Pt A, Ch 1, Sec 3

SECTION 3 ASSIGNMENT OF CLASS

1 General 2.1.4 As part of his interventions during the ship’s construc-


tion, the Surveyor will:
• conduct an overall examination of the parts of the unit
1.1 covered by the Rules
• examine the construction methods and procedures
1.1.1 Class is assigned to a unit upon a survey, with the when required by the Rules
associated operations, which is held in order to verify
• check selected items covered by the rule requirements
whether it is eligible to be classed on the basis of the Rules
of the Society (see Ch 1, Sec 1, [1.3.2]). This may be • attend tests and trials where applicable and deemed
achieved through: necessary.

• the completion of the new building, during which a sur- Note 1: The Society’s surveys cannot be considered as a substitute
for the construction control which remains the responsibility of the
vey has been performed
Builder, nor for the unit’s acceptance which remains the responsi-
• a survey carried out according to the agreement devel- bility of the Owner.
oped by the IACS Member Societies when units change
2.1.5 Use of materials, machinery, appliances and
class between members, or
items
• a specific admission to class survey, in cases where a As a general rule, all materials, machinery, boilers, auxiliary
unit is classed with a non-IACS Society or is not classed installations, equipment, items etc. (generally referred to as
at all. “products”) which are covered by the class and used or fitted
on board units surveyed by the Society during construction
are to be new and, where intended for essential services as
2 New building procedure defined in Ch 1, Sec 1, [1.2.1], tested by the Society.
Second hand materials, machinery, appliances and items
2.1 Units surveyed by the Society during may be used subject to the specific agreement of the Soci-
construction ety and the Owner.
The requirements for the selection of materials to be used in
2.1.1 When a unit is surveyed by the Society during con- the construction of the various parts of a unit, the character-
struction, it is to comply with those requirements of the istics of products to be used for such parts and the checks
Rules which are in force and applicable depending on the required for their acceptance are to be as stated in Part C
class of the ship, taking into account the provisions of Ch 1, and in NR216 Materials and Welding, as applicable, or in
Sec 1, [2.2] and Ch 1, Sec 1, [2.3]. other Parts of the Rules or as specified on approved plans. In
particular, the testing of products manufactured according
2.1.2 The Society: to quality assurance procedures approved by the Society
and the approval of such procedures are governed by the
• approves the plans and documentation submitted as requirements of NR216 Materials and Welding.
required by the Rules
2.1.6 Defects or deficiencies and their repair
• proceeds, if required, with the appraisal of the design of
The Society may, at any time, reject items found to be
materials and equipment used in the construction of the
defective or contrary to rule requirements or require supple-
unit and their inspection at works
mentary inspections and tests and/or modifications, not-
• carries out surveys or obtains appropriate evidence to withstanding any previous certificates issued.
satisfy itself that the scantlings and construction meet the All repairs are subject to the preliminary agreement of the
rule requirements in relation to the approved drawings Society. When the limits of tolerance for defects are speci-
• attends tests and trials provided for in the Rules fied in the Rules concerned or by the Manufacturer, they are
to be taken into account for repairs.
• assigns the construction mark {; refer to Ch 1, Sec 2, It is incumbent upon the Interested Party to notify the Soci-
[3.1.2]. ety of any defects noted during the construction of the unit
and/or of any item not complying with the applicable
2.1.3 The Society defines in specific Rules which materials requirements or in any case unsatisfactory. Proposals
and equipment used for the construction of units built regarding remedial actions intended to be adopted to elimi-
under survey are, as a rule, subject to appraisal of their nate such defects or unsatisfactory items are to be submitted
design and to inspection at works, and according to which to the Society and, if accepted, carried out to the Surveyor’s
particulars. satisfaction.