REKAPITULASI

KEGIATAN : PEMBANGUNAN KLINIK BERSALIN


PAKET KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
LOKASI : KELURAHAN SEBENGKOK

JUMLAH
NO. URAIAN PEKERJAAN HARGA
( Rp )

I PEKERJAAN PENDAHULUAN Rp. 6,033,408.00


II PEKERJAAN TANAH Rp. 13,705,989.95
III PEKERJAAN PONDASI DAN TIANG PANCANG Rp. 119,727,089.06
IV PEKERJAAN STRUKTUR BETON BERTULANG Rp. 362,972,561.56
V PEKERJAAN DINDING Rp. 116,998,312.72
VI PEKERJAAN LANTAI Rp. 96,461,439.97
VII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp. 124,531,704.28
VIII PEKERJAAN RANGKA KAP ATAP Rp. 94,486,402.18
IX PEKERJAAN PLAFOND Rp. 51,196,680.00
X PEKERJAAN INSTALASI LISTRIK Rp. 56,400,000.00
XI PEKERJAAN KUNCI DAN PENGGANTUNG Rp. 12,166,800.00
XII PEKERJAAN PENGECATAN Rp. 34,131,335.82
XIII PEKERJAAN SANITAIR Rp. 21,090,500.00
XIV PEKERJAAN SEPTIC TANK 2. BH Rp. 5,999,360.48
XV PEKERJAAN LAIN - LAIN Rp. 20,769,770.14
A. JUMLAH ( I + II + ……. + XV ) Rp. 1,115,901,584.01
B IJIN MENDIRIKAN BANGUNAN ( IMB ) Rp. 500,000.00
C. JAMINAN SOSIAL DAN TENAGA KERJA SEKTOR KONSTRUKSI Rp. 1,889,081.90
D. PPN 10% Rp. 111,590,158.40
E JUMLAH Rp. 1,229,880,824.31
F DIBULATKAN Rp. 1,229,880,000.00

Terbilang : //

Tarakan, Januari 2012

Dibuat Oleh
Konsultan Perencana
CV. SANINDO ANDAL KONSULTAN

H. Iskandar, AP, S.T


Direktur
ENGINEER ESTIMATE
(E-E)
KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
PAKET KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
LOKASI : KELURAHAN SEBENGKOK

VOLUME HARGA JUMLAH


NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
2 Pemasangan Bowplank 68.00 m1 49,756.00 3,383,408.00
3 Pemasangan Plank Nama Proyek ( Digital Print) 1.00 bh 150,000.00 150,000.00
4 Foto dokumentasi 1.00 ls 1,500,000.00 1,500,000.00
Jumlah - I 6,033,408.00
II PEKERJAAN TANAH
1 Buangan tanah Galian 68.00 m3 60,376.00 4,105,568.00
2 Galian Tanah Pondasi 40.97 m3 45,300.00 1,855,714.50
3 Urugan Tanah Kembali 8.19 m 3
22,650.00 185,571.45
4 Urugan Tanah Bawah Lantai 78.00 m 3
87,720.00 6,842,160.00
5 Urugan Pasir Bawah Lantai 7.80 m3 91,920.00 716,976.00
Jumlah - II 13,705,989.95
III PEKERJAAN PONDASI DAN TIANG PANCANG
1 Pengadaan Pancang Mini Pile 20/20 K - 300, P : 4 m 98.00 Btg 650,000.00 63,700,000.00
- Pemancangan tiang pancang 98.00 Bh 50,000.00 4,900,000.00
- Penyambungan tiang pancang 54.00 Ttk 25,000.00 4,900,000.00
- Potong Kepala Tiang pancang 54.00 Ttk 40,000.00 1,350,000.00
2 Cor lantai Kerja tebal 3 cm K-125 1.20 m3 830,605.37 995,480.54
3 Cor beton Poer P1 (150x150x40) K-225 9.90 m 3
4,143,868.06 41,024,293.81
4 Pancang Ulin 10/10 -2 M 0.16 m3 5,895,000.00 943,200.00
5 Pas. Pondasi Batu Gunung 2.28 m 3
839,524.00 1,914,114.72
Jumlah - III 119,727,089.06
IV PEKERJAAN STRUKTUR BETON BERTULANG
1 Cor Sloof 30/50 cm K-225 9.48 m3 4,428,635.74 41,983,466.80
2 Cor Sloof 20/35 cm K-225 1.12 m3 5,433,589.85 6,085,620.63
3 Cor Sloof 10/ 20 cm k-225 0.40 m 3
6,975,181.82 2,790,072.73
4 Cor Letai 10/15 cm k-225 L : 1 dan 2 1.32 m3 6,975,181.82 9,207,240.00
5 Cor Beton K1 30/30 cm K-225. L. 1 3.96 m 3
6,342,666.11 25,116,957.80
6 Cor Beton K1 30/30 cm K-225. L. 2 3.96 m 3
6,342,666.11 25,116,957.80
7 Cor Beton K2 20/20 cm K-225 (Teras ) 0.80 m3 9,568,647.57 7,654,918.06
8 Cor Beton K1 10/10 cm K-225 ( Praktis ) L : 1 dan 2 1.54 m 3
9,921,894.10 15,230,107.44
9 Cor Beton Balok B1 (30/45 cm) K-225 7.52 m3 7,536,774.58 56,706,691.93
10 Cor Beton Balok B2 (20/35 cm) K-225 2.30 m 3
5,244,808.35 12,063,059.20
11 Cor Beton Balok Ring balk B1 (20/30 cm) K-225 2.52 m3 5,850,957.74 14,744,413.51
12 Cor Beton Balok Ring balk B2 (15/20 cm) K-225 0.66 m 3
8,551,356.19 5,643,895.08
13 Cor Beton Plat lantai t = 12 cm K-225 15.20 m 3
5,227,117.07 79,466,815.42
14 Cor Beton Plat Dak Atap t= 10 cm K-225 2.55 m3 6,058,771.02 15,463,498.34
15 Cor Beton Balok Dak Atap BD (25/40 cm) K-225 1.20 m 3
5,476,036.49 6,571,243.79
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
16 Cor Beton balok tangga 20/30 cm K-225 0.36 m 3
9,568,647.57 3,444,713.13
17 Cor Beton plat tangga t=10 cm K-225 0.98 m3 5,552,232.05 5,413,426.25
18 Cor Beton plat bordes t = 10 cm K-225 0.23 m 3
5,552,232.05 1,249,252.21
19 Cor Beton anak tangga K-225 1.68 m 3
2,119,448.43 3,567,031.71
20 Cor Kanopy Beton tebal 7 cm K-225 2.45 m3 7,422,474.57 18,148,692.57
21 Cor Beton Balok Kenopi (10/20 cm) K-225 1.00 m3 7,319,125.41 7,304,487.16
Jumlah - IV 362,972,561.56
V PEKERJAAN DINDING
1 Pasangan Dinding Bata 1 : 4 59.65 m3 968,372.20 57,764,370.10
2 Plesteran Dinding 1 : 4 + Acian 1,193.02 m 2
48,546.33 57,916,742.62
3 Benangan 65.86 m1 20,000.00 1,317,200.00
Jumlah - V 116,998,312.72
VI PEKERJAAN LANTAI
1 Cor Rabat Lantai Dasar tebal 5 cm K-225 7.80 m3 830,605.37 6,478,721.89
2 Cor Rabat Keliling Bangunan tebal 5 cm K-225 2.05 m 3
1,650,627.97 3,383,787.33
3 Pas. Lantai Keramik 40 x 40 cm Granito 252.00 m2 248,606.20 62,648,762.40
4 Pas. Dinding Keramik 20 x 25 untuk KM/WC 119.58 m2 126,606.20 15,139,569.40
5 Pas. Lantai Keramik 20 x 20 untuk KM/WC 13.75 m2 120,606.20 1,658,335.25
6 Pas. Dinding Keramik 20 x 25 untuk KM/WC 22.50 m 2
120,606.20 2,713,639.50
7 Pas. Lantai Tangga Tegel Keramik Kasar 40 x 40 17.13 m2 248,606.20 4,258,624.21
8 List Keramik Ujung Anak Tangga 36.00 m 1
5,000.00 180,000.00

Jumlah - VI 96,461,439.97
VII PEKERJAAN KUSEN, PINTU DAN JENDELA
1 Kusen Almunium Cokelat 267.40 m1 184,342.20 49,293,104.28
2 Daun Pintu Almunium Cokelat ( 80 x 210 ) Aksesoris 16.00 bh 1,300,000.00 20,800,000.00
3 Daun Pintu Almunium Cokelat ( 70 x 210 ) Aksesoris 1.00 bh 1,300,000.00 1,300,000.00
3 Daun Jendela Almunium Cokelat ( 70 x 80 ) 66.00 bh 250,000.00 16,500,000.00
4 Daun Jendela Almunium Cokelat ( 70 x 130 ) 96.00 bh 250,000.00 24,000,000.00
4 Daun Jendela Almunium Cokelat ( 70 x 170 ) 19.20 bh 250,000.00 4,800,000.00
4 Daun Pintu PVC Lengkap 6.00 bh 350,000.00 2,100,000.00
8 Kaca Raiben 5 mm 30.36 m2 135,000.00 4,098,600.00
9 Roster (RS) 82.00 bh 20,000.00 1,640,000.00
Jumlah - VII 124,531,704.28
VIII PEKERJAAN RANGKA KAP ATAP
1 Rangka Atap Baja Ringan 233.14 m2 257,400.00 60,010,236.00
2 Atap Metal Multi Roof 233.14 m 2
113,700.00 26,508,018.00
3 Bubungan Atap Metal roof Model Bulat ( C ) 48.00 m 1
104,260.00 5,004,480.00
4 Listplank Kayu Lebr 36 cm 18.52 m2 160,008.00 2,963,668.18
Jumlah - VIII 94,486,402.18
IX PEKERJAAN PLAFOND
1 Pasang Rangka Plafond Besi Holow + Plafond Gipsumboar 9 mm 268.80 m2 171,100.00 45,991,680.00
2 List Plafond Profil 208.20 m1 25,000.00 5,205,000.00
Jumlah - IX 51,196,680.00
X PEKERJAAN INSTALASI LISTRIK
1 Titik Lampu XL 18 watt + Intelasi 53.00 ttk 275,000.00 14,575,000.00
2 Saklar Tunggal + instalasi 10.00 ttk 275,000.00 2,750,000.00
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
3 Saklar Double + instalasi 25.00 ttk 275,000.00 6,875,000.00
4 Stop Kontak + instalasi 23.00 ttk 275,000.00 6,325,000.00
5 Stop Kontak AC + Instalasi 9.00 ttk 275,000.00 2,475,000.00
6 Box MCB 2 Group 1.00 Unit 400,000.00 400,000.00
7 Biaya Penyambungan dari PLN 25 A 1.00 ls 15,000,000.00 15,000,000.00
8 Pasang Penangkal Petir 4 Split dan 2 Arde 1.00 ls 8,000,000.00 8,000,000.00

Jumlah - X 56,400,000.00
XI PEKERJAAN KUNCI DAN PENGGANTUNG
1 Engsel Pintu 66.00 bh 54,450.00 3,593,700.00
2 Engsel Jendela 102.00 bh 30,250.00 3,085,500.00
3 Kunci Tanam 2 Kali Putar 17.00 bh 145,200.00 2,468,400.00
4 Grendel Jendela 51.00 bh 20,000.00 1,020,000.00
5 Hak Kait Angin 102.00 bh 12,100.00 1,234,200.00
6 Handle Jendela 51.00 bh 15,000.00 765,000.00
Jumlah - XI 12,166,800.00
XII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dengan Cat Tembok 1,193.02 m2 23,105.00 27,564,727.10
2 Pengecatan Plafond Dengan Cat Air 268.80 m 2
21,355.00 5,740,224.00
3 Pengecatan listplank dan list Profil Dengan Cat Kilap 28.93 m2 28,563.00 826,384.72
Jumlah - XII 34,131,335.82
XIII PEKERJAAN SANITAIR
1 Pasang Pipa PVC Diameter 1/2" 19.50 Btg 17,500.00 341,250.00
2 Pasang Pipa PVC Diameter 4" 11.00 Btg 92,000.00 1,012,000.00
3 Pasang Pipa PVC Diameter 2" 19.50 Btg 41,500.00 809,250.00
4 Pasang Kran Air Diameter 1/2" 6.00 bh 20,000.00 120,000.00
5 Pasang Klosed Duduk + Aksesoris 4.00 bh 1,800,000.00 7,200,000.00
6 Pasang Floor drain 6.00 bh 50,000.00 300,000.00
7 Washtafel Porslint lengkap + Aksesoris 8.00 bh 726,000.00 5,808,000.00
8 Pasang Profil Tank 1100 Ltr + Aksesoris 2.00 bh 1,500,000.00 3,000,000.00
9 Pemyambungan PDAM 1.00 ls 2,500,000.00 2,500,000.00
Jumlah - XIII 21,090,500.00

XIV PEKERJAAN SEPTIC TANK 2. BH


1 Galian tanah 14.48 m3 45,300.00 655,717.50
2 Pasangan batu bata 1 : 4 3.00 m3 968,372.20 2,905,116.60
3 Plesteran 1 :4 24.00 m2 48,546.33 1,165,111.92
4 Pipa 4" 2.00 btg 92,000.00 184,000.00
5 Cor beton bertulang penutup bak 0.66 m3 1,650,627.97 1,089,414.46
Jumlah - XIV 5,999,360.48

XV PEKERJAAN LAIN - LAIN


1 Pembuatan Saluran Bangunan 7.32 m3 968,372.20 7,088,484.50
2 Plasteran Saluran 73.20 m2 48,546.33 3,553,591.36
3 Cor lantai Saluran 0.61 m3 830,605.37 506,669.28
4 Pasang griil besi 20.00 m1 250,000.00 5,000,000.00
5 Railing Tangga Pipa stainless 2" 70.55 m1 65,500.00 4,621,025.00
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )

Jumlah - XV 20,769,770.14
DAFTAR ANALISA

HARGA HARGA HARGA JUMLAH


NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6

PEKERJAAN PERSIAPAN
1 m Pekerjaan Pasang Bouplank
0.01 m3 Kayu Meranti 2,800,000.00 28,000.00
0.05 kg Paku 20,000.00 1,000.00
0.05 kg Cat 60,000.00 3,000.00
0.2 OH Tukang Kayu 65,000.00 13,000.00
0.024 OH Kepala Tukang Kayu 70,000.00 1,680.00
0.052 OH Pekerja 55,000.00 2,860.00
0.003 OH Mandor 72,000.00 216.00
17,756.00 32,000.00 49,756.00

I. PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa
0.75 Pekerja 58,000.00 43,500.00
0.025 Mandor 72,000.00 1,800.00
45,300.00 - 45,300.00

2 1 M3 Galian Tanah Keras


1 Pekerja 58,000.00 58,000.00
0.033 Mandor 72,000.00 2,376.00
60,376.00 - 60,376.00

3 1 M3 Galian Tanah Cadas


2 Pekerja 58,000.00 116,000.00
0.0068 Mandor 72,000.00 489.60
116,489.60 - 116,489.60

4 1 M3 Galian Tanah Lumpur


1.5 Pekerja 58,000.00 87,000.00
0.05 Mandor 72,000.00 3,600.00
90,600.00 - 90,600.00

3 1 M3 Urugan Tanah Kembali


0.5 1 M³ Galian Tanah Biasa 22,650.00

4 1 M3 Urugan Tanah diratakan


1.2 1 M³ Tanah Urug 58,000.00 69,600.00
0.3 Pekerja 58,000.00 17,400.00
0.01 Mandor 72,000.00 720.00
18,120.00 69,600.00 87,720.00

5 1 M3 Mengurug Pasir dan Penyiraman


1.2 M³ Pasir Urug 61,500.00 73,800.00
0.3 Pekerja 58,000.00 17,400.00
0.01 Mandor 72,000.00 720.00
18,120.00 73,800.00 91,920.00

6 Pancang Ulin 10/10 - 2m


0.0200 M3 Balok Kayu Ulin 4,500,000.00 90,000.00
1.0000 Kg Alat Bantu 1,000.00 1,000.00
0.3000 Pekerja 58,000.00 17,400.00
0.4000 Tukang Kayu 65,000.00 26,000.00
0.0040 Kepala tukang Kayu 70,000.00 280.00
6
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.0200 Mandor 72,000.00 1,440.00
45,120.00 91,000.00 136,120.00
II. PEKERJAAN BATU
1 1 M3 Pasangan Pondasi Batu Gunung ( 1 : 4 )
1.2 M³ Batu Gunung 350,000.00 420,000.00
3.260 Zak Semen 4.04 75,000.00 244,500.00
0.520 M³ Pasir Pasangan 63,700.00 33,124.00
0.750 Tukang Batu 65,000.00 48,750.00
0.075 Kepala Tukang Batu 70,000.00 5,250.00
1.500 Pekerja 55,000.00 82,500.00
0.075 Mandor 72,000.00 5,400.00
141,900.00 697,624.00 839,524.00

2 1 M3 Pasangan Batu Kosongan ( Aanstamping )


1.2 M³ Batu Gunung 350,000.00 420,000.00
1.5 Pekerja 55,000.00 82,500.00
0.075 Mandor 72,000.00 5,400.00
87,900.00 420,000.00 507,900.00

7
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
2 1 M2 Pasangan Batu bata ( 1 : 4 )
450.000 Bh Batu Bata 875.00 393,750.00
3.352 Zak Semen 75,000.00 251,400.00
0.406 M³ Pasir Pasangan 63,700.00 25,862.20
1.200 Tukang Batu 65,000.00 78,000.00
0.1200 Kepala Tukang Batu 70,000.00 8,400.00
3.600 Pekerja 55,000.00 198,000.00
0.180 Mandor 72,000.00 12,960.00
1 M2 Pasangan Batu Bata ( 1 : 4 ) 297,360.00 671,012.20 968,372.20

3 1 M2 Pasangan Batu Bata ( 1 : 2 )


450.00 Bh Batu Bata 875.00 393,750.00
5.5450 Zak Semen 75,000.00 415,875.00
0.3330 M³ Pasir Pasangan 63,700.00 21,212.10
1.2000 Tukang Batu 65,000.00 78,000.00
0.1200 Kepala Tukang Batu 70,000.00 8,400.00
3.6000 Pekerja 55,000.00 198,000.00
0.1800 Mandor 72,000.00 12,960.00
1 M2 Pasangan Batu Bata ( 1 : 2 ) 297,360.00 830,837.10 1,128,197.10

5 1 M2 Pasangan Batako ( 1 : 5 )
14 Bh Batako ( 20 x 30 ) Bata Lubang 1,815.00 25,410.00
12.5 Bh Batako ( 20 x 40 ) Bata Lubang 2,238.00 27,975.00
0.5 Zak Semen 75,000.00 37,500.00
0.05 M³ Pasir Pasangan 63,700.00 3,185.00
0.24 Tukang Batu 65,000.00 15,600.00
0.02 Kepala Tukang Batu 70,000.00 1,400.00
0.72 Pekerja 55,000.00 39,600.00
0.05 Mandor 72,000.00 3,600.00
1 M2 Pasangan Batako ( 20 x 30 ) Bata Lubang 60,200.00 66,095.00 126,295.00
1 M2 Pasangan Batako ( 20 x 40 ) Bata Lubang 60,200.00 68,660.00 128,860.00

8
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
6 1 M2 Pasangan Paving Block
36 Bh Paving Bujur Sangkar ( t = 8 cm ) 1,750.00 63,000.00
36 Bh Paving Bujur Sangkar ( t = 10 cm ) 2,000.00 72,000.00
27 Bh Paving Segi Enam ( B ) 2,550.00 68,850.00
30 Bh Paving Segi Enam ( K ) 2,250.00 67,500.00
0.05 Tukang Batu 65,000.00 3,250.00
0.025 Kepala Tukang Batu 70,000.00 1,750.00
0.2 Pekerja 55,000.00 11,000.00
0.025 Mandor 72,000.00 1,800.00
1 M2 Pasangan Paving Bujur Sangkar ( t = 8 cm ) 17,800.00 63,000.00 80,800.00
1 M2 Pasangan Paving Bujur Sangkar ( t = 10 cm ) 17,800.00 72,000.00 89,800.00
1 M2 Pasangan Paving Segi Enam ( B ) 17,800.00 68,850.00 86,650.00
1 M2 Pasangan Paving Segi Enam ( K ) 17,800.00 67,500.00 85,300.00

4 1 M2 Plesteran Tebal 1 Cm ( 1 : 2 )
0.143 Zak Semen 75,000.00 10,725.00
0.0084 M³ Pasir Pasangan 63,700.00 535.08
0.15 Tukang Batu 65,000.00 9,750.00
0.015 Kepala Tukang Batu 70,000.00 1,050.00
0.4 Pekerja 55,000.00 22,000.00
0.02 Mandor 72,000.00 1,440.00
34,240.00 11,260.08 45,500.08
5 1 M2 Plesteran Tebal 1.5 Cm ( 1 : 4 )
0.125 Zak Semen 75,000.00 9,375.00
0.0209 M³ Pasir Pasangan 63,700.00 1,331.33
0.2 Tukang Batu 65,000.00 13,000.00
0.02 Kepala Tukang Batu 70,000.00 1,400.00
0.4 Pekerja 55,000.00 22,000.00
0.02 Mandor 72,000.00 1,440.00
37,840.00 10,706.33 48,546.33

6 1 M2 Plsteran Tebal 0.6 Cm ( 1 : 3 ) Untuk Lantai Beton


0.072 Zak Semen 75,000.00 5,400.00
0.0086 M³ Pasir Pasangan 63,700.00 547.82
0.1 Tukang Batu 65,000.00 6,500.00
0.01 Kepala Tukang Batu 70,000.00 700.00
0.03 Pekerja 55,000.00 1,650.00
0.015 Mandor 72,000.00 1,080.00
9,930.00 5,947.82 15,877.82

11 1 M2 Plesteran Tebal 1.5 Cm ( 1 : 3 )


0.163 Zak Semen 75,000.00 12,225.00
0.0194 M³ Pasir Pasangan 63,700.00 1,235.78
0.2 Tukang Batu 65,000.00 13,000.00
0.02 Kepala Tukang Batu 70,000.00 1,400.00
0.4 Pekerja 55,000.00 22,000.00
0.02 Mandor 72,000.00 1,440.00
37,840.00 13,460.78 51,300.78

III. PEKERJAAN BETON


1 1 M3 Beton K-125 ( Bo )
5.520 Zak Semen 75,000.00 414,000.00
0.591 M³ Pasir Pasangan 63,700.00 37,674.00
0.750 M³ Kerikil dari Batu Pecah 2/3 350,000.00 262,370.37
0.275 Tukang Batu 65,000.00 17,875.00
0.028 Kepala Tukang Batu 70,000.00 1,960.00
1.650 Pekerja 55,000.00 90,750.00
0.083 Mandor 72,000.00 5,976.00

9
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
116,561.00 714,044.37 830,605.37
2 1 M3 Beton K-175 ( B1 )
6.52 Zak Semen 75,000.00 489,000.00
0.543 M³ Pasir Pasangan 63,700.00 34,580.00
0.762 M³ Batu pecah 350,000.00 266,777.78
0.275 Tukang Batu 65,000.00 17,875.00
0.028 Kepala Tukang Batu 70,000.00 1,960.00
1.65 Pekerja 55,000.00 90,750.00
0.083 Mandor 72,000.00 5,976.00
116,561.00 790,357.78 906,918.78
3 1 M3 Beton K- 225
7.420 Zak Semen 75,000.00 556,500.00
0.4986 M³ Pasir Pasangan 63,700.00 31,760.82
0.776 M³ Kerikil dari Batu Pecah 2/3 350,000.00 271,460.00
0.275 Tukang Batu 65,000.00 17,875.00
0.028 Kepala Tukang Batu 70,000.00 1,960.00
1.65 Pekerja 55,000.00 90,750.00
0.083 Mandor 72,000.00 5,976.00
116,561.00 859,720.82 976,281.82
4 10 Kg Pekerjaan Besi Beton (ulir)
10.500 Kg Besi Beton (ulir) 17,500.00 183,750.00 ###
0.150 Kg Kawat Beton 20,000.00 3,000.00 ###
0.007 Tukang Besi 65,000.00 455.00 ###
0.004 Kepala Tukang Besi 70,000.00 280.00 ###
0.070 Pekerja 55,000.00 3,850.00 ###
4,585.00 186,750.00
Jumlah @ 191,335.00
1 Kg Bahan dan Upah Besi Beton ……………………………………….. 1/10 x Jumlah @ 19,133.50

10
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6

5 10 Kg Pekerjaan Besi Beton (polos)


10.500 Kg Besi Beton (polos) 14,000.00 147,000.00
0.150 Kg Kawat Beton 20,000.00 3,000.00
0.007 Tukang Besi 65,000.00 455.00
0.004 Kepala Tukang Besi 70,000.00 280.00
0.070 Pekerja 55,000.00 3,850.00

4,585.00 150,000.00
Jumlah @ 154,585.00
1 Kg Bahan dan Upah Besi Beton ……………………………………….. 1/10 x Jumlah @ 15,458.50

6 10 m3 Pekerjaan Begisting/ 1 M3
0.4 M³ Papan meranti 2,800,000.00 1,120,000.00
0.4 M³ balok meranti 2,800,000.00 1,120,000.00
4 Kg Paku Kayu 20,000.00 80,000.00
5 Tukang Kayu 65,000.00 325,000.00
0.5 Kepala Tukang kayu 70,000.00 35,000.00
4 Pekerja 55,000.00 220,000.00
0.1 Mandor 72,000.00 7,200.00
587,200.00 2,320,000.00
Jumlah @ 2,907,200.00
1 M2 bahan & Upah Pemasangan Papan kayu Begesting …………… 1.e = 1/10Jumlah @ 290,720.00

1 Cor beton rabat k-175


1.000 M³ Beton K-175 830,605.37 830,605.37

830,605.37

2 Cor beton Poer P1 (150x150x40) K-225


1.000 M³ Beton K-225 976,281.82 976,281.82
87.048 Kg Bahan dan Upah Besi beton (Ulir) 19,133.50 1,665,532.91
5.167 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 1,502,053.33
4,143,868.06

3 Cor Sloof 35/50 cm k-225


1.000 M³ Beton K-225 976,281.82 976,281.82
73.922 Kg Bahan dan Upah Besi beton (ulir) 19,133.50 1,414,381.12
24.369 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 376,715.66
5.714 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 1,661,257.14
4,428,635.74
3 Cor Sloof 20/35 cm k-225
1.000 M³ Beton K-225 976,281.82 976,281.82

100.275 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 1,550,108.03


10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
5,433,589.85
4 Cor Sloof 10/ 20 cm k-225
1.000 M³ Beton K-225 976,281.82 976,281.82
200.000 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 3,091,700.00
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
6,975,181.82

5 Cor Beton Balok B1 (30/45 cm) K-225


1.000 M³ Beton K-225 976,281.82 976,281.82
200.000 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 3,091,700.00
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
6,975,181.82

6 Cor Beton K1 30/30 cm K-225. L. 1


1.000 M³ Beton K-225 976,281.82 976,281.82
101.000 Kg Bahan dan Upah Besi beton (ulir) 19,133.50 1,932,483.50
34.072 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 526,700.79
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
11
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
6,342,666.11
7 Cor Beton K2 20/20 cm K-225 (Teras )
1.000 M³ Beton K-225 976,281.82 976,281.82
179.705 Kg Bahan dan Upah Besi beton (Polos) 15,458.50 2,777,965.75
20.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 5,814,400.00
9,568,647.57
8 Cor Beton K1 10/10 cm K-225 ( Praktis ) L : 1 dan 2
1.000 M³ Beton K-250 976,281.82 976,281.82
272.704 Kg Bahan dan Upah Besi beton (polos) 15,458.50 4,215,597.88
16.270 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 4,730,014.40
9,921,894.10
9 Cor Beton Balok B1 (30/45 cm) K-225
1.000 M³ Beton K-250 976,281.82 976,281.82
153.543 Kg Bahan dan Upah Besi beton (ulir) 19,133.50 2,937,814.99
55.687 Kg Bahan dan Upah Besi beton (polos) 15,458.50 860,837.77
9.500 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,761,840.00
7,536,774.58

12
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
10 Cor Beton Balok B2 (20/35 cm) K-225
1.000 M³ Beton K-250 976,281.82 976,281.82
100.601 Kg Bahan dan Upah Besi beton (polos) 15,458.50 1,555,139.86
9.333 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,713,386.67
5,244,808.35
11 Cor Beton Balok Ring balk B1 (20/30 cm) K-225
1.000 M³ Beton K-250 976,281.82 976,281.82
64.586 Kg Bahan dan Upah Besi beton (polos) 15,458.50 998,409.26
13.333 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 3,876,266.67
5,850,957.74
12 Cor Beton Balok Ring balk B2 (15/20 cm) K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
145.241 Kg Bahan dan Upah Besi beton (polos) 15,458.50 2,245,207.70
18.333 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 5,329,866.67
8,551,356.19
13 Cor Beton Plat lantai t = 12 cm K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
118.263 Kg Bahan dan Upah Besi beton (polos) 15,458.50 1,828,168.59
8.333 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,422,666.67
5,227,117.07
14 Cor Beton Plat Dak Atap t= 10 cm K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
140.718 Kg Bahan dan Upah Besi beton (polos) 15,458.50 2,175,289.20
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
6,058,771.02
15 Cor Beton Balok Dak Atap BD (25/40 cm) K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
50.294 Kg Bahan dan Upah Besi beton (ulir) 19,133.50 962,307.90
31.367 Kg Bahan dan Upah Besi beton (polos) 15,458.50 484,886.77
10.500 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 3,052,560.00
5,476,036.49
16 Cor Kanopy Beton tebal 7 cm K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
148.336 Kg Bahan dan Upah Besi beton (polos) 15,458.50 2,293,049.89
14.286 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 4,153,142.86
7,422,474.57
17 Cor Beton Balok Kenopi (10/20 cm) K-225
1.000 M³ Beton K-225 976,281.82 976,281.82
128.914 Kg Bahan dan Upah Besi beton (polos) 19,133.50 2,466,576.92
13.333 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 3,876,266.67
7,319,125.41
18 Cor Rabat Keliling Bangunan tebal 5 cm K-225
1.000 M³ Beton K-250 976,281.82 976,281.82
43.623 Kg Bahan dan Upah Besi beton (polos) 15,458.50 674,346.15
1,650,627.97

19 Cor Beton balok tangga 20/30 cm K-225


1.000 M³ Beton K-250 976,281.82 976,281.82
179.70 Kg Bahan dan Upah Besi beton (polos) 15,458.50 2,777,965.75
20.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 5,814,400.00
9,568,647.57

20 Cor Beton plat tangga t=10 cm K-225


1.000 M³ Beton K-225 976,281.82 976,281.82
107.950 Kg Bahan dan Upah Besi beton (polos) 15,458.50 1,668,750.23
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 2,907,200.00
5,552,232.05

21 Cor Beton anak tangga K-225


1.000 M³ Beton K-225 976,281.82 976,281.82
23.453 Kg Bahan dan Upah Besi beton (polos) 15,458.50 362,548.20

13
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
2.685 M2 Bahan dan Upah Papan /Kayu Bekisting 290,720.00 780,618.41
2,119,448.43

IV. PEKERJAAN KAYU


1 1 M3 Pekerjaan Kuzen ( Bangunan Permanen / -
Rumah Induk )
1.1 M³ Kayu lembasung 3,500,000.00 3,850,000.00
0.2 Kg Paku 20,000.00 4,000.00
36 Tukang Kayu 65,000.00 2,340,000.00
3.6 Kepala Tukang kayu 70,000.00 252,000.00
12 Pekerja 55,000.00 660,000.00
0.6 Mandor 72,000.00 43,200.00
3,295,200.00 3,854,000.00 7,149,200.00
2 1 M3 Pekerjaan Kuda - kuda Bentangan 7 M1
1.1 M³ Kayu Kapur 3,500,000.00 3,850,000.00
0.2 Kg Paku 20,000.00 4,000.00
24 Tukang Kayu 65,000.00 1,560,000.00
2.4 Kepala Tukang kayu 70,000.00 168,000.00
8 Pekerja 55,000.00 440,000.00
0.4 Mandor 72,000.00 28,800.00
2,196,800.00 3,854,000.00 6,050,800.00
1 M2 Pasangan Rangka Atap Baja Ringan
1 M2 Kuda - Kuda Zincalume (100.35.0,70) 123,200.00 123,200.00
1 M2 Reng Zincalume (30.45.40.15.0,6) 56,900.00 56,900.00
1 Ls Asesories 30,000.00 30,000.00
0.025 Org Kepala Tukang Kayu 70,000.00 1,750.00
0.25 Tukang 65,000.00 16,250.00
0.5 Pekerja 55,000.00 27,500.00
0.025 Mandor 72,000.00 1,800.00
47,300.00 210,100.00 257,400.00

3 1 M2 Rangka Atap Seng


0.012 M³ Kayu Kapur 3,500,000.00 42,000.00
0.1 Kg Paku 20,000.00 2,000.00
0.1 Tukang Kayu 65,000.00 6,500.00
0.01 Kepala Tukang kayu 70,000.00 700.00
0.15 Pekerja 55,000.00 8,250.00
0.075 Mandor 72,000.00 5,400.00
20,850.00 44,000.00 64,850.00
3 1 M2 Memasang Rangka Atap Genteng / Sirap /
Seng Multiroof
0.01 M³ Kayu Meranti 2,800,000.00 28,000.00
0.25 Kg Paku Kayu 20,000.00 5,000.00
0.1 Tukang Kayu 65,000.00 6,500.00
0.01 Kepala Tukang Kayu 70,000.00 700.00
0.1 Pekerja 55,000.00 5,500.00
0.005 Mandor 72,000.00 360.00
13,060.00 33,000.00 46,060.00
5 1 M2 Pasangan Atap Seng BJLS
1 Lbr Seng BJLS 20 45,000.00 45,000.00
1 Lbr Seng BJLS 30 58,000.00 58,000.00
0.15 Kg Paku Seng 25,000.00 3,750.00

14
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.02 Kepala Tukang Kayu 70,000.00 1,400.00
0.1 Pekerja 55,000.00 5,500.00
0.05 Mandor 72,000.00 3,600.00
Seng BJLS 20 10,500.00 48,750.00 59,250.00
Seng BJLS 30 10,500.00 61,750.00 72,250.00

4 1 M2 Pasangan Atap Multi Colour


1.35 Bh Atap Multi Roof 75,000.00 101,250.00
10 Paku Atap Multi Roof 195.00 1,950.00
0.02 Kepala Tukang Kayu 70,000.00 1,400.00
0.1 Pekerja 55,000.00 5,500.00
0.05 Mandor 72,000.00 3,600.00
10,500.00 103,200.00 113,700.00
1 M2 Pasangan Atap Surya Colour
1.7 Bh Atap Surya Roof 60,500.00 102,850.00
10 Paku Atap Surya Roof 195.00 1,950.00
0.02 Kepala Tukang Kayu 70,000.00 1,400.00
0.1 Pekerja 55,000.00 5,500.00
0.05 Mandor 72,000.00 3,600.00
10,500.00 104,800.00 115,300.00
1 M2 Pasangan Atap Sakura Roof
1.7 Bh Atap Sakura Roof 42,350.00 71,995.00
10 Paku Atap Sakura Roof 195.00 1,950.00
0.02 Kepala Tukang Kayu 70,000.00 1,400.00
0.1 Pekerja 55,000.00 5,500.00
0.05 Mandor 72,000.00 3,600.00
10,500.00 73,945.00 84,445.00

15
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
5 1 M1 Pasangan Bubungan Multi Colour
3.3 Lbr Multi Roof 30,000.00 99,000.00
3.3 Lbr Surya Roof 21,500.00 70,950.00
3.3 Lbr Sakura Roof 15,700.00 51,810.00
8 Bh Paku 195.00 1,560.00
0.25 Tukang 65,000.00 16,250.00
0.025 Kepala Tukang 70,000.00 1,750.00
0.25 Pekerja 55,000.00 13,750.00
31,750.00 132,310.00
1 M1 Pasangan Bubungan Atap Multi roof 104,260.00
1 M1 Pasangan Bubungan Atap Surya roof 85,120.00
1 M1 Pasangan Bubungan Atap Sakura roof

BJLS 30 31,750.00 335,400.00 367,150.00


BJLS 20 31,750.00 330,450.00 362,200.00
1 M1 Pasangan Bubungan Atap Seng BJLS 30 36,715.00
1 M1 Pasangan Bubungan Atap Seng BJLS 30 36,220.00

8 1 M2 Pasangan Dinding Papan Susun Sirih


0.025 M³ Papan Meranti 2,800,000.00 70,000.00
0.025 M³ Papan Kapur 3,500,000.00 87,500.00
0.025 M³ Papan Ulin 4,500,000.00 112,500.00
0.15 Kg Paku Biasa 20,000.00 3,000.00
0.15 Kg Paku Ulin 22,000.00 3,300.00
0.4 Tukang Kayu 65,000.00 26,000.00
0.04 Kepala Tukang Kayu 70,000.00 2,800.00
0.14 Pekerja 55,000.00 7,700.00
0.007 Mandor 72,000.00 504.00
1 M2 Pasangan Dinding Papan Susun Sirih Meranti 37,004.00 73,000.00 110,004.00
1 M2 Pasangan Dinding Papan Susun Sirih Kapur 37,004.00 90,800.00 127,804.00
1 M2 Pasangan Dinding Papan Susun Sirih Ulin 37,004.00 115,800.00 152,804.00

9 1 M2 Pasangan Dinding Papan Susun Tegak


0.028 M³ Papan Meranti 2,800,000.00 78,400.00
0.028 M³ Papan Kapur 3,500,000.00 98,000.00
0.028 M³ Papan Ulin 4,500,000.00 126,000.00
0.2 Kg Paku Biasa 20,000.00 4,000.00
0.2 Kg Paku Ulin 22,000.00 4,400.00
0.8 Tukang Kayu 65,000.00 52,000.00
0.08 Kepala Tukang Kayu 70,000.00 5,600.00
0.028 Pekerja 55,000.00 1,540.00
0.014 Mandor 72,000.00 1,008.00
1 M2 Pasangan Dinding Papan Susun Tegak Meranti 60,148.00 82,400.00 142,548.00
1 M2 Pasangan Dinding Papan Susun Tegak Kapur 60,148.00 102,400.00 162,548.00
1 M2 Pasangan Dinding Papan Susun Tegak Ulin 60,148.00 130,400.00 190,548.00

1 M2 Pasangan rangka dinding


Jarak Rangka 60 Cm
0.007 M³ Kayu kapur 3,500,000.00 24,500.00
0.315 Kg Paku 20,000.00 6,300.00
1 Tukang Kayu 65,000.00 65,000.00
0.1 Kepala Tukang Kayu 70,000.00 7,000.00
72,000.00 30,800.00 102,800.00

0.08 Kepala Tukang Kayu 70,000.00 5,600.00

16
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.28 Pekerja 55,000.00 15,400.00
0.014 Mandor 72,000.00 1,008.00
74,008.00 91,500.00 165,508.00
13 1 M2 Pasangan Lantai dari Kayu Ulin
0.025 M³ Papan Kayu Ulin 4,500,000.00 112,500.00
0.2 Kg Paku 20,000.00 4,000.00
0.8 Tukang Kayu 65,000.00 52,000.00
0.08 Kepala Tukang Kayu 70,000.00 5,600.00
0.28 Pekerja 55,000.00 15,400.00
0.014 Mandor 72,000.00 1,008.00
74,008.00 116,500.00 190,508.00
14 1 M3 Pasangan Sloof dan Gelagar Kayu Kapur
1 M³ Balok Kayu Kapur 3,500,000.00 3,500,000.00
1 Kg Paku Ulin 22,000.00 22,000.00
15 Tukang Kayu 65,000.00 975,000.00
1.5 Kepala Tukang Kayu 70,000.00 105,000.00
5 Pekerja 55,000.00 275,000.00
0.25 Mandor 72,000.00 18,000.00
1,373,000.00 3,522,000.00 4,895,000.00
7 1 M2 Pasangan Tongkat, Sloof, Gelagar, Suai
Sepatu Ulin
1 M³ Balok Kayu Ulin 4,500,000.00 4,500,000.00
1 Kg Paku Ulin 22,000.00 22,000.00
15 Tukang Kayu 65,000.00 975,000.00
1.5 Kepala Tukang Kayu 70,000.00 105,000.00
5 Pekerja 55,000.00 275,000.00
0.25 Mandor 72,000.00 18,000.00
1,373,000.00 4,522,000.00 5,895,000.00
8 1 M2 Rangka Plafond dan Plafond Plywood
0.021 M³ Kayu Kapur 3,500,000.00 73,500.00
0.5 Lbr Plywood 4 MM 60,000.00 30,000.00
0.5 Lbr Plywood 6 MM 79,000.00 39,500.00
0.5 Lbr Plywood 1,8 CM 175,450.00 87,725.00
0.04 Kg Paku 20,000.00 800.00
0.32 Tukang Kayu 65,000.00 20,800.00
0.032 Kepala Tukang Kayu 70,000.00 2,240.00
0.8 Pekerja 55,000.00 44,000.00

0.08 Mandor 72,000.00 5,760.00


Plywood 4 MM 72,800.00 104,300.00 177,100.00
Plywood 6 MM 72,800.00 113,800.00 186,600.00
Plywood 1,8 CM 72,800.00 88,525.00 161,325.00

17 1 M2 Pasangan Plafond dari Plywood


0.5 Lbr Plywood 1,8 CM 175,450.00 87,725.00
0.5 Lbr Plywood 4 MM 60,000.00 30,000.00
0.5 Lbr Plywood 6 MM 79,000.00 39,500.00
0.02 Kg Paku 20,000.00 400.00
0.5 Pekerja 55,000.00 27,500.00
0.025 Mandor 72,000.00 1,800.00
Plywood 1,8 MM 29,300.00 88,125.00 117,425.00
Plywood 4 MM 29,300.00 30,400.00 59,700.00
Plywood 6 MM 29,300.00 39,900.00 69,200.00

9 1 M2 Pasangan Lesplank 2 / 20
0.024 M³ Papan Kayu Kapur 3,500,000.00 84,000.00
0.1 Kg Paku 20,000.00 2,000.00
0.8 Tukang Kayu 65,000.00 52,000.00
0.08 Kepala Tukang Kayu 70,000.00 5,600.00
17
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.28 Pekerja 55,000.00 15,400.00
0.014 Mandor 72,000.00 1,008.00
74,008.00 86,000.00 160,008.00
10 1 M1 Mengukur dan Pasang Bouwplank
0.019 M³ Papan Meranti 2,800,000.00 53,480.00
0.013 M³ Balok Meranti 2,800,000.00 37,240.00
0.01 Kg Paku 20,000.00 200.00
0.03 Tukang Kayu 65,000.00 1,950.00
0.003 Kepala Tukang Kayu 70,000.00 210.00
0.06 Pekerja 55,000.00 3,300.00
5,460.00 90,920.00 96,380.00

11 1 M2 Pasangan Plafond dari gypsumboard


0.364 Lbr Gypsumboard 9 mm 75,000.00 27,300.00
0.11 Kg Paku Sekrup 25,000.00 2,750.00
3.6 m Profil Aluminium 20,000.00 72,000.00
0.15 Kg Kawat dia 4 mm 25,000.00 3,750.00
0.5 Pekerja 55,000.00 27,500.00
0.5 Tukang Besi 65,000.00 32,500.00
0.05 Kepala Tukang 70,000.00 3,500.00
0.025 Mandor 72,000.00 1,800.00
65,300.00 105,800.00 171,100.00
18 1 M Pasangan Kusen Pintu Almunium
1.100 m Almunium Cokelat 160,500.00 176,550.00
2.000 bh Skrup Fixer 250.00 500.00
0.060 tube Sealant 28,000.00 1,680.00
0.043 Pekerja 55,000.00 2,365.00
0.043 Tukang Khusus Almunium 65,000.00 2,795.00
0.0043 Kepala Tukang 70,000.00 301.00
0.0021 Mandor 72,000.00 151.20
5,612.20 178,730.00 184,342.20

V. PEKERJAAN LANTAI
1 1 M2 Pasangan Keramik
1 M² Keramik 40 x 40 Asia 57,500.00 57,500.00
1 M² Keramik 20 x 20 Asia 52,000.00 52,000.00
1 M² Keramik 20 x 25 Asia 58,000.00 58,000.00
1 M² Keramik 30 x 30 Roman 70,000.00 70,000.00
1 M² Keramik 20 x 20 65,000.00 65,000.00
1 M² Keramik Innesa 193,600.00 193,600.00
1 M² Keramik Maestro 78,650.00 78,650.00
1 M² Keramik 60 x 60 Granito 220,000.00 220,000.00
1 M² Keramik 40 x 40 Granito 180,000.00 180,000.00 ###
1 M² Keramik 30 x 60 Granito 310,000.00 310,000.00
0.25 Zak Semen 75,000.00 18,750.00
0.01 Zak Semen Putih 90,000.00 900.00
0.026 M³ Pasir 63,700.00 1,656.20
0.25 Tukang Batu 65,000.00 16,250.00
0.025 Kepala Tukang Batu 70,000.00 1,750.00
0.5 Pekerja 55,000.00 27,500.00
0.025 Mandor 72,000.00 1,800.00

18
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
1 M² Keramik 40 x 40 Asia 47,300.00 78,806.20 126,106.20
1 M² Keramik 20 x 20 Asia 47,300.00 73,306.20 120,606.20
1 M² Keramik 20 x 25 Asia 47,300.00 79,306.20 126,606.20
1 M² Keramik 40 x 40 Roman 47,300.00 91,306.20 138,606.20
1 M² Keramik 20 x 20 47,300.00 86,306.20 133,606.20
1 M² Keramik Innesa 47,300.00 214,906.20 262,206.20
1 M² Keramik 60 x 60 Granito 47,300.00 241,306.20 288,606.20
1 M² Keramik 40 x 40 Granito 47,300.00 201,306.20 248,606.20
1 M² Keramik 30 x 60 Granito 47,300.00 310,000.00 357,300.00
1 M² Keramik Maestro 47,300.00 99,956.20 147,256.20
2 1 m2 List Tegel Keramik 5 x 30 cm (Tangga)
67 bh Tegel Keramik 5 x 30 cm 22,500.00 1,507,500.00
0.25 zak Semen 75,000.00 18,750.00
0.01 zak Semen Warna 90,000.00 900.00
0.026 m3 Pasir Pasangan 63,700.00 1,656.20
0.25 Tukang Batu 65,000.00 16,250.00
0.025 Kepala Tukang Batu 70,000.00 1,750.00
0.5 Pekerja 55,000.00 27,500.00
0.025 Mandor 72,000.00 1,800.00
47,300.00 1,528,806.20 1,576,106.20

3 1 m2 Pasang Glass Box


25.000 bh Glass Box 27,500.00 687,500.00
0.250 kg Lem Kaca (Silicom) 28,000.00 7,000.00
0.500 OH Tukang Kayu 65,000.00 32,500.00
0.050 OH Kepala Tukang Kayu 70,000.00 3,500.00
1.000 OH Pekerja 55,000.00 55,000.00
0.050 OH Mandor 72,000.00 3,600.00
94,600.00 694,500.00 789,100.00

VI. PEKERJAAN PENGECATAN


1 1 M2 Upah Pengecatan
0.075 Tukang Cat 65,000.00 4,875.00
0.008 Kepala Tukang Cat 70,000.00 525.00
0.05 Pekerja 55,000.00 2,750.00
0.003 Mandor 72,000.00 180.00
8,330.00 - 8,330.00
2 10 M2 Menggosok / menyekrap dempul / Plamir.
0.8 Kg Dempul 39,000.00 31,200.00
2 Lbr Amplas 4,500.00 9,000.00
0.4 Tukang Cat 65,000.00 26,000.00
0.04 Kepala Tukang Cat 70,000.00 2,800.00
28,800.00 40,200.00 69,000.00
1 M2 Menggosok / menyekrap dempul / Plamir. 6,900.00

3 1 M2 Pengecatan dengan Cat Air ( 2 kali Cat )


0.35 Kg Cat Air Paragon 17,500.00 6,125.00
0.35 Kg Cat Air Metrolite 22,500.00 7,875.00
0.35 Kg Cat Air Dulux ( ici ) 30,500.00 10,675.00
1 Upah Plamir / Dempul 6,900.00 6,900.00
1 Upah Pengecatan 8,330.00 8,330.00

1 M2 Pengecatan dengan Cat Air Paragon ( 2 kali Cat ) 15,230.00 6,125.00 21,355.00
1 M2 Pengecatan dengan Cat Air Metrolite ( 2 kali Cat ) 15,230.00 7,875.00 23,105.00
1 M2 Pengecatan dengan Cat Air Dulux ( 2 kali Cat ) 15,230.00 10,675.00 25,905.00

4 1 M2 Pengecatan dengan Cat Kilap Avian ( 2 kali Cat )


0.35 Kg Cat Kilap Avian 35,000.00 12,250.00
0.057 Lt Pengencer Cat 19,000.00 1,083.00
1 Upah Plamir / Dempul 6,900.00 6,900.00
1 Upah Pengecatan 8,330.00 8,330.00

19
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
15,230.00 13,333.00 28,563.00
5 1 M2 Pengecatan Dasar / Meni
0.12 Kg Cat Meni 20,000.00 2,400.00
0.057 Lt Pengenceran Cat 19,000.00 1,083.00
1 Upah Pengecatan 8,330.00 8,330.00
8,330.00 3,483.00 11,813.00

20
1 M3 Beton K- 225
3.710 Zak Semen 75,000.00 278,250.00
0.698 M³ Pasir Pasangan 63,700.00 44,462.60
1.047 M³ Kerikil dari Batu Pecah 350,000.00 366,450.00
0.215 Tukang Batu 65,000.00 13,975.00
0.028 Kepala Tukang Batu 70,000.00 1,960.00
1.65 Pekerja 55,000.00 90,750.00
0.083 Mandor 72,000.00 5,976.00
112,661.00 689,162.60 801,823.60
110 Kg Pekerjaan besi beton
173.52 1 110 Kg Besi beton
1 2 2 Kg Kawat ikat
173.52 0.06136364 6.75 Tukang besi
173.52 0.02045455 2.25 Kepala Tk besi
173.52 0.06136364 6.75 Pekerja

0.4 0.5 0.2 1 5.0000

21
Besi Beton Polos 10.500
Kawat Bendrat 0.150

Pekerja 0.070
Tukang Besi 0.007
Kepala Tukang Besi 0.004

22
5,920,000.00

23
5,920,000.00

24
112,000.00
56,900.00
30,000.00
70,000.00
65,000.00
55,000.00
72,000.00

25
427,100.00
462,100.00
518,100.00

26
1.000 Upah kerja 34,000.00 34,000.00
Jumlah 78,100.00

27
DAFTAR HARGA SATUAN DASAR
( BASIC PRICE )
BAHAN BANGUNAN, UPAH DAN PERALATAN

JENIS HARGA SATUAN


No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5

I Harga Satuan Upah


1 Pekerja Biasa Hari Rp. 55,000.00 6,875.00 /Jam
2 Mandor Hari Rp. 72,000.00 9,000.00 /Jam
3 Tukang Kayu Hari Rp. 65,000.00 8,125.00 /Jam
4 Kepala Tukang Kayu Hari Rp. 70,000.00 8,750.00 /Jam
5 Tukang Batu Hari Rp. 65,000.00 8,125.00 /Jam
6 Kepala Tukang Batu Hari Rp. 70,000.00 8,750.00 /Jam
7 Tukang Cat Hari Rp. 65,000.00 8,125.00 /Jam
8 Kepala Tukang Cat Hari Rp. 70,000.00 8,750.00 /Jam
9 Tukang Besi Hari Rp. 65,000.00 8,125.00 /Jam
10 Kepala Tukang Besi Hari Rp. 70,000.00 8,750.00 /Jam
11 Tukang Gali Tanah Hari Rp. 65,000.00 8,125.00 /Jam
12 Kepala Tukang Gali Tanah Hari Rp. 70,000.00 8,750.00 /Jam

II Bahan Pasangan
1 Batu Gunung M3 Rp. 350,000.00
2 Pasir Urug M3 Rp. 61,500.00
3 Tanah Urug M3 Rp. 58,000.00
4 Pasir Pasangan M3 Rp. 63,700.00
5 Kerikil Beton M3 Rp. 205,000.00
6 Batu Pecah 2/3 cm M3 Rp. 350,000.00
7 Abu Batu M3 Rp. 319,000.00
8 Batu Bata Bh Rp. 875.00
9 Batu Bata Press Bh Rp. 875.00
10 Batu Tempel M2 Rp. 125,000.00
11 Bataco 20 x 30 Bh Rp. 1,815.00
12 Bataco 20 x 40 Bh Rp. 2,238.00
10 Semen PC (50 Kg) Zak Rp. 75,000.00
11 Semen Putih Kg Rp. 90,000.00
12 Roster (B) Bh Rp. 20,000.00
13 Roster (K) Bh Rp. 15,000.00
14 Paving Bujur Sangkar T = 8 cm Bh Rp. 1,750.00
15 Paving Bujur Sangkar T = 10 cm Bh Rp. 2,000.00
16 Paving Segi Enam (B) Bh Rp. 2,550.00
17 Paving Segi Enam (K) Bh Rp. 2,250.00
18 Glass Box Bh Rp. 27,500.00
19 Ijuk Kg Rp. 45,000.00

III Bahan Listrik


1 Stop Kontak + Instalasi Ttk Rp. 275,000.00
2 Lampu TL 1 x 18 watt + Instalasi Ttk Rp. 250,000.00
3 Lampu TL 2 x 18 watt + Instalasi Ttk Rp. 275,000.00
4 Lampu TL 2 x 20 watt + Instalasi Ttk Rp. 400,000.00
5 Lampu XL 18 watt + Instalasi Ttk Rp. 275,000.00
6 Lampu XL 20 watt + Instalasi Ttk Rp. 300,000.00
7 Lampu XL 14 watt + Instalasi Ttk Rp. 245,000.00
8 Lampu XL 200 watt + Instalasi Ttk Rp. 1,000,000.00
9 Box MCB 2 Group unit Rp. 400,000.00
10 Saklar Tunggal "Brocco" Ttk Rp. 275,000.00
11 Saklar Double "Brocco" Ttk Rp. 275,000.00
12 Stop Kontak "Brocco" Ttk Rp. 275,000.00
13 Sekering Kast group Rp. 275,000.00
14 Pasang Penangkal Petir 4 Split dan 2 Arde ls Rp. 8,000,000.00
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
IV Bahan Penggantung
1 Engsel Lokal Bh Rp. 30,250.00
2 Kunci-kunci Lokal Ttk Rp. 140,000.00
3 Hak Angin Lokal Bh Rp. 12,000.00
4 Expagnolet Lokal Bh Rp. 133,000.00
5 Grendel Lokal Bh Rp. 20,000.00
6 Kunci Tanam Union Bh Rp. 217,800.00
7 Kunci Tanam Yale Bh Rp. 145,200.00
8 Expagnolet Bh Rp. 135,000.00
9 Engsel Kupu-kupu 4" Psg Rp. 54,450.00
10 Engsel Kupu-kupu 3" Psg Rp. 30,250.00
11 Engsel Kupu-kupu 2" Psg Rp. 18,150.00
12 Hak Angin Bh Rp. 12,100.00
13 Handle jendela Bh Rp. 15,000.00

V Bahan Langit-langit
1 Eternit (asbes) Lbr Rp. 28,000.00
2 Plywood 3.6 mm Lbr Rp. 50,000.00
3 Teakwood Lbr Rp. 78,000.00
4 Acustik 30 x 60 Lbr Rp. 104,000.00
5 Plywood 4 mm Lbr Rp. 60,000.00
6 Plywood 6 mm Lbr Rp. 79,000.00
7 Plywood 18 mm Lbr Rp. 175,450.00
8 Gipsumboard 9 mm Lbr Rp. 75,000.00
9 Lem Aibon Kg Rp. 32,500.00
10 Plafond teakwood M2 Rp. 97,500.00
11 List Profil M1 Rp. 25,000.00
Profil Aluminum M1 Rp. 20,000.00
VI Bahan Lantai
1 Porselin 11 x 11 Bh/Box Rp. 75,000.00
2 Porselin 10 x 15 Bh/Box Rp. 55,000.00
3 Porselin 15 x 15 Bh/Box Rp. 60,000.00
4 Porselin 20 x 20 Bh/Box Rp. 60,000.00
5 Ubin Mozaik 30 x 30 Bh Rp. 8,500.00
6 Ubin Abu-abu 20 x 20 Bh Rp. 8,500.00
7 Plint Ubin Abu-abu 15 x 20 Bh Rp. 10,000.00
8 Ubin Berwarna 20 x 20 Bh Rp. 7,500.00
9 Plint Ubin Berwarna 15 x 20 Bh Rp. 7,500.00
10 Ubin Teraso 30 x 30 Bh Rp. 7,500.00
11 Plint Ubin Teraso 15 x 20 Bh Rp. 7,500.00
12 Ubin wafel 20 x 20 Bh Rp. 7,500.00
5 Keramik 30 x 30 M2 Rp. 70,000.00
6 Keramik 20 x 20 M2 Rp. 65,000.00
7 Tegel Innesa M2 Rp. 193,600.00
8 tegel Maestro M2 Rp. 78,650.00
9 Tegel Mozaik ( 20 x 20 ) M2 Rp. 139,150.00
7 List Keramik M2 Rp. 22,500.00
8 Marmer M2 Rp. 110,500.00
9 Keramik Ezenza M2 Rp. 236,600.00
10 Plint Keramik ezenza M 2
Rp. 23,400.00
8 Tegel Keramik 40 x 40 cm (Asia) dos Rp. 57,500.00
9 Tegel Keramik 30 x 30 cm (Asia) dos Rp. 55,000.00
10 Tegel Keramik 20 x 20 cm (Asia) dos Rp. 52,000.00
11 Tegel Keramik 20 x 25 cm (Asia) dos Rp. 58,000.00
12 Tegel Keramik 7 x 20 cm (Asia) bh Rp. 9,000.00
13 Tegel Keramik 5 x 30 cm (Asia) bh Rp. 11,500.00
14 Tegel Keramik 60 x 60 cm ( Granito ) m2 Rp. 220,000.0
15 Tegel Keramik 40 x 40 cm ( Granito ) m2 Rp. 180,000.0
16 Tegel Keramik 30 x 60 cm ( Granito ) m2 Rp. 310,000.00

VII Bahan Sanitair


1 Kloset Monoblok Lokal Bh Rp. 545,000.00
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
2 Bak Mandi Teraso Bh Rp. -
1 Bak Mandi Fibre Bh Rp. 275,000.00
2 Bak Mandi Porselen Bh Rp. 690,000.00
3 Bak Mandi Plastik Bh Rp. 295,000.00
4 Kloset Jongkok Teraso Bh Rp. 150,000.00
2 Kloset Jongkok Keramik Bh Rp. 276,400.00
3 Kloset duduk Keramik Ekstra Bh Rp. 1,800,000.00
4 Kloset duduk ToTo Non Polos Bh Rp. 2,050,000.00
4 Urinoir Porselin Bh Rp. 995,040.00
6 Pintu PVC Lengkap Bh Rp. 350,000.00

5 Urinoir Monoblok Bh Rp. 2,200,000.00


6 Bak Cuci Piring Teraso Bh Rp. 175,000.00
7 Bak Cuci Piring Logam Bh Rp. 455,000.00
5 Sumur Pompa Tangan Terpasang Bh Rp. 7,800,000.00
6 Bak Cuci Tangan/Washtafel ( Keramik ) Bh Rp. 252,000.00
7 Meja Dapur Bh Rp. 650,000.00
7 Bak Mandi Keramik Bh Rp. 975,000.00
8 Washtafel Porslint lengkap Bh Rp. 726,000.00
9 Bak Cuci Alumunium Satu Lubang Bh Rp. 242,000.00
10 Profil 1100 liter Bh Rp. 1,500,000.00
10 Profil 1100 liter Bh Rp. 2,750,000.00
11 Floor drain Bh Rp. 50,000.00

VIII Bahan Paku


1 Paku Kayu Kg Rp. 20,000.00
2 Paku Seng Kg Rp. 25,000.00
3 Paku Ulin Kg Rp. 22,000.00
4 Paku Plywood Kg Rp. 22,500.00
5 Paku Sekrup Kg Rp. 25,000.00
6 Paku Asbes Bh/Ktk Rp. 1,500.00
7 Paku Kait Bh Rp. 2,000.00
8 Paku Sumbat Bh Rp. 2,000.00
9 Paku Reng Kg Rp. 22,500.00
10 Paku Multiroof Kg Rp. 19,500.00
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5

IX Bahan Kayu
1 Papan Ulin M3 Rp. 4,500,000.00
2 Balok Ulin M3 Rp. 4,500,000.00
3 Papan Kapur M3 Rp. 3,500,000.00
4 Balok Kapur M3 Rp. 3,500,000.00
5 Balok Meranti M3 Rp. 2,800,000.00
6 Papan Meranti M3 Rp. 2,800,000.00
7 Balok Bengkirai / Lembasung M3 Rp. 3,500,000.00
8 Papan Bengkirai / Lembasung M3 Rp. 3,500,000.00
9 Kayu Perancah M3 Rp. 726,000.00
10 Lumbre seering ( 1/10 cm x 200 cm ) lbr Rp. 22,500.00

X Bahan Sanitasi
1 Buis Beton Diameter 10 cm Bh Rp. 32,500.00
2 Buis Beton Diameter 20 cm Bh Rp. 47,000.00
3 Buis Beton Diameter 30 cm Bh Rp. 65,000.00

X Bahan Atap
1 Sirap Lbr Rp. 750.00
2 Atap Daun Lbr Rp. 2,000.00
3 Genteng Flam Bh Rp. 9,000.00
4 Karpus Genteng Flam Bh Rp. 9,000.00
5 Genteng Kodok Bh Rp. 9,000.00
6 Karpus Genteng Kodok Bh Rp. 9,000.00
7 Genteng Beton Bh Rp. 7,000.00
8 Karpus Genteng Beton Bh Rp. 9,000.00
9 Asbes Gelombang Besar Bh Rp. 28,000.00
10 Asbes Gelombang Kecil Bh Rp. 30,000.00
11 Karpus Asbes Gelombang Besar Bh Rp. 22,000.00
12 Karpus Asbes Gelombang Kecil Bh Rp. 275,000.00
13 Seng Gelombang BJLS 30 Lbr Rp. 58,000.00
14 Seng Gelombang BJLS 27 Lbr Rp. 45,000.00
15 Seng Profil Lbr Rp. 53,900.00
16 Seng Plat BJLS 30 Lbr Rp. 55,275.00
17 Seng Plat BJLS 27 Lbr Rp. 54,450.00
18 Genteng Kaca Bh Rp. 32,500.00
19 Genteng Keramik Bh Rp. 28,000.00
20 Karpus Genteng Keramik Bh Rp. 27,500.00
21 Genteng Metal Multicolour Lbr Rp. 75,000.00
22 Bubungan Metal Multicolour Lbr Rp. 30,000.00
23 Genteng Surya Colour Lbr Rp. 60,500.00
24 Bubungan Surya Colour Lbr Rp. 21,500.00
25 Genteng Sakura Colour Lbr Rp. 42,350.00
26 Bubungan Sakura Colour Lbr Rp. 15,700.00
27 Kuda - kuda Galvalum M2 Rp. 123,200.00
28 Reng Galvalum M2 Rp. 56,900.00
29 Asesories Ls Rp. 30,000.00

XI Bahan Kaca
1 Kaca Bening Tebal 3 mm M2 Rp. 54,000.00
1 Kaca Bening Tebal 5 mm M2 Rp. 85,000.00
2 Kaca Rayband Tebal 5 mm M2 Rp. 135,000.00
3 Naco ( Kerangka dan Daun ) M2 Rp. 127,000.00
4 Jendela Kaca M2 Rp. 149,500.00
3 Glass blok Bh Rp. 27,500.00
4 Kaca Polos Tebal 3 mm M2 Rp. 59,400.00
5 Kaca Buram Tebal 3 mm M2 Rp. 66,550.00
6 Kaca Buram Tebal 5 mm M2 Rp. 108,900.00
7 Kaca Rayband Tebal 3 mm M2 Rp. 66,550.00
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
8 Kaca Nako Polos Tebal 3 mm Set Rp. 114,950.00
9 Kaca Nako Rayband Tebal 3 mm Set Rp. 127,050.00
4 Lem kaca (silicon) Kg Rp. 28,000.00

XII Bahan Pipa


1 Pipa PVC Diameter 1/2" Btg Rp. 17,500.00
2 Pipa PVC Diameter 3/4" Btg Rp. 20,500.00
3 Pipa PVC Diameter 1" Btg Rp. 32,500.00
4 Pipa PVC Diameter 2" Btg Rp. 41,500.00
5 Pipa PVC Diameter 4" Btg Rp. 92,000.00
6 Pipa Diameter 4" Galvanis Btg Rp. 450,000.00
7 Pipa Diameter 3/4" Btg Rp. 65,000.00
8 Pipa Diameter 1" Btg Rp. 90,000.00
9 Pipa Diameter 1/2" Btg Rp. 50,500.00
10 Kran Air Btg Rp. 20,000.00
11 Pipa Air 1/2" Btg Rp. 29,250.00
12 Elbow 1/2" - 4" Btg Rp. 2.000,00
13 Pipa Galvanis 1/2" Btg Rp. 48,400.00
14 Pipa Galvanis 3/4" Btg Rp. 65,000.00
15 Pipa Galvanis 1" Btg Rp. 90,000.00
16 Pipa Galvanis 1,5" Btg Rp. 108,900.00
17 Pipa Galvanis 2" Btg Rp. 151,250.00
18 Pipa Galvanis 3" Btg Rp. 302,500.00
19 Pipa Galvanis 4" Btg Rp. 450,000.00
20 Pipa Stainless 2,5" M 1
Rp. 80,000.00
21 Pipa Stainless 2" M 1
Rp. 65,500.00
22 pipa Stainless 1,5" M1 Rp. 37,500.00
23 Pipa Satinless 1" M 1
Rp. 25,000.00
24 Talang Stainless 8/5 cm M1 Rp. 78,750.00

XIII Bahan Besi


1 Besi Beton Polos Kg Rp. 14,000.00
2 Besi Beton Ulir Kg Rp. 17,500.00
3 Reservoir Air Rangka Baja 0,5 M3 Bh Rp. -
4 Reservoir Air Rangka Baja 1 M3 Bh Rp. 7,150,000.00
5 Besi eugel / Bout ( Kuda-kuda) Kg Rp. 19,500.00
6 Sumur Pompa Tangan Terpasang Bh Rp. 7,800,000.00
7 Teralis Besi Plat/Siku M2 Rp. 250,000.00
8 Stainlist Steel M2 Rp. 720,000.00
9 Kusen Alumunium Coklat 4" M1 Rp. 160,500.00
10 Kusen Alumunium Silver 4" M1 Rp. 96,800.00

XIV Bahan Kawat


1 Kawat Beton/Bendrat Kg Rp. 20,000.00
2 Kawat Duri Kg Rp. 40,000.00
3 Kawat Harmonika 4 x 4 M 2
Rp. 26,620.00
4 Kawat Nyamuk/ Kasa besi M 2
Rp. 29,000.00
5 Kawat Nyamuk/ Kasa Plastik M2 Rp. 25,000.00
6 Kawat Las Listrik (Elektroda) Kg Rp. 16,500.00
7 Kawat Kg Rp. 25,000.00
8 Kawat Bronjong Pabrikan :
a. Ukuran ( 2 x 1 x 1 ) Unit Rp. 408,500.00
b. Ukuran ( 2 x 1 x 0,5 ) Unit Rp. 304,000.00
c. Ukuran ( 3 x 1 x 0,5 ) Unit Rp. 411,000.00
d. Ukuran ( 1,5 x 1 x 1 ) Unit Rp. 359,000.00
9 Kawat BRC M2 Rp. 205,000.00
10 Kawat Ayam M2 Rp. 13,612.50
11 Kawat Nyamuk Hitam M2 Rp. 24,502.50
12 Kawat Nyamuk Putih M2 Rp. 22,687.50

XV Bahan Finishing
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
1 Amplas Kayu Lbr Rp. 4,500.00
2 Cat Meni Kg Rp. 20,000.00
3 Dempul Kayu Kg Rp. 39,000.00
4 Cat Kayu Mengkilat Kg Rp. 45,500.00
5 Cat Kayu Dasar Kg Rp. 17,000.00
7 Kerosin/Minyak Tanah Ltr Rp. 2,500.00
8 Plamur Tembok Kg Rp. 34,500.00
9 Minyak Cat Ltr Rp. 19,000.00
10 Residu Ltr Rp. 2,600.00
11 Cat Tembok 5 Kg Rp. 60,000.00
12 Cat Kilap Avian Kg Rp. 35,000.00
13 Cat Air Paragon Kg Rp. 17,500.00
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
14 Cat air Metrolite Kg Rp. 22,500.00
15 Cat Air dulux ( ici ) Ltr Rp. 30,500.00
16 Tear Oil Kg Rp. 18,150.00
17 Cat Khusus Atap Kg Rp. 28,000.00
18 Plitur Kg Rp. 4,000.00
19 Alkali Kg Rp. 35,000.00

XVI Bahan Lain-lain


1 Agregat Halus Untuk Pondasi M3 Rp. 254,800.00
2 Agregat Kasar Untuk ATB M 3
Rp. 315,900.00
3 Agregat Kasar Untuk Beton M 3
Rp. 293,800.00

4 Agregat Kasar Untuk Pondasi M 3


Rp. 255,450.00
5 Agregat Halus Untuk ATB M3 Rp. 312,000.00
6 Filter Kg Rp. 750.00
7 Sirtu M3 Rp. 210,000.00
8 Pasir M3 Rp. 20,000.00 Quary
9 Tanah Timbunan M3 Rp. 12,000.00 Quary
10 Tiang Pancang Beton 350 mm K-600 M1 Rp. 318,500.00
11 Tiang Pancang Beton 400 mm K-600 M 1
Rp. 403,000.00
12 Tiang Pancang Beton 450 mm K-600 M1 Rp. 500,500.00
13 Tiang Pancang Beton 500 mm K-600 M1 Rp. 608,000.00
14 Beton Roster/Kerawang Bh Rp. 39,000.00
15 Beton Tumbuk M3 Rp. 845,000.00
1 Ijuk Kg Rp. 45,000.00
2 Septictank dan Rembesan 1 M3 Bh Rp. 10,075,000.00
2 Septictank dan Rembesan 2 M 3
Unit Rp. 5,000,000.00
3 Septictank dan Rembesan 6 M3 Bh Rp. 15,600,000.00
4 Septictank dan Rembesan 10 M3 Bh Rp. 19,500,000.00
3 Tiang Bendera bh Rp. 2,000,000.00
4 Pasang Penangkal Petir 10 split dan 2 arde Ls Rp. 8,000,000.00
5 Biaya Penyambungan dari PLN 25 A Ls Rp. 15,000,000.00
6 Folding Gate 1,2 mm m2 Rp. 15,000,000.00
7 Biaya Pembuatan Sumur Bor Ls Rp. 7,500,000.00
8 Ground Reservoir 2 x 2,5 x 2 m + Asessories Unit Rp. 7,500,000.00
9 Profil Tank 1100 ltr + Asessories dan Instalasinya Unit Rp. 3,000,000.00
10 Pompa Air 250 watt Merek SANYO bh Rp. 2,250,000.00
11 Pancang Mini Pile 20/20 K-300 L=4m Btg Rp. 650,000.00
12 Biaya Pemancangan / Titik Titik Rp. 50,000.00
13 Biaya Penyambungan tiang pancang Titik Rp. 25,000.00
14 Biaya pembobokan Titik Rp. 40,000.00
15 Alat Bantu Rp. 1,000.00
KOP PERUSAHAAN

REKAPITULASI
RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN KLINIK BERSALIN


PAKET KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
LOKASI : KELURAHAN SEBENGKOK

JUMLAH
NO. URAIAN PEKERJAAN HARGA
( Rp )

I PEKERJAAN PENDAHULUAN Rp. 0.00


II PEKERJAAN TANAH Rp. 0.00
III PEKERJAAN PONDASI DAN TIANG PANCANG Rp. 0.00
IV PEKERJAAN STRUKTUR BETON BERTULANG Rp. 0.00
V PEKERJAAN DINDING Rp. 0.00
VI PEKERJAAN LANTAI Rp. 0.00
VII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp. 0.00
VIII PEKERJAAN RANGKA KAP ATAP Rp. 0.00
IX PEKERJAAN PLAFOND Rp. 0.00
X PEKERJAAN INSTALASI LISTRIK Rp. 0.00
XI PEKERJAAN KUNCI DAN PENGGANTUNG Rp. 0.00
XII PEKERJAAN PENGECATAN Rp. 0.00
XIII PEKERJAAN SANITAIR Rp. 0.00
XIV PEKERJAAN SEPTIC TANK 2. BH Rp. 0.00
XV PEKERJAAN LAIN - LAIN Rp. 0.00
A. JUMLAH ( I + II + ……. + XV ) Rp. 0.00
B IJIN MENDIRIKAN BANGUNAN ( IMB ) Rp. 0.00
C. ASURANSI TENAGA KERJA = (0 - 100 )Jt = 0.24 +(100-500)Jt = 2.0 +(500-1)M = 1.5 +(1 - 5 )m = 0.1 Rp. 0.00
D. PPN 10% Rp. -
E JUMLAH Rp. 0.00
F DIBULATKAN Rp. 0.00

Terbilang : //

Tarakan, …………………............... 2010

Penawar
PT / CV...........................................

materai
Rp. 6000

..................................
Direktur
KOP PERUSAHAAN

RENCANA ANGGARAN BIAYA


( RAB)
KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
PAKET KEGIATAN : PEMBANGUNAN KLINIK BERSALIN
LOKASI : KELURAHAN SEBENGKOK

VOLUME HARGA JUMLAH


NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 1.00 Ls 0.00 0.00
2 Pemasangan Bowplank 68.00 m1 0.00 0.00
3 Pemasangan Plank Nama Proyek ( Digital Print) 1.00 bh 0.00 0.00
4 Foto dokumentasi 1.00 ls 0.00 0.00
Jumlah - I 0.00
II PEKERJAAN TANAH
1 Buangan tanah Galian 68.00 m3 0.00 0.00
2 Galian Tanah Pondasi 40.97 m 3
0.00 0.00
3 Urugan Tanah Kembali 8.19 m3 0.00 0.00
4 Urugan Tanah Bawah Lantai 78.00 m 3
0.00 0.00
5 Urugan Pasir Bawah Lantai 7.80 m3 0.00 0.00
Jumlah - II 0.00
III PEKERJAAN PONDASI DAN TIANG PANCANG
1 Pengadaan Pancang Mini Pile 20/20 K - 300, P : 4 m 98.00 Btg 0.00 0.00
- Pemancangan tiang pancang 98.00 Bh 0.00 0.00
- Penyambungan tiang pancang 54.00 Ttk 0.00 0.00
- Potong Kepala Tiang pancang 54.00 Ttk 0.00 0.00
2 Cor lantai Kerja tebal 3 cm K-125 1.20 m3 0.00 0.00
3 Cor beton Poer P1 (150x150x40) K-225 9.90 m 3
0.00 0.00
4 Pancang Ulin 10/10 -2 M 0.16 m3 0.00 0.00
5 Pas. Pondasi Batu Gunung 2.28 m3 0.00 0.00
Jumlah - III 0.00
IV PEKERJAAN STRUKTUR BETON BERTULANG
1 Cor Sloof 30/50 cm K-225 9.48 m3 0.00 0.00
2 Cor Sloof 20/35 cm K-225 1.12 m3 0.00 0.00
3 Cor Sloof 10/ 20 cm k-225 0.40 m 3
0.00 0.00
4 Cor Letai 10/15 cm k-225 L : 1 dan 2 1.32 m 3
0.00 0.00
5 Cor Beton K1 30/30 cm K-225. L. 1 3.96 m3 0.00 0.00
6 Cor Beton K1 30/30 cm K-225. L. 2 3.96 m 3
0.00 0.00
7 Cor Beton K2 20/20 cm K-225 (Teras ) 0.80 m3 0.00 0.00
8 Cor Beton K1 10/10 cm K-225 ( Praktis ) L : 1 dan 2 1.54 m 3
0.00 0.00
9 Cor Beton Balok B1 (30/45 cm) K-225 7.52 m3 0.00 0.00
10 Cor Beton Balok B2 (20/35 cm) K-225 2.30 m 3
0.00 0.00
11 Cor Beton Balok Ring balk B1 (20/30 cm) K-225 2.52 m 3
0.00 0.00
12 Cor Beton Balok Ring balk B2 (15/20 cm) K-225 0.66 m3 0.00 0.00
13 Cor Beton Plat lantai t = 12 cm K-225 15.20 m 3
0.00 0.00
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
14 Cor Beton Plat Dak Atap t= 10 cm K-225 2.55 m3
0.00 0.00
15 Cor Beton Balok Dak Atap BD (25/40 cm) K-225 1.20 m3 0.00 0.00
16 Cor Beton balok tangga 20/30 cm K-225 0.36 m3
0.00 0.00
17 Cor Beton plat tangga t=10 cm K-225 0.98 m3
0.00 0.00
18 Cor Beton plat bordes t = 10 cm K-225 0.23 m3 0.00 0.00
19 Cor Beton anak tangga K-225 1.68 m3
0.00 0.00
20 Cor Kanopy Beton tebal 7 cm K-225 2.45 m3 0.00 0.00
21 Cor Beton Balok Kenopi (10/20 cm) K-225 1.00 m3
0.00 0.00
Jumlah - IV 0.00
V PEKERJAAN DINDING
1 Pasangan Dinding Bata 1 : 4 59.65 m3 0.00 0.00
2 Plesteran Dinding 1 : 4 + Acian 1,193.02 m2
0.00 0.00
3 Benangan 65.86 m1
0.00 0.00
Jumlah - V 0.00
VI PEKERJAAN LANTAI
1 Cor Rabat Lantai Dasar tebal 5 cm K-225 7.80 m3 0.00 0.00
2 Cor Rabat Keliling Bangunan tebal 5 cm K-225 2.05 m3
0.00 0.00
3 Pas. Lantai Keramik 40 x 40 cm Granito 252.00 m2 0.00 0.00
4 Pas. Dinding Keramik 20 x 25 untuk KM/WC 119.58 m2
0.00 0.00
5 Pas. Lantai Keramik 20 x 20 untuk KM/WC 13.75 m2 0.00 0.00
6 Pas. Dinding Keramik 20 x 25 untuk KM/WC 22.50 m2
0.00 0.00
7 Pas. Lantai Tangga Tegel Keramik Kasar 40 x 40 17.13 m2
0.00 0.00
8 List Keramik Ujung Anak Tangga 36.00 m1 0.00 0.00

Jumlah - VI 0.00
VII PEKERJAAN KUSEN, PINTU DAN JENDELA
1 Kusen Almunium Cokelat 267.40 m1 0.00 0.00
2 Daun Pintu Almunium Cokelat ( 80 x 210 ) Aksesoris 16.00 bh 0.00 0.00
3 Daun Pintu Almunium Cokelat ( 70 x 210 ) Aksesoris 1.00 bh 0.00 0.00
3 Daun Jendela Almunium Cokelat ( 70 x 80 ) 66.00 bh 0.00 0.00
4 Daun Jendela Almunium Cokelat ( 70 x 130 ) 96.00 bh 0.00 0.00
4 Daun Jendela Almunium Cokelat ( 70 x 170 ) 19.20 bh 0.00 0.00
4 Daun Pintu PVC Lengkap 6.00 bh 0.00 0.00
8 Kaca Raiben 5 mm 30.36 m2 0.00 0.00
9 Roster (RS) 82.00 bh 0.00 0.00
Jumlah - VII 0.00
VIII PEKERJAAN RANGKA KAP ATAP
1 Rangka Atap Baja Ringan 233.14 m2 0.00 0.00
2 Atap Metal Multi Roof 233.14 m2 0.00 0.00
3 Bubungan Atap Metal roof Model Bulat ( C ) 48.00 m1
0.00 0.00
4 Listplank Kayu Lebr 36 cm 18.52 m2 0.00 0.00
Jumlah - VIII 0.00
IX PEKERJAAN PLAFOND
1 Pasang Rangka Plafond Besi Holow + Plafond Gipsumboar 9 mm 268.80 m2 0.00 0.00
2 List Plafond Profil 208.20 m1
0.00 0.00
Jumlah - IX 0.00
X PEKERJAAN INSTALASI LISTRIK
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
1 Titik Lampu XL 18 watt + Intelasi 53.00 ttk 0.00 0.00
2 Saklar Tunggal + instalasi 10.00 ttk 0.00 0.00
3 Saklar Double + instalasi 25.00 ttk 0.00 0.00
4 Stop Kontak + instalasi 23.00 ttk 0.00 0.00
5 Stop Kontak AC + Instalasi 9.00 ttk 0.00 0.00
6 Box MCB 2 Group 1.00 Unit 0.00 0.00
7 Biaya Penyambungan dari PLN 25 A 1.00 ls 0.00 0.00
8 Pasang Penangkal Petir 4 Split dan 2 Arde 1.00 ls 0.00 0.00

Jumlah - X 0.00
XI PEKERJAAN KUNCI DAN PENGGANTUNG
1 Engsel Pintu 66.00 bh 0.00 0.00
2 Engsel Jendela 102.00 bh 0.00 0.00
3 Kunci Tanam 2 Kali Putar 17.00 bh 0.00 0.00
4 Grendel Jendela 51.00 bh 0.00 0.00
5 Hak Kait Angin 102.00 bh 0.00 0.00
6 Handle Jendela 51.00 bh 0.00 0.00
Jumlah - XI 0.00
XII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dengan Cat Tembok 1,193.02 m2 0.00 0.00
2 Pengecatan Plafond Dengan Cat Air 268.80 m 2
0.00 0.00
3 Pengecatan listplank dan list Profil Dengan Cat Kilap 28.93 m 2
0.00 0.00
Jumlah - XII 0.00
XIII PEKERJAAN SANITAIR
1 Pasang Pipa PVC Diameter 1/2" 19.50 Btg 0.00 0.00
2 Pasang Pipa PVC Diameter 4" 11.00 Btg 0.00 0.00
3 Pasang Pipa PVC Diameter 2" 19.50 Btg 0.00 0.00
4 Pasang Kran Air Diameter 1/2" 6.00 bh 0.00 0.00
5 Pasang Klosed Duduk + Aksesoris 4.00 bh 0.00 0.00
6 Pasang Floor drain 6.00 bh 0.00 0.00
7 Washtafel Porslint lengkap + Aksesoris 8.00 bh 0.00 0.00
8 Pasang Profil Tank 1100 Ltr + Aksesoris 2.00 bh 0.00 0.00
9 Pemyambungan PDAM 1.00 ls 0.00 0.00
Jumlah - XIII 0.00

XIV PEKERJAAN SEPTIC TANK 2. BH


1 Galian tanah 14.48 m3 0.00 0.00
2 Pasangan batu bata 1 : 4 3.00 m3 0.00 0.00
3 Plesteran 1 :4 24.00 m2 0.00 0.00
4 Pipa 4" 2.00 btg 0.00 0.00
5 Cor beton bertulang penutup bak 0.66 m3 0.00 0.00
Jumlah - XIV 0.00

XV PEKERJAAN LAIN - LAIN


1 Pembuatan Saluran Bangunan 7.32 m3 0.00 0.00
2 Plasteran Saluran 73.20 m2 0.00 0.00
3 Cor lantai Saluran 0.61 m3 0.00 0.00
VOLUME HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
( Rp ) ( Rp )
4 Pasang griil besi 20.00 m1 0.00 0.00
5 Railing Tangga Pipa stainless 2" 70.55 m1 0.00 0.00

Jumlah - XV 0.00
DAFTAR ANALISA

HARGA HARGA HARGA JUMLAH


NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6

PEKERJAAN PERSIAPAN
1 m Pekerjaan Pasang Bouplank
0.01 m3 Kayu Meranti - -
0.05 kg Paku - -
0.05 kg Cat - -
0.2 OH Tukang Kayu - -
0.024 OH Kepala Tukang Kayu - -
0.052 OH Pekerja - -
0.003 OH Mandor - -
- - -

I. PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa
0.75 Pekerja - -
0.025 Mandor - -
- - -

2 1 M3 Galian Tanah Keras


1 Pekerja - -
0.033 Mandor - -
- - -

3 1 M3 Galian Tanah Cadas


2 Pekerja - -
0.0068 Mandor - -
- - -

4 1 M3 Galian Tanah Lumpur


1.5 Pekerja - -
0.05 Mandor - -
- - -

3 1 M3 Urugan Tanah Kembali


0.5 1 M³ Galian Tanah Biasa -

4 1 M3 Urugan Tanah diratakan


1.2 1 M³ Tanah Urug - -
0.3 Pekerja - -
0.01 Mandor - -
- - -

5 1 M3 Mengurug Pasir dan Penyiraman


1.2 M³ Pasir Urug - -
0.3 Pekerja - -
0.01 Mandor - -
- - -

6 Pancang Ulin 10/10 - 2m


0.0200 M3 Balok Kayu Ulin - -
1.0000 Kg Alat Bantu - -
0.3000 Pekerja - -
0.4000 Tukang Kayu - -
0.0040 Kepala tukang Kayu - -
40
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.0200 Mandor - -
- - -
II. PEKERJAAN BATU
1 1 M3 Pasangan Pondasi Batu Gunung ( 1 : 4 )
1.2 M³ Batu Gunung - -
3.260 Zak Semen 4.04 - -
0.520 M³ Pasir Pasangan - -
0.750 Tukang Batu - -
0.075 Kepala Tukang Batu - -
1.500 Pekerja - -
0.075 Mandor - -
- - -

2 1 M3 Pasangan Batu Kosongan ( Aanstamping )


1.2 M³ Batu Gunung - -
1.5 Pekerja - -
0.075 Mandor - -
- - -

41
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
2 1 M2 Pasangan Batu bata ( 1 : 4 )
450.000 Bh Batu Bata - -
3.352 Zak Semen - -
0.406 M³ Pasir Pasangan - -
1.200 Tukang Batu - -
0.1200 Kepala Tukang Batu - -
3.600 Pekerja - -
0.180 Mandor - -
1 M2 Pasangan Batu Bata ( 1 : 4 ) - - -

3 1 M2 Pasangan Batu Bata ( 1 : 2 )


450.00 Bh Batu Bata - -
5.5450 Zak Semen - -
0.3330 M³ Pasir Pasangan - -
1.2000 Tukang Batu - -
0.1200 Kepala Tukang Batu - -
3.6000 Pekerja - -
0.1800 Mandor - -
1 M2 Pasangan Batu Bata ( 1 : 2 ) - - -

5 1 M2 Pasangan Batako ( 1 : 5 )
14 Bh Batako ( 20 x 30 ) Bata Lubang - -
12.5 Bh Batako ( 20 x 40 ) Bata Lubang - -
0.5 Zak Semen - -
0.05 M³ Pasir Pasangan - -
0.24 Tukang Batu - -
0.02 Kepala Tukang Batu - -
0.72 Pekerja - -
0.05 Mandor - -
1 M2 Pasangan Batako ( 20 x 30 ) Bata Lubang - - -
1 M2 Pasangan Batako ( 20 x 40 ) Bata Lubang - - -

42
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
6 1 M2 Pasangan Paving Block
36 Bh Paving Bujur Sangkar ( t = 8 cm ) - -
36 Bh Paving Bujur Sangkar ( t = 10 cm ) - -
27 Bh Paving Segi Enam ( B ) - -
30 Bh Paving Segi Enam ( K ) - -
0.05 Tukang Batu - -
0.025 Kepala Tukang Batu - -
0.2 Pekerja - -
0.025 Mandor - -
1 M2 Pasangan Paving Bujur Sangkar ( t = 8 cm ) - - -
1 M2 Pasangan Paving Bujur Sangkar ( t = 10 cm ) - - -
1 M2 Pasangan Paving Segi Enam ( B ) - - -
1 M2 Pasangan Paving Segi Enam ( K ) - - -

4 1 M2 Plesteran Tebal 1 Cm ( 1 : 2 )
0.143 Zak Semen - -
0.0084 M³ Pasir Pasangan - -
0.15 Tukang Batu - -
0.015 Kepala Tukang Batu - -
0.4 Pekerja - -
0.02 Mandor - -
- - -
5 1 M2 Plesteran Tebal 1.5 Cm ( 1 : 4 )
0.125 Zak Semen - -
0.0209 M³ Pasir Pasangan - -
0.2 Tukang Batu - -
0.02 Kepala Tukang Batu - -
0.4 Pekerja - -
0.02 Mandor - -
- - -

6 1 M2 Plsteran Tebal 0.6 Cm ( 1 : 3 ) Untuk Lantai Beton


0.072 Zak Semen - -
0.0086 M³ Pasir Pasangan - -
0.1 Tukang Batu - -
0.01 Kepala Tukang Batu - -
0.03 Pekerja - -
0.015 Mandor - -
- - -

11 1 M2 Plesteran Tebal 1.5 Cm ( 1 : 3 )


0.163 Zak Semen - -
0.0194 M³ Pasir Pasangan - -
0.2 Tukang Batu - -
0.02 Kepala Tukang Batu - -
0.4 Pekerja - -
0.02 Mandor - -
- - -

III. PEKERJAAN BETON


1 1 M3 Beton K-125 ( Bo )
5.520 Zak Semen - -
0.591 M³ Pasir Pasangan - -
0.750 M³ Kerikil dari Batu Pecah 2/3 - -
0.275 Tukang Batu - -
0.028 Kepala Tukang Batu - -
1.650 Pekerja - -
0.083 Mandor - -

43
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
- - -
2 1 M3 Beton K-175 ( B1 )
6.52 Zak Semen - -
0.543 M³ Pasir Pasangan - -
0.762 M³ Batu pecah - -
0.275 Tukang Batu - -
0.028 Kepala Tukang Batu - -
1.65 Pekerja - -
0.083 Mandor - -
- - -
3 1 M3 Beton K- 225
7.420 Zak Semen - -
0.4986 M³ Pasir Pasangan - -
0.776 M³ Kerikil dari Batu Pecah 2/3 - -
0.275 Tukang Batu - -
0.028 Kepala Tukang Batu - -
1.65 Pekerja - -
0.083 Mandor - -
- - -
4 10 Kg Pekerjaan Besi Beton (ulir)
10.500 Kg Besi Beton (ulir) - - ###
0.150 Kg Kawat Beton - - ###
0.007 Tukang Besi - - ###
0.004 Kepala Tukang Besi - - ###
0.070 Pekerja - - ###
- -
Jumlah @ -
1 Kg Bahan dan Upah Besi Beton ……………………………………….. 1/10 x Jumlah @ -

44
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6

5 10 Kg Pekerjaan Besi Beton (polos)


10.500 Kg Besi Beton (polos) - -
0.150 Kg Kawat Beton - -
0.007 Tukang Besi - -
0.004 Kepala Tukang Besi - -
0.070 Pekerja - -

- -
Jumlah @ -
1 Kg Bahan dan Upah Besi Beton ……………………………………….. 1/10 x Jumlah @ -

6 10 m3 Pekerjaan Begisting/ 1 M3
0.4 M³ Papan meranti - -
0.4 M³ balok meranti - -
4 Kg Paku Kayu - -
5 Tukang Kayu - -
0.5 Kepala Tukang kayu - -
4 Pekerja - -
0.1 Mandor - -
- -
Jumlah @ -
1 M2 bahan & Upah Pemasangan Papan kayu Begesting …………… 1.e = 1/10Jumlah @ -

1 Cor beton rabat k-175


1.000 M³ Beton K-175 - -

2 Cor beton Poer P1 (150x150x40) K-225


1.000 M³ Beton K-225 - -
87.048 Kg Bahan dan Upah Besi beton (Ulir) - -
5.167 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

3 Cor Sloof 35/50 cm k-225


1.000 M³ Beton K-225 - -
73.922 Kg Bahan dan Upah Besi beton (ulir) - -
24.369 Kg Bahan dan Upah Besi beton (Polos) - -
5.714 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
3 Cor Sloof 20/35 cm k-225
1.000 M³ Beton K-225 - -

100.275 Kg Bahan dan Upah Besi beton (Polos) - -


10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
4 Cor Sloof 10/ 20 cm k-225
1.000 M³ Beton K-225 - -
200.000 Kg Bahan dan Upah Besi beton (Polos) - -
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

5 Cor Beton Balok B1 (30/45 cm) K-225


1.000 M³ Beton K-225 - -
200.000 Kg Bahan dan Upah Besi beton (Polos) - -
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

6 Cor Beton K1 30/30 cm K-225. L. 1


1.000 M³ Beton K-225 - -
101.000 Kg Bahan dan Upah Besi beton (ulir) - -
34.072 Kg Bahan dan Upah Besi beton (Polos) - -
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
45
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
-
7 Cor Beton K2 20/20 cm K-225 (Teras )
1.000 M³ Beton K-225 - -
179.705 Kg Bahan dan Upah Besi beton (Polos) - -
20.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
8 Cor Beton K1 10/10 cm K-225 ( Praktis ) L : 1 dan 2
1.000 M³ Beton K-250 - -
272.704 Kg Bahan dan Upah Besi beton (polos) - -
16.270 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
9 Cor Beton Balok B1 (30/45 cm) K-225
1.000 M³ Beton K-250 - -
153.543 Kg Bahan dan Upah Besi beton (ulir) - -
55.687 Kg Bahan dan Upah Besi beton (polos) - -
9.500 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

46
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
10 Cor Beton Balok B2 (20/35 cm) K-225
1.000 M³ Beton K-250 - -
100.601 Kg Bahan dan Upah Besi beton (polos) - -
9.333 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
11 Cor Beton Balok Ring balk B1 (20/30 cm) K-225
1.000 M³ Beton K-250 - -
64.586 Kg Bahan dan Upah Besi beton (polos) - -
13.333 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
12 Cor Beton Balok Ring balk B2 (15/20 cm) K-225
1.000 M³ Beton K-225 - -
145.241 Kg Bahan dan Upah Besi beton (polos) - -
18.333 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
13 Cor Beton Plat lantai t = 12 cm K-225
1.000 M³ Beton K-225 - -
118.263 Kg Bahan dan Upah Besi beton (polos) - -
8.333 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
14 Cor Beton Plat Dak Atap t= 10 cm K-225
1.000 M³ Beton K-225 - -
140.718 Kg Bahan dan Upah Besi beton (polos) - -
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
15 Cor Beton Balok Dak Atap BD (25/40 cm) K-225
1.000 M³ Beton K-225 - -
50.294 Kg Bahan dan Upah Besi beton (ulir) - -
31.367 Kg Bahan dan Upah Besi beton (polos) - -
10.500 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
16 Cor Kanopy Beton tebal 7 cm K-225
1.000 M³ Beton K-225 - -
148.336 Kg Bahan dan Upah Besi beton (polos) - -
14.286 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
17 Cor Beton Balok Kenopi (10/20 cm) K-225
1.000 M³ Beton K-225 - -
128.914 Kg Bahan dan Upah Besi beton (polos) - -
13.333 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-
18 Cor Rabat Keliling Bangunan tebal 5 cm K-225
1.000 M³ Beton K-250 - -
43.623 Kg Bahan dan Upah Besi beton (polos) - -
-

19 Cor Beton balok tangga 20/30 cm K-225


1.000 M³ Beton K-250 - -
179.70 Kg Bahan dan Upah Besi beton (polos) - -
20.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

20 Cor Beton plat tangga t=10 cm K-225


1.000 M³ Beton K-225 - -
107.950 Kg Bahan dan Upah Besi beton (polos) - -
10.000 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

21 Cor Beton anak tangga K-225


1.000 M³ Beton K-225 - -
23.453 Kg Bahan dan Upah Besi beton (polos) - -

47
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
2.685 M2 Bahan dan Upah Papan /Kayu Bekisting - -
-

IV. PEKERJAAN KAYU


1 1 M3 Pekerjaan Kuzen ( Bangunan Permanen / -
Rumah Induk )
1.1 M³ Kayu lembasung - -
0.2 Kg Paku - -
36 Tukang Kayu - -
3.6 Kepala Tukang kayu - -
12 Pekerja - -
0.6 Mandor - -
- - -
2 1 M3 Pekerjaan Kuda - kuda Bentangan 7 M1
1.1 M³ Kayu Kapur - -
0.2 Kg Paku - -
24 Tukang Kayu - -
2.4 Kepala Tukang kayu - -
8 Pekerja - -
0.4 Mandor - -
- - -
1 M2 Pasangan Rangka Atap Baja Ringan
1 M2 Kuda - Kuda Zincalume (100.35.0,70) - -
1 M2 Reng Zincalume (30.45.40.15.0,6) - -
1 Ls Asesories - -
0.025 Org Kepala Tukang Kayu - -
0.25 Tukang - -
0.5 Pekerja - -
0.025 Mandor - -
- - -

3 1 M2 Rangka Atap Seng


0.012 M³ Kayu Kapur - -
0.1 Kg Paku - -
0.1 Tukang Kayu - -
0.01 Kepala Tukang kayu - -
0.15 Pekerja - -
0.075 Mandor - -
- - -
3 1 M2 Memasang Rangka Atap Genteng / Sirap /
Seng Multiroof
0.01 M³ Kayu Meranti - -
0.25 Kg Paku Kayu - -
0.1 Tukang Kayu - -
0.01 Kepala Tukang Kayu - -
0.1 Pekerja - -
0.005 Mandor - -
- - -
5 1 M2 Pasangan Atap Seng BJLS
1 Lbr Seng BJLS 20 - -
1 Lbr Seng BJLS 30 - -
0.15 Kg Paku Seng - -

48
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.02 Kepala Tukang Kayu - -
0.1 Pekerja - -
0.05 Mandor - -
Seng BJLS 20 - - -
Seng BJLS 30 - - -

4 1 M2 Pasangan Atap Multi Colour


1.35 Bh Atap Multi Roof - -
10 Paku Atap Multi Roof - -
0.02 Kepala Tukang Kayu - -
0.1 Pekerja - -
0.05 Mandor - -
- - -
1 M2 Pasangan Atap Surya Colour
1.7 Bh Atap Surya Roof - -
10 Paku Atap Surya Roof - -
0.02 Kepala Tukang Kayu - -
0.1 Pekerja - -
0.05 Mandor - -
- - -
1 M2 Pasangan Atap Sakura Roof
1.7 Bh Atap Sakura Roof - -
10 Paku Atap Sakura Roof - -
0.02 Kepala Tukang Kayu - -
0.1 Pekerja - -
0.05 Mandor - -
- - -

49
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
5 1 M1 Pasangan Bubungan Multi Colour
3.3 Lbr Multi Roof - -
3.3 Lbr Surya Roof - -
3.3 Lbr Sakura Roof - -
8 Bh Paku - -
0.25 Tukang - -
0.025 Kepala Tukang - -
0.25 Pekerja - -
- -
1 M1 Pasangan Bubungan Atap Multi roof -
1 M1 Pasangan Bubungan Atap Surya roof -
1 M1 Pasangan Bubungan Atap Sakura roof

BJLS 30 - - -
BJLS 20 - - -
1 M1 Pasangan Bubungan Atap Seng BJLS 30 -
1 M1 Pasangan Bubungan Atap Seng BJLS 30 -

8 1 M2 Pasangan Dinding Papan Susun Sirih


0.025 M³ Papan Meranti - -
0.025 M³ Papan Kapur - -
0.025 M³ Papan Ulin - -
0.15 Kg Paku Biasa - -
0.15 Kg Paku Ulin - -
0.4 Tukang Kayu - -
0.04 Kepala Tukang Kayu - -
0.14 Pekerja - -
0.007 Mandor - -
1 M2 Pasangan Dinding Papan Susun Sirih Meranti - - -
1 M2 Pasangan Dinding Papan Susun Sirih Kapur - - -
1 M2 Pasangan Dinding Papan Susun Sirih Ulin - - -

9 1 M2 Pasangan Dinding Papan Susun Tegak


0.028 M³ Papan Meranti - -
0.028 M³ Papan Kapur - -
0.028 M³ Papan Ulin - -
0.2 Kg Paku Biasa - -
0.2 Kg Paku Ulin - -
0.8 Tukang Kayu - -
0.08 Kepala Tukang Kayu - -
0.028 Pekerja - -
0.014 Mandor - -
1 M2 Pasangan Dinding Papan Susun Tegak Meranti - - -
1 M2 Pasangan Dinding Papan Susun Tegak Kapur - - -
1 M2 Pasangan Dinding Papan Susun Tegak Ulin - - -

1 M2 Pasangan rangka dinding


Jarak Rangka 60 Cm
0.007 M³ Kayu kapur - -
0.315 Kg Paku - -
1 Tukang Kayu - -
0.1 Kepala Tukang Kayu - -
- - -

0.08 Kepala Tukang Kayu - -

50
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.28 Pekerja - -
0.014 Mandor - -
- - -
13 1 M2 Pasangan Lantai dari Kayu Ulin
0.025 M³ Papan Kayu Ulin - -
0.2 Kg Paku - -
0.8 Tukang Kayu - -
0.08 Kepala Tukang Kayu - -
0.28 Pekerja - -
0.014 Mandor - -
- - -
14 1 M3 Pasangan Sloof dan Gelagar Kayu Kapur
1 M³ Balok Kayu Kapur - -
1 Kg Paku Ulin - -
15 Tukang Kayu - -
1.5 Kepala Tukang Kayu - -
5 Pekerja - -
0.25 Mandor - -
- - -
7 1 M2 Pasangan Tongkat, Sloof, Gelagar, Suai
Sepatu Ulin
1 M³ Balok Kayu Ulin - -
1 Kg Paku Ulin - -
15 Tukang Kayu - -
1.5 Kepala Tukang Kayu - -
5 Pekerja - -
0.25 Mandor - -
- - -
8 1 M2 Rangka Plafond dan Plafond Plywood
0.021 M³ Kayu Kapur - -
0.5 Lbr Plywood 4 MM - -
0.5 Lbr Plywood 6 MM - -
0.5 Lbr Plywood 1,8 CM - -
0.04 Kg Paku - -
0.32 Tukang Kayu - -
0.032 Kepala Tukang Kayu - -
0.8 Pekerja - -

0.08 Mandor - -
Plywood 4 MM - - -
Plywood 6 MM - - -
Plywood 1,8 CM - - -

17 1 M2 Pasangan Plafond dari Plywood


0.5 Lbr Plywood 1,8 CM - -
0.5 Lbr Plywood 4 MM - -
0.5 Lbr Plywood 6 MM - -
0.02 Kg Paku - -
0.5 Pekerja - -
0.025 Mandor - -
Plywood 1,8 MM - - -
Plywood 4 MM - - -
Plywood 6 MM - - -

9 1 M2 Pasangan Lesplank 2 / 20
0.024 M³ Papan Kayu Kapur - -
0.1 Kg Paku - -
0.8 Tukang Kayu - -
0.08 Kepala Tukang Kayu - -
51
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
0.28 Pekerja - -
0.014 Mandor - -
- - -
10 1 M1 Mengukur dan Pasang Bouwplank
0.019 M³ Papan Meranti - -
0.013 M³ Balok Meranti - -
0.01 Kg Paku - -
0.03 Tukang Kayu - -
0.003 Kepala Tukang Kayu - -
0.06 Pekerja - -
- - -

11 1 M2 Pasangan Plafond dari gypsumboard


0.364 Lbr Gypsumboard 9 mm - -
0.11 Kg Paku Sekrup - -
3.6 m Profil Aluminium - -
0.15 Kg Kawat dia 4 mm - -
0.5 Pekerja - -
0.5 Tukang Besi - -
0.05 Kepala Tukang - -
0.025 Mandor - -
- - -
18 1 M Pasangan Kusen Pintu Almunium
1.100 m Almunium Cokelat - -
2.000 bh Skrup Fixer - -
0.060 tube Sealant - -
0.043 Pekerja - -
0.043 Tukang Khusus Almunium - -
0.0043 Kepala Tukang - -
0.0021 Mandor - -
- - -

V. PEKERJAAN LANTAI
1 1 M2 Pasangan Keramik
1 M² Keramik 40 x 40 Asia - -
1 M² Keramik 20 x 20 Asia - -
1 M² Keramik 20 x 25 Asia - -
1 M² Keramik 30 x 30 Roman - -
1 M² Keramik 20 x 20 - -
1 M² Keramik Innesa - -
1 M² Keramik Maestro - -
1 M² Keramik 60 x 60 Granito - -
1 M² Keramik 40 x 40 Granito - - ###
1 M² Keramik 30 x 60 Granito - -
0.25 Zak Semen - -
0.01 Zak Semen Putih - -
0.026 M³ Pasir - -
0.25 Tukang Batu - -
0.025 Kepala Tukang Batu - -
0.5 Pekerja - -
0.025 Mandor - -

52
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
1 M² Keramik 40 x 40 Asia - - -
1 M² Keramik 20 x 20 Asia - - -
1 M² Keramik 20 x 25 Asia - - -
1 M² Keramik 40 x 40 Roman - - -
1 M² Keramik 20 x 20 - - -
1 M² Keramik Innesa - - -
1 M² Keramik 60 x 60 Granito - - -
1 M² Keramik 40 x 40 Granito - - -
1 M² Keramik 30 x 60 Granito - - -
1 M² Keramik Maestro - - -
2 1 m2 List Tegel Keramik 5 x 30 cm (Tangga)
67 bh Tegel Keramik 5 x 30 cm - -
0.25 zak Semen - -
0.01 zak Semen Warna - -
0.026 m3 Pasir Pasangan - -
0.25 Tukang Batu - -
0.025 Kepala Tukang Batu - -
0.5 Pekerja - -
0.025 Mandor - -
- - -

3 1 m2 Pasang Glass Box


25.000 bh Glass Box - -
0.250 kg Lem Kaca (Silicom) - -
0.500 OH Tukang Kayu - -
0.050 OH Kepala Tukang Kayu - -
1.000 OH Pekerja - -
0.050 OH Mandor - -
- - -

VI. PEKERJAAN PENGECATAN


1 1 M2 Upah Pengecatan
0.075 Tukang Cat - -
0.008 Kepala Tukang Cat - -
0.05 Pekerja - -
0.003 Mandor - -
- - -
2 10 M2 Menggosok / menyekrap dempul / Plamir.
0.8 Kg Dempul - -
2 Lbr Amplas - -
0.4 Tukang Cat - -
0.04 Kepala Tukang Cat - -
- - -
1 M2 Menggosok / menyekrap dempul / Plamir. -

3 1 M2 Pengecatan dengan Cat Air ( 2 kali Cat )


0.35 Kg Cat Air Paragon - -
0.35 Kg Cat Air Metrolite - -
0.35 Kg Cat Air Dulux ( ici ) - -
1 Upah Plamir / Dempul - -
1 Upah Pengecatan - -

1 M2 Pengecatan dengan Cat Air Paragon ( 2 kali Cat ) - - -


1 M2 Pengecatan dengan Cat Air Metrolite ( 2 kali Cat ) - - -
1 M2 Pengecatan dengan Cat Air Dulux ( 2 kali Cat ) - - -

4 1 M2 Pengecatan dengan Cat Kilap Avian ( 2 kali Cat )


0.35 Kg Cat Kilap Avian - -
0.057 Lt Pengencer Cat - -
1 Upah Plamir / Dempul - -
1 Upah Pengecatan - -

53
HARGA HARGA HARGA JUMLAH
NO U R A I A N SATUAN UPAH BAHAN HARGA
(RP ) (RP ) (RP ) (RP )
1 2 3 4 5 6
- - -
5 1 M2 Pengecatan Dasar / Meni
0.12 Kg Cat Meni - -
0.057 Lt Pengenceran Cat - -
1 Upah Pengecatan - -
- - -

54
1 M3 Beton K- 225
3.710 Zak Semen - -
0.698 M³ Pasir Pasangan - -
1.047 M³ Kerikil dari Batu Pecah - -
0.215 Tukang Batu - -
0.028 Kepala Tukang Batu - -
1.65 Pekerja - -
0.083 Mandor - -
- - -
110 Kg Pekerjaan besi beton
173.52 1 110 Kg Besi beton
1 2 2 Kg Kawat ikat
173.52 0.06136364 6.75 Tukang besi
173.52 0.02045455 2.25 Kepala Tk besi
173.52 0.06136364 6.75 Pekerja

0.4 0.5 0.2 1 5.0000

55
Besi Beton Polos 10.500
Kawat Bendrat 0.150

Pekerja 0.070
Tukang Besi 0.007
Kepala Tukang Besi 0.004

56
1,235,800,000.00

57
112,000.00
56,900.00
30,000.00
70,000.00
65,000.00
55,000.00
72,000.00

58
-
-
-

59
1.000 Upah kerja 34,000.00 34,000.00
Jumlah 78,100.00

60
DAFTAR HARGA SATUAN DASAR
( BASIC PRICE )
BAHAN BANGUNAN, UPAH DAN PERALATAN

JENIS HARGA SATUAN


No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5

I Harga Satuan Upah


1 Pekerja Biasa Hari Rp. - /Jam
2 Mandor Hari Rp. - /Jam
3 Tukang Kayu Hari Rp. - /Jam
4 Kepala Tukang Kayu Hari Rp. - /Jam
5 Tukang Batu Hari Rp. - /Jam
6 Kepala Tukang Batu Hari Rp. - /Jam
7 Tukang Cat Hari Rp. - /Jam
8 Kepala Tukang Cat Hari Rp. - /Jam
9 Tukang Besi Hari Rp. - /Jam
10 Kepala Tukang Besi Hari Rp. - /Jam
11 Tukang Gali Tanah Hari Rp. - /Jam
12 Kepala Tukang Gali Tanah Hari Rp. - /Jam

II Bahan Pasangan
1 Batu Gunung M3 Rp.
2 Pasir Urug M3 Rp.
3 Tanah Urug M3 Rp.
4 Pasir Pasangan M3 Rp.
5 Kerikil Beton M3 Rp.
6 Batu Pecah 2/3 cm M3 Rp.
7 Abu Batu M3 Rp.
8 Batu Bata Bh Rp.
9 Batu Bata Press Bh Rp.
10 Batu Tempel M2 Rp.
11 Bataco 20 x 30 Bh Rp.
12 Bataco 20 x 40 Bh Rp.
10 Semen PC (50 Kg) Zak Rp.
11 Semen Putih Kg Rp.
12 Roster (B) Bh Rp.
13 Roster (K) Bh Rp.
14 Paving Bujur Sangkar T = 8 cm Bh Rp.
15 Paving Bujur Sangkar T = 10 cm Bh Rp.
16 Paving Segi Enam (B) Bh Rp.
17 Paving Segi Enam (K) Bh Rp.
18 Glass Box Bh Rp.
19 Ijuk Kg Rp.

III Bahan Listrik


1 Stop Kontak + Instalasi Ttk Rp.
2 Lampu TL 1 x 18 watt + Instalasi Ttk Rp.
3 Lampu TL 2 x 18 watt + Instalasi Ttk Rp.
4 Lampu TL 2 x 20 watt + Instalasi Ttk Rp.
5 Lampu XL 18 watt + Instalasi Ttk Rp.
6 Lampu XL 20 watt + Instalasi Ttk Rp.
7 Lampu XL 14 watt + Instalasi Ttk Rp.
8 Lampu XL 200 watt + Instalasi Ttk Rp.
9 Box MCB 2 Group unit Rp.
10 Saklar Tunggal "Brocco" Ttk Rp.
11 Saklar Double "Brocco" Ttk Rp.
12 Stop Kontak "Brocco" Ttk Rp.
13 Sekering Kast group Rp.
14 Pasang Penangkal Petir 4 Split dan 2 Arde ls Rp.
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
IV Bahan Penggantung
1 Engsel Lokal Bh Rp.
2 Kunci-kunci Lokal Ttk Rp.
3 Hak Angin Lokal Bh Rp.
4 Expagnolet Lokal Bh Rp.
5 Grendel Lokal Bh Rp.
6 Kunci Tanam Union Bh Rp.
7 Kunci Tanam Yale Bh Rp.
8 Expagnolet Bh Rp.
9 Engsel Kupu-kupu 4" Psg Rp.
10 Engsel Kupu-kupu 3" Psg Rp.
11 Engsel Kupu-kupu 2" Psg Rp.
12 Hak Angin Bh Rp.
13 Handle jendela Bh Rp.

V Bahan Langit-langit
1 Eternit (asbes) Lbr Rp.
2 Plywood 3.6 mm Lbr Rp.
3 Teakwood Lbr Rp.
4 Acustik 30 x 60 Lbr Rp.
5 Plywood 4 mm Lbr Rp.
6 Plywood 6 mm Lbr Rp.
7 Plywood 18 mm Lbr Rp.
8 Gipsumboard 9 mm Lbr Rp.
9 Lem Aibon Kg Rp.
10 Plafond teakwood M2 Rp.
11 List Profil M1 Rp.
Profil Aluminum M1 Rp.
VI Bahan Lantai
1 Porselin 11 x 11 Bh/Box Rp.
2 Porselin 10 x 15 Bh/Box Rp.
3 Porselin 15 x 15 Bh/Box Rp.
4 Porselin 20 x 20 Bh/Box Rp.
5 Ubin Mozaik 30 x 30 Bh Rp.
6 Ubin Abu-abu 20 x 20 Bh Rp.
7 Plint Ubin Abu-abu 15 x 20 Bh Rp.
8 Ubin Berwarna 20 x 20 Bh Rp.
9 Plint Ubin Berwarna 15 x 20 Bh Rp.
10 Ubin Teraso 30 x 30 Bh Rp.
11 Plint Ubin Teraso 15 x 20 Bh Rp.
12 Ubin wafel 20 x 20 Bh Rp.
5 Keramik 30 x 30 M2 Rp.
6 Keramik 20 x 20 M2 Rp.
7 Tegel Innesa M2 Rp.
8 tegel Maestro M2 Rp.
9 Tegel Mozaik ( 20 x 20 ) M2 Rp.
7 List Keramik M2 Rp.
8 Marmer M2 Rp.
9 Keramik Ezenza M2 Rp.
10 Plint Keramik ezenza M 2
Rp.
8 Tegel Keramik 40 x 40 cm (Asia) dos Rp.
9 Tegel Keramik 30 x 30 cm (Asia) dos Rp.
10 Tegel Keramik 20 x 20 cm (Asia) dos Rp.
11 Tegel Keramik 20 x 25 cm (Asia) dos Rp.
12 Tegel Keramik 7 x 20 cm (Asia) bh Rp.
13 Tegel Keramik 5 x 30 cm (Asia) bh Rp.
14 Tegel Keramik 60 x 60 cm ( Granito ) m2 Rp.
15 Tegel Keramik 40 x 40 cm ( Granito ) m2 Rp.
16 Tegel Keramik 30 x 60 cm ( Granito ) m2 Rp.

VII Bahan Sanitair


1 Kloset Monoblok Lokal Bh Rp.
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
2 Bak Mandi Teraso Bh Rp.
1 Bak Mandi Fibre Bh Rp.
2 Bak Mandi Porselen Bh Rp.
3 Bak Mandi Plastik Bh Rp.
4 Kloset Jongkok Teraso Bh Rp.
2 Kloset Jongkok Keramik Bh Rp.
3 Kloset duduk Keramik Ekstra Bh Rp.
4 Kloset duduk ToTo Non Polos Bh Rp.
4 Urinoir Porselin Bh Rp.
6 Pintu PVC Lengkap Bh Rp.

5 Urinoir Monoblok Bh Rp.


6 Bak Cuci Piring Teraso Bh Rp.
7 Bak Cuci Piring Logam Bh Rp.
5 Sumur Pompa Tangan Terpasang Bh Rp.
6 Bak Cuci Tangan/Washtafel ( Keramik ) Bh Rp.
7 Meja Dapur Bh Rp.
7 Bak Mandi Keramik Bh Rp.
8 Washtafel Porslint lengkap Bh Rp.
9 Bak Cuci Alumunium Satu Lubang Bh Rp.
10 Profil 1100 liter Bh Rp.
10 Profil 1100 liter Bh Rp.
11 Floor drain Bh Rp.

VIII Bahan Paku


1 Paku Kayu Kg Rp.
2 Paku Seng Kg Rp.
3 Paku Ulin Kg Rp.
4 Paku Plywood Kg Rp.
5 Paku Sekrup Kg Rp.
6 Paku Asbes Bh/Ktk Rp.
7 Paku Kait Bh Rp.
8 Paku Sumbat Bh Rp.
9 Paku Reng Kg Rp.
10 Paku Multiroof Kg Rp.
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5

IX Bahan Kayu
1 Papan Ulin M3 Rp.
2 Balok Ulin M3 Rp.
3 Papan Kapur M3 Rp.
4 Balok Kapur M3 Rp.
5 Balok Meranti M3 Rp.
6 Papan Meranti M3 Rp.
7 Balok Bengkirai / Lembasung M3 Rp.
8 Papan Bengkirai / Lembasung M3 Rp.
9 Kayu Perancah M3 Rp.
10 Lumbre seering ( 1/10 cm x 200 cm ) lbr Rp.

X Bahan Sanitasi
1 Buis Beton Diameter 10 cm Bh Rp.
2 Buis Beton Diameter 20 cm Bh Rp.
3 Buis Beton Diameter 30 cm Bh Rp.

X Bahan Atap
1 Sirap Lbr Rp.
2 Atap Daun Lbr Rp.
3 Genteng Flam Bh Rp.
4 Karpus Genteng Flam Bh Rp.
5 Genteng Kodok Bh Rp.
6 Karpus Genteng Kodok Bh Rp.
7 Genteng Beton Bh Rp.
8 Karpus Genteng Beton Bh Rp.
9 Asbes Gelombang Besar Bh Rp.
10 Asbes Gelombang Kecil Bh Rp.
11 Karpus Asbes Gelombang Besar Bh Rp.
12 Karpus Asbes Gelombang Kecil Bh Rp.
13 Seng Gelombang BJLS 30 Lbr Rp.
14 Seng Gelombang BJLS 27 Lbr Rp.
15 Seng Profil Lbr Rp.
16 Seng Plat BJLS 30 Lbr Rp.
17 Seng Plat BJLS 27 Lbr Rp.
18 Genteng Kaca Bh Rp.
19 Genteng Keramik Bh Rp.
20 Karpus Genteng Keramik Bh Rp.
21 Genteng Metal Multicolour Lbr Rp.
22 Bubungan Metal Multicolour Lbr Rp.
23 Genteng Surya Colour Lbr Rp.
24 Bubungan Surya Colour Lbr Rp.
25 Genteng Sakura Colour Lbr Rp.
26 Bubungan Sakura Colour Lbr Rp.
27 Kuda - kuda Galvalum M2 Rp.
28 Reng Galvalum M2 Rp.
29 Asesories Ls Rp.

XI Bahan Kaca
1 Kaca Bening Tebal 3 mm M2 Rp.
1 Kaca Bening Tebal 5 mm M2 Rp.
2 Kaca Rayband Tebal 5 mm M2 Rp.
3 Naco ( Kerangka dan Daun ) M2 Rp.
4 Jendela Kaca M2 Rp.
3 Glass blok Bh Rp.
4 Kaca Polos Tebal 3 mm M2 Rp.
5 Kaca Buram Tebal 3 mm M2 Rp.
6 Kaca Buram Tebal 5 mm M2 Rp.
7 Kaca Rayband Tebal 3 mm M2 Rp.
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
8 Kaca Nako Polos Tebal 3 mm Set Rp.
9 Kaca Nako Rayband Tebal 3 mm Set Rp.
4 Lem kaca (silicon) Kg Rp.

XII Bahan Pipa


1 Pipa PVC Diameter 1/2" Btg Rp.
2 Pipa PVC Diameter 3/4" Btg Rp.
3 Pipa PVC Diameter 1" Btg Rp.
4 Pipa PVC Diameter 2" Btg Rp.
5 Pipa PVC Diameter 4" Btg Rp.
6 Pipa Diameter 4" Galvanis Btg Rp.
7 Pipa Diameter 3/4" Btg Rp.
8 Pipa Diameter 1" Btg Rp.
9 Pipa Diameter 1/2" Btg Rp.
10 Kran Air Btg Rp.
11 Pipa Air 1/2" Btg Rp.
12 Elbow 1/2" - 4" Btg Rp.
13 Pipa Galvanis 1/2" Btg Rp.
14 Pipa Galvanis 3/4" Btg Rp.
15 Pipa Galvanis 1" Btg Rp.
16 Pipa Galvanis 1,5" Btg Rp.
17 Pipa Galvanis 2" Btg Rp.
18 Pipa Galvanis 3" Btg Rp.
19 Pipa Galvanis 4" Btg Rp.
20 Pipa Stainless 2,5" M 1
Rp.
21 Pipa Stainless 2" M 1
Rp.
22 pipa Stainless 1,5" M1 Rp.
23 Pipa Satinless 1" M 1
Rp.
24 Talang Stainless 8/5 cm M1 Rp.

XIII Bahan Besi


1 Besi Beton Polos Kg Rp.
2 Besi Beton Ulir Kg Rp.
3 Reservoir Air Rangka Baja 0,5 M3 Bh Rp.
4 Reservoir Air Rangka Baja 1 M3 Bh Rp.
5 Besi eugel / Bout ( Kuda-kuda) Kg Rp.
6 Sumur Pompa Tangan Terpasang Bh Rp.
7 Teralis Besi Plat/Siku M2 Rp.
8 Stainlist Steel M2 Rp.
9 Kusen Alumunium Coklat 4" M1 Rp.
10 Kusen Alumunium Silver 4" M1 Rp.

XIV Bahan Kawat


1 Kawat Beton/Bendrat Kg Rp.
2 Kawat Duri Kg Rp.
3 Kawat Harmonika 4 x 4 M 2
Rp.
4 Kawat Nyamuk/ Kasa besi M 2
Rp.
5 Kawat Nyamuk/ Kasa Plastik M2 Rp.
6 Kawat Las Listrik (Elektroda) Kg Rp.
7 Kawat Kg Rp.
8 Kawat Bronjong Pabrikan :
a. Ukuran ( 2 x 1 x 1 ) Unit Rp.
b. Ukuran ( 2 x 1 x 0,5 ) Unit Rp.
c. Ukuran ( 3 x 1 x 0,5 ) Unit Rp.
d. Ukuran ( 1,5 x 1 x 1 ) Unit Rp.
9 Kawat BRC M2 Rp.
10 Kawat Ayam M2 Rp.
11 Kawat Nyamuk Hitam M2 Rp.
12 Kawat Nyamuk Putih M2 Rp.

XV Bahan Finishing
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
1 Amplas Kayu Lbr Rp.
2 Cat Meni Kg Rp.
3 Dempul Kayu Kg Rp.
4 Cat Kayu Mengkilat Kg Rp.
5 Cat Kayu Dasar Kg Rp.
7 Kerosin/Minyak Tanah Ltr Rp.
8 Plamur Tembok Kg Rp.
9 Minyak Cat Ltr Rp.
10 Residu Ltr Rp.
11 Cat Tembok 5 Kg Rp.
12 Cat Kilap Avian Kg Rp.
13 Cat Air Paragon Kg Rp.
JENIS HARGA SATUAN
No. Satuan KETERANGAN
( BAHAN, UPAH DAN PERALATAN) ( Tidak termasuk PPn 10% )
1 2 3 4 5
14 Cat air Metrolite Kg Rp.
15 Cat Air dulux ( ici ) Ltr Rp.
16 Tear Oil Kg Rp.
17 Cat Khusus Atap Kg Rp.
18 Plitur Kg Rp.
19 Alkali Kg Rp.

XVI Bahan Lain-lain


1 Agregat Halus Untuk Pondasi M3 Rp.
2 Agregat Kasar Untuk ATB M 3
Rp.
3 Agregat Kasar Untuk Beton M 3
Rp.

4 Agregat Kasar Untuk Pondasi M 3


Rp.
5 Agregat Halus Untuk ATB M3 Rp.
6 Filter Kg Rp.
7 Sirtu M3 Rp.
8 Pasir M 3
Rp. Quary
9 Tanah Timbunan M3 Rp. Quary
10 Tiang Pancang Beton 350 mm K-600 M1 Rp.
11 Tiang Pancang Beton 400 mm K-600 M 1
Rp.
12 Tiang Pancang Beton 450 mm K-600 M1 Rp.
13 Tiang Pancang Beton 500 mm K-600 M1 Rp.
14 Beton Roster/Kerawang Bh Rp.
15 Beton Tumbuk M3 Rp.
1 Ijuk Kg Rp.
2 Septictank dan Rembesan 1 M3 Bh Rp.
2 Septictank dan Rembesan 2 M 3
Unit Rp.
3 Septictank dan Rembesan 6 M3 Bh Rp.
4 Septictank dan Rembesan 10 M3 Bh Rp.
3 Tiang Bendera bh Rp.
4 Pasang Penangkal Petir 10 split dan 2 arde Ls Rp.
5 Biaya Penyambungan dari PLN 25 A Ls Rp.
6 Folding Gate 1,2 mm m2 Rp.
7 Biaya Pembuatan Sumur Bor Ls Rp.
8 Ground Reservoir 2 x 2,5 x 2 m + Asessories Unit Rp.
9 Profil Tank 1100 ltr + Asessories dan Instalasinya Unit Rp.
10 Pompa Air 250 watt Merek SANYO bh Rp.
11 Pancang Mini Pile 20/20 K-300 L=4m Btg Rp.
12 Biaya Pemancangan / Titik Titik Rp.
13 Biaya Penyambungan tiang pancang Titik Rp.
14 Biaya pembobokan Titik Rp.
15 Alat Bantu Rp.
PERHITUNGAN NILAI JAMINAN SOSIAL DAN TENAGA KERJA

Nilai Proyek (Belum Termasuk PPN 10%) = Rp 1,115,901,584.01

Nilai Jaminan Sosial dan Tenaga Kerja Sektor Konstruksi :

A = ( Rp 100,000,000.00 - Rp -

B = ( Rp 500,000,000.00 - Rp 100,000,000.00

C = ( Rp 1,000,000,000.00 - Rp 500,000,000.00

D = ( Rp 1,115,901,584.01 - Rp 1,000,000,000.00

Jadi Nilai Jaminan Sosial dan Tenaga Kerja Se


TENAGA KERJA SEKTOR KONSTRUKSI

) x 0.24% = Rp 240,000.00

) x 0.19% = Rp 760,000.00

) x 0.15% = Rp 750,000.00

) x 0.12% = Rp 139,081.90

dan Tenaga Kerja Sektor Konstruksi = Rp 1,889,081.90


PERHITUNGAN NILAI JAMINAN SOSIAL DAN TENAGA KERJA

Nilai Proyek (Belum Termasuk PPN 10%) = Rp 1,115,901,584.01

Nilai Jaminan Sosial dan Tenaga Kerja Sektor Konstruksi :

A = ( Rp 100,000,000.00 - Rp -

B = ( Rp 500,000,000.00 - Rp 100,000,000.00

C = ( Rp 1,000,000,000.00 - Rp 500,000,000.00

D = ( Rp 5,000,000,000.00 - Rp 1,000,000,000.00

E = ( Rp 1,115,901,584.01 - Rp 5,000,000,000.00

Jadi Nilai Jaminan Sosial dan Tenaga Kerja Se


TENAGA KERJA SEKTOR KONSTRUKSI

) x 0.24% = Rp 240,000.00

) x 0.19% = Rp 760,000.00

) x 0.15% = Rp 750,000.00

) x 0.12% = Rp 4,800,000.00

) x 0.10% = Rp (3,884,098.42)

dan Tenaga Kerja Sektor Konstruksi = Rp 2,665,901.58