Anda di halaman 1dari 18

METRADO DE ALGUNAS PARTIDAS Y SUBPARTIDAS

02.01.00 LIMPIEZA DEL TERRENO

DESCRIPCION LARGO ANCHO AREA(m2)


LIMPIEZA DEL 20 5 100
TERRENO

02.02.00 TRAZO, NIVEL Y REPLANTEO

DESCRIPCION LARGO ANCHO AREA(m2)


TRAZO NIVEL Y 20 5 100
REPLANTEO

03.00.00 MOVIMIENTO DE TIERRAS


03.01.00 EXCAVACION DE ZANJAS
03.01.01 ZAPATAS

METROS
DESCRIPCION
TIPO DE ZAPATA
LADO 1 LADO 2 ALTURA N° REPETI
CUBICOS
Z1 1.40 1.40 1.30 2.00 5.10
EJE 1-1
Z1" 0.80 0.80 1.30 1.00 0.83
Z2 2.35 1.30 1.30 2.00 7.94
EJE 2-2
Z2" 1.00 1.00 1.30 1.00 1.30

EJE 3-3 Z3 2.50 1.35 1.30 2.00 8.78

EJE 4-4 Z4 2.00 1.35 1.30 2.00 7.02

EJE 55 Z5 2.10 1.35 1.30 2.00 7.37

TOTAL 38.34

03.01.02 CIMIENTOS CORRIDOS Y VIGA DE CIMENTACIÓN

TIPO DE METROS
DESCRIPCION ANCHO ALTURA LONGITUD N° REPET.
CORTE CUBICOS
2' - 2' 0.50 1.00 6.38 1 3.19
EJE A-A
4-4 0.45 0.90 3.28 1 1.33
2-2 0.50 1.10 1.41 1 0.78
3-3 0.50 0.90 7.23 1 3.25
EJE A-B
4-4 0.45 0.90 4.10 1 1.66
1-1 0.25 0.80 8.24 1 1.65
2' - 2' 0.50 1.00 6.38 1 3.19
EJE B-B
4-4 0.45 0.90 3.28 1 1.33
TOTAL 16.38
03.01.03 EXCAVACIÓN PARA CISTERNA Y ESCALERA

DESCRIPCION LARGO ANCHO ALTO VOLUMEN (m3)


CISTERNA 1.60 1.60 1.65 4.224
ESCALERA 1.05 0.50 0.50 0.2625
TOTAL 4.49

03.02.00 RELLENO CON MATERIAL PROPIO


03.02.01 ZAPATAS

METROS
DESCRIPCION
TIPO DE ZAPATA
LADO 1 LADO 2 ALTURA N° REPETI
CUBICOS
Z1 1.40 1.40 0.70
C-2 0.25 0.30 0.70
2.00 2.43
VC-0A 0.25 1.10 0.40
EJE 1-1 VC-01 0.25 1.15 0.50
Z1" 0.80 0.80 0.70
C-4 0.25 0.25 0.70 1.00 0.34
VC-01 0.25 0.55 0.50
Z2 2.35 1.30 0.70
C-2 0.25 0.30 0.70 2.00 4.02
VC-0A 0.25 2.05 0.40
EJE 2-2
Z2' 1.00 1.00 0.70
C-4 0.25 0.25 0.70 1.00 0.56
VC-02 0.25 0.75 0.5
Z3 2.50 1.35 0.70
C1 0.25 0.30 0.70
EJE 3-3 2.00 4.32
VC-OA 0.25 2.25 0.40
VC-03 0.25 1.05 0.50
Z4 2.00 1.35 0.70
C1 0.25 0.30 0.70
EJE 4-4 2.00 3.42
VC-OA 0.25 1.75 0.40
VC-04 0.25 1.05 0.50
Z5 2.10 1.35 1.30
C1 0.25 0.30 0.70
EJE 55 2.00 7.09
VC-OA 0.25 0.93 0.40
VC-05 0.25 1.05 0.50
TOTAL 22.19
03.02.02 CIMIENTOS CORRIDOS

TIPO DE METROS
DESCRIPCION ANCHO ALTURA LONGITUD N° REPET.
CORTE CUBICOS
2' - 2' 0.50 0.60 6.38
SC 0.15 0.20 6.38
EJE A-A 1 1.92
4-4 0.45 0.20 3.28
SC 0.15 0.20 3.23
2-2 0.50 0.70 1.41
SC 0.15 0.20 1.41
3-3 0.50 0.20 7.23
SC 0.15 0.20 7.23
EJE A-B 1 1.42
4-4 0.45 0.20 4.10
SC 0.15 0.20 4.10
1-1 0.25 0.20 8.24
SC 0.25 0.20 8.24
2' - 2' 0.50 0.60 6.38
SC 0.15 0.20 6.38
EJE B-B 1 1.92
4-4 0.45 0.20 3.28
SC 0.15 0.20 3.23
TOTAL 5.26

03.02.00 ELIMINACION DEL MATERIAL EXCEDENTE

03.02.01 ZAPATAS

DESCRIPCION VOLUMEN F.E. F.C. VOLUMEN FINAL


EXCAVACIÓN 38.34 15% 18% 44.09

RELLENO 22.19 15% 18% 31.12

TOTAL 12.97

03.02.02 CIMIENTOS CORRIDOS


DESCRIPCION
EXCAVACIÓN 16.38

RELLENO 5.26
TOTAL 11.12
04.00.00 METRADO DE OBRAS DE CONCRETO SIMPLE

04.01.00 CONCRETO PARA CIMIENTOS CORRIDOS

TIPO DE METROS
DESCRIPCION ANCHO ALTURA LONGITUD N° REPET.
CORTE CUBICOS
2' - 2' 0.50 0.40 6.38 1 1.28
EJE A-A
4-4 0.45 0.70 3.28 1 1.03
2-2 0.50 0.40 1.41 1 0.28
EJE A-B 3-3 0.50 0.70 7.23 1 2.53
4-4 0.45 0.70 4.10 1 1.29
2' - 2' 0.50 0.40 6.38 1 1.28
EJE B - B
4-4 0.45 0.70 3.28 1 1.03
TOTAL 8.72

04.02.00 CONCRETO PARA SOBRECIMIENTOS

TIPO DE METROS
DESCRIPCION ANCHO ALTURA LONGITUD N° REPET.
CORTE CUBICOS
2' - 2' 0.50 0.40 6.38 1 1.28
EJE A-A
4-4 0.45 0.70 3.28 1 1.03
2-2 0.50 0.40 1.41 1 0.28
EJE A-B 3-3 0.50 0.70 7.23 1 2.53
4-4 0.45 0.70 4.10 1 1.29
2' - 2' 0.50 0.40 6.38 1 1.28
EJE B - B
4-4 0.45 0.70 3.28 1 1.03
TOTAL 8.72

V_3-3 0.15 0.8 0.55 1 0.07


TAB. EJE 2-2
H_3-3 0.15 0.8 1.7 1 0.2
EJE 3-3 2'-2' 0.15 1.64 5.25 1 1.29
V_3-3 0.15 0.8 1.75 1 0.21
TAB. EJE 3-3
H_3-3 0.15 0.8 3.95 1 0.47
EJE 4-4 2'-2' 0.15 1.64 4.75 1 1.17
EJE 5-5 4-4 0.15 1.64 5.25 1 1.29
TOTAL 22.14

04.03.00 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS


METROS
TIPO DE
DESCRIPCION N° ELEMENTOSALTURA LONGITUD N° REPET. CUADRAD
CORTE
OS
1_1 2 0.8 7.25 1 11.6
EJE A-A
EJE A-A
2_2 2 1.64 6.48 1 21.25
1'_1' 2 0.8 5.4 1 8.64
1'''_1''' 2 0.8 1.45 1 2.32
EJE B-B
2'_2' 2 1.64 4.28 1 14.04
2''_2'' 2 0 0 1 0
1_1 2 0.8 5.06 1 8.1
EJE C-C
2_2 2 1.64 6.63 1 21.75
EJE 1-1 1_1 2 0.8 2.25 1 3.6
EJE 1'-1' 1_1 2 0.8 2.5 1 4
1'_1' 2 0.8 2.5 1 4
EJE 2-2
1''_1'' 2 0 2.75 1 0
V_3-3 2 0.8 0.55 1 0.88
TAB. EJE 2-2
H_3-3 2 0.8 1.7 1 2.72
EJE 3-3 2'-2' 2 1.64 5.25 1 17.22
V_3-3 2 0.8 1.75 1 2.8
TAB. EJE 3-3
H_3-3 2 0.8 3.95 1 6.32
EJE 4-4 2'-2' 2 1.64 4.75 1 15.58
EJE 5-5 2 1.64 5.25 1 17.22
TOTAL 162.04

TOTAL PIES TABLARES 1744

04.04.00 SOLADO

DESCRIPCIONTIPO DE ZAPATA
LADO 1 LADO 2 N° REPETIMETROS CUADRADOS
Z4 1.35 1.35 2 3.65
EJE A-A Z5 1.3 1.3 1 1.69
Z7 1 1 2 2
Z1 1.8 1.8 1 3.24
Z2 1.7 1.7 1 2.89
EJE B-B
Z3 1.6 1.6 1 2.56
Z4 1.35 1.35 1 1.82
Z6 1.2 1.2 1 1.44
EJE B-B
Z7 1 1 1 1
Z4 1.35 1.35 2 3.65
EJE C-C Z5 1.3 1.3 1 1.69
Z7 1 1 2 2
TOTAL 27.63

05.00.00 OBRAS DE CONCRETO ARMADO

05.01.00 ZAPATAS

05.01.01 CONCRETO EN ZAPATAS


METROS
DESCRIPCION
TIPO DE ZAPATA
LADO 1 LADO 2 ALTURAN° REPETICIONES
CUBICOS
Z4 1.35 1.35 0.5 2 1.82
EJE A-A Z5 1.3 1.3 0.5 1 0.85
Z7 1 1 0.5 2 1
Z1 1.8 1.8 0.5 1 1.62
Z2 1.7 1.7 0.5 1 1.45
EJE B-B
Z3 1.6 1.6 0.5 1 1.28
Z4 1.35 1.35 0.5 1 0.91
Z6 1.2 1.2 0.5 1 0.72
EJE B-B
Z7 1 1 0.5 1 0.5
Z4 1.35 1.35 0.5 2 1.82
EJE C-C Z5 1.3 1.3 0.5 1 0.85
Z7 1 1 0.5 2 1
TOTAL 13.82

05.02.00 VIGAS DE CIMENTACION

05.02.01 CONCRETO ENVIGAS DE CIMENTACION

METROS
DESCRIPCION ANCHO ALTURA LONGITUD N° REPET.
CUBICOS
eje A - A 0.25 0.4 17.68 1 1.77
eje B - B 0.25 0.4 17.43 1 1.74
eje C - C 0.25 0.4 15.63 1 1.56
eje 1-1 0.25 0.4 2.5 1 0.25
eje 1'-1' 0.25 0.4 2.75 1 0.28
eje 2-2 0.25 0.4 5.25 1 0.53
eje 3-3 0.25 0.4 5.25 1 0.53
eje 4-4 0.25 0.4 5.25 1 0.53
eje 5-5 0.25 0.4 5.25 1 0.53
TOTAL 7.72
05.02.02 ACERO EN VIGAS DE CIMENTACION

DESCRIPCION Und. N°veces Ø Ldiseño N°veces KG/ML METRADO


eje A - A KG 1 1/2" 15.68 5.00 1.20 94.08
estribos KG 1 3/8" 1.26 78.00 0.56 55.04
eje B - B KG 1 1/2" 15.68 5.00 1.20 43.90
estribos KG 1 3/8" 1.26 78.00 0.56 55.04
eje C - C KG 1 1/2" 13.63 5.00 1.20 38.16
estribos KG 1 3/8" 1.26 67.00 0.56 47.28
eje 1-1 KG 1 1/2" 3.40 5.00 1.20 20.40
estribos KG 1 3/8" 1.26 14.00 0.56 9.88
eje 1'-1' KG 1 1/2" 3.65 5.00 1.20 21.90
estribos KG 1 3/8" 1.26 15.00 0.56 10.58
eje 2-2 KG 1 1/2" 6.40 5.00 1.20 38.40
estribos KG 1 3/8" 1.26 30.00 0.56 21.17
eje 3-3 KG 1 1/2" 6.40 5.00 1.20 38.40
estribos KG 1 3/8" 1.26 30.00 0.56 21.17
eje 4-4 KG 1 1/2" 6.40 5.00 1.20 38.40
estribos KG 1 3/8" 1.26 30.00 0.56 21.17
eje 5-5 KG 1 1/2" 6.40 5.00 1.20 38.40
estribos KG 1 3/8" 1.26 30.00 0.56 21.17
TOTAL KG 634.53

05.02.03 ENCOFRADO EN VIGAS DE CIMENTACION


METROS
DESCRIPCION
N° ELEMENTOSALTURA LONGITUD N° REPET. CUADRAD
OS
eje A - A 2 0.4 17.68 1 14.14
eje B - B 2 0.4 17.43 1 13.94
eje C - C 2 0.4 15.63 1 12.5
eje 1-1 2 0.4 2.5 1 2
eje 1'-1' 2 0.4 2.75 1 2.2
eje 2-2 2 0.4 5.25 1 4.2
eje 3-3 2 0.4 5.25 1 4.2
eje 4-4 2 0.4 5.25 1 4.2
eje 5-5 2 0.4 5.25 1 4.2
TOTAL 61.58

05.03.00 COLUMNAS

05.03.01 CONCRETO EN COLUMNAS

METROS
DESCRIPCION
TIPO DE COLUMNA
ANCHO b ANCHO h ALTURA N° REPET.
CUBICOS
COLUMNAS C1 0.25 0.25 3.65 2 0.45625
EJE 1-1 COLUMNAS C2 0.25 0.15 3.65 1 0.136875
COLUMNAS C3 0.15 0.15 3.65 1 0.082125
COLUMNAS C1 0.25 0.25 3.65 2 0.45625
EJE 1'-1' COLUMNAS C2 0.25 0.15 3.65 2 0.27375
COLUMNAS C3 0.15 0.15 3.65 1 0.082125
COLUMNAS C1 0.25 0.25 3.65 3 0.684375
EJE 2-2 COLUMNAS C3 0.15 0.15 3.65 2 0.16425
COLUMNAS C4 0.25 0.2 3.65 1 0.1825
COLUMNAS C1 0.25 0.25 4.5 3 0.84375
EJE 3-3
COLUMNAS C2 0.25 0.15 4.5 2 0.3375
COLUMNAS C1 0.25 0.25 4.5 3 0.84375
EJE 4-4 COLUMNAS C2 0.25 0.15 4.5 1 0.16875
COLUMNAS C4 0.25 0.2 4.5 1 0.225
EJE 5-5 COLUMNAS C1 0.25 0.2 4.5 3 0.675
TOTAL 5.61225
05.03.03 ENCOFRADO EN COLUMNAS
METROS
DESCRIPCION N°veces L N°caras H CUADRAD
OS
Columnas C-1 16 0.70 1.00 6.50 72.80
Columnas C-2 5 0.65 1.00 5.50 17.88
Columnas C-3 3 0.45 1.00 5.50 7.43
Columnas C-4 1 0.45 1.00 5.50 2.48
TOTAL 100.575

05.04.00 VIGAS

05.04.01 CONCRETO EN VIGAS

DESCRIPCION N°veces L b hMETRADO CUBICOS


V1 EJE 1-1 , ENTRE A
YC 1 5.25 0.25 0.40 0.53
V2 EJE 2-2 , ENTRE B
YC 1 3.25 0.25 0.20 0.16
viga VCH. 25x20, En
eje 2-2, 3-3, 4-4, 5-5 1 5.70 0.25 0.20 0.29
viga VP. 1 25x35, En
eje B-B 1 14.03 0.25 0.35 1.23
viga VP. 2 25x35, En
eje A-A 1 14.03 0.25 0.35 1.23
viga VP. 2 25x35, En
eje C-C 1 12.58 0.25 0.35 1.10
viga VB 10x20 1 9.34 0.10 0.20 0.19
TOTAL 4.72

05.04.02 ACERO EN VIGAS

DESCRIPCION N°veces Ø L N°veces KG/MLMETRADO EN KG


viga VCH. 25x20, En ej 1 1/2" 3.20 4.00 1.20 15.36
estribos 1 3/8" 0.86 16.00 0.56 7.71
viga VCH. 25x20, En eje 1 1/2" 3.95 4.00 1.20 18.96
estribos 1 3/8" 0.86 20.00 0.56 9.63
viga VCH. 25x20, En eje 1 5/8" 6.70 4.00 1.30 34.84
estribos 1 3/8" 0.86 34.00 0.56 16.37
viga VP. 1 25x35, En e 1 5/8" 15.60 4.00 1.30 81.12
bastones 1 1/2" 28.26 1.00 1.20 33.91
estribos 1 3/8" 1.16 86.00 0.56 55.87
viga VP. 2 25x35, En e 1 5/8" 15.60 4.00 1.30 81.12
bastones 1 5/8" 20.08 1.00 1.30 26.10
estribos 1 3/8" 1.16 86.00 0.56 55.87
viga VP. 2 25x35, En 1 5/8" 14.15 2.00 1.30 36.79
bastones 1 5/8" 18.63 1.00 1.30 24.22
estribos 1 3/8" 1.16 77.00 0.56 50.02
viga VB 10x20 1 3/8" 9.80 4.00 0.56 21.95
estribos 1 1/4" 0.22 50.00 0.25 2.75
TOTAL(KG) 572.59

05.04.03 ENCOFRADO EN VIGAS

DESCRIPCION N°veces L N°caras H


METROS CUADRADOS
viga VCH. 25x20, En ej 1 2.50 1.00 0.25 0.63
viga VCH. 25x20, En eje 1 3.25 1.00 0.25 0.81
viga VCH. 25x20, En eje 1 5.70 1.00 0.25 1.43
viga VP. 1 25x35, En e 1 14.03 1.00 0.75 10.52
viga VP. 2 25x35, En e 1 14.03 1.00 0.75 10.52
viga VP. 2 25x35, En 1 12.58 1.00 0.75 9.44
viga VB 10x20 1 9.34 2.00 0.20 3.74
TOTAL (M2) 37.08
05.05.00 ALIGERADO

05.05.01 CONCRETO EN LOZA

DESCRIPCION N°veces L A H METRADO


viguetas en paño Tipo
1 18 5.25 0.10 0.15 1.42
viguetas en paño Tipo
2 5 3.65 0.10 0.15 0.27
viguetas en paño Tipo
3 2 2.75 0.10 0.15 0.08
viguetas en paño Tipo
4 2 2.10 0.10 0.15 0.06
viguetas en paño Tipo
3 6 2.50 0.10 0.15 0.23
losa 1 67.00 0.05 3.35
TOTAL (M3) 5.41
UNIVERSIDAD NACIONAL DE CAJAMARCA - SEDE JAÉN

05.01.02 ACERO EN ZAPATAS

N° PESO EN KILOGRAMOS
DESCRIPC METROS
ø LONG. N° EST. ELEMEN
ION LINEALES
TOS 1/4'' 3/8'' 1/2'' 5/8'' 3/4'' 1''
0.25 0.56 1.2 1.3 1.6 2.1
Z1 HOR. 1/2'' 1.65 1 10 16.5 19.8
Z1 VERT. 1/2'' 1.65 1 10 16.5 19.8
Z2 HOR. 1/2'' 1.55 1 9 13.95 16.74
Z2 VERT. 1/2'' 1.55 1 9 13.95 16.74
Z3 HOR. 1/2'' 1.45 1 9 13.05 15.66
Z3 VERT. 1/2'' 1.45 1 9 13.05 15.66
Z4 HOR. 1/2'' 1.2 5 7 42 50.4
Z4 VERT. 1/2'' 1.2 5 7 42 50.4
Z5 HOR. 1/2'' 1.15 2 7 16.1 19.32
Z5 HOR. 1/2'' 1.15 2 7 16.1 19.32
Z6 VERT. 1/2'' 1.05 1 6 6.3 7.56
Z6 VERT. 1/2'' 1.05 1 6 6.3 7.56
Z7 HOR. 1/2'' 0.85 5 5 21.25 25.5
Z7 VERT. 1/2'' 0.85 5 5 21.25 25.5
TOTAL LONGITUD ACERO ø 1 /2'' EN
TOTAL PESOMETROS
ACERO ø 1 /2'' EN 258.3
KILOGRAMOS 309.96

ING. ABEL RUIZ NAVARRETE METRADO DE UNA VIVIENDA CONSTRUCCIONES


UNIVERSIDAD NACIONAL DE CAJAMARCA - SEDE JAÉN

05.03.02 ACERO EN COLUMNAS

N° PESO EN KILOGRAMOS
DESCRIPC TIPO DE METROS
ø LONG. N° REP. ELEMENT
ION ACERO LINEALES 1/4'' 3/8'' 1/2'' 5/8'' 3/4''
OS
0.25 0.56 1.2 1.3 1.6
ACERO
LOMNGIT
UDINAL
COLUMNAS C1 1/2'' 5.05 2 4 40.4 48.48
EJE 1-1 COLUMNAS C2 1/2'' 5.05 1 4 20.2 24.24
COLUMNAS C3 1/2'' 5.05 1 4 20.2 24.24
COLUMNAS C1 1/2'' 5.05 2 4 40.4 48.48
EJE 1'-1' COLUMNAS C2 1/2'' 5.05 2 4 40.4 48.48
COLUMNAS C3 1/2'' 5.05 1 4 20.2 24.24
COLUMNAS C1 1/2'' 5.05 3 4 60.6 72.72
EJE 2-2 COLUMNAS C3 1/2'' 5.05 2 4 40.4 48.48
COLUMNAS C4 1/2'' 5.05 1 4 20.2 24.24
COLUMNAS C1 1/2'' 5.9 3 4 70.8 84.96
EJE 3-3
COLUMNAS C2 1/2'' 5.9 2 4 47.2 56.64
COLUMNAS C1 1/2'' 5.9 3 4 70.8 84.96
EJE 4-4 COLUMNAS C2 1/2'' 5.9 1 4 23.6 28.32
COLUMNAS C4 1/2'' 5.9 1 4 23.6 28.32
EJE 5-5 COLUMNAS C1 1/2'' 5.9 3 4 70.8 84.96
TOTAL 731.76
ESTRIBOS
COLUMNAS C1 3/8'' 0.96 2 26 49.92 14.56
EJE 1-1 COLUMNAS C2 3/8'' 0.76 1 26 19.76 14.56
COLUMNAS C3 3/8'' 0.56 1 26 14.56 14.56
COLUMNAS C1 1/2'' 0.96 2 26 49.92 14.56
EJE 1'-1' COLUMNAS C2 3/8'' 0.76 2 26 39.52 14.56
COLUMNAS C3 1/2'' 0.56 1 26 14.56 14.56
COLUMNAS C1 3/8'' 0.96 3 26 74.88 14.56
EJE 2-2 COLUMNAS C3 1/2'' 0.56 2 26 29.12 14.56

ING. ABEL RUIZ NAVARRETE METRADO DE UNA VIVIENDA CONSTRUCCIONES


UNIVERSIDAD NACIONAL DE CAJAMARCA - SEDE JAÉN
EJE 2-2
COLUMNAS C4 3/8'' 0.86 1 26 22.36 14.56
EJE 3-3 COLUMNAS C1 1/2'' 5.05 3 30 454.5 16.8
EJE 3-3 COLUMNAS C2 3/8'' 0.76 2 30 45.6 16.8
COLUMNAS C1 1/2'' 0.96 3 30 86.4 16.8
EJE 4-4 COLUMNAS C2 3/8'' 0.76 1 30 22.8 16.8
COLUMNAS C4 1/2'' 0.86 1 30 25.8 16.8
EJE 5-5 COLUMNAS C1 3/8'' 0.96 3 30 86.4 16.8
TOTAL 231.84

ING. ABEL RUIZ NAVARRETE METRADO DE UNA VIVIENDA CONSTRUCCIONES


UNIVERSIDAD NACIONAL DE CAJAMARCA - SEDE JAÉN

1''
2.1

ING. ABEL RUIZ NAVARRETE METRADO DE UNA VIVIENDA CONSTRUCCIONES

Anda mungkin juga menyukai