LAPORAN HARIAN SINGKAT OPERASI

DRILLING & WORKOVER PT PERTAMINA EP


27 May 2019 39158
4454
Kepada Yth :
1 Kadiv Survey dan Pemboran SKK Migas
2 Director Operation & Production
3 VP West Area Exploration 25 May 2019
4 VP East Area Exploration
5 VP Exploitation 24 June 2019
6 VP Strategic Planning & Risk Management
7 VP Controller
8 VP Supply Chain Management
9 Asset 1 General Manager
10 Asset 2 General Manager
11 Asset 3 General Manager
12 Asset 4 General Manager
13 Asset 5 General Manager
14 VP Upstream Technology Center
15 Direktur Utama PT. PDSI

No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan


A. EKSPLORASI
1 AMJ-002 Bor 30" @ 50 m - 47 m Anggaran : Lanjut bor semen dan R shoe dari 849 m sampai 854.7 m. ROP lambat, Cek Sample cutting di 854.7 m di dapat
Rig : PDSI #42.3/N1500-E H= 15 20" @ 350 m - 349 m $ 14,019,716.00 100% formasi. Tidak didapat kemajuan dgn DOT Diputuskan cabut ke permukaan.
AFE : 19-190-008-OO D= 854 m 13 3/8" @ 866 m - 852 m Realisasi Anggaran : - Parameter : WOB/MFI/SPP/RPM/Tq/ROPavg :4-20 klbs/385-700 gpm/370-1130 psi/10-50/970-2500 lbs.ft/48 mpm
Rig Rate : Rp 289,750,000 / Day K= 0 m 9 5/8" @ 1540 m $ 4,842,069.15 - Sweepout Hivis 30 bbls @ 854 m
Target Operasi Sumur : 7" @ 1470-2125 m %Realisasi - Sample cutting 100% formasi @ 854.7 m : 30% MARL, 70% SHALE
Realisasi Pekerjaan Selesai : Cabut rangkaian TCB 12-1/4" + BHA Rotary sampai permukaan.
Total NPT Rig : Jam - Dull Grading : 1-1-WT-A-E-I-CT-BHA.
Co Man : Bastian - Flow check, baik.
Persiapan M/U rangkaian PDC 12-1/4" NB + BHA DD. M/U dan masuk rangkaian PDC 12-1/4" NB (Baker, tipe
TD506, S/N 5280107, TFA 1.243 in2) + BHA DD (9-1/2" MM + 8-1/4" FS + 12-1/4" UG Stab + 8-1/2" NMDC + 8-1/2"
MWD Slimpulse + 8-1/2" NMDC + 8-1/4" PBL Sub + 4 jts DC 8" + 8" Jar + 4 jts DC 8" + X/O 6-5/8" Reg x 4-1/2" IF +
15 jts HWDP 5") dari permukaan sampai 124 m.
34.54%
- Test PBL tools di permukaan baik.

Tajak : 13 Mei 2019 Jam 00:00 WIB Status Pagi : Lanjut masuk rangkaian PDC 12-1/4" + BHA DD dari 124 m sampai 854 m.
- Shallow test di 178 m, OK.
- Stab in RCD bearing di 807 m.

2 MRL-001 Rig Move (H = 23) : 0 %, Kum : 61 %


Rig : PDSI#01.2/N80B-M Move Out (RWG-001) : 100 %
Move In (MRL-001) : 0 % ; kum : 86 %

Kegiatan :

Jakarta
Tunggu jadwal pemberangkatan kapal dari Pelabuhan Tanjung Priok ke Pelabuhan Banjarmasin untuk pengangkutan
peralatan tambahan (est 29 Mei 2019).

Banjarmasin
- M/O : 3 load ; kum : 138 load
- M/I (MRL-001) : 16 load ; kum : 129 load
- Kapal / Barge 2 sandar di dermaga tgl. 23 Mei 2019 pkl. 15.00 WIB.
- Kapal / Barge 1 selesai bongkar tgl. 20 Mei 2019

A s s . M a n . D r ill. O p s .
Eksplorasi
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
B ASSET I (FIELD Rantau, FIELD P. Susu, FIELD Jambi, FIELD Lirik, FIELD Ramba)
FIELD RAMBA
1 Rig Maintenance (H:1)
- Persiapan rig move ke lokasi MJ-INF07
Rig : PDSI #17.2/NT45-M.
FIELD RANTAU
2 KSB-060 (KSB-C9) Bor Anggaran : Lanjut pendinginan hasil pengelasan. NDT hasil pengelasan, baik. N/U BOP 13-5/8” x 3000 psi. Function Test dan
Rig : PDSI #23.1/CWKT-210 M. H= 4 $ 2,323,939.00 Pressure test BOP 13-5/8” x 3000 psi dengan tekanan 500 psib(low)/5 mnt & 2500 psi (high)/5 mnt, baik. M/U dan
AFE : D= 127 m Realisasi Anggaran : Masuk rangkaian PDC bit 12 1/4" (RR) + BHA rotary sampai 112 m, duduk 5 klbs (TOC). Sirkulasi. Pressure test
Rig Rate : / Day K= 2 m $ 633,377.98 casing 500 psi/5 mnt, baik. Bor semen dari 112 m sampai 127 m (2 m formasi baru).
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai : Status Pagi : Sirkulasi bersih & cek cutting @127 m, cutting 100% formasi baru (CLST 70% + SST 30%). MOT
Total NPT Rig : Jam dengan MW 1.06 SG, pressure permukaan 90 psi, EMW 1.5 SG. Run Gyro survey. Cabut rangkaian pahat PDC 12-
Co Man : Wahyu Berbudi L 1/4" + BHA Rotary dari 127 m sampai permukaan.
27.25%

Tajak : 24 Mei 2019 Jam 12:00 WIB

A s s . M a n . D r ill. O p s .
Asset I
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
C ASSET II
FIELD PRABUMULIH
1 TLJ-247 (TLJ-B31) Bor 30" @ 40 m - 40 m Anggaran : Lanjut bor berarah lubang 12-1/4" dari 1338 – 1519 mMD (Casing Point 9-5/8”). Sirkulasi bersih. Cabut PDC 12-1/4”
Rig : PDSI#29.3/D1500-E H= 18 20" @ 265 m - 263 m $ 4,145,514.00 + BHA DD dari 1519 – 902 mMD
AFE : 19-190-409-OO D= 1519 m 13 3/8" @ 550 m - 552.81 m Realisasi Anggaran :
Rig Rate : US $ 24,575.25 / Day K= 181 m 9 5/8" @ 1510 m $ 2,412,717.92 Status Pagi : Lanjut cabut PDC 12-1/4” + BHA DD dari 902 – 728 mMD.
Target Operasi Sumur : 7" @ 2328 m %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Jhonny AH
58.20%
Co Man : Ariefandin H

Tajak : 10 Mei 2019 Jam 02:00 WIB


FIELD LIMAU
2 BEL-033A WO Anggaran : Observasi tertutup. Pcsg / Ptbg = 0 psi. Swab job, lapisan R7 & R8 (interval 1461-1464 & 1470-1472 m), 33x swab
Rig : PDSI #.46.1 H= 18 $ 397,058.00 run/Cumm : 59x swab run. Total fluid recovery 15.8 bbls/Cumm. 39.97 bbls. String volume : 27.8 bbls.
Co Man : Joko P Realisasi Anggaran : Masuk EMR spi 1456 m. Shut in well. Rendam EMR. Observasi surface Pressure SITP/SICP: 120 psi/0 psi
Co Man : Yoga $ 240,384.54
%Realisasi Status Pagi : Lanjut rendam EMR. SITP/SICP: 130 psi/0 psi
Mulai Operasi : 10 Mei 2019 Jam 12:00 WIB 60.54%
3 BED-01 WO Anggaran : Bor Semen dari 1456 - 1518 m, blong. Test Casing 500 psi/5 mnt, Ok. Lanjut Masuk TCB 8-1/2" + BHA Rotary dr
Rig : PDSI#20.2/EMSCO D2 H= 16 $ 4,854,894.00 1518 - 1850 m. Sirkulasi bersih. Cabut TCB 8-1/2" spi 157 m.
Co Man : Bima Andeka Realisasi Anggaran :
Co Man : Hafrinaldo $ 5,616,878.00 Status Pagi : Cabut TCB 8-1/2" spi permukaan. Masuk Scraper 9-5/8" spi 953 m.
%Realisasi
Mulai Operasi : 12 Mei 2019 Jam 10:00 WIB 115.70%

A s s . M a n . D r ill. O p s .
Asset II
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
No Sumur Pekerjaan Target / Realisasi Kegiatan
D ASSET III
1 JAS-013 (JAS-D3) Bor Lapisan BRF Anggaran : Lanjut cabut tandem scraper. Cased hole logging 9-5/8" GR-CBL-CAST intv 1500-2736 m, hasil CBL pada rencana
Rig : D1500-E H= 56 30" @ 40 m - 40 m $ 7,591,204.00 intv perforasi 40 mV. Cased hole logging 7" GR-CBL-CAST. L/D tubular.
AFE : 19-190-786-OO D= 3190 m 20" @ 350 m - 349 m Realisasi Anggaran :
Rig Rate : / Day K= m 13 3/8" @ 1527 m - 1511 m $ 5,995,072.96 Status pagi : Lanjut L/D tubular.
Target Operasi Sumur : 9 5/8" @ 2800 m - 2796 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 3190 m - 3184 m
Total NPT Rig : Jam
Co Man : Peter B 78.97%

Tajak : 02 April 2019 Jam 04:30 WIB


2 MLD-010 (MLD-B3) Bor Lapisan TAF-3.2 & TAF-5 Anggaran : Lanjut bor lubang 8-1/2" sampai 3024 m.
Rig : PDSI#12.3/N110-M H= 41 30" @ 40 m - 40 m $ 7,535,581.00
AFE : 19-190-409-OO D= 3040 m 20" @ 350 m - 348 m Realisasi Anggaran : Status pagi : Sedang lanjut bor sampai 3040 m.
Rig Rate : Rp 465,040,950 / Day K= 59 m 13 3/8" @ 1350 m - 1348 m $ 5,390,381.00
Target Operasi Sumur : 9 5/8" @ 2548 m - 2521 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 3105 m
Total NPT Rig : Jam
Co Man : Warnandes AM
71.53%
Co Man : Arif RH

Tajak : 17 April 2019 Jam 18:00 WIB


3 JAS-014 (JAS-A4) Bor Lapisan BRF Anggaran : Lanjut masuk BHA Trip sampai 2854 m (reaming kondisikan lubang intv 2657-2686 m & 2843-2854 m). Sirkulasi.
Rig : PDSI #15.3/N110-M H= 30 30" @ 40 m - 41 m $ 7,785,853.00 Sedang cabut BHA Trip sampai 1054 m.
AFE : 19-190-785-OO D= 2854 m 20" @ 350 m - 349 m Realisasi Anggaran :
Rig Rate : / Day K= 0 m 13 3/8" @ 1575 m - 1550 m $ 4,117,762.53 Status pagi : Lanjut cabut BHA Trip sampai permukaan. Sedang RU wireline.
Target Operasi Sumur : 9 5/8" @ 2802 m %Realisasi
Realisasi Pekerjaan Selesai : 7" @ 3207 m
Total NPT Rig : Jam
Co Man : Jovie Y
52.89%

Tajak : 28 April 2019 Jam 18:00 WIB


4 ABG-007 (ABG-B3) Bor Anggaran : R/U (H-13) : 100%. Tajak Lokasi ABG-B3 sebagai Sumur ABG-007 tmt 27 Mei 2019 Pukul 15.00 WIB . Bor
Rig : PDSI #38.2/D1000E H= 1 $ 4,612,504.00 lubang 26" sampai 150 m.
AFE : 19-190-785-OO D= 182 m Realisasi Anggaran :
Rig Rate : / Day K= 112 m $ 937,093.16 Status pagi : Sedang lanjut bor sampai 182 m.
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Deddy N
20.32%

Tajak : 27 Mei 2019 Jam 15:00 WIB


5 JAS-007 WO Anggaran : R/U (H-7) : 100%. Rig PDSI#25.2/LTO-750-M dinyatakan mulai operasi tmt 27 Mei 2019 pukul 09.00 WIB. Ablas
Rig : PDSI#25.2/LTO-750M H= 1 $ 613,150.00 tekanan casing dan tubing. Fill up sumur. Observasi terbuka. N/D X-tree. N/D THS. BOP job.
Co Man : Nurdiansyah Realisasi Anggaran :
$ 148,557.46 Status pagi : Sedang lanjut BOP job.
%Realisasi
Mulai Operasi : 27 Mei 2019 Jam 09:00 WIB 24.23%
6 KRT-001 WO R/U (H-1) : 25%.
Rig : PDSI #32.2/N80UE

A s s . M a n . D r il l. O p s .
Asset III
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
E ASSET IV
FIELD CEPU
1 NGL-P03 R/M H-1 : Move out dari lok NGL-P2 (8 trip/27%), Move in di lok NGL-P3 (8 trip/27%)
Rig : H35-M (UY6)
Co Man : Eko A
A s s . M a n . D r ill. O p s .
Asset IV
E k s p lo r a s i

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
No Sumur Pekerjaan Target / Realisasi Biaya / Realisasi Kegiatan
F ASSET V
FIELD BUNYU
1 B-196 (B-1806) Bor Anggaran : Lanjut cabut scrapper 9-5/8” sampai 430 m. UTS dengan 400 Psi turun ke 240 Psi, stabil. Lanjut cabut scrapper 9-
Rig : PDSI #04.3/N-110M1 (1500 HP) H= 36 $ 3,663,696.00 5/8” sampai permukaan. CH Logging 9-5/8” : USIT-CCL-VDL-GR. Perforasi lapisan C-70 int 545-547 mMD dengan
AFE : D= 2700 m Realisasi Anggaran : Enerjet 2-1/8" - 6 spf, 40ea meledak. Masuk RPP (9-5/8” Packer + 3 KSB + Tubing 2-7/8”) sampai 195 mMD.
Rig Rate : /Day K= 0 m $ 3,177,231.00
Target Operasi Sumur : %Realisasi Status Pagi : Lanjut Masuk RPP sampai UR di 534 mMD, Set Packer 9-5/8” di 514 mMD.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Obi B
86.72%
Co Man : Wingsang U

Tajak : 22 April 2019 Jam 21:00 WITA


2 B-1810 R/U Rig H-26 : Kum 49%. Sedang pasang Sheave Wheel di A-Frame dan pasang Raising Line di DS dan ODS.
Rig : PDSI #09.2/N80UE
Co Man : I Made Arisudana
3 BN-56 (B-1815) R/D H-6 : kum 90 %.
Rig : PDSI #11.2/N80B-M
Co Man : Anwar S
FIELD TARAKAN
4 SBK-77 (SBK-PSE) Bor 20" @ 40 m - 40 m Anggaran : OH Logging 12-1/4" Run#2 : FMI-GR, duduk di 550 mMD. Logging dari 550 - 204 m (J-type max sudut 50 derajat).
Rig : PDSI#18.2/LTO650-M H= 8 13 3/8" @ 200 m - 204 m $ 2,874,635.00 Masuk PDC 12-1/4" RR + BHA Trip, sampai 703 mMD. Sirkulasi. Cabut PDC 12-1/4"+BHA trip sampai permukaan.
AFE : 19-190-732-OO D= 703 m 9 5/8" @ 700 m Realisasi Anggaran : OH Logging 12-1/4” Re-run#2 : FMI-GR int 645 - 550 m. R/U CDS. Masuk Casing 9-5/8” sampai 12 m.
Rig Rate : US$ 17,163.00 /Day K= m 7" @ 630-1682 m $ 1,222,178.88
Target Operasi Sumur : %Realisasi Status Pagi : Lanjut masuk Casing 9-5/8” sampai 600 mMD.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Imam A
42.52%

Tajak : 20 Mei 2019 Jam 17:00 WITA


FIELD SANGATTA
5 ST-194 (ST-D12) Bor 20" @ 80 m - 83 m Anggaran : Lanjut Masuk kembali RPP sampai UR di 1083 m. N/D BOP Group 13-5/8" x 5K. N/U dan Pressure Test X-mass
Rig : PDSI #10.2/D700-M H= 32 13 3/8" @ 300 m - 299 m $ 3,945,593.00 Tree 3-1/8" x 2-1/16" x 5000 psi. Swab Job di Lapisan P-4 interval 1089-1091 m. Uji Produksi Gross/Nett/Gas/WC/:
AFE : 16-190-661-OO D= 1725 m 9 5/8" @ 1000 m - 1006.4 m Realisasi Anggaran : 940 BLPD/917 BOPD/254.2 MSCFD/2.4%. Pcs/Ptb/Pfl/P Sep: 400 psi/480 psi/70 psi/20 psi. L/D DP 3-1/2” dan DP
Rig Rate : US$ 15,693.00 /Day K= 0 m 7" @ 1725 m - 950-1723 m $ 2,481,886.95 5”. Rig dinyatakan Released T.M.T 27 Mei 2019 pukul 24.00 WITA dan sumur ST-194 dinyatakan sebagai
Target Operasi Sumur : %Realisasi Sumur Penghasil Minyak pada Lapisan P4 interval 1089-1091 m.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam Status Pagi : Persiapan R/D Rig PDSI #10.2/D700-M.
Co Man : Fiaribowo
62.90%
Co Man : Zamhir Islamie

Tajak : 26 April 2019 Jam 00:00 WITA

 
LAPORAN HARIAN SINGKAT OPERASI
DRILLING & WORKOVER PT PERTAMINA EP
27 May 2019 39158
4454
FIELD SANGASANGA
6 NKL-1111 (NKL-P1712) Bor Anggaran : OH Logging 8-1/2" Run #3: RDT-FLID-ICS-GR (10/16 Titik), powering tools RDT Rusak. Ganti dengan Back Up
Rig : PDSI #21.2/OW700-M H= 18 $ 3,193,463.00 (NPT Wireline 5 jam). Lanjut Run #3: RDT-FLID-ICS-GR (25 titik Pressure Test, 5 titik LFA). Masuk PDC 8-1/2"
AFE : D= 1712 m Realisasi Anggaran : (RR) + BHA trip sampai 284 m.
Rig Rate : /Day K= m $ 2,148,148.18
Target Operasi Sumur : %Realisasi Status Pagi : Lanjut Masuk PDC 8-1/2" (RR) + BHA trip sampai 1550 m.
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Tunjung WK
67.27%

Tajak : 10 Mei 2019 Jam 16:00 WITA


7 SBJ-337 (SBJ-P20) Bor Anggaran : Lanjut masuk casing 9-5/8” sampai 1043 m. Sirkulasi. Penyemenan Casing 9-5/8” (100% Excess), Bumped Plug di
Rig : PDSI #22.2/OW700/40 H= 13 $ 2,907,031.00 1500 Psi, 10 Bbls Semen SG 1.50 sampai permukaan. TSK.
AFE : D= 1048 m Realisasi Anggaran :
Rig Rate : /Day K= m $ 1,587,002.88 Status Pagi : Lanjut TSK. Persiapan Gantung BOP 13-5/8”x5K
Target Operasi Sumur : %Realisasi
Realisasi Pekerjaan Selesai :
Total NPT Rig : Jam
Co Man : Suparkat
54.59%
Co Man : Ariesta F

Tajak : 15 Mei 2019 Jam 21:00 WITA


A s s . M a n . D r ill. O p s .
Asset V
E k s p lo r a s i

Jakarta, 28 Mei 2019


Pjs. VP Drilling & Workover,

Sugeng Prayitno