PERHITUNGAN VOLUME

NO. MATA PEMB. : 7.1.(8)


ITEM PEKERJAAN : BETON MUTU RENDAH DENGAN FC'=15 Mpa
SATUAN : M3
Tebal Lebar Panjang
NO BENTUK Perhitungan
(M) (M) (M)
BOX CULVERT (3X4X3) 20M

1 LANTAI KERJA
P Luas Penampang =
A=TxL
0.10 10.2 20.0 0.10 x 10.20 = 1.02 m2
T
L Volume Beton =
V=AxP
1.02 x 20.00 = 20.40 m3
Panjang box = 20 m

VOLUME TOTAL
TUNGAN VOLUME

Volume
(M3)

20.40

20.40
REKAPITULASI VOLUME
NO. MATA PEMB. : 7.1.(7)a
ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3

DIMENSI
NO BENTUK Perhitungan
(m) (m) (m)

BOX CULVERT (3X4X3) 20 M STA 3 + 700

1 Dinding Box T H P Volume =


T 0.3 4.00 20 V= T x H x P
jumlah 4 sisi V = 0.30 x 4.00 x 20.00 = 24.00 m3

H jumlah 4 sisi kanan kiri


P Vtot= 4x 24.00 = 96.00 m3

2 Lantai Bawah dan Atas

T L P Volume =
P 0.3 10.2 20 V= T x L x P
T V = 0.30 x 10.20 x 20.00 = 61.20 m3
L
jumlah : 2 sisi jumlah 2 sisi atas bawah
Vtot= 2x 61.20 = 122.40 m3
3 Siku Dalam
H L P Volume =
H 0.3 0.3 20 V= H x L x P
V = 0.30 x 0.30 x 20.00 = 1.80 m3
P
L jumlah 6 sisi (2 atas 2 bawah) TRIPEL
jumlah : 6 sisi Vtot= 6x 1.80 = 10.80 m3

4 Dinding Sayap
t
H L t Volume =
H 0.3 4 0.3 V= H x L x t
V = 0.30 x 4.00 x 4.60 = 5.52 m3
L jumlah 4 sisi
jumlah : 4 sisi
Vtot= 4x 5.52 = 22.08 m3

Sub Total
NO. MATA PEMB. : 7.1.(7)a
ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3 Halaman :
PERHITUNGAN STA
DIMENSI
NO BENTUK Perhitungan
(m) (m) (m) (m)
5 Kerb
t1 P Volume
t1 t2 H1 P V1 = (t1 + t2) /2 x H1 x
0.20 0.3 0.3 10.20 V1 = (0,20 + 0,30) /2 x 0.30 x
H1 V1 = 0.765
T2 H2 P
0.30 0.2 10.20 V2 = T2 x H2 x P
V2 = 0.3 x 0.20 x 10.20
V2 = 0.612
H2
V= V1 + V2 = 0.77 + 0.61 = 1.38

t2 Volume Dua Sisi


Jumlah = 2 sisi Vtot = 2.00 x 1.38 = 2.75

6 Koker

T T H P Volume =
0.40 1.00 10.20 V= T x H x P
H V= 0.40 x 1.00 x 10.20 = 4.08

P jumlah 2 sisi kanan kiri


Vtot= 2x 4.08 = 8.16
jumlah : 2
Sub. Total
VOLUME TOTAL
KAPITULASI VOLUME

Volume
Perhitungan
(M3)

96.00

122.40

10.80

22.08

b Total 251.28
Halaman : 2
ERHITUNGAN STA
Volume
Perhitungan
(M3)

P
10.20

1.38

2.75 2.75

m3

m3 8.16

. Total 10.91
ME TOTAL 262.19
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d e
TRIPLE BOX CULVERT (3X4X3 )20M STA 4+700

I Lantai dan Dinding Box

A ø 19 - 20 72 72 190 34

B ø 19 - 20 72 72 190 34

C ø 16 - 20 213

D ø 19 - 20 80 102 24 34

E ø 10 - 20 79
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d e

F ø 10 - 20 24 454

G
ø 10 - 20 2000

H ø 12 - 18 1014 24

J ø 12 - 20 354 24

K ø 16 - 20 117 189 34
Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )

402 404 1624.08 2.226 3,614.50

402 404 1624.08 2.226 3,614.50

213 606 1,290.78 1.578 2,037.16

194 404 783.76 2.226 1,744.31

79 400 316 0.617 194.81


Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )

5 966 400 3,864 0.617 2,382.16

2000 202 4,040 0.617 2,490.66

1038 116 1,204 0.888 1,068.93

5 766 202 1,547 0.888 1,373.65

374 808 3,022 1.578 4,769.32

Sub Total 23,289.99


PERHITUNGAN VOLUME
NO. MATA PEMB. : 7.1.(8)
ITEM PEKERJAAN : BETON MUTU RENDAH DENGAN FC'=15 Mpa
SATUAN : M3

Tebal Lebar Panjang


NO BENTUK Perhitungan
(M) (M) (M)
BOX CULVERT (2x2,5) 20 M

1 LANTAI KERJA
P Luas Penampang =
A=TxL
0.10 2.52 20.0 0.10 x 2.52 = 0.25 m2
T
L Volume Beton =
V=AxP
0.25 x 20.00 = 5.04 m3
Panjang box = 20 m

VOLUME TOTAL
TUNGAN VOLUME

Volume
(M3)

5.04

5.04
REKAPITULASI VOLUME

NO. MATA PEMB. : 7.1.(7)a


ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3
DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (

SINGLE BOX CULVERT (2X 2,5) 20 M

1 Dinding Box T H P Volume =


T 0.26 2.50 20 V= T x H x P
jumlah 2 sisi V = 0.26 x 2.50 x 20.00 = 13.00 m3
H
P jumlah 2 sisi kanan kiri
Vtot= 2x 13.00 = 26.00 m3

2 Lantai Bawah dan Atas

T L P Volume =
P 0.26 2.5 20 V= T x L x P
T V = 0.26 x 2.50 x 20.00 = 13.00 m3
L
jumlah : 2 sisi jumlah 2 sisi atas bawah
Vtot= 2x 13.00 = 26.00 m3
3 Siku Dalam
H L P Volume =
H 0.26 0.26 20 V= H x L x P
V = 0.26 x 0.26 x 20.00 = 1.35 m3
P
L jumlah 4 sisi (2 atas 2 bawah)
jumlah : 4 sisi Vtot= 2x 1.35 = 2.70 m3

4 Dinding Sayap
t
H L t Volume =
H 3 3 0.25 V= H x L x t
V = 3.00 x 3.00 x 0.25 = 2.25 m3
L
jumlah : 4 sisi Vtot= 4x 2.25 = 9.00 m3

Sub Total
DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (m) (
5 Kerb
Volume
t1 P t1 t2 H1 P V1 = (t1 + t2) /2 x H1 x P
0.20 0.3 0.3 2.50 V1 = (0,20 + 0,30) /2 x 0.30 x 2.50
H1 V1 = 0.1875
T2 H2 P
0.30 0.2 2.50 V2 = T2 x H2 x P
V2 = 0.3 x 0.20 x 2.50
H2 V2 = 0.15

V= V1 + V2 = 0.19 + 0.15 = 0.34


t2
Volume Dua Sisi
Jumlah = 2 sisi Vtot = 0.34 x 2.00 = 0.68
6 Koker

T T H P Volume =
0.40 1.00 2.50 V= T x H x P
H V= 0.40 x 1.00 x 2.50 = 1.00 m3

P jumlah 2 sisi kanan kiri


Vtot= 2 x 1.00 = 2.00 m3
jumlah : 2
Sub. Total
VOLUME TOTAL
KAPITULASI VOLUME

Volume
(M3)

26.00

26.00

2.70

9.00

63.704
Volume
(M3)

0.68
2.00

2.68
66.38
REKAPITULASI VOLUM
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d
SINGLE BOX CULVERT (2X 2,5 )20M STA 5+800
1 Lantai dan Dinding Box

a
d
A c ø 19 - 40 48 61 133 28
b

d
B

ø 19 - 40 48 61 133 28

a
C
e b ø 12 - 20 246 20

D ø 12 - 20 296 20
e
b

E e a e ø 10 - 20 2000

tulangan bagi

a
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
a ( Cm ) a b c d
F ø 10 - 20 68

2 A Sayap

a
A1 ø 12 - 18

e b

a
B
B1 b ø 12 - 18
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d
3 A Kerb

a
ø 10 - 20 15 60 33 34

b
d
e

B
e e
ø 10 - 10 850
a

4 A Koker

a
ø 10 - 20 36 92

e
b

B
e e
a
8 ø 10 246
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d
Diketahui Oleh : Diketahui Oleh : Diketahui Oleh : Periksa Ole
Pejabat Pelaksana Teknis Kegiatan ( PPTK ) Pengawas Teknis Pengawas Teknis Konsultan Pen
DINAS PEKERJAAN UMUM DINAS PEKERJAAN UMUM DINAS PEKERJAAN UMUM CV. TIKA KREATIF
KABUPATEN LAMANDAU KABUPATEN LAMANDAU KABUPATEN LAMANDAU KONSULTA

DENI APRILA, ST DWI SUGIYANTO, A.Md RIDUWAN BILL MILNER


NIP. 19810407 201101 2 001 NIP. 19790822 201001 1 013 NIP. 19730529 200502 1 001 Supervision En
PITULASI VOLUME

Panjang Jumlah Total Berat Total


Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )

298 204 607.92 2.226 1,352.97

298 204 607.92 2.226 1,352.97

5 542 202 1,094.84 0.888 971.96

5 642 202 1,296.84 0.888 1,151.28

10 2020 100 2020 0.617 1,245.33


Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )
68 400 272 0.617 167.69

Sub Total 6,242.19

68 0.888 936.00

72 1.578 908.00

Sub Total 1,844.00


Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )

5 48 200 85 170 0.617 104.81

5 860 24 206.4 0.617 127.25

Sub Total 232.05

5 266 25 65.436 0.617 40.34

5 256.00 32 81.92 0.617 50.50

Sub Total 90.84


Jumlah Total ( Kg ) 8,409.08
Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )
Periksa Oleh : Periksa Oleh : Dibuat Oleh :
Konsultan Pengawas Konsultan Pengawas Kontraktor Pelaksana
CV. TIKA KREATIF DESAIN CV. TIKA KREATIF DESAIN PT. SANGGA BUANA
KONSULTAN KONSULTAN MULTI KARYA

BILL MILNER, ST PRIS OKTONADI, ST DIKI RIYADI


Supervision Engineer Inspector Site Manager
PERHITUNGAN VOLUME

NO. MATA PEMB. : 7.1.(8)


ITEM PEKERJAAN : BETON MUTU RENDAH DENGAN FC'=15 Mpa
SATUAN : M3
Tebal Lebar Panjang
NO BENTUK Perhitungan
(M) (M) (M)
BOX CULVERT (2X3) 20 M

1 LANTAI KERJA
P Luas Penampang =
A=TxL
0.10 2.56 20.0 0.10 x 2.56 = 0.26 m2
T
L Volume Beton =
V=AxP
0.26 x 20.00 = 5.12 m3
Panjang box = 20 m

VOLUME TOTAL
TUNGAN VOLUME

Volume
(M3)

5.12

5.12
REKAPITULASI VOLUME

NO. MATA PEMB. : 7.1.(7)a


ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3

DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (

SINGLE BOX CULVERT (2X 3) 20 M

1 Dinding Box T H P Volume =


T 0.3 3.00 20 V= T x H x P
jumlah 2 sisi V = 0.30 x 3.00 x 20.00 = 18.00 m3

H jumlah 2 sisi kanan kiri


P Vtot= 2x 18.00 = 36.00 m3

2 Lantai Bawah dan Atas

T L P Volume =
P 0.3 2.6 20 V= T x L x P
T V = 0.30 x 2.60 x 20.00 = 15.60 m3
L
jumlah : 2 sisi jumlah 2 sisi atas bawah
Vtot= 2x 15.60 = 31.20 m3
3 Siku Dalam
H L P Volume =
H 0.3 0.3 20 V= H x L x P
V = 0.30 x 0.30 x 20.00 = 1.80 m3
P
L jumlah 4 sisi (2 atas 2 bawah)
jumlah : 4 sisi Vtot= 2x 1.80 = 3.60 m3

4 Dinding Sayap
t
H L t Volume =
H 3 3.6 0.3 V= H x L x t
V = 3.00 x 3.60 x 0.30 = 3.24 m3
L jumlah 2 sisi
jumlah : 2 sisi
t Vtot= 4x 3.24 = 12.96 m3
P
P H t Volume =
3.56 3.28 0.3 V= P x P x t x 0.5
H V = 2.25 x 3.28 x 0.30 x 0.5 = 1.107
jumlah sisi
Vtot= 2x 1.11 = 2.21 m3
t
P P H t Volume =
3.56 3.28 0.3 V= P x P x t x 0.5
H V = 2.25 x 3.28 x 0.30 x 0.5 = 1.107
jumlah 2 sisi
Vtot= 2x 1.11 = 2.21 m3
Sub Total
NO. MATA PEMB. : 7.1.(7)a
ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3 Halaman : 2
PERHITUNGAN STA
DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (m) (
5 Kerb
Volume
t1 P t1 t2 H1 P V1 = (t1 + t2) /2 x H1 x P
0.20 0.3 0.3 2.58 V1 = (0,20 + 0,30) /2 x 0.30 x 2.58
V1 = 0.1935
H1
T2 H2 P
0.30 0.2 2.58 V2 = T2 x H2 x P
V2 = 0.3 x 0.20 x 2.58
V2 = 0.1548
H2
V= V1 + V2 = 0.19 + 0.15 = 0.35

t2 Volume Dua Sisi


Jumlah = 2 sisi Vtot = 0.35 x 2.00 = 0.70

6 Koker

T T H P Volume =
0.40 1.00 2.60 V= T x H x P
H V= 0.40 x 1.00 x 2.60 = 1.04 m3

P jumlah 2 sisi kanan kiri


Vtot= 2 x 1.04 = 2.08 m3
jumlah : 2
Sub. Total
VOLUME TOTAL
KAPITULASI VOLUME

Volume
(M3)

36.00

31.20

3.60

12.96
83.76
ERHITUNGAN STA
Volume
(M3)

0.70

2.08

2.78
86.54
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d
SINGLE BOX CULVERT (2X 3 )20M STA 5+340
1 Lantai dan Dinding Box

a
d
A c ø 19 - 40 48 73 136 31
b

d
B

ø 19 - 40 48 73 136 31

a
C
e b ø 12 - 20 250 22

D ø 12 - 20 350 22
e
b

E e a e ø 10 - 20 2000

tulangan bagi

a
F ø 10 - 20 73
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
NO.ITEM PEMBAYARAN : 7.3 (1)
SATUAN PEMBAYARAN : KG
Diameter
Dimensi ( Cm )
N0 Type Sketsa Jarak
( Cm ) a b c d

2 A Sayap

a
A1 ø 12 - 18

e b

B a
B1 b
ø 12 - 18
Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )

319 204 650.76 2.226 1,448.31

319 204 650.76 2.226 1,448.31

5 554 202 1,119.08 0.888 993.47

5 754 202 1,523.08 0.888 1,352.13

10 2020 100 2020 0.617 1,245.33

73 400 292 0.617 180.02


Panjang Jumlah Total Berat Total
Dimensi ( Cm )
Pot. Pot. Panjang Satuan Berat
e f ( cm ) ( Buah ) (m) ( Kg/m' ) ( Kg )
Sub Total 6,667.57

116 0.888 1,828.00

136 1.578 2,012.00

Sub Total 3840.0000


PERHITUNGAN VOLUME

NO. MATA PEMB. : 7.1.(8)


ITEM PEKERJAAN : BETON MUTU RENDAH DENGAN FC'=15 Mpa
SATUAN : M3

Tebal Lebar Panjang


NO BENTUK Perhitungan
(M) (M) (M)
SINGLE BOX CULVERT (2X 2 ) 20 M

1 LANTAI KERJA
P Luas Penampang =
A=TxL
0.10 2.5 20.0 0.10 x 2.50 = 0.25 m2
T
L Volume Beton =
V=AxP
0.25 x 20.00 = 5.00 m3
Panjang box = 20 m

VOLUME TOTAL
ITUNGAN VOLUME

Volume
(M3)

5.00

5.00
REKAPITULASI VOLUME

NO. MATA PEMB. : 7.1.(7)a


ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3

DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (

SINGLE BOX CULVERT (2X 2) 20 M

1 Dinding Box T H P Volume =


T 0.25 2.00 20 V= T x H x P
jumlah 2 sisi V = 0.25 x 2.00 x 20.00 = 10.00 m3

H jumlah 2 sisi kanan kiri


P Vtot= 2x 10.00 = 20.00 m3

2 Lantai Bawah dan Atas

T L P Volume =
P 0.25 2.5 20 V= T x L x P
T V = 0.25 x 2.50 x 20.00 = 12.50 m3
L
jumlah : 2 sisi jumlah 2 sisi atas bawah
Vtot= 2x 12.50 = 25.00 m3
3 Siku Dalam
H L P Volume =
H 0.25 0.25 20 V= H x L x P
V = 0.25 x 0.25 x 20.00 = 1.25 m3
P
L jumlah 4 sisi (2 atas 2 bawah)
jumlah : 4 sisi Vtot= 2x 1.25 = 2.50 m3

4 Dinding Sayap
t
H L t Volume =
H 2.5 2.5 0.25 V= H x L x t
V = 2.50 x 2.50 x 0.25 = 1.56 m3
L jumlah 2 sisi
jumlah : 2 sisi
Vtot= 4x 1.56 = 6.25 m3
t
P P H t Volume =
2.5 2.25 0.25 V= P x P x t x 0.5
H V = 2.25 x 2.25 x 0.25 x 0.5 = 0.633
jumlah 2 sisi
Vtot= 2x 0.63 = 1.27 m3

t
P P H t Volume =
2.5 2.25 0.25 V= P x P x t x 0.5
H V = 2.25 x 2.25 x 0.25 x 0.5 = 0.633
jumlah 2 sisi
Vtot= 2x 0.63 = 1.27 m3
Sub Total
NO. MATA PEMB. : 7.1.(7)a
ITEM PEKERJAAN : BETON MUTU SEDANG DENGAN FC'=20 Mpa
SATUAN : M3 Halaman : 2
PERHITUNGAN STA
DIMENSI Vo
NO BENTUK Perhitungan
(m) (m) (m) (m) (
5 Kerb
Volume
t1 P t1 t2 H1 P V1 = (t1 + t2) /2 x H1 x P
0.20 0.3 0.3 2.46 V1 = (0,20 + 0,30) /2 x 0.30 x 2.46
V1 = 0.1845
H1
T2 H2 P
0.30 0.2 2.46 V2 = T2 x H2 x P
V2 = 0.3 x 0.20 x 2.46
V2 = 0.1476
H2
V= V1 + V2 = 0.18 + 0.15 = 0.33

t2 Volume Dua Sisi


Jumlah = 2 sisi Vtot = 0.33 x 2.00 = 0.66

6 Koker

T T H P Volume =
0.40 1.00 2.50 V= T x H x P
H V= 0.40 x 1.00 x 2.50 = 1.00 m3

P jumlah 2 sisi kanan kiri


Vtot= 2 x 1.00 = 2.00 m3
jumlah : 2
Sub. Total
VOLUME TOTAL
KAPITULASI VOLUME

Volume
(M3)

20.00

25.00

2.50

6.25

53.75
ERHITUNGAN STA
Volume
(M3)

0.66

2.00

2.66
56.41
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
LOKASI : BERUTA BELANTIKAN

Diameter Panjang
N0 Type Sketsa
Dimensi ( Cm ) Pot.
Jarak
( Cm ) a b c d e f ( cm )
SINGLE BOX CULVERT (2X 2 )
1 Lantai dan Dinding Box

a
d c
A b ø 19 - 40 48 48 132 27 282

a
B
b ø 12 - 20 245 20 530

a ø 10 - 20 995 995
C

D ø 10 - 20 65 65

Sub Total

2 A Sayap
a
A1 ø 16 - 20 245 15 520

B
b
B1 ø 16 - 20 245 15 545

Sub Total
Jumlah Total Berat Total Harga
Pot. Panjang Satuan Berat 12m/btg Satuan
( Buah ) (m) ( Kg/m' ) ( Kg ) (Rp)

192 541.440 2.224 1,204.42 45 165,000

200 1,060.00 0.887 940.57 88 90,000

104 1,034.80 0.616 637.644 86 75,000

200 130 0.616 80.106 11 75,000

2,862.74

52 270.40 1.577 426.5484 23 120,000

52 283.40 1.577 447.0556 24 120,000

873.60
Harga

7,444,800.00

7,950,000.00

6,467,500.00

812,500.00

22,674,800

2,704,000.00

2,834,000.00

5,538,000
Harga
ITEM PEKERJAAN : BAJA TULANGAN U24 POLOS
LOKASI : BERUTA BELANTIKAN

Diameter Panjang
N0 Type Sketsa
Dimensi ( Cm ) Pot.
Jarak
( Cm ) a b c d e f ( cm )

3 A Kerb
a
ø 10 - 20 25 120 35 75 300.9
f

b
d

B a 7 ø 10 245 245

Sub Total

4 A Koker

a
ø 10 - 20 120 35 310

B a

8 ø 10 245 245

Sub Total

TOTAL PEMBESIAN
Jumlah Total Berat Total Harga
Pot. Panjang Satuan Berat 12m/btg Satuan
( Buah ) (m) ( Kg/m' ) ( Kg ) (Rp)

26 78.234 0.616 48.20779 7 75,000

14 34.3 0.616 21.13566 3 75,000

69.34345

26 80.6 0.616 49.66572 7 75,000

16 39.2 0.616 24.15504 3 75,000

73.821
3,879.51
Harga

488,962.50

214,375.00

703,338

503,750.00

245,000.00

748,750

29,664,888

10560000.0000