Anda di halaman 1dari 1

WAKTU DALAM MINGGU

No KEGIATAN BIAYA BOBOT (%) WAKTU KET


1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 PERSIAPAN 1,350,000 1.582 1-2 0.791 0.791
2 PEK. TANAH 3,667,000 4.296 2-5 1.074 1.074 1.074 1.074
3 PEK. PONDASI 5,700,000 6.678 5-7 2.226 2.226 2.226
4 PEK. BETON 17,986,000 21.072 6-8 7.024 7.024 7.024
5 PEK. PASANGAN 4,789,000 5.611 8-10 1.870 1.870 1.870
6 PEK. KAYU HALUS 6,875,000 8.055 9-10 4.027 4.027
7 PEK. ATAP 11,500,000 13.473 10-12 4.491 4.491 4.491
8 PEK. PLAFON 6,890,700 8.073 12 8.073
9 PEK. LANTAI 8,785,000 10.292 12-14 3.431 3.431 3.431
10 PEK. ELEKTRIKAL 4,456,000 5.221 7-8 & 10-12 1.044 1.044 1.044 1.044 1.044
11 PEK. PENGECATAN 8,896,000 10.423 11-14 2.606 2.606 2.606 2.606
12 PEK. PERLENGKAPAN 4,459,000 5.224 12-14 1.741 1.741 1.741
JUMLAH
TOTAL 85,353,700 100 0.791 1.865 1.074 1.074 3.300 9.250 10.294 9.938 5.898 11.433 8.141 21.386 7.778 7.778
PERMINGGU
JUMLAH
NAMA : CAHYA SUCI WULANDHARI 0.791 2.656 3.730 4.804 8.104 17.354 27.648 37.587 43.484 54.917 63.058 84.444 92.222 100