PARKS AND RECREATION: CAPITAL PLANNING REPORT JUNE 2019

Project Project Name Funding Source Ward Active Phase Comments


Manager
R. Just Armory Park Improvements Tucson Delivers & 6 Yes In design Joint project with Rio Nuevo to design and construct improvements to Armory Park, including new stage with
Rio Nuevo shade, renovation of existing restroom, hardscape and plaza, new site furnishings and lighting improvements.
Conceptual planning is in progress and conceptual approvals from various entities will be sought in the near
future. The project is being designed through Rio Nuevo. A formal agreement has yet to be executed.

R. Just Cherry Avenue Park Improvements Tucson Delivers 5 Yes Planning Design and construct multiple renovations including basketball court resurfacing, adding a large playground with
shade, ramada, and restrooms. Accounting setup and consultant selection are in progress.

J. O'Neill El Pueblo Pool Slide Tower Replacement Tucson Delivers 5 Yes In design Structural review underway. Construction contract awarded to Durazo.
R. Just Estevan Park Field Lighting Tucson Delivers Yes Planning New lighting for existing multi-purpose field. Accounting setup and consultant selection are in progress.
1
H. Dutt Jesse Owens Park - Pool Equipment Tucson Delivers 2 Yes Complete Renovating and replacing pool filtration equipment. Completion is expected June 14, 2019.
Renovation

R. Just Chuck Ford Lakeside Park Improvements Tucson Delivers Yes Planning Replace existing playground shade and upgrade lighting on softball field 1. Accounting setup and consultant
4
selection are in progress.
R. Just Mission Manor Park Improvements Tucson Delivers Yes Planning New shade for existing playground and new splash pad. Accounting setup and consultant selection are in
1
progress.
H. Dutt Lincoln Splash Pad Tucson Delivers 4 Yes In design Design underway for project completion in March 2020
J. O'Neill Purple Heart Park Tucson Delivers 4 Yes Complete Requested proposal from design consultant for softball field lighting and new splash pad.

R. Just Palo Verde Pool Renovations Tucson Delivers 2 Yes In Renovate existing pool and resurface deck. Construction is substantially complete and punch list is in progress.
construction Pool reopening celebration scheduled for 06/15/19.
J. O'Neill Reid Park Splash Pad Tucson Delivers 6 Yes Planning New splash pad in Reid Park. Funding available July 2019 for desigh. Requesting proposal for design phase.
Researching the best location within Reid Park to site the splash pad.

J. O'Neill Sears Park Tucson Delivers 6 Yes Planning Requested proposal from design consultant for Phase II irrigation improvements.
R. Just Udall Park Splash Pad Tucson Delivers 2 Yes Planning New splash pad adjacent to existing pool at Udall Park. Accounting setup and consultant selection are in
progress.

Revised: 06/12/19 1 of 1 1