1 Mutu Beton

fck fc' fc'

K   fck 
K .( 0,098 ) 0,76  0,2. log 15 . fck K .( 0,083 )
  
275 26.95 21.85 22.83
300 29.40 24.06 24.90
600 58.80 51.67 49.80
1 Dimensi Awal Balok
fc = 25 MPa
fy = 400 MPa

Bentang  f    f    fy   fy 
 0,4  y   0 , 4  y   0 , 4    0 , 4  
(mm) 16  700  21 700 8 700
18 ,5  700    
8000 485.71 420.08 370.07 971.43
4000 242.86 210.04 185.03 485.71
1000 60.71 52.51 46.26 121.43

h = 800 mm
b = 300 mm

2 Perencanaan Tebal Pelat


LnX = 3750 mm
LnY = 3700 mm
β = 1.01
= 2 Arah
t rencana = 120 mm

a) Rasio

Balok L bW h t bE = bW + (h - t) bE = bW + 4t

L 3000 300 700 120 880 780


T 4000 300 600 120 1260 1260
T 4000 200 500 120 960 1160
T 4000 300 700 120 1460 1260

b) Cek Tebal Pelat

 fy   fy 
n  0,8   n  0,8  
αm Ln  1400  1400 h
h h  
36  5  m  0,2  36  9 
2 3750 90.232 90.232 90.232
 fy 
 0 , 4  
8 700 
971.43
485.71
121.43

bE bE/bW t/h k Ib Is α

780 2.600 0.171 1.451 1.245E+10 2.160E+08 57.618


1260 4.200 0.200 1.775 9.584E+09 5.760E+08 16.639
960 4.800 0.240 1.879 3.915E+09 5.760E+08 6.796
1260 4.200 0.171 1.746 1.497E+10 5.760E+08 25.989

1 26.761
t
2 18.853
3 34.668
120 OK 4
5
6
7

A 24.784
B 26.761
C 22.807
D
E
3 Perencanaan Kolom

Komponen beban Beban (kN/m2)


Rumah sakit :
Ruang operasi, laboratorium q1 = 2.87
Ruang pasien q2 = 1.92
Koridor diatas lantai pertama q3 = 3.83
Ruang Pertemuan q3 = 4.79
Atap q4 = 0.96
Air Hujan 5 cm q5 = 0.50
Plafond 11 kg/m2
q6 = 0.18
Penggantung 7 kg/m2
Pelat lantai tipikal 12 cm q7 = 2.88
Penutup lantai :
Plester 2 cm q8 = 0.66
Keramik 1 cm
Plumbing dan MEP (asumsi) 25 kg/m2 q9 = 0.25
Dinding :
Berat batako 120 kg/m q10 = 1.2
Plesteran 0 0.04 m
Balok induk 30 70 cm q11 = 4.176
Balok anak 30 60 cm q12 = 3.456
Balok anak 20 50 cm q13 = 1.824
Balok anak cm = 0
Balok anak cm = 0
Balok anak cm = 0
Lantai 1,2 dan 7 Lantai 3 Lantai 4, 5. 6 dan 8
11.52 306.56 11.52 183.68 11.52 122.88
184.32 184.32 184.32
42.24 42.24 42.24
16 16 16
76.8 76.8 76.8
33.408 33.408 33.408
27.648 27.648 27.648
14.592 14.592 14.592

406.528 306.56 406.528 183.68 406.528 122.88


978.330 781.722 684.442
6897.766

Ag = 70 cm = 0.49 m
H1 = 5m = 5m
H2 = 4.5 m = 4.5 m

WK1 = 5.88 kN
WK2 = 5.292 kN
WK = 48.804 kN
PU = 6956.331 kN

fc' = 25 MPa
fy = 400 MPa
Ast = 1% Ag
Ag = 0.050 Pn(max)

Pn(max) = 0.8 x ( 21.250 - 0.213 + 4 )


= 0.8 x ( 25.038 Ag)
= 20.030 Ag
Ag = 0.050 Pn(max)

Pn(max) Kolom
Ag (mm2) h Syarat
(kN) b (cm) h (cm)
6956.331 347295.617 70 70 49.614 OK
tai 4, 5. 6 dan 8 Lantai Atap
122.88 11.52 61.44
184.32

16

33.408
27.648
14.592

122.88 287.488 61.44


684.442 443.290
1 Kolom gempa
fc = 25 Mpa Tingkat Kolom
Tingkat
Ec = 23500 kg/cm2 (cm) 90 80
Atap 500
8 450
7 450
6 450
5 450
4 450
3 450
2 450
1 500
Kolom Jumlah k1 (kg/cm) k2 (kg/cm) k3 (kg/cm) k4 (kg/cm) k5 (kg/cm)
70 60 50 Kolom
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
kt 0,8(kti 1  kti  2  kti 3 )
(kg/cm)
k ti  0 , 7 k ti  1 kti 
3
0 - -
0 OK -
0 OK -
0 OK OK
0 OK OK
0 OK OK
0 OK OK
0 OK OK
0 OK OK
Langkah - Langkah Perhitungan : 1 Cari nilai N (Klasifikasi Situs)
2 Cari nilai SS dan S1
3 Cari nilai Fa dan Fv
4 Cari nilai SDS dan SD1
5 Buat Kurva (T0, TS dan Sa)
6 Perioda Fundamental

1 Cari nilai N (Klasifikasi Situs)


Tebal
Lapisan Kedalaman lapisan, d Nilai di/Ni
N-SPT, Ni N
ke i (m) i
(m)
1 0 0 0 0.000
2 2 2 0 0.000
3 4 2 0 0.000
4 6 2 0 0.000
5 8 2 1 2.000
6 10 2 1 2.000
7 12 2 1 2.000
8 14 2 1 2.000
9 16 2 2 1.000 2.675
10 18 2 2 1.000
11 20 2 3 0.667
12 22 2 5 0.400
13 24 2 50 0.040
14 26 2 53 0.038
15 28 2 57 0.035
16 30 2 59 0.034
∑ 30 11.213

2 Cari nilai SS dan S1


SS = 0.017 g
S1 = 0.022 g

3 Cari nilai Fa dan Fv


Interpolasi : SS/S1 1 1.1 1.25
Situs 1.1 1.06 1

Fa = 2.5
Fv = 3.5

4 Cari nilai SDS dan SD1


SMS = 0.043 g
SM1 = 0.077 g
SDS = 0.028 g
SD1 = 0.051 g
5 Buat Kurva (T0, TS dan Sa)
T0 = 0.362 s
TS = 1.812 s

T T Sa
(detik) (detik) (g)
T 0 0.0113
T0 0.362 0.0283
TS 1.812 0.0283
Ts + 0.188 2.000 0.0257
Ts + 0.438 2.250 0.0228
Ts + 0.688 2.500 0.0205
Ts + 0.938 2.750 0.0187
Ts + 1.188 3.000 0.0171
Ts + 1.438 3.250 0.0158
Ts + 1.688 3.500 0.0147
Ts + 1.938 3.750 0.0137
Ts + 2.188 4.000 0.0128
Ts + 2.438 4.250 0.0121
Ts + 2.688 4.500 0.0114
Ts + 2.938 4.750 0.0108
Ts + 3.188 5.000 0.0103

6 Perioda Fundamental
Ct = 0.0466
hn = 41.5
x = 0.9
Cu = 1.7
Ta = 1.332 s
Tmaks = 2.265 s
Tc = 2.1 s
T = 2.100 s
Syarat 2 (Dimensi Memenuhi)
Tebal
Lapisan Kedalaman Nilai
lapisan, di di /Ni N
ke i (m) N-SPT, Ni
(m)
1 0 0 0 0.000
2 2 2 0 0.000
3 4 2 0 0.000
4 6 2 0 0.000
5 8 2 1 2.000
6 10 2 1 2.000
7 12 2 1 2.000
8 14 2 1 2.000
9 16 2 2 1.000 2.675
10 18 2 2 1.000
11 20 2 3 0.667
12 22 2 5 0.400
13 24 2 50 0.040
14 26 2 53 0.038
15 28 2 57 0.035
16 30 2 59 0.034
∑ 30 11.213
Pe rce p atan Re sp o n s Sp e kt r u m , S a (g )

Kurva Respon Spektrum


Wilayah Kota Pontianak
0.0300

0.0250

0.0200

0.0150

0.0100

0.0050

0.0000
0 1 2 3 4 5 6
Periode, T (detik)
1 Garasi / Parkir 1.92 kN/m² Super Dead (SD)
2 Ruang Kelas 1.92 kN/m² Lantai Beban
3 Ruang Kantor 2.4 kN/m² berat finishing pelat dak
4 Ruang Komputer 4.79 kN/m² Atap berat plester expose
5 Ruang Pertemuan 4.79 kN/m² berat plumbing dan instalasi listrik
6 Ruang Makan dan Restoran 4.79 kN/m² Total
7 Perpustakaan 7.18 kN/m² berat finishing pelat lantai
8 Gudang 6 kN/m² 2 - 10 berat plester expose
9 Atap 0.96 kN/m² berat plumbing dan instalasi listrik
Total
berat finishing pelat lantai
1 berat plester expose
berat plumbing dan instalasi listrik
Total
Base berat finishing pelat lantai

Beban
Dinding 1 m
Dinding 2 m
Dinding 3 m
Dinding 3,5 m
Dinding 4 m
Dead (SD) Beban Hidup (LL)
eban kN/m² Lantai Fungsi lantai kN/m² Lantai
ing pelat dak 0.315 base Parkir Mobil 1.92 atap
ster expose 0.315 1 Parkir Motor 1.92 10
dan instalasi listrik 0.25 Kantin 4.79 9
2
0.88 Ruang Administrasi 2.4 3-8
ng pelat lantai 0.66 3 Ruang Dosen 2.4 2
ster expose 0.315 4-6 Ruang Kelas 1.92 1
dan instalasi listrik 0.25 7 Ruang Komputer 4.79 base
1.225 8 Perpustakaan 7.18
ng pelat lantai 0.315 9 Ruang Serba Guna 4.79
ster expose 0.315 10 Gudang 6 Lantai
dan instalasi listrik 0.25 11 Atap 0.96 atap
0.88 10
ng pelat lantai 0.315 9
3-8
eban kN/m² 2
ing 1 m 1.83 1
ing 2 m 3.66 base
ing 3 m 5.49
ng 3,5 m 6.405
ing 4 m 7.32
Angin (W) dari depan
Kecepatan Tinggi Jarak Tekan Hisap Jarak Tekan Hisap
0.4 1.5 4 2.16 0.96 6 3.24 1.44
0.4 3 4 4.32 1.92 6 6.48 2.88
0.4 3.5 4 5.04 2.24 6 7.56 3.36
0.4 4 4 5.76 2.56 6 8.64 3.84
0.4 3.875 4 5.58 2.48 6 8.37 3.72
0.4 3.75 3 4.05 1.8 6 8.1 3.6
0.4 1.875 3 2.025 0.9 6 4.05 1.8

Angin (W) dari kanan


Kecepatan Tinggi Jarak Tekan Hisap Jarak Tekan Hisap Jarak Tekan Hisap
0.4 1.5 3 1.62 0.72 6 3.24 1.44 8 4.32 1.92
0.4 3 3 3.24 1.44 6 6.48 2.88 8 8.64 3.84
0.4 3.5 3 3.78 1.68 6 7.56 3.36 8 10.08 4.48
0.4 4 3 4.32 1.92 6 8.64 3.84 8 11.52 5.12
0.4 3.875 3 4.185 1.86 6 8.37 3.72 8 11.16 4.96
0.4 3.75 2 2.7 1.2 6 8.1 3.6 8 10.8 4.8
0.4 1.875 2 1.35 0.6 6 4.05 1.8 8 5.4 2.4
Jarak Tekan Hisap
4 2.16 0.96
Kombinasi DL SD LL Wx Wy EQx EQy
Comb1 1.4 1.4
Comb2 1.2 1.2 1.6
Comb3 1.2 1.2 1 1
Comb4 1.2 1.2 1 -1
Comb5 1.2 1.2 1 1
Comb6 1.2 1.2 1 -1
Comb7 1.2056 1.2056 1 1 0.3
Comb8 1.2056 1.2056 1 -1 0.3
Comb9 1.2056 1.2056 1 -1 -0.3
Comb10 1.2056 1.2056 1 1 -0.3
Comb11 1.2056 1.2056 1 0.3 1
Comb12 1.2056 1.2056 1 0.3 -1
Comb13 1.2056 1.2056 1 -0.3 -1
Comb14 1.2056 1.2056 1 -0.3 1
Comb15 0.9 0.9 1
Comb16 0.9 0.9 -1
Comb17 0.9 0.9 1
Comb18 0.9 0.9 -1
Comb19 0.8944 0.8944 1 0.3
Comb20 0.8944 0.8944 -1 0.3
Comb21 0.8944 0.8944 -1 -0.3
Comb22 0.8944 0.8944 1 -0.3
Comb23 0.8944 0.8944 0.3 1
Comb24 0.8944 0.8944 0.3 -1
Comb25 0.8944 0.8944 -0.3 -1
Comb26 0.8944 0.8944 -0.3 1