Action Plan
Action Plan
Prod
Edisi Rev 0
1 Timbunan Jalan Kerja sisi Kiri dan Sisi Kanan M3 268,800 22,400 22,400 3,200 3,200 3,200 3,200 3,200 3,200 3,200 Volume Rencana
2 Clearing / Striping/Grabbing M2 144,000 18,000 18,000 2,571 2,571 2,571 2,571 2,571 2,571 2,571 Volume Rencana
3 Pemasangan Geotextile Woven/non Woven M2 112,000 7,000 7,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 Volume Rencana
Volume Realisasi
4 Timbunan Badan Jalan (mainroad) M3 61,875 3,867 3,867 1,289 1,289 1,289 Volume Rencana
.………...., ……………….2017
Diketahui / Disetujui, Dibuat oleh :
Kalap Pelaksana
.................................................... ....................................................
Form . Prod 12
PROGRAM PENGADAAN SUMBER DAYA MINGGUAN Edisi 1 Rev 0
ÿ ALAT
PROYEK : ……………….
LOKASI : ……………….
NO JENIS MATERIAL SAT KUANT.KEB EST.TERSEDIA PROGRAM / REALISASI TGL ……… S/D TGL ……….. KET
TOTAL AKHIR MGG INI KUANTITAS TGL …… TGL …… TGL …… TGL …… TGL …….. TGL …….. TGL ……..
1 2 3 4 5 6 7 8 9 10 11 12 13 14
.……....., ……………….
Diketahui / Disetujui, Dibuat oleh :
Kalap Pelaksana
....................................................
....................................................
Form . Prod
Edisi 1 Rev 0
PROYEK : ……………….
LOKASI : ……………….
PERIODE : ………………..
LAPORAN PELAKSANAAN
KONDISI CUACA
TANGGAL
JAM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 KET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
....……..., ………………..
Diketahui / Disetujui, Dibuat oleh,
..........................................… ..........................................…