Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA

KANTOR PJR
BOGOR

NO ITEM PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Direksi Keet & gudang bahan M2 12.00 120,000 1,440,000
2 Pengukuran,pemasangan bouplank M' 52.00 15,000 780,000
4 Pembersihan lahan,pengukuran lanscape ( jalan ) M2 137.73 20,000 2,754,600

SUB TOTAL A 4,974,600

B PEKERJAAN STRUKTUR BANGUNAN UTAMA


I PEKERJAAN TANAH DAN PONDASI DAN BETON
1 Galian Pondasi batu kali tapak dan sloof M3 101.31 120,000 12,157,200
2 Urugan pasir bawah pondasi M3 3.22 25,000 80,500
3 Urugan Pasir bawah lantai M3 6.06 25,000 151,500
4 pek. Pas pondasi batu kali M3 24.14 110,000 2,655,400
5 Pek. Pondasi tapak
Beton K225 M3 2.29 900,000 2,061,000

6 Pek. Urugan Kembali Bekas Galian M3 74.29 30,000 2,228,700


7 Pek. Sloof S1 20 x 25
Beton K225 M3 3.54 900,000 3,186,000

8 Pek. Sloof S2 15 x 20
Beton K225 M3 1.14 900,000 1,026,000

9 Pek. Sloof S3 15 x 15
Beton K225 M3 0.78 900,000 702,000

10 Pek. Kolom K1 15 x 40
Beton K225 M3 0.68 900,000 612,000

11 Pek. Kolom K2 15 X 30
Beton K225 M3 3.42 900,000 3,078,000

12 Pek. Kolom KP 15 x 15
Beton K225 M3 1.44 1,200,000 1,728,000

13 Balok B1 15 x 40
Beton K225 M3 1.83 900,000 1,647,000

14 Balok B1 15 x 30
Beton K225 M3 1.08 1,200,000 1,296,000

15 Balok B2 15 x 20
Beton K225 M3 1.61 900,000 1,449,000

16 Pek. Ring Balok 10 x 10


Beton K225 M3 0.39 1,200,000 468,000

17 Pek. Floor lantai kerja ` M3 6.06 700,000 4,242,000


18 Pek. Cor dak beton lantai atap
Beton K225 M3 1.31 1,200,000 1,572,000

19 Pek Topian Beton


Beton K225 M3 4.96 1,200,000 5,952,000
HALAMAN 1
NO ITEM PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)

20 Pek. Cor meja beton pantry Unit 1.00 1,200,000 1,200,000

SUB TOTAL B 47,492,300

C PEKERJAAN ARSITEKTUR BANGUNAN UTAMA


I PEKERJAAN DINDING
1 Pek. Pasang dinding Bata M2 212.50 40,000 8,500,000
2 Pek. Plesteran M2 207.00 30,000 6,210,000
3 Pek. Acian Dinding M2 207.00 20,000 4,140,000
4 Pek. Dinding Partisi double M2 73.44 40,000 2,937,600
5 Pek openingan pintu dan jendela M' 79.45 60,000 4,767,000
6 Keramik dinding Toilet service 20 x 25 M2 21.00 40,000 840,000
7 Pasang Keramik dinding dapur 20 x 25 M2 13.20 40,000 528,000
8 Keramik dinding Ruang Wudhu 20 x 25 M2 3.50 40,000 140,000

SUB TOTAL 28,062,600

II PEKERJAAN LANTAI BANGUNAN UTAMA


1 Pasang lantai Keramik 40 x 40 M2 64.00 30,000 1,920,000
2 Pasang Lantai keramik KM 40 x 40 M2 5.00 35,000 175,000
3 Pasang Lantai Keramik teras 40 x 40 M2 53.00 30,000 1,590,000
4 Pasang keramik meja dapur 20 x 25 M2 1.20 40,000 48,000
5 Acian halus topian beton M2 75.50 60,000 4,530,000

SUB TOTAL 8,263,000

SUB TOTAL C 36,325,600

D PEKERJAAN ATAP
5 Waterproofing dak talang M2 12.00 20,000 240,000
6 Waterproofing Topian beton M2 75.50 20,000 1,510,000

SUB TOTAL D 1,750,000

E PEKERJAAN PENGECATAN
1 Pengecatan dinding exsterior M2 212.50 12,000 2,550,000
2 Pengecatan dinding interior M2 335.88 12,000 4,030,560
3 Pengecatan Plafond M2 120.00 12,000 1,440,000

SUB TOTAL E 8,020,560

F PEKERJAAN ME PLAMBING & LISTRIK


1 PEKERJAAN SANITAIR
1 Pek. Pasang Instalasi air kotor padat 4 " M' 10.00 40,000 400,000
2 Septictank biotec Unit 1.00 1,500,000 1,500,000
3 Pas. Pasang Instalasi air bekas 3 " M' 8.00 30,000 240,000
4 Pas. Pasang Instalasi air bekas 2,5" M' 4.00 30,000 120,000
5 Pek. Pasang Instalasi air Bersih 2 " M' 20.00 10,000 200,000
6 Pek. Pasang Instalasi air Bersih 1 " M' 30.00 10,000 300,000
7 Pek. Pasang Instalasi air Bersih 1/2 " M' 12.00 10,000 120,000
8 Pek. Pasang Instalasi Air Hujan 3 " M' 25.00 15,000 375,000
9 Pek. Pasang Floor drain bh 3.00 25,000 75,000
10 Pek. Pasang Klosed duduk bh 2.00 200,000 400,000
11 Pek. Jet Washer bh 2.00 40,000 80,000
12 Pasang Kran bh 4.00 10,000 40,000
13 Pasang Kran dapur bh 1.00 10,000 10,000
14 Pasang torn air ( @ 1 m3 ) bh 1.00 300,000 300,000
HALAMAN 2
NO ITEM PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
15 Pasang Kitchen zink Unit 1.00 150,000 150,000
17 Pasang bak kontrol uk. 50 x 50 Unit 2.00 150,000 300,000

SUB TOTAL 4,610,000

SUB TOTAL F 4,610,000

JUMLAH TOTAL A + B + C + D + E + F 103,173,060

Jakarta, 02 Agustus 2017

Tarsadi
Sub Kontraktor

HALAMAN 3