FUEL GAS FABRICATION SCHEDULE

Activity ID Activity Name Original Week


Duration
-3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

FUEL GAS 22.0w FUEL GAS


MILESTONES 22.0w MILESTONES
A1000 Project Effective Date 0.0w Project Effective Date
A1010 Start Date for Fabrication 0.0w Start Date for Fabrication
A1020 Finish Date for Fabrication 0.0w Finish Date for Fabrication
A1030 Finish Date for Delivery 0.0w Finish Date for Delivery
ENGINEERING
ENGINEERIN 6.4w ENGINEERING
A1035 Receive Specification, Data Sheet... 0.1w Receive Specification, Data Sheet...
A1040 3D Modeling 2.0w 3D Modeling
A1037 Approval Data Sheet 1.0w Approval Data Sheet
A1050 Calculate 4.0w Calculate
A1060 Issued DWGs 0.3w Issued DWGs
PROCUREME
PROCUREMENT 18.0w PROCUREMENT
A1070 Fuel Gas Supper Heater 18.0w Fuel Gas Supper Heater
A1080 Fuel Gas Filter 18.0w Fuel Gas Filter
A1100 Manual Valves 17.0w Manual Valves
A1110 Gauge 16.0w Gauge
A1120 Transmitter 16.0w Transmitter
A1130 Actuated Valves 17.0w Actuated Valves
A1140 Pressure Safety Valve 17.0w Pressure Safety Valve
A1150 Juntion Box 12.0w Juntion Box
A1090 Piping Bulks 6.0w Piping Bulks
A1065 Structure, Pipe Support, E&I Support 6.0w Structure, Pipe Support, E&I Support
CONSTRUCTION
CONSTRUCT 9.5w CONSTRUCTION
A1160 Structure Fabrication & Erection 3.0w Structure Fabrication & Erection
A1180 Piping Fabrication & Hydrotest 3.0w Piping Fabrication & Hydrotest
A1170 Pipe Support, E&I Support Fabrication & Erection 2.0w Pipe Support, E&I Support Fabrication & Erection
A1190 Blasting/ Painting Framing 0.6w Blasting/ Painting Framing
A1200 Blasting/ Painting Pipe Spools 0.6w Blasting/ Painting Pipe Spools
A1210 Install Piping & Valves 2.1w Install Piping & Valves
A1220 Install Fuel Gas Filter 0.1w Install Fuel Gas Filter
A1230 Install Fuel Gas Supper Heater 0.1w Install Fuel Gas Supper Heater
A1250 Install Juntion Box, Gauge,Transmitter 0.3w Install Juntion Box, Gauge,Transmitter
A1260 FAT & Final Inspection 1.0w FAT & Final Inspection
A1270 Touch-up Painting 0.3w Touch-up Painting
A1280 Packing & Transportation 0.4w Packing & Transportation

Actual Level of Effort Critical Remaining Work summary Date Revision Checked Approved
Page 1 of 1
07-May-18
Remaining Work Milestone