LAPORAN HARIAN SINGKAT OPERASI

DRILLING & WORKOVER PT PERTAMINA EP


11 June 2019 39158
4469
Kepada Yth :
1 Kadiv Survey dan Pemboran SKK Migas
2 Director Operation & Production
3 VP West Area Exploration 9 June 2019
4 VP East Area Exploration
5 VP Exploitation 9 July 2019
6 VP Strategic Planning & Risk Management
7 VP Controller
8 VP Supply Chain Management
9 Asset 1 General Manager
10 Asset 2 General Manager
11 Asset 3 General Manager
12 Asset 4 General Manager
13 Asset 5 General Manager
14 VP Upstream Technology Center
15 Direktur Utama PT. PDSI

No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan


A. EKSPLORASI
1 AMJ-002 Bor 30" @ 50 m - 47 m Anggaran : Geser drilling line 7 m. Test Crown O matic DW OK. Lanjut masuk rangkaian PDC 8-1/2" + BHA DD sampai 1541 m.
Rig : PDSI #42.3/N1500-E H= 30 20" @ 350 m - 349 m $ 14,019,716.00 Sirkulasi. Bor formasi lubang 8-1/2" dari 1541 - 1872 m.
AFE : 19-190-008-OO D= 1872 m 13 3/8" @ 866 m - 852 m Realisasi Anggaran : - Parameter : WOB/GPM/SPP/RPM/RPM-MM/Tq/ROPavg : 3-15 klbs/550-565 gpm/2300-2820 psi/50-80/140-
Rig Rate : Rp 289,750,000 / Day K= 331 m 9 5/8" @ 1540 m - 1537.5 m $ 6,264,074.52 155/2080-6000 lbs.ft/2.21 mpm
Target Operasi Sumur : 7" @ 1470-2125 m %Realisasi - Lithology @ 1872 m : 100% Shale.
Realisasi Pekerjaan Selesai : - BG/MG : 10-30 u / 310 U di 1638 m
Total NPT Rig : Jam - Survey @ 1845.13 mMD/1845.01 mTVD : Inc 1.56 deg, Azm 141.01 deg, C2C 1.08 m.
Co Man : Bastian - Int Sliding : 1763-1770 m.
Co Man : Arief Wahyu W - Swept out hivis di 1638 m, 1753 m, 1840 m.

Status Pagi : Lanjut bor formasi lubang 8-1/2" dari 1872 - 1927 m.
44.68% - Parameter : WOB/GPM/SPP/RPM/RPM-MM/Tq/ROPavg : 6-15 klbs/550-565 gpm/2300-2820 psi/50-90/140-
155/2080-5800 lbs.ft/2 mpm
- Lithology @ 1910 m : 5% Shale, 95% LST.
Tajak : 13 Mei 2019 Jam 00:00 WIB - BG/MG : 10-40 u / 514 U di 1906 m
- Survey @ 1874.3 mMD/1874.20 mTVD : Inc 1.35 deg, Azm 143.66 deg, C2C 0.61 m.
- Int Sliding : 1908-1912 m.

2 MRL-001 R/M (H = 37) : 7 % kumm : 100 %. R/U (H = 1) : 6% kumm : 5 %


Rig : PDSI#01.2/N80B-M Kapal 3 ON WATER tmt. 29 Mei 2019 (pengangkutan peralatan2 tambahan, dll) est. tiba di lokasi MRL-001 13 Juni 2019.

Tanjung Priuk
Kapal 3 ON WATER tmt. 29 Mei 2019 (pengangkutan peralatan2 tambahan, dll) est. tiba di lokasi MRL-001 13 Juni 2019

Marlin (MRL)-001
Kegiatan :
- Gulung Drilling Line
- Gulung sling pancingan driling line ke hospel
- Lanjut pasang accesories menara
- Set gumbo trap
- Pasang tangga mud tank
- Pasang canopy mud hopper
- Lanjut pasang pagar-pagar mud tank ( selesai)
- Pressure test BPM, test 3500 psi
1 unit gate valve 41/16 x 5k ( bocor)
1 unit gate valve 31/8 x 5k ( bocor)
- Pasang tenda porta camp ( potong / sambung tiang tenda)
- Lanjut perbaikan work way shaker

A s s . M a n . D r ill. O p s .
Eksplorasi
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
11 June 2019 39158
4469
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
B ASSET I (FIELD Rantau, FIELD P. Susu, FIELD Jambi, FIELD Lirik, FIELD Ramba)
FIELD RAMBA
1 MJ-INF07 R/U (H:9) = 2%, Kumm R/U = 90%.
Rig : PDSI #17.2/NT45-M. Endurance test: Bor formasi lubang 12-1/4" sampai 81 m. Trip. Masuk casing 9-5/8" sampai 80 m. Masuk rangkaian
tubing poorboy sampai 74 m. Penyemenan casing 9-5/8", cabut poorboy tubing. TSK sambil S/U DP.
Co Man : Hari S / Zamhir I

FIELD RANTAU
2 KSB-060 (KSB-C9) Bor Anggaran : Lanjut masuk casing 7" dari 204 mMD sampai 1201 mMD. Sirkulasi kondisikan lumpur. Penyemenan casing 7",
Rig : PDSI #23.1/CWKT-210 M. H= 19 $ 2,323,939.00 keluar kontaminasi semen SG 1,46, bumping pressure 2000 psi.
AFE : D= 1202 m Realisasi Anggaran :
Rig Rate : / Day K= m $ 1,413,528.35 Status Pagi : TSK sambil persiapan BOP job.
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Freddy Haryo
60.82%
Co Man : Wahyu Berbudi

Tajak : 24 Mei 2019 Jam 12:00 WIB

A s s . M a n . D r ill. O p s .
Asset I
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
11 June 2019 39158
4469
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
C ASSET II
FIELD PRABUMULIH
1 TLJ-247 (TLJ-B31) Bor 30" @ 40 m - 40 m Anggaran : Penyemenan Liner 7” dengan pompakan 98 bbls Lead Slurry SG 1.62 dan 33 bbls Tail Slurry SG 1.90. Drop DPWP.
Rig : PDSI#29.3/D1500-E H= 33 20" @ 265 m - 263 m $ 4,145,514.00 Displace dengan 192 bbls sampai bumping 1600 psi, hold 5’, Ok. Ablas tekanan, aliran balik 1 bbl, Ok. Selama
AFE : 19-190-409-OO D= 2328 m 13 3/8" @ 550 m - 552.81 m Realisasi Anggaran : penyemenan aliran balik normal. Set Liner Packer, Ok. Reverse out circulation, keluar 10 bbls Slurry semen SG 1.50.
Rig Rate : US $ 24,575.25 / Day K= m 9 5/8" @ 1510 m - 1517.5 m $ 3,367,253.00 Cabut DP 5” penghantar + running tool sambil L/D 120 jts DP 5”. L/D 21 jts HWDP 5” dan 6 jts DC 6-1/4”. Masuk TCB
Target Operasi Sumur : 7" @ 2328 m - 2326 m %Realisasi 6” + Scraper 7” + Tubing 2-7/8” (joint per joint) + DP 5” sampai 327 m.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam Status pagi : Sedang lanjut masuk TCB 6” + Scraper 7” + Tubing 2-7/8” (joint per joint) + DP 5” sampai 905 mMD.
Co Man : Jhonny AH 81.23%

Tajak : 10 Mei 2019 Jam 02:00 WIB

A s s . M a n . D r ill. O p s .
Asset II
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
11 June 2019 39158
4469
No Sumur Pekerjaan Target / Realisasi Kegiatan
D ASSET III
1 MLD-010 (MLD-B3) Bor Lapisan TAF-3.2 & TAF-5 Anggaran : Korelasi. Set Hydraulic Packer 7". Test packer, baik. N/D BOP. N/U X-tree.
Rig : PDSI#12.3/N110-M H= 56 30" @ 40 m - 40 m $ 7,535,581.00
AFE : 19-190-409-OO D= 3126 m 20" @ 350 m - 348 m Realisasi Anggaran : Status pagi : Pasang line produksi. Sedang masuk CT sampai 680 m.
Rig Rate : Rp 465,040,950 / Day K= m 13 3/8" @ 1350 m - 1348 m $ 6,533,422.39
Target Operasi Sumur : 9 5/8" @ 2548 m - 2521 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 3105 m - 2450-3124 m
Total NPT Rig : Jam
Co Man : Bambang H 86.70%

Tajak : 17 April 2019 Jam 18:00 WIB


2 JAS-014 (JAS-A4) Bor Lapisan BRF Anggaran : Logging run#3 : RDT (14 titik). Masuk liner 7" sampai 505 m.
Rig : PDSI #15.3/N110-M H= 45 30" @ 40 m - 41 m $ 7,785,853.00
AFE : 19-190-785-OO D= 3260 m 20" @ 350 m - 349 m Realisasi Anggaran : Status pagi : Sedang masuk liner 7" sampai 1185 m.
Rig Rate : / Day K= m 13 3/8" @ 1575 m - 1550 m $ 5,684,155.37
Target Operasi Sumur : 9 5/8" @ 2802 m - 2851 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 3207 m
Total NPT Rig : Jam
Co Man : Mustafa S
Co Man : Jovie Y 73.01%
Co Man : Atok I

Tajak : 28 April 2019 Jam 18:00 WIB


3 ABG-007 (ABG-B3) Bor Lapisan L Anggaran : Bleed off pressure inside casing 13-3/8" dari 450-0 psi, check LEL 0. Buka annulus, check LEL 0. Observasi terbuka,
Rig : PDSI #38.2/D1000E H= 16 30" @ 50 m - 48 m $ 4,612,504.00 statik. Sax job. Las ring plate.
AFE : 19-190-807-OO D= 1200 m 20" @ 350 m - 348 m Realisasi Anggaran :
Rig Rate : / Day K= m 13 3/8" @ 1200 m - 1199 m $ 2,295,246.15 Status pagi : N/D diverter 21-1/4". Sedang final cut csg 13-3/8".
Target Operasi Sumur : 9 5/8" @ 2147.78 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 2358.22 m
Total NPT Rig : Jam
Co Man : Eko Agustian
49.76%
Co Man : Tunjung W

Tajak : 27 Mei 2019 Jam 15:00 WIB


4 JAS-007 WO Anggaran : Lanjut masuk ESP sampai 1304 m. Pressure tes tubing 500 psi pressure turun. Cabut ESP sampai 852 m, ditemukan
Rig : PDSI#25.2/LTO-750M H= 16 $ 613,150.00 kebocoran pada coupling hydrotest. Masuk kembali ESP sampai 942 m.
Co Man : Bima Andeka Realisasi Anggaran :
$ 509,492.04 Status pagi : Sedang lanjut masuk ESP sampai 1304 m.
%Realisasi
Mulai Operasi : 27 Mei 2019 Jam 09:00 WIB 83.09%
5 KRT-001 WO Anggaran : Lanjut killing, pompa kum 35.4 bbls, pump pressure 600-1500 psi, annulus pressure naik 0-220 psi (ada komunikasi
Rig : PDSI #32.2/N80UE H= 11 $ 2,454,399.00 string dan annulus). Sirkulasi kondisikan lumpur SG in/out : 1.34/1.34. Cek leaking komunikasi dengan pompa cycle
Co Man : Wihandono/Joko P Realisasi Anggaran : hivis, est tbg leak di 1024 m. Observasi, sumur statik. Masuk chemical cutter#2. Potong tubing 2280 m, fired.
$ 562,826.59
%Realisasi Status pagi : Sirkulasi SG in/out 1.45. Sedang coba angkat RPP dengan tension 155 klbs, belum ada progress.

Mulai Operasi : 01 Juni 2019 Jam 08:00 WIB 22.93%

6 JAS-013 (JAS-D3) R/D rig (H-4) : 100%.


Rig : D1500-E Maintenance rig (H-1)
Co Man : Peter B

A s s . M a n . D r il l. O p s .
Asset III
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
11 June 2019 39158
4469
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
E ASSET IV
FIELD CEPU
1 NGL-P03 WO Anggaran : Lanjut milling CR 7" dari 1019.20-1020 m, Dorong CR 7" spi 1181 m (tidak ada kemajuan), Sirkulasi sweep hivis,
Rig : H35-M (UY6) H= 10 $ 771,227.00 Cabut wash over shoe+junk sub (Hasil 3 kg serpihan metal), Masuk rangk OE DP 3.1/2" spi 1035 m, Sirkulasi (loss
Co Man : Toto S / Giat P Realisasi Anggaran : din/stat 0.5/0.2 bpm), Cement squeeze plug job int perfo 1027-1022 m & 1016-1011 m dengan 10 bbls cement slurry,
$ 186,826.00 Cabut OE DP spi 760 m, Cement squeeze plug job Int 753-748 m, 667-663 m & 660-656 m dgn 25 bbls cement
%Realisasi slurry, TSK vacum.

Mulai Operasi : 02 Juni 2019 Jam 06:00 WIB 24.22% Status Pagi : TSK Vacum, Observasi loss (no loss), Sirkulasi (no loss).

A s s . M a n . D r ill. O p s .
Asset IV
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
11 June 2019 39158
4469
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
F ASSET V
FIELD BUNYU
1 B-197 (B-1810) Bor Anggaran : Lanjut penyemenan top job. Gantung diverter. Potong & L/D casing 13-3/8”. N/D diverter. N/U wellhead section A 13-
Rig : PDSI #09.2/N80UE H= 6 $ 3,707,690.00 5/8" x 3 kpsi (welded). N/U BOP Group 13-5/8" x 5000 psi.
AFE : D= 544 m Realisasi Anggaran :
Rig Rate : /Day K= m $ 1,217,162.69 Status pagi : Lanjut N/U BOP Group 13-5/8" x 5000 psi.
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Obi B 32.83%

Tajak : 06 Juni 2019 Jam 18:00 WITA


2 B-1913B MIRU : H-15
Rig : PDSI #11.2/N80B-M R/M Rig kum 100%. R/U Rig kum 80%.
Endurance test TMT 11 Juni 2019 pukul 20.30 WITA. Bor lubang 26" dengan TCB 26" NB Varrel + BHA Rotary
Co Man : Anwar S / Wingsang U sampai 46 m (casing point 20”). Round trip.

3 B-1813 R/M Rig H-10 : Kum 44%


Rig : PDSI #04.3/N-110M1 (1500 HP)
FIELD TARAKAN
4 SBK-77 (SBK-PSE) Bor 20" @ 40 m - 40 m Anggaran : Lanjut masuk pahat PDC 8-1/2" + Rotary Pendulum BHA dari 360 mMD sampai 1703 mMD. Sirkulasi bersih. Cabut
Rig : PDSI#18.2/LTO650-M H= 23 13 3/8" @ 200 m - 204 m $ 2,874,635.00 normal pahat PDC 8-1/2" + BHA Rotary dari 1703 mMD sampai permukaan. Masuk rangkaian casing Liner 7" (K-55,
AFE : 19-190-732-OO D= 1703 m 9 5/8" @ 700 m - 701 m Realisasi Anggaran : 26 ppf, BTC, R3 & R2) sampai 531 mMD.
Rig Rate : US$ 17,163.00 /Day K= m 7" @ 630-1682 m $ 2,139,720.63
Target Operasi Sumur : %Realisasi Status pagi : Lanjut masuk rangkaian casing Liner 7" (K-55, 26 ppf, BTC, R3 & R2) dari 531 mMD sampai 969 mMD.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Sahat N / Arde Gunawan 74.43%

Tajak : 20 Mei 2019 Jam 17:00 WITA


FIELD SANGATTA
5 H-12 : Tunggu lokasi ST-E13.
Rig : PDSI #10.2/D700-M
FIELD SANGASANGA
6 SBJ-337 (SBJ-P20) Bor Anggaran : Squeeze cementing job. Hesitation squeeze 8 bbls. TSK. Cabut ROE DP 5” sampai permukaan. Masuk TCB 8-1/2”
Rig : PDSI #22.2/OW700/40 H= 28 $ 2,907,031.00 sampai 225 m.
AFE : D= 1750 m Realisasi Anggaran :
Rig Rate : /Day K= m $ 2,361,107.38 Status pagi : Lanjut masuk TCB 8-1/2” sampai jajak TOC di 270 m. Sirkulasi. Test casing 1000 psi, baik. M/U Kelly.
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Suparkat 81.22%

Tajak : 15 Mei 2019 Jam 21:00 WITA


7 Persiapan R/M ke lokasi SBR-C8.
R/M H-1 : Armada moving terkendala banjir di derah PM. Noor Samarinda, sehingga armada moving tidak bisa
Rig : PDSI #21.2/OW700-M melewati zona banjir tersebut.

A s s . M a n . D r ill. O p s .
Asset V
E k s p lo r a s i

Jakarta, 12 Juni 2019


VP Drilling & Workover,

Pranefo Maaruf