Activity a
• Can be completed by 3 days with a cost of $40.
• Can be completed by 2 days with a cost of $80.
Activity b
• Can be completed by 2 days with a cost of $20.
• Can be completed by 1 days with a cost of $80.
Activity c
• Cannot be crashed
Example – Crashing a Project
Activity d
• Allow partial crashing
• Can be completed by 4 days with a cost of $30
• Can be completed by 3 days with a cost of $60
• Can be completed by 2 days with a cost of $90
• Can be completed by 1 day with a cost of $120
Activity e
• Can be completed by 3 days with a cost of $10
• Can be completed by 1 day with a cost of $80
Example – Crashing a Project
Example – Crashing a Project
2 ($20)
3 ($10)
3 ($40)
2 ($20)
4 ($30)
Total duration : 8 days
Total cost : $120
Example – Crashing a Project
2 ($20)
4 ($30)
Total duration : 7 days
Total cost : $160
Example – Crashing a Project
1 ($80)
3 ($10)
OPTION Y 2 ($80) 2 ($20)
4 ($30)
Total duration : 6 days
Total cost : $220
Example – Crashing a Project
2 ($20)
OPTION Y 2 ($80) 1 ($80)
2 ($20)
3 ($60)
Total duration : 5 days
Total cost : $260
Example – Crashing a Project
2 ($90)
Example – Crashing a Project
Probabilistic Activity Durations
• Three time estimates made for both normal
resource loading and crash resource
loading
• Variance of normal activity may be
different than variance of crash time
Fast-Tracking a Project
• Used Primarily in Construction Industry
• Building phase started before design and
planning phases completed
• Particularly appropriate when large
proportion of work is routine
RESOURCE LOADING
Resource Loading
• Amount of specific resources that are
scheduled for use on specific activities or
projects at specific times.
• Helps project managers develop a general
understanding of the demands a project
will make on the organization’s resources
and individual people’s schedules
• Usually a list or table.
Example of Resource Usage Calendar
RESOURCE LEVELING
Resource Leveling
• Resource leveling aims to minimize the
period-by-period variations in resource
loading by shifting tasks within their slack
allowances.
• In other words, resource leveling is a
technique for resolving resource conflicts
by delaying tasks
• The purpose is to create a smoother
distribution of resource usage
Resource Leveling
• Advantages
– More efficient resource management
– When resources are used on a more constant
basis, they require less management
– Be able to use ‘just in time’ inventory policy
with right quantity delivered
– If the resource being leveled is people, it
improves morale and results in fewer
problems in the personnel and payroll offices
Example of Resource Leveling
The activity time is shown
above the arc, and
resource usage (one
resource, workers) is in
brackets below the arc.
Without Resource Leveling
Example of Resource Leveling
Assume that each task takes 10 days to complete and standard deviation of 3
days. How many days to complete the project for each scenario
Table 6-6 Project Completion Time Statistics Based
on Simulating Three Projects 200 Times