and Resources Advertising Sales Manager, Rick Huntzicker
for lower consumer power Account Executive and
Sichuan’s rich hydropower Reprints Manager, Jennifer Ahlert
rates. Three industry trade
resources offer many Production Manager, Roberta Olmstead
groups offer their views on
opportunities for project Circulation Manager, Linda Thomas
FERC’s action.
development.
SALES OFFICES:
F rance
Fuels By Shi Wanjian Daniel R. Bernard
+33-1-39-14-67-80; Fax: +33-1-39-14-70-14
76 Asian Peat e-mail: danielb@pennwell.com
France, Belgium, Spain, Portugal, So. Switzerland
Prospectus 90 Names In The News G erm any
Wilhelm F. Sicking
Interest in peat as a fuel for +49-201-77-98-61; Fax: +49-201-78-17-41
e-mail: wilhelms@pennwell.com
power production is growing in Germany, Austria, No. Switzerland, Luxembourg,
various Asian markets, including Eastern Europe, Denmark
Indonesia. Hong Kong
Colin Low
By Tim Hennagir +852-28151889; Fax: +852-28159391
e-mail: colinlow@HK.Super.NET
India
Power Equipment Amarjit Singh, MBE
+91 - 11 -546-5210; Fax: +91 -11 -545-9155
D E P A R T M E N T S
78 Captive Italy
Luigi Rancati
SUPPLIERS SOURCE GUIDE:
Applications +39-2-703-00088; Fax: +39-2-703-00074
Jap a n
E urope.....................................61 Ken Takahashi
Recent power generation station Ken Associates Inc.
orders from countries such as SERVICE SOURCE GUIDE: +81-33-443-2748; Fax: +81-33-443-8275

China and India continue to Business & Financial................... 95


Korea
Paek Kwon
document the popularity of the Inti Media Services Co. Ltd.
dependable diesel. COMPANY IN D EX....................... 94 +822-783-9555; Fax: +822-783-9553
Singapore
By Tim Hennagir CALENDAR............................... 95 Mike Seah
Bell Associated Agency
ADVERTISERS IN D EX.................. 96 +65-299-0413; Fax: +65-758-7850
United Kingdom
David Betham-Rogers/David Levitt
Independent Energy magazine provides senior OK 74112. Phone: (918) 835-3161. Second class +44-181-744-2345 Fax: +44-181-744-9932
executives at companies that develop, own and postage paid at Tulsa, OK and additional mailing e-mail: davidbr@pennweil.com
e-mail: davidl@pennwell.com
operate independent power production facilities offices. Postmaster: Please send change of address UK, Scandinavia, The Netherlands
with news and critical insights that help them to Independent Energy magazine, P.O. Box 3105,
b e tte r m anage th eir grow ing b u sin esses. In Tulsa, OK 74101-3105. SUBSCRIPTIONS:
North America $97-one year (10 issues); $156-two years
addition, it provides equipment manufacturers, P hotocopy perm ission: W here necessary, (20 issues). Foreign (airmail only) $124-one year; $217-
engineering and construction firms and financial permission is granted by the copyright owner for two years. Single issues $14.00 each, except December.
service firms, which serve the independent power those registered with the Copyright Clearance Single copies of the December Industry Directory are
$75.00. Allow 5 weeks for change of address of delivery
industry with industry news, inform ation and Center (CCC), 222 Rosewood Dr., Danvers, Mass. of magazine.
analysis which is vital to their marketing plans. 01923, to photocopy any article herein, for personal For custom er service and address corrections, call or
write: Independent Energy, P.O. Box 3105, Tulsa, OK
A rticles and opinions found in Independent or internal reference use only, for the flat fee of 74101-3105. Tel: (918) 835-3161, FAX: (918) 831-9834.
Energy magazine reflect the views of the authors $1.00 per copy of each article, plus $0.35 per page. Correspondence relating to subscription problems
should include the computer/sub-scription address label.
and not necessarily those of PennWell Publishing Send payment to the CCC. Copying for other than
The month and year of expiration appears on your label.
Co. In d e p e n d e n t E nergy m agazine has not personal or internal reference use w ithout the
investigated and makes no representations as to express permission of PennWell Publishing Co. is V bpa
the accuracy or completeness of any information prohibited. Requests for special permission bulk Circulation audited
presented herein. orders or article reprints should be addressed to the by the Business Publications Association
Independent E nergy IS S N -1043-7320 is publisher at P.O. Box 3105, Tulsa, OK 74101-3105. Copyright 1996 by PennWell Publishing Co.
p ublished m onthly, except bim onthly in This publication is available in microfilm. For All Rights Reserved

January/February and July/August, by PennWell information write Dept. FA, University Microfilms P ennWell
Publishing Co., 1421 So. Sheridan Rd., Tulsa, International, 300 N. Zeeb Rd., Ann Arbor, MI 48106. PUBLISHING COMPANY

2 INDEPENDENT ENERGY/July/August 1996


S P E C I A L S E C T I O N

India

Pow er
investment in infrastructure and the
need to end India’s protectionist regime.

The Power Sector


The power industry, including gener­

Shift ation and T&D, has been the domain of


the public sector since the Industrial
Policy of 1956 and private power
accounts for a meager 4 percent of gen­
eration today. The Indian Energy
Vishvjeet Kanwarpal, Asia Consulting Group Supply Act of 1948 established the
State E lectricity Boards (SEBs) to
develop the power sector at the state
level and the Central Electricity
he Indian liberalization process tain trials. As an example, the Dabhol Authority (CEA) at the central govern­

T initiated in the early 1990s has


awakened the sleeping giant.
Private sector participation, public sec­
tor disinvestment, deregulation, lower­
project was confronted by challenges
and setbacks that could have sealed the
fate of the project. However, Enron has
overcome these with vision, insightful
ment level to develop and coordinate
national power policy.
Until the late 1970s India was a
power surplus country. Today, the
ing of trade barriers, and a radical over­ strategy, and firm resolve. While other country is experiencing acute shortage
developers are unlikely to face similar of electricity with average shortfall of
haul of industrial, financial, and tax
risks, they will still have to earn their 10 percent and peak shortfall of 20 per­
policies have unleashed Indian econom­
rewards in India. cent. Regional shortfall is estimated at
ic and market potential in an unprece­
The Enron imbroglio demonstrated 27 percent in the eastern region, 22 per­
dented manner.
that political risk can be substantial in a cent in the northern region, 18 percent
Decades of central planning, govern­
country like India. However, the ensuing in the western region, 17 percent in the
ment controls, subsidies, and a public
national debate and wide publicity southern region, and 12 percent in the
sector notorious for its low productivi­
brought home several facts .to the Indian northeastern region.
ty, all collectively served to exhaust the
political ideologues and ordinary citizens. While government investment in the
government’s financial ability to meet
First, there is serious infrastructure crisis sector has been inadequate, there also
the needs of the nation. Left with little
in India. Second, the nation cannot meet has been a slowdown based on lack of
choice, in 1991 India opened its doors, the requirement indigenously. And final­ funds and the expectation that IPPs will
invited foreign capital, and looked to ly, foreign investment is needed. add the required capacity. In the eighth,
participate in the global market. As no political party received a clear 5-year plan (1992-1997) the govern­
However, economic growth and mar­ mandate to form the government in the ment had planned to add 45 GW.
ket demand are easier unleashed than recent national
sustained in a country of 900 million elections, there FIGURE1: F o r e c a s t in g E l e c t r ic it y D e m a n d — S u p p l y in I n d ia
people with double digit growth in is caution about
many key sectors. There is an enormous the nature of the
strain on the country’s infrastructure — coalition form­
power, telecommunication, and trans­ ing the new gov­
portation, combined with power short­ ernment and its
age threaten to retard the economic foreign invest­
boom. Key factors such as political and ment policy.
national consensus on the need for for­ N e v e rth e le ss,
eign investment in the infrastructure almost all par­
sectors, streamlining of the investment ties highlighted
process, and overcoming bureaucratic the need for
inertia have all taken their due time. in fra stru c tu re
These are unavoidable processes in a d e v e lo p m e n t
country accustomed to four decades of using foreign
central planning and control. investment.
The Indian power market promises to Indian politi­
be more than $150 billion in the next cal, industrial,
decade. Success is a function of long­ and financial
term strategic commitments to develop systems have
the market, a flexibility to adapt to accepted the
Note: PLF average for new projects pegged at 75%, without fuel availability constraints.
dynamically evolving market condi­ essential realities
tions, and the will and resources to sus­ of foreign Source: Asia Consulting Group

40 INDEPENDENT ENERGY / July/August 1996


IPP Case History: Jegurupadu
GVK Industries’ combined-cycle supply. The bankers insisted on a fool­
power plant at Jegurupadu will be one proof contract from the Gas Authority
of the first IPP projects to come on of India (GAI), with which the GAI did Successive revisions reduced the target to
line with its first unit of 53 MW sched­ not agree. GVK Industries has now 30 GW. The currently expected govern­
uled to become operational in July. ment capacity addition is expected to be
taken the fuel risk on its own. Due to
The project consists of three gas tur­ 19 GW or 42 percent of the original tar­
the shortage of gas, gas linkages are get for the eighth plan. With IPPs includ­
bines and a steam turbine based on
available for only two units and at ing fast track projects facing slow devel­
waste heat from the gas turbines.
least one unit of the project will be opment, the crisis is deepening further.
The first unit which was scheduled
to be commissioned in March was forced to operate on naphtha. Since The eighth plan of the government
naphtha is twice as costly as gas, the (1992-1997) allocated $23 billion for
delayed two months as the finance
finance ministry has objected to this. the five-year plan or an average annual
ministry delayed the counter guaran­
amount of $4.6 billion. This is planned
tee clearance. This held up the After all these hurdles, the
for the entire power industry, not just
release of funds by the IFC. The SEB, Jegurupadu project is one of the first for capacity additions. Private sector
on behalf of whom the central govern­ IPPs nearing completion. Power will investment is not a matter of choice, it is
ment grants the counter guarantee, is be sold at a levelized tariff of Rs 2.06 a critical need.
expected to clear the operation per unit, based on the assumption The wide range of conflicting fore­
finance action plan (OFAP) and earn casts of India’s power requirement sug­
that the gas based power station will
a minimum 3 percent rate of return. gests that the magnitude of the crisis is
run for 15 years before the first major
The SEB revenue earning is not up to yet to be accurately determined. And
overhaul is due. As per the govern­ without a reliable demand forecast,
the mark and the state government
will have to pay up the subsidies to ment guidelines the insurance premi­ planning for the power industry cannot
Andhra Pradesh SEB for it to clear its ums are kept at a cap of 1 percent of be conducted optimally.
OFAP. In Andhra Pradesh 43 percent the capital cost and O&M expenses to One demand forecast suggests that
of the power is consumed by the high­ 2 percent of the capital cost. 142,000 MW of additional capacity will
ly subsidized agricultural sector (20 The three gas turbines will be set
be required, including peak demand, in
paise per unit or 0.0057 cents) which the next 10 years only under certain
up in June, August and December of
is already affecting the financial posi­
conditions. One such set of conditions is
1996 and the steam turbine in May that new projects are operated at 75 per­
tion of the SEB.
1997. The total project cost is Rs 827 cent PLF, T&D losses continue at 22
The restricted counter guarantee
crores (US$237.2 million) of which the percent, no further captive or cogenera­
which was subsequently cleared by tion capacity is added, and no installed
equity portion is Rs. 252 crores
the m inistry covers only the debt base plants are repowered. However, all
obligations and not the energy pay­ (US$72.3 million) and the debt portion
of these are untenable as most PPAs are
ment dues from the SEB. is Rs 575 crores (US$165 million).
signed for 85 percent to 90 percent off­
Further, GVK’s request for allowing take, T&D losses are likely to decrease
it to sell power in excess of 68.5 per­ Break up of equity (percent) with privatization in the medium future,
cent PLF has been turned down by GVK group (including an offshore captive and cogeneration capacity will
the Ministry of Power. The ministry company in Mauritius) 26.5 increase rapidly in the near future, and
also has scaled down certain incen­ there are extensive plans for installed
Asian Infrastructure Fund 29.75
tives for power generation in excess base repowering.
CMS Generation USA 18.75 Under these conditions the demand for
of 68.5 percent PLF.
IFC Washington 10 additional capacity in the next 10 years
Selling power to the third party
directly by the company would mean
ABB 5 could fall below 100,000 MW. This fig­
APSEB 10 ure may be further reduced with wheel­
substantial loss in revenues to the
ing of power from surplus areas to deficit
SEB. The industrial consumers who
areas and in the long run through DSM.
are charged the highest tariffs would Indian financial institutions involved
These aspects can have an enormous
prefer this more reliable power supply. include: Industrial Development Bank effect on capacity planning and particu­
The stand of both the finance ministry of India; Industrial Credit Investment larly PPAs that will be signed in the next
and the ministry of power suggests Corp. of India; the Former Shipping five years, especially since there has been
they do not want to abolish the Credit and Investment Corp. of India; about 250,000 MW of new capacity
monopoly of the SEB in power distrib­ addition activity recorded to date (See
and Industrial Reconstruction Bank of
ution, instead of looking at the possi­ Figures 1 and 2).
India. Also, the Life Insurance Corp.
bility of improving the performance of The call for private participation in the
of India and the Unit Trust of India will power sector by the government has been
the SEB through competition. The cost
of power from a new IPP like this lend Rs 330 crores (US$94.7 million), overwhelming since mid-1994. In
would be more than that from the and the International Finance Corp. December 1995 the ministry of power
depreciated SEB’s power plants. and the Nordic Investment Bank will recorded more than 225 proposals by
GVK also faced problems with fuel fund Rs 245 crores (US$70.3 million). developers totaling about 100,000 MW in
power generation capacity (See Figure 3).
42 INDEPENDENT ENERGY / July/August 1996
Since then the crisis in the power The clearance issued by the CEA is a clearance was initially not required for
sector has worsened and projects have techno-economic clearance that exam­ projects under Rs. 25 crore (US$7.2 mil­
continued to be slow in developing. ines all param eters of a project. lion). This limit has been progressively
The government has responded by ini­ However, many say that the CEA clear­ been increased to Rs.100 crore (US$28.7
tiating several measures to accelerate ance —which is to be applied for after million), then Rs. 200 crore (US$57.4
project development, weed out less the rigors of detailed feasibility studies, m illion), and finally Rs. 400 crore
serious projects, and streamline the securing a PPA, and FSA— is too gener­ (US$114.7 million).
project clearance process. al in nature, adds little value, and unnec­ State governments have taken advan­
tage of these changes and taken inde­
One of the most significant initiatives essarily delays projects. According to
pendent initiatives to woo private power
has been to eliminate the mandated some former senior power sector offi­ developers. Asia Consulting Group’s
clearance required from Central cials and industry leaders, India’s CEA National Project Track is currently
Electricity Authority (CEA) for projects does not possess the resources to assess tracking almost 1,300 projects under
costing less than Rs. 400 crore ($115 the large number of private power pro­ development in the country. These pro­
million), thus giving a boost to medium jects of increasing structural, technical, jects include IPPs, captive projects, new
and small power project development. and financial complexity. The CEA government projects, as well as small
projects. Collectively these account for
250.000 MW of capacity under devel­
IPP Case History: lb Valley opment with IPPs accounting for almost
189.000 MW.
AES Corporation’s lb Valley power of the PPA and other issues relating Cumulatively the installed base and
project, one of the initial fast track pro­ to high capital costs. The SEB insist­ projects under development present a
jects, faced challenges as the ed on a tariff of Rs. 1.55 to Rs. 1.60 dreamy picture of Indian power with a
Congress government ordered a per unit pointing out that the first two power project sited for every 50 kms of
review of the project as soon as it units of lb Valley operated by the habitable land in India, sometime in the
came to power last year. The project Orissa Power Generation Co. were future. However, preliminary analysis
was initiated in the regime of the earlier already supplying power at a rate of at the project level suggests a maximum
Janata Dal government. Review was Rs 1.55 per unit to the SEB. addition of about 95 GW within the
next 10 years. IPPs are expected to
ordered on the basis of allegations of Subsequently AES reduced the tariff
account for almost 60 percent of the
lack of transparency, excessively high rates in stages, from Rs. 2.39 per unit
total addition.
project costs and high tariff rates. to Rs. 2.04 and further down to Rs.
Analysis further suggests that power
The comptroller and auditor gener­ 1.90 per unit. Project costs were projects currently under development
al also criticized the Orissa SEB for reduced from Rs. 4.76 crores will undergo an attrition of almost 60
not following the route of global ten­ (US$1.4 million) per MW to Rs. 4.15 percent in the coming years based on
dering and also signing a power pur­ crores (US$1.2 million). The project demand based analysis alone.
chase agreem ent (PPA) which it site was changed from lb Valley units
termed as financially disadvanta­ 3 and 4 of 210 MW each to lb Valley Private Power A ttrition
geous. A report by the comptroller units 5 and 6 each of 250 MW.
and auditor general highlighted the Project for units 3 and 4 will be Some estimates are that project activ­
following points. undertaken by O rissa Power ity in the country will pass through sev­
□ There is no clause in the PPA to Generation Corp. eral stages of attrition in the next five to
protect the interest of the SEB in lb Valley was the only fast track seven years. Several factors will deter­
case of late repayment of loans by project, apart from Dabhol, to have mine this attrition.
AES attracting penal interest. received a counter guarantee from One is that a large number of devel­
□ The PPA did not have a provi­ the central and state governments. opers will not succeed in completing
sion through which the Orissa SEB But renegotiation and subsequent the requisite clearances due to project
could verify the actual consumption of changes will require AES to put in a deficiencies and delays within the clear­
fuel by AES even though the board fresh proposal for the counter-guar­ ance mechanisms. Additionally, envi­
ronmental and political factors have and
was to reimburse the heavy cost of antee and draft a new PPA.
may continue to hinder some projects
fuel on actual basis. Considering the present situation of
from successful completion.
□ The SEB opened a letter of acute shortage of power the ministry
Next, there seems to be as much diver­
credit amounting to Rs. 142.66 crores of power and the ministry of finance sity among developers as there is in pro­
(US$41 million) which is the power are likely to give quick clearances to jects. The initial ease of entry into the pri­
supply bill for three months. This was the project. vate power industry witnessed an
apart from the guarantee and counter Two units of 250 MW each is likely unprecedented random diversification
guarantee by the central and state to be commissioned in 1999. GE will into private power by companies, agen­
governments. be supplying the steam turbines and cies, and individuals with no core-compe­
□ High capital cost of the project generators for both the units. The tence in this sector. This lack of expertise
will mean an additional payment of company is seeking linkages of 2 mil­ and its effects are already being detected
Rs 9.95 crores (US$2.9 million) every lion tons of coal from the near lb in projects which are floundering.
year as O&M expenses. Valley coalfields of Mahanadi Coalfield Third, there may be shortages in coal
These charges led to renegotiation Ltd, a subsidiary of Coal India Ltd. and gas availability, and transportation
constraints may jeopardize signing of
46 INDEPENDENT ENERGY / July/August 1996
FIGURE 2: I ndia Electricity S upply Forecast

will apply more power generation and its sale to SEBs


acutely to project are in a clear advantage.
developers who Restructuring is most talked of in elec­
have no prior or tricity boards that are characterized by
core competence high T&D losses, highly subsidized agri­
in the power cultural tariffs and excessive numbers of
industry. employees. T&D losses are more than
A second area 20 percent in most states. A majority of
is financing costs the consumers are from the privileged
and project feas­ agricultural sector who are charged less
ibility. Contin­ than half the cost of generation.
uous revisions Electricity theft is not easy to stamp out.
of PPAs have According to N.K.P. Salve the former
pushed project union power minister, inefficiency of
and tariff costs state electricity boards is a significant
Source: Asia Consulting Group down toward problem, and he urged the states to
internationally
change their attitude toward entry of
acceptable fuel supply agreements acceptable stan­
private companies. Meanwhile, the cen­
(FSAs) or render them risky documents. dards. However, project risks in India
tral government has suggested several
Also, Asia Consulting Group’s forecast continue to be high. With higher project
and country risks built into the lending models of restructuring programs to
for the next 10-years of demand sug­ facilitate reformation of SEBs to make
gests an additional 100,000 MW of rates and with higher risk insurance pre­
miums, the PPAs may well return to them commercially viable, to regulate
capacity —including peak demand— and rationalize the tariffs and improve
will be required. Given that there is haunt some developers.
the T&D network.
roughly 250,000 MW under various
The power sector has posted some
stages of development, there will be 60 Genesis Of The Power Crisis impressive efficiency gains in the past
percent project attrition.
10 years. The national average plant
Currently the SEBs are the primary The genesis of the crisis in the Indian
load factor (PLF) for thermal plants has
purchasers of power. PPAs signed by power sector lies in India’s policies and
increased from 44.3 percent in 1979 to
the SEBs have to be supported by rev­ objectives of rural electrification, subsi­
dized electricity to the agricultural and 61 percent in 1993, with the central
enues. Given the highly subsidized tariff
domestic sectors, and use of the power sector recording a PLF of nearly 70
structure in India, T&D losses, theft,
industry as an employment scheme. percent in 1993.
and collection irregularities, the demand
These policies received their most However, India’s national public
forecasts will not be reflected in the rev­
aggressive boost in the early 1980s. power sector PLF, including all tech­
enue streams of the SEBs. Hence the
Almost 75 percent of the population is nologies, is under 50 percent. The east­
SEB ability to sign up and honor PPAs
is substantially lower than what the rural, and the government has electri­ ern and northeastern regions record
demand figures suggest. Even in the fied nearly 85 percent of In d ia’s PLFs as low as 38 percent and 29 per­
event of tariff rationalization and reduc­ 580,000 villages. Today agriculture cent respectively. The most ailing units
tion of losses, the situation is unlikely to consumes 30 percent of power generat­ are below 140 MW and have run for
improve dramatically. ed in the country and pays an average more than 100,000 hours. About 250
Another forecast suggests that the of 0.6 cents per KWh. The agricultural such units exist in India and every 10
Asian power industry will require an sector consumption has been growing at percent rise in PLF can increase the
investment of more than $700 billion in more than 12 percent in recent years. generation by 3 percent — equivalent to
the next 10 years. This assessment of The Indian power industry employs adding 2.2 GW at one fourth the cost.
the Asian infrastructure investment about 1.7 million people for a 21 per­ The cost of life extension by 15 years
need and sources of possible funding sonnel per MW ratio. Subsequently, the is 20 percent to 30 percent the cost of a
suggests there is not enough capital accumulated losses of the public power greenfield project, and the implementa­
worldwide to accom modate this sector stand at US$6.4 billion. tion period is half that of a greenfield
requirement. India’s need for $100 bil­ The SEBs seem to bear the brunt of project. This has been an important area
lion in power generation and $60 billion criticism in the power crisis. They have of focus for the government which has
in T&D cannot be met by the collective been forced to serve as instruments of identified about 160 old plants for reno­
resources of the government, multi-lat­ national and state policy for decades vation and modernization. To date 22
eral lending agencies and domestic cap­ and cannot be held solely responsible stations with 55 units have been reno­
ital markets. In effect, India is in com­ for the current state of affairs. The vated and an average of 18 percent PLF
petition for international funds with all demands on the SEBs have been increase per unit has been achieved.
other Asian countries (See Table 2). tremendous, with inadequate budgetary
The project finance hurdle in com­ support from the government. Today, State Restructuring
missioning capacity also will be a criti­ SEBs are being expected to deliver per­
cal one with two primary areas of con­ formance like private corporations. Orissa was the first state to opt for
tention. First is that securing financing Central agencies such as National restructuring. Orissa’s electricity reform
itself is a substantial challenge. This Thermal Power Corp. that focus only on bill was passed in November last year,
48 INDEPENDENT ENERGY / July/August 1996
Installed ment of coal projects at mine pit-heads.
Major coal producing states have
Capacity added a number of coal based projects
between 1965 and 1975. These include:
India currently Bihar, six; West Bengal, 11; Orissa,
accounts for 2.7 four; Madhya Pradesh, 10; and Andhra
percent of the Pradesh, five. Only eight coal projects
total global —West Bengal with five and Bihar
installed capaci­ with three— existed before 1965 in
ty. It has in­ these states. With expanding transporta­
creased its capa­ tion networks, coal-based projects
city fifty-fold in began growing rapidly in regions of
the post inde­ power demand, which explains why
pendence era. non-coal producing states of
This growth is Maharashtra and Gujarat have maxi­
heavily front- mum, coal-based generating capacity.
subsequently the SEB was broken into loaded, largely Hydropower projects are uniformly
three separate entities in charge of gen­ owing to the m ulti-purpose, mega distributed by river states with the top 10
hydropower projects. Though the hydropower states comprising only 44
eration, T&D, and an independent regu­
demand since the late 1980s has grown percent of installed hydropower.
latory body which will set the operating
steadily, capacity additions have failed to Maharashtra, Gujarat, Uttar Pradesh,
norms and fix tariff structures. This
keep pace. Of the installed base, 96 per­ West Bengal and Madhya Pradesh
process was funded by the World Bank cent is under public utilities — the cen­ account for 50 percent of coal-based
which has expressed an interest in fund­ tral sector is 27 percent and state sector power. The major gas producing states of
ing reform projects in many other states is 69 percent. M aharashtra, Gujarat, and Assam
provided they set up independent regu­ In 1970, thermal capacity accounted account for 68 percent of the total gas-
latory authorities. for 54 percent and hydropower for 43 based power. The availability of gas in
Haryana is also undergoing a similar percent. Today 70 percent of the capaci­ domestic and international markets and
process by forming three separately ty is thermal and 27 percent hydropow­ the relative costs shall determine whether
managed entities and a regulatory com­ er. This reflects India’s increasing the optimistic addition of gas-based
mission which will safeguard the inter­ dependence on coal-based power power — 6.8 GW in eighth, 5-year
est of consumers. The World Bank will despite a hydropower potential of about plan— is achievable. India has 1.8 GW
provide US$350 million to Orissa and 130 GW. Hydropower project develop­ of installed diesel and windpower plants
$500 million to Haryana to undertake ment challenges include funding short­ and 2 GW of nuclear based plants. Issues
their restructuring plans. Both Orissa falls, environmental and land acquisi­ of nuclear waste disposal, funding con­
and Haryana have ignored the problem tion problems, water-sharing disputes straints and political sensitivity have been
of over staffing in their respective among states, population relocation, a deterrent to nuclear energy addition.
boards. However waning for a natural and rising maintenance and manage­ Even amidst the current uncertainty
attrition of staff, may affect the intend­ ment costs. Of today’s installed capaci­ associated with a newly formed govern­
ed benefits of restructuring. Labor ty, 66.5 percent is coal-fired. But an 11 ment, India appears ready to continue
unions in Orissa have approached the percent demand shortfall in coal its economic reform and rapid growth.
High Court requesting a stay on the requirement by existing capacity of Developers and financiers willing to
restructuring process. power generation (at 60 percent PLF) face the risks will continue to find
Bihar, too, has made a policy deci­ including current import of 10 million ample opportunities for investment in
sion on restructuring its board. Bihar to 20 million tons and an increasing what is one of the world’s significant
has outstanding dues of more than 100 forecasted coal-dependence poses mul­ power markets. ■
percent of its annual turnover from its tiple challenges.
various consumers and owes about Rs India began its power generation pro­
1,000 crores (US$286.9 million) to gram by stressing multi-purpose mega
central undertakings like NTPC. hydropower projects to support the agri­
Uttar Pradesh has also initiated culture-based policies of the first two
restructuring studies with external assis­ five-year plans. Regional load dispatch
tance. However, the government is centers (RLDCs) were formed near
delaying the process of reforms keeping these projects, and to avoid high trans­ Vishvjeet Kanwarpal is a consultant with Asia

in view the discontent among the mission losses, coal projects of 90 MW Consulting Group in Delhi.. Asia
to 100 MW were erected close to these Consulting Group is a strategy consulting firm
employees and its likely effect on elec­ focused primarily in the power and energy sectors
tions. The World Bank has expressed an dispatch centers. In the 1960s, endeav­
which provides strategy, intelligence, and imple­
interest in funding restructured plans. At ors toward erecting larger units were
mentation services to companies seeking the com­
the same time, the SEBs of other states driven by the requirement of decreasing petitive advantage in Asian markets.
like Rajasthan, Andhra Pradesh, and costs and increasing operating efficien­ Contact Details Updated
Punjab are also heading for a change. cies. Thus began the gradual develop- Email: ceo.gis.acg@gmail.com
Website: www.gis-acg.com

Anda mungkin juga menyukai