CONTRACT ID : 19GK0198

CONTRACT NAME : Construction of Multi-Purpose Building - Construction of Multi-Purpose Building,


Barangay Cudangdang, EB Magalona, Negros Occidental
LOCATION OF THE CONSTRACT: E.B. Magalona, Negros Occidental

CASH FLOW BY QUARTER & PAYMENT SCHEDULE

90 calendar days
Description 1st 2nd 3rd 4th
QUARTERLY % ACCOMPLISHMENT 25.00 25.00 25.00 25.00
PHYSICAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE % 50.00
ACCOMPLISHMENT 25.00 75.00 100.00
QUARTERLY CASHFLOW 804,407.56 804,407.56 804,407.56 804,407.56
FINANCIAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE CASH
FLOW 804,407.56 ### ### ###
Total ###

Prepared By:
CONTRACT ID : 19GK0198
CONTRACT NAME : Construction of Multi-Purpose Building - Construction of Multi-Purpose Building,
Barangay Cudangdang, EB Magalona, Negros Occidental
LOCATION OF THE CONSTRACT: E.B. Magalona, Negros Occidental

DETAILED ESTIMATES

B.5 Project Billboard/Sign Board Qty = 1.00 ea

a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Marine Plywood 1.00 pcs 400.00 400.00
Coco lumber 37.50 bd.ft. 35.00 1,312.50
Tarpaulin 32.00 sq.ft. 25.00 800.00
Common Wire Nails 2.00 kgs 80.00 160.00
Sub - Total 2,672.50

b. Labor
Description Qty No. of Day Rate/Day Total
Mason/Carpentry 1.0 1.0 500.00 500.00
Laborer/Helper 1.0 1.0 350.00 350.00
Sub - Total 850.00

Direct Cost 3,522.50


Indirect Cost
OCM
Profit 352.25
Tax 464.97
Direct + Indirect Cost 4,339.72
Unit Price 4,339.72 ea
Total for Item B.5 4,339.72

Occupational Safety & Health


B.7(2) Qty = 1.00 l.s.
Program

a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Safety Shoes(Different Sizes) 150.00 mandays 2.50 375.00
Safety Helmet (free size) 150.00 mandays 7.50 1,125.00
Safety Gloves (free size) 150.00 mandays 0.25 37.50
Baricades and Signages 1.00 l.s 4,500.00 4,500.00
Sub - Total 6,037.50

b. Labor
Description Qty No. of Day Rate/Day Total
Safety Practitioner 1.0 30.00 500.00 15,000.00
First Aider 1.0 30.00 450.00 13,500.00
Sub - Total 28,500.00

Direct Cost 34,537.50


Indirect Cost
OCM
Profit 3,453.75
Tax 4,558.95
Direct + Indirect Cost 42,550.20
Unit Price 42,550.20 l.s.
Total for Item B.7(2) 42,550.20

ITEM NO.

B.3 Permits and Clearances Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Permits and Clearances 1.00 l.s. 35,000.00 35,000.00
Sub-total 35,000.00

Direct Cost 35,000.00


Indirect Cost
OCM 1,750.00
Profit 3,500.00
Tax 4,830.00
Direct + Indirect Cost 45,080.00
Unit Price 45,080.00 l.s.
Total for Item No. B.3 45,080.00

ITEM NO.

Additional Geotechnical
B.13 Investigation Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Additional Geotechnical
Investigation 1.00 l.s. 40,000.00 40,000.00
Sub-total 40,000.00

Direct Cost 40,000.00


Indirect Cost
OCM 2,000.00
Profit 4,000.00
Tax 5,520.00
Direct + Indirect Cost 51,520.00
Unit Price 51,520.00 l.s.
Total for Item No. B.13 51,520.00

TOTAL PART I 143,489.92

ITEM NO.

803(1)a Structure Excavation (Common Soil) Qty = 147.70 cu.m.


A. Material
Description QTY. UNIT UNIT COST AMOUNT

B. Labor
Description Qty No. of Day Rate/Day Total
Project Engineer 1.0 2.0 700.00 1,400.00
Construction Foreman 1.0 2.0 500.00 1,000.00
Mason/Carpentry 1.0 2.0 400.00 800.00
Laborer/Helper 3.0 2.0 300.00 1,800.00
Sub - Total 5,000.00
C. Equipment Rentals ( including Operator, Fuel, Oil , Lub. )
Description Qty No. of Day Rate/Day Total
Backhoe 1.0 2.0 14,200.00 28,400.00
Dumptruck 2.0 2.0 7,200.00 28,800.00
Sub - Total 57,200.00

Direct Cost 62,200.00


Indirect Cost
OCM 3,110.00
Profit 6,220.00
Tax 8,583.60
Direct + Indirect Cost 80,113.60
Unit Price 542.41 cu.m.
Total for Item No. 803(1)a 80,113.96

804(1)a Embankment From Structure Excavation Qty = 113.47 cu.m.


A. Material
Description QTY. UNIT UNIT COST AMOUNT

B. Labor
Description Qty No. of Day Rate/Day Total
Project Engineer 1.0 1.0 700.00 700.00
Construction Foreman 1.0 1.0 500.00 500.00
Mason/Carpentry 1.0 1.0 350.00 350.00
Laborer/Helper 3.0 1.0 250.00 750.00
Sub - Total 2,300.00
C. Equipment Rentals ( including Operator, Fuel, Oil , Lub. )
Description Qty No. of Day Rate/Day Total
Backhoe 1.0 0.8 14,400.00 11,520.00
Dumptruck 2.0 0.8 7,500.00 12,000.00
Sub - Total 23,520.00

Direct Cost 25,820.00


Indirect Cost
OCM 1,291.00
Profit 2,582.00
Tax 3,563.16
Direct + Indirect Cost 33,256.16
Unit Price 293.08 cu.m.
Total for Item No. 804(1)a 33,255.79

ITEM NO.

804(1)b Embankment (From Common Borrow) Qty = 31.70 cu.m.


A. Material
Description QTY. UNIT UNIT COST AMOUNT
Embankment (From Common
Borrow) 31.70 cu.m. 600.00 19,020.00

B. Labor
Description Qty No. of Day Rate/Day Total
Project Engineer 1.0 1.0 500.00 500.00
Construction Foreman 1.0 1.0 450.00 450.00
Mason/Carpentry 1.0 1.0 300.00 300.00
Laborer/Helper 4.0 1.0 200.00 800.00
Sub - Total 2,050.00
C. Equipment Rentals ( including Operator, Fuel, Oil , Lub. )
Description Qty No. of Day Rate/Day Total

Sub - Total -

Direct Cost 21,070.00


Indirect Cost
OCM 1,053.50
Profit 2,107.00
Tax 2,907.66
Direct + Indirect Cost 27,138.16
Unit Price 856.09 cu.m.
Total for Item No. 804(1)b 27,138.05

TOTAL PART A 140,507.80

ITEM NO.

900(1)c1 Structural Concrete Qty = 59.93 cu.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Structural Concrete 59.93 cu.m. 7,200.00 431,496.00


Sub-total 431,496.00

Direct Cost 431,496.00


Indirect Cost
OCM 21,574.80
Profit 43,149.60
Tax 59,546.45
Direct + Indirect Cost 555,766.85
Unit Price 9,273.60 cu.m.
Total for Item No. 900(1)c1 555,766.85

ITEM NO.

Reinforcing Steel (Deformed)


902(1)a1 Grade 40 Qty = 6,658.46 kg

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Reinforcing Steel (Deformed)
Grade 40 6,658.46 kg 55.00 366,215.30
Sub-total 366,215.30

Direct Cost 366,215.30


Indirect Cost
OCM 18,310.77
Profit 36,621.53
Tax 50,537.71
Direct + Indirect Cost 471,685.31
Unit Price 70.84 kg
Total for Item No. 902(1)a1 471,685.31

ITEM NO.

903(1) Formworks and Falseworks Qty = 1.00 ls

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Formworks and Falseworks 1.00 ls 60,000.00 60,000.00
Sub-total 60,000.00

Direct Cost 60,000.00


Indirect Cost
OCM 3,000.00
Profit 6,000.00
Tax 8,280.00
Direct + Indirect Cost 77,280.00
Unit Price 77,280.00 ls
Total for Item No. 903(1) 77,280.00

TOTAL PART B ###

ITEM NO.

CHB Non Load Bearing


1046(2)a1 (including Reinforcing Steel) Qty = 277.80 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

CHB Non Load Bearing


(including Reinforcing Steel) 277.80 sq.m. 880.00 244,464.00
Sub-total 244,464.00

Direct Cost 244,464.00


Indirect Cost
OCM 12,223.20
Profit 24,446.40
Tax 33,736.03
Direct + Indirect Cost 314,869.63
Unit Price 1,133.44 sq.m.
Total for Item No. 1046(2)a1 314,869.63
1010(2)b Doors Qty = 13.44 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Doors 13.44 sq.m. 2,200.00 29,568.00
Sub-total 29,568.00

Direct Cost 29,568.00


Indirect Cost
OCM 1,478.40
Profit 2,956.80
Tax 4,080.38
Direct + Indirect Cost 38,083.58
Unit Price 2,833.60 sq.m.
Total for Item No. 1010(2)b 38,083.58

1008(1)a Aluminum Glass Windows Qty = 41.04 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Aluminum Glass Windows 41.04 sq.m. 3,500.00 143,640.00
Sub-total 143,640.00

Direct Cost 143,640.00


Indirect Cost
OCM 7,182.00
Profit 14,364.00
Tax 19,822.32
Direct + Indirect Cost 185,008.32
Unit Price 4,508.00 sq.m.
Total for Item No. 1008(1)a 185,008.32

ITEM NO.

1007(1)b Aluminum Framed Glass Door Qty = 6.72 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Aluminum Framed Glass Door 6.72 sq.m. 3,200.00 21,504.00
Sub-total 21,504.00

Direct Cost 21,504.00


Indirect Cost
OCM 1,075.20
Profit 2,150.40
Tax 2,967.55
Direct + Indirect Cost 27,697.15
Unit Price 4,121.60 sq.m.
Total for Item No. 1007(1)b 27,697.15

ITEM NO.

1021(1)a Cement Floor Finish Qty = 133.00 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Cement Floor Finish 133.00 sq.m. 250.00 33,250.00
Sub-total 33,250.00

Direct Cost 33,250.00


Indirect Cost
OCM 1,662.50
Profit 3,325.00
Tax 4,588.50
Direct + Indirect Cost 42,826.00
Unit Price 322.00 sq.m.
Total for Item No. 1021(1)a 42,826.00

ITEM NO.

1027(1) Cement Plaster Finish Qty = 155.40 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Cement Plaster Finish 155.40 sq.m. 310.00 48,174.00
Sub-total 48,174.00

Direct Cost 48,174.00


Indirect Cost
OCM 2,408.70
Profit 4,817.40
Tax 6,648.01
Direct + Indirect Cost 62,048.11
Unit Price 399.28 sq.m.
Total for Item No. 1027(1) 62,048.11

ITEM NO.

1003(1)a Ceiling Qty = 116.25 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Ceiling 116.25 sq.m. 820.00 95,325.00
Sub-total 95,325.00

Direct Cost 95,325.00


Indirect Cost
OCM 4,766.25
Profit 9,532.50
Tax 13,154.85
Direct + Indirect Cost 122,778.60
Unit Price 1,056.16 sq.m.
Total for Item No. 1003(1)a 122,778.60

ITEM NO.

1018(1) Glazed Tiles and Trims Qty = 84.52 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Glazed Tiles and Trims 84.52 sq.m. 750.00 63,390.00
Sub-total 63,390.00

Direct Cost 63,390.00


Indirect Cost
OCM 3,169.50
Profit 6,339.00
Tax 8,747.82
Direct + Indirect Cost 81,646.32
Unit Price 966.00 sq.m.
Total for Item No. 1018(1) 81,646.32

ITEM NO.

1018(2) Unglazed Tiles Qty = 7.00 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Unglazed Tiles 7.00 sq.m. 750.00 5,250.00
Sub-total 5,250.00

Direct Cost 5,250.00


Indirect Cost
OCM 262.50
Profit 525.00
Tax 724.50
Direct + Indirect Cost 6,762.00
Unit Price 966.00 sq.m.
Total for Item No. 1018(2) 6,762.00

ITEM NO.

Painting Works
1032(1)a (Masonry/Concrete) Qty = 155.40 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Painting Works
(Masonry/Concrete) 155.40 sq.m. 240.00 37,296.00
Sub-total 37,296.00
Direct Cost 37,296.00
Indirect Cost
OCM 1,864.80
Profit 3,729.60
Tax 5,146.85
Direct + Indirect Cost 48,037.25
Unit Price 309.12 sq.m.
Total for Item No. 1032(1)a 48,037.25

ITEM NO.

1032(1)b Painting Works (Wood) Qty = 116.25 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Painting Works (Wood) 116.25 sq.m. 160.00 18,600.00


Sub-total 18,600.00

Direct Cost 18,600.00


Indirect Cost
OCM 930.00
Profit 1,860.00
Tax 2,566.80
Direct + Indirect Cost 23,956.80
Unit Price 206.08 sq.m.
Total for Item No. 1032(1)b 23,956.80

ITEM NO.

1032(1)c Painting Works Steel Qty = 25.63 sq.m.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Painting Works Steel 25.63 sq.m. 160.00 4,100.80
Sub-total 4,100.80

Direct Cost 4,100.80


Indirect Cost
OCM 205.04
Profit 410.08
Tax 565.91
Direct + Indirect Cost 5,281.83
Unit Price 206.08 sq.m.
Total for Item No. 1032(1)c 5,281.83

ITEM NO.

Prepainted Metal Sheets (Long


1014(1)b1 Span, Corrugated, 0.5mm thk) Qty = 114.33 sq.m.
Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Prepainted Metal Sheets (Long


Span, Corrugated, 0.5mm thk) 114.33 sq.m. 550.00 62,881.50
Sub-total 62,881.50

Direct Cost 62,881.50


Indirect Cost
OCM 3,144.08
Profit 6,288.15
Tax 8,677.65
Direct + Indirect Cost 80,991.37
Unit Price 708.40 sq.m.
Total for Item No. 1014(1)b1 80,991.37

ITEM NO.

Fabricated Metal Roofing


1013(2)a2 Accessory (Flashing) Qty = 44.68 m

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost

Fabricated Metal Roofing


Accessory (Flashing) 44.68 m 280.00 12,510.40
Sub-total 12,510.40

Direct Cost 12,510.40


Indirect Cost
OCM 625.52
Profit 1,251.04
Tax 1,726.44
Direct + Indirect Cost 16,113.40
Unit Price 360.64 m
Total for Item No. 1013(2)a2 16,113.40

ITEM NO.

1047(1) Structural Steel Qty = 1.00 ls

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Structural Steel 1.00 ls 382,000.00 382,000.00
Sub-total 382,000.00

Direct Cost 382,000.00


Indirect Cost
OCM 19,100.00
Profit 38,200.00
Tax 52,716.00
Direct + Indirect Cost 492,016.00
Unit Price 492,016.00 ls
Total for Item No. 1047(1) 492,016.00

TOTAL PART C ###

ITEM NO.

1002(4) Plumbing Fixtures Qty = 1.00 ls

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Plumbing Fixtures 1.00 ls 90,000.00 90,000.00
Sub-total 90,000.00

Direct Cost 90,000.00


Indirect Cost
OCM 4,500.00
Profit 9,000.00
Tax 12,420.00
Direct + Indirect Cost 115,920.00
Unit Price 115,920.00 ls
Total for Item No. 1002(4) 115,920.00

TOTAL PART D 115,920.00

ITEM NO.

Conduits, Boxes & Fittings


(Conduit Works/Conduit Rough
1100(10) in) Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Conduits, Boxes & Fittings
(Conduit Works/Conduit Rough
in) 1.00 l.s. 28,000.00 28,000.00
Sub-total 28,000.00

Direct Cost 28,000.00


Indirect Cost
OCM 1,400.00
Profit 2,800.00
Tax 3,864.00
Direct + Indirect Cost 36,064.00
Unit Price 36,064.00 l.s.
Total for Item No. 1100(10) 36,064.00

ITEM NO.

1101(33) Wires and Wiring Devices Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Wires and Wiring Devices 1.00 l.s. 40,000.00 40,000.00
Sub-total 40,000.00
Direct Cost 40,000.00
Indirect Cost
OCM 2,000.00
Profit 4,000.00
Tax 5,520.00
Direct + Indirect Cost 51,520.00
Unit Price 51,520.00 l.s.
Total for Item No. 1101(33) 51,520.00

ITEM NO.

Panelboard with Main &


1102(1) Branch Breakers Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Panelboard with Main &
Branch Breakers 1.00 l.s. 25,000.00 25,000.00
Sub-total 25,000.00

Direct Cost 25,000.00


Indirect Cost
OCM 1,250.00
Profit 2,500.00
Tax 3,450.00
Direct + Indirect Cost 32,200.00
Unit Price 32,200.00 l.s.
Total for Item No. 1102(1) 32,200.00

ITEM NO.

1103(1) Lighting Fixtures and Lamps Qty = 1.00 l.s.

Materials/Labor/Equipment
Description Qty. Unit Unit Cost Total Cost
Lighting Fixtures and Lamps 1.00 l.s. 35,000.00 35,000.00
Sub-total 35,000.00

Direct Cost 35,000.00


Indirect Cost
OCM 1,750.00
Profit 3,500.00
Tax 4,830.00
Direct + Indirect Cost 45,080.00
Unit Price 45,080.00 l.s.
Total for Item No. 1103(1) 45,080.00

TOTAL PART E 164,864.00


TOTAL BID COST 3,217,630.24

Prepared By:
CONTRACT ID : 19GK0198
CONTRACT NAME : Construction of Multi-Purpose Building - Construction of Multi-Purpose Building,
Barangay Cudangdang, EB Magalona, Negros Occidental
LOCATION OF THE CONSTRACT: E.B. Magalona, Negros Occidental

BILL OF QUANTITIES

Item No. Description Unit Quantity Unit Price Amount


(Pesos) (Pesos)
PART I OTHER GENERAL REQUIREMENTS

#VALUE! 4,339.72
B.5 Project Billboard/Sign Board ea 1.00

4,339.72

Occupational Safety & Health #VALUE! 42,550.20


B.7(2) l.s. 1.00
Program

42,550.20

#VALUE! 45,080.00
B.3 Permits and Clearances l.s. 1.00

45,080.00

Additional Geotechnical #VALUE! 51,520.00


B.13 l.s. 1.00
Investigation

51,520.00
TOTAL
PART I
#VALUE! 143,489.92

PART II CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING


PART A EARTHWORKS

Structure Excavation (Common #VALUE! 80,113.96


803(1)a cu.m. 147.70
Soil)
542.41

Embankment From Structure #VALUE! 33,255.79


804(1)a cu.m. 113.47
Excavation
293.08

Embankment (From Common #VALUE! 27,138.05


804(1)b cu.m. 31.70
Borrow)

856.09
TOTAL
PART A
#VALUE! 140,507.80
PART B PLAIN AND REINFORCED CONCRETE WORKS

#VALUE! 555,766.85
900(1)c1 Structural Concrete cu.m. 59.93

9,273.60

Reinforcing Steel (Deformed) #VALUE! 471,685.31


902(1)a1 kg 6,658.46
Grade 40
70.84

#VALUE! 77,280.00
903(1) Formworks and Falseworks ls 1.00

77,280.00
TOTAL
PART B
#VALUE! 1,104,732.15

PART C FINISHING
C.1 Masonry Works

CHB Non Load Bearing #VALUE! 314,869.63


1046(2)a1 sq.m. 277.80
(including Reinforcing Steel)

1,133.44
C.2 Fabricated Materials

#VALUE! 38,083.58
1010(2)b Doors sq.m. 13.44

2,833.60

#VALUE! 185,008.32
1008(1)a Aluminum Glass Windows sq.m. 41.04

4,508.00

#VALUE! 27,697.15
1007(1)b Aluminum Framed Glass Door sq.m. 6.72

4,121.60
C.3 Finishing Works

#VALUE! 42,826.00
1021(1)a Cement Floor Finish sq.m. 133.00

322.00

#VALUE! 62,048.11
1027(1) Cement Plaster Finish sq.m. 155.40

399.28

#VALUE! 122,778.60
1003(1)a Ceiling sq.m. 116.25
1003(1)a Ceiling sq.m. 116.25

1,056.16

#VALUE! 81,646.32
1018(1) Glazed Tiles and Trims sq.m. 84.52

966.00

#VALUE! 6,762.00
1018(2) Unglazed Tiles sq.m. 7.00

966.00
C.4 Painting Works

Painting Works #VALUE! 48,037.25


1032(1)a sq.m. 155.40
(Masonry/Concrete)
309.12

#VALUE! 23,956.80
1032(1)b Painting Works (Wood) sq.m. 116.25

206.08

#VALUE! 5,281.83
1032(1)c Painting Works Steel sq.m. 25.63

206.08
C.5 Roof Framing and Roofing Work

Prepainted Metal Sheets (Long #VALUE! 80,991.37


1014(1)b1 sq.m. 114.33
Span, Corrugated, 0.5mm thk)
708.40

Fabricated Metal Roofing #VALUE! 16,113.40


1013(2)a2 m 44.68
Accessory (Flashing)
360.64

#VALUE! 492,016.00
1047(1) Structural Steel ls 1.00

492,016.00
TOTAL
PART C

#VALUE! 1,548,116.37

PART D PLUMBING/SANITARY WORKS

#VALUE! 115,920.00
1002(4) Plumbing Fixtures ls 1.00

115,920.00
TOTAL
PART D
#VALUE! 115,920.00

PART E ELECTRICAL
Conduits, Boxes & Fittings #VALUE! 36,064.00
1100(10) (Conduit Works/Conduit Rough l.s. 1.00
in)
36,064.00

#VALUE! 51,520.00
1101(33) Wires and Wiring Devices l.s. 1.00

51,520.00

Panelboard with Main & Branch #VALUE! 32,200.00


1102(1) l.s. 1.00
Breakers
32,200.00

#VALUE! 45,080.00
1103(1) Lighting Fixtures and Lamps l.s. 1.00

45,080.00
TOTAL
PART E
#VALUE! 164,864.00

TOTAL #VALUE!

3,217,630.24

SUBMITTED BY:
Department of Public Works and Highways
CONTRACT ID : 19GK0198
CONTRACT NAME : Construction of Multi-Purpose Building - Construction of Multi-Purpose Building,
Barangay Cudangdang, EB Magalona, Negros Occidental
LOCATION OF THE CONSTRACT: E.B. Magalona, Negros Occidental

SUMMARY OF BID PRICES


( All Parts of Bill of Quantities or BOQ)

Part No. Part Description Total Amount


PART I OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Sign Board 4,339.72
B.7(2) Occupational Safety & Health Program 42,550.20
B.3 Permits and Clearances 45,080.00
B.13 Additional Geotechnical Investigation 51,520.00
TOTAL PART I 143,489.92
PART II CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART A EARTHWORKS
803(1)a Structure Excavation (Common Soil) 80,113.96
804(1)a Embankment From Structure Excavation 33,255.79
804(1)b Embankment (From Common Borrow) 27,138.05
TOTAL PART A 140,507.80
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete 555,766.85
902(1)a1 Reinforcing Steel (Deformed) Grade 40 471,685.31
903(1) Formworks and Falseworks 77,280.00
TOTAL PART B 1,104,732.15
PART C FINISHING
C.1 Masonry Works
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel) 314,869.63
C.2 Fabricated Materials
1010(2)b Doors 38,083.58
1008(1)a Aluminum Glass Windows 185,008.32
1007(1)b Aluminum Framed Glass Door 27,697.15
C.3 Finishing Works
1021(1)a Cement Floor Finish 42,826.00
1027(1) Cement Plaster Finish 62,048.11
1003(1)a Ceiling 122,778.60
1018(1) Glazed Tiles and Trims 81,646.32
1018(2) Unglazed Tiles 6,762.00
C.4 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 48,037.25
1032(1)b Painting Works (Wood) 23,956.80
1032(1)c Painting Works Steel 5,281.83
C.5 Roof Framing and Roofing Works
1014(1)b1 Prepainted Metal Sheets (Long Span, Corrugated, 0.5mm thk) 80,991.37
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing) 16,113.40
1047(1) Structural Steel 492,016.00
TOTAL PART C 1,548,116.37
PART D PLUMBING/SANITARY WORKS
1002(4) Plumbing Fixtures 115,920.00
TOTAL PART D 115,920.00
PART E ELECTRICAL
1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough in) 36,064.00
1101(33) Wires and Wiring Devices 51,520.00
1102(1) Panelboard with Main & Branch Breakers 32,200.00
1103(1) Lighting Fixtures and Lamps 45,080.00
TOTAL PART E 164,864.00
Total of Amount P 3,217,630.24
Total of All Amounts in words
#VALUE!

Name __________________________________________ in the capacity of ____________________


Signed _________________________________________ Date ______________________________
Duly authorized to sign the Bid for and behalf of ____________________________________________