Anda di halaman 1dari 6

PEMERINTAH KOTA SUNGAI PENUH

DINAS PEKERJAAN UMUM DAN PENATAAN RUANG


TAHUN ANGGARAN 2019

GAMBAR RENCANA
KEGIATAN :
REHABILITASI / PEMELIHARAAN JALAN

PEKERJAAN :
REHABILITASI JALAN SIMPANG III RAWANG - AIR SEMPIT

TAHUN ANGGARAN 2019


CL
AC -BC t = 6 CM
KLAS A t = 15 CM

2% 2%

175 175 CROSS SECTION


200 200
STA 0 + 897

CL
AC -BC t = 6 CM
KLAS A t = 15 CM

2% 2%

175 175 CROSS SECTION


200 200
STA 0 + 900

CL
AC -BC t = 6 CM
KLAS A t = 15 CM

2% 2%

175 175 CROSS SECTION


200 200
STA 0 + 955
CL
AC -BC t = 6 CM
KLAS A t = 15 CM

2% 2%

175 175 CROSS SECTION


200 200
STA 2 + 350

CL
AC -BC t = 6 CM
KLAS A t = 15 CM
TIMBUNAN BIASA DARI SUMBER GALIAN t = 50
CM
2% 2%

175 175
200 200 CROSS SECTION
225 225
STA 2 + 400

CL
AC -BC t = 6 CM
KLAS A t = 15 CM
TIMBUNAN BIASA DARI SUMBER GALIAN t = 50
CM
2% 2%

175 175
200 200 CROSS SECTION
225 225
STA 2 + 450
CL

TIMBUNAN BIASA DARI SUMBER GALIAN t = 50


CM
2% 2%

200 200 CROSS SECTION


225 225
STA 2 + 800

CL

TIMBUNAN BIASA DARI SUMBER GALIAN t = 50


CM
2% 2%

200 200 CROSS SECTION


225 225
STA 2 + 850

CL

TIMBUNAN BIASA DARI SUMBER GALIAN t = 50


CM
2% 2%

200 200 CROSS SECTION


225 225
STA 2 + 910