PRESUPUESTO ALTERNATIVA I

PROYECTO : “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION - CUSCO

UBICACIÓN
SECTOR : HELARES
DISTRITO : KIMRIRI
PROVINCIA : LA CONVENCION
DEPARTAMENTO : CUSCO
ITEM DESCRIPCION UND METRADO C.U.

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und 1.00 974.21
01.02 CONSTRUCCION DE ALAMACEN Y CAMPAMENTO PROVISIONAL 12M X 6M GLB 1.00 3,533.52
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2 328.00 0.63
02.02 TRAZO Y REPLANTEO PRELIMINAR m2 328.00 0.26
02.03 CONTROL TOPOGRAFICO EN PROCESO CONSTRUCTIVO m2 328.00 1.27
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION MATERIAL CON BOLONERIA BAJO AGUA m3 88.20 69.99
03.02 EXCAVACION MATERIAL CON BOLONERIA m3 88.00 18.98
03.03 EXCAVACION CON MAQUINARIA m3 600.60 10.36
03.04 RELLENO COMPACTADO CON MATERIAL GRANULAR m3 142.20 50.19
03.05 RELLENO COMPACTADO CON MATERIAL PROPIO m3 406.07 15.69
03.06 ACARREO DE MATERIAL EXCEDENTE D=30 MT. m3 211.44 7.59
04 OBRAS DE CONCRETO SIMPLE
04.01 FALZA ZAPATAS, MEZCLA C:H 1:10 + 30%P.G. m3 27.00 200.35
04.02 CONCRETO F'C=175 KG/CM2 + 40% P.G. m3 96.00 239.29
04.03 ENCOFRADO Y DESENCOFRADO. m2 114.40 25.49
05 OBRAS DE CONCRETO ARMADO
05.01 ZAPATA DE ESTRIBO
05.01.01 CONCRETO F'C= 210 KG/CM2 m3 67.50 398.27
05.01.02 ENCOFRADO Y DESENCOFRADO. m2 46.00 25.49
05.01.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg 3,945.38 4.55
05.02 PANTALLA Y ALAS
05.02.01 CONCRETO F'C= 210 KG/CM2 m3 68.95 398.27
05.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 246.10 44.72
05.02.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg 2,088.05 4.55
05.03 COLUMNAS EN TORRE DE CONCRETO ARMADO
05.03.01 CONCRETO F'C= 210 KG/CM2 m3 6.34 398.27
05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 63.36 44.72
05.03.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,908.48 4.55
05.04 VIGAS EN TORRE DE CONCRETO ARMADO
05.04.01 CONCRETO F'C= 210 KG/CM2 m3 1.58 398.27
05.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 13.20 44.72
05.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg 191.33 4.55
06 SUPERESSTRUCTURA DE PUENTE COLGANTE
06.01 MONTAJE MECANICO DE SUPERESTRUCTURA DE PUENTE COLGANTE. GLB 1.00 37,650.98
06.02 COLOCACION DE PENDOLAS. und 66.00 211.87
06.03 VIGA 4" X 6" und 33.00 226.10
06.04 TABLERO DE MADERA. GLB 1.00 65,296.24
06.05 BARANDA DE MADERA. GLB 1.00 69,755.74
06.06 COLOCACION DE CARRILES. und 4.00 1,753.09
06.07 ARMADO Y COLOCACION DE TEMPLADORES EN CAMARA DE ANCLAJE. GLB 1.00 36,520.32
07 OBRAS DE PROTECCION
07.01 ENCAUSAMIENTO DE CURSOS DE AGUA m3 3,000.00 8.10
07.02 PROTECCION DE ESTRIBOS m3 2,820.00 9.13
08 PINTURA
08.01 PINTURA ANTICORROSIVO EPOXI ZINCROMATO m 571.56 6.84
08.02 PINTURA ESMALTE SINTETICO EN SUPERFICIE METALICO (02 MANOS) m 571.56 6.12
08.03 PINTURA ESMALTE SINTETICO EN SUPERFICIE DE CONCRETO (02 MANOS) m2 225.82 12.82
08.04 ACABADO EN CARPINTERIA DE MADERA m2 281.84 13.62
09 CONTROL DE CALIDAD
09.01 ENSAYO DE ROTURA DE PROBETA DE CONCRETO und 26.00 30.00
09.02 SEGURIDAD PERSONAL
09.02.01 INDUCCION EN SEGURIDAD PERSONAL GLB 1.00 1,500.00
09.02.02 EQUIPO DE PROPTECCION PERSONAL GLB 1.00 5,250.00
10 PLACA RECORDEATORIA
10.01 PLACA RECORDATORIA ACRILICA und 1.00 604.27
11 FLETE Y TRANSPORTE TERRESTRE
11.01 FLETE PARA TRASLADO DE ACCESORIOS GLB 1.00 15,000.00
12 CONFORMACION DE COMITE DE GESTION
12.01 CONFORMACION DE COMITE DE GESTION GLB 1.00 1,500.00
12.02 MANUAL DE CAPACITACION und 1.00 375.00
01 PROGRAMAS DE CAPACITACION Y SENSIBILIZACION EN TEMAS DE MANTENIMIENTO
01.01 PROGRAMA DE CAPACITACION Y SENSIBILIZACION EN MANTENIMIENTO und 1.00 1,300.00
01.02 MATERIALES DE CAPACITACION GLB 1.00 236.00
14 PLAN DE MANEJO AMBIENTAL
14.01 SENSIBILIZACIÓN Y CAPACITACIÓN EN TEMAS AMBIENTALES
14.01.01 CONSTRUCCION DE MICRO RELLENO SANITARIO m3 27.00 193.64
14.01.02 RECOLECCION MANUAL DE RESIDUOS DE AREA DE TRABAJO m3 20.00 25.32
14.01.04 RECUPERACION DE AREA DE BOTADERO E INST. DE COBERTURA VEGETAL M2 9.00 0.95
14.01.05 SEÑALES INFORMATIVAS (IMPACTO AMBIENTAL) und 4.00 130.37
14.01.06 LIMPIEZA FINAL DE OBRA m2 328.00 0.76

COSTO DIRECTO
GASTOS GENERALES (12.30% C.D.)

SUB TOTAL - VALOR REFERENCIAL


COSTO DEL EXPEDIENTE TECNICO (1.83% C.D.)
GASTOS DE SUPERVISION (5.50% V.R.)
GASTOS ADMINISTRATIVOS (1.0% V.R.)

TOTAL PRESUPUESTO
- CUSCO”

TOTALES TOTALES

4,507.73
974.21
3,533.52
708.48
206.64
85.28
416.56
29,178.67
6,173.12
1,670.24
6,222.22
7,137.02
6,371.24
1,604.83
31,297.35
5,409.45
22,971.84
2,916.06
110,106.38
46,007.25
26,883.23
1,172.54
17,951.48
47,966.94
27,460.72
11,005.59
9,500.63
14,042.07
2,525.03
2,833.46
8,683.58
2,090.12
629.27
590.30
870.55
237,680.36
37,650.98
13,983.42
7,461.30
65,296.24
69,755.74
7,012.36
36,520.32
50,046.60
24,300.00
25,746.60
14,141.09
3,909.47
3,497.95
2,895.01
3,838.66
7,530.00
780.00
6,750.00
1,500.00
5,250.00
604.27
604.27
15,000.00
15,000.00
1,875.00
1,500.00
375.00
1,536.00
1,300.00
236.00
6,513.99
6,513.99
5,228.28
506.40
8.55
521.48
249.28

510,725.92
62,819.29

573,545.21
10,500.00
31,544.99
5,735.45

621,325.65

FACTORES DE CORRECCION A PRECIOS SOCIALES

DESCRIPCION VALOR
MANO DE OBRA CALIFICADA 0.91
MANO DE OBRA NO CALIFICADA 0.41
BIENES NO TRANSABLES 0.84
BIENES TRANSABLES 0.86
S SOCIALES

FUENTE
guia de perfil MEF
guia de perfil MEF
guia de perfil MEF
guia de perfil MEF
Precios y cantidades de recursos reque

Obra 0494006CONSTRUCCION PUENTE PEATONAL HELARES, L=65M

Fecha 01/03/2010
Lugar 080907 CUSCO - LA CONVENCION - KIMBIRI

Código Recurso Unidad

MANO DE OBRA CALIFICADA

TOPOGRAFO hh
OPERARIO hh
OFICIAL hh
OPERADOR MONTAJISTA hh
OPERARIO CARPINTERO hh
OFICIAL DE OPERARIO MONTAJISTA hh
CAPACITADOR SOCIAL EN TEMAS DE MANTENIMIENTO DE PUENTES PEATONALES und

MANO DE OBRA NO CALIFICADA

PEON hh

MATERIALES

ACEITE PARA MOTOR GRADO 30 gln


CLAVOS PARA MADERA C/C 2 1/2" kg
CLAVOS PARA MADERA C/C 3" kg
CLAVOS PARA MADERA C/C 4" kg
CLAVOS PARA MADERA C/C 5" kg
ABRAZADERA SUPERIOR PARA CABLE 1 3/8", E=1/4", FORJADAS CON MATRICES, NORMA ASME B30und
ABRAZADERA INFERIOR PARA VIGA 4"X6, E=1/4", FORJADA, NORMA ASME B30.20, INC/TUERCAS Y und
DISPOSITIVO DE SUJECION ANTIDESLIZANTE, E=1/4", FORJADA, NORMA ASME B30.20, INC/TUERCund
BARRA DE ANCLAJE Ø 1 1/2", L=5.0M, LONGITUD DE ROSCA 1.0M, NORMA ASTM A193M/193M-04C und
ALAMBRE NEGRO N°16 kg
ALAMBRE NEGRO N°8 kg
FIERRO LISO DE 5/8" x 6 m. kg
SOCKET CONICO DE ANCLAJE PARA CABLE DE ACERO DE 1 1/4", NORMA ASME B30.20, SEGUN E und
SOCKET CILINDRICO DE ANCLAJE PARA CABLE DE ACERO DE 1 1/4", NORMA ASME B30.20, SEGU und
TUERCAS PARA BARRA DE ANCLAJE DE 1 1/2" ASTM A194M/194M-04a und
ARANDELAS DE PRESION PARA BARRA DE ANCLAJE DE 1 1/2" ASTM F436-86 und
PLACA DE ANCLAJE DE 1" X 20" X 20", ASTM A36, CON 4 AGUJEROS PARA BARRA DE 1 1/2" und
ACERO DE REFUERZO FY=4200 GRADO 60 kg
ARENA FINA m3
PIEDRA GRANDE DE 8" m3
ARENA GRUESA m3
PIEDRA ZARANDEADA DE 3/4" m3
MATERIAL GRANULAR m3
ENSAYO DE ROTURA DE PROBETA DE CONCRETO ENSAYO DE ROTURA Cª und
CEMENTO PORTLAND TIPO I (42.5KG) BOL
TUERCA DE ACERO DE 3/8" und
PERNO DE ACERO DE 3/8" X 14" und
PERNO DE ACERO DE 3/8" X 6" und
PERNO DE ACERO DE 3/8" X 7" und
PERNO DE ACERO DE 3/8" X 9" und
WAYPE kg
SOLDADURA kg
YESO DE 25 Kg BOL
LACA DESMOLDANTE P/MADERA/METAL gln
PINTURA ANTICORROSIVA EPOXI ZINCROMATO gln
ESCOBILLA DE ACERO und
CABLE DE ACERO TIPO BOA 6X19 (9/9/1) RD SEALE, ALMA DE ACERO DE Ø 1 1/4". NORMA: API 9A m
BROCA DIAMANTADA DE 3/8" und
CINTA MASKINTAPE DE 2" rll
PLUMONES JUEGO und
CUADERNO 50 HOJAS und
FLETE ADICIONAL LIMA - KIMBIRI GLB
FLETE LOCAL GLB
GASOLINA 84 OCTANOS gln
WINCHA DE 50 m und
HORMIGON (PREPARADA Y PUESTO EN OBRA) m3
LIJA PAPEL GRANATE ASA 80 plg
HOJA DE SIERRA und
LIJA PARA MADERA und
AGUA m3
LAPICEROS und
PAPEL CANSON m
CARTEL INFORMATIVO AMBIENTAL (SEGUN DISEÑO) und
PAPEL BOND A4 80 GRAMOS mll
CARTEL DE OBRA 3.60Mx2.40M TRANSPORTE E INSTALACION GLB
MADERA ROLLIZO Ø6" und
MADERA TORNILLO DE 3" X 5" X 14' p2
MADERA TORNILLO DE 3" X 4" X 3.5' p2
MADERA TORNILLO DE 3" X 4" X 7.2' p2
MADERA TORNILLO DE 2" X 4" X 4.3' p2
MADERA TORNILLO DE 3" X 2" X 6.9' p2
MADERA TORNILLO DE 1 1/2" X 8" X 7' p2
MADERA QUINACHO DE 4" X 6" X 10' p2
TRIPLAY DE 4'x8'x 12 mm pln
MADERA NACIONAL P/ENCOFRADO p2
AMBIENTALISTA und
THINER gln
PINTURA ESMALTE SINTETICO gln
BARNIZ MARINO gln
SELLADOR gln
PRESERVANTE DE MADERA gln
ARANDELA DE ACERO DE 3/8" und
PLANCHA DE ACERO 3MM X 3" m
PLANCHA DE ACERO 3MM X 4" m
PLANCHA DE ACERO 3MM X 11" m
CALAMINA pza
ARPILLERA m
TUBO PVC AGUA SP C-10 DE 1/2" m
PLACA ACRILICA und
MANUAL DE CAPACITACION und

Sub. Total

EQUIPOS

CASCO AMARILLO und


GUANTES DE CUERINA PAR
ARNES DE SEGURIDAD und
GARLOPA hm
GUANTES DE JEBE PAR
BOTAS DE JEBE 38 -40 PAR
MASCARA CONTRA POLVO pza
LENTES DE PROTECCION pza
MOTOBOMBA 10 HP 4" hm
TIRFOR DE 5 TON. DIA
SIERRA CIRCULAR hm
COMPRESORA DE AIRE 4HP hm
COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm
RETROEXCAVADOR S/ORUG 170-250HP 1.1-2.75 hm
MOTOSOLDADORA DE 250 AMP. hm
CANASTILLA DESLIZANTE DE 0.50TN DIA
TECLE DE 5 TN DIA
MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm
SIERRA ELECTRICA DE 7 1/4" DIA
GRUPO ELECTROGENO hm
VIBRADOR DE 4 HP CAP.=1.50" hm
CARRO DE DILATACION PARA 02 CABLE DE 1 1/4", NORMA ASME B30.20, SEGUN PLANO und
NIVEL TOPOGRAFICO hm
TEODOLITO hm
CEPILLADORA ELECTRICA hm
TALADRO ELECTRICO hm
TALADRO ELECTRICO DE 1/2" DE 2 VELOCIDADES DIA
AMOLADORA D=6" DIA
Sub. Total

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES %MO


Sub. Total
COSTO DIRECTO

FACTORES DE CORRECCION A PRECIOS SOCIALES

DESCRIPCION VALOR FUENTE


MANO DE OBRA CALIFICADA 0.91 guia de perfil MEF
MANO DE OBRA NO CALIFICADA 0.41 guia de perfil MEF
BIENES NO TRANSABLES 0.84 guia de perfil MEF
BIENES TRANSABLES 0.86 guia de perfil MEF
Página : 1

es de recursos requeridos

PRECIO F.C. PRECIO


Cantidad Precio S/. Parcial S/. PRIVADO SOCIAL

OBRA CALIFICADA

18.7900 9.03 169.71 170.56 0.91 155.21


1,806.4800 7.22 13,042.79 13,055.85 0.91 11,880.82
2,118.4800 5.42 11,482.15 11,520.32 0.91 10,483.49
40.0000 7.22 288.80 288.80 0.91 262.81
305.6000 7.22 2,206.43 2,206.30 0.91 2,007.73
40.0000 5.42 216.80 216.80 0.91 197.29
1.0000 1,300.00 1,300.00 1,300.00 0.91 1,183.00
28,706.68 28,758.63 26,170.35
BRA NO CALIFICADA

6,047.2500 4.52 27,333.59 27,336.87 0.41 11,208.12


27,333.59 27,336.87 11,208.12

22.4800 40.00 899.07 899.07 0.84 755.22


67.6500 5.50 372.06 373.67 0.84 313.88
72.8700 5.50 400.80 403.21 0.84 338.70
26.0000 5.50 143.00 143.00 0.84 120.12
1.0000 6.00 6.00 6.00 0.84 5.04
66.0000 45.00 2,970.00 2,970.00 0.84 2,494.80
66.0000 75.00 4,950.00 4,950.00 0.84 4,158.00
66.0000 35.00 2,310.00 2,310.00 0.84 1,940.40
8.0000 1,450.00 11,600.00 11,600.00 0.84 9,744.00
487.9900 5.50 2,683.97 2,683.98 0.84 2,254.54
209.4300 5.50 1,151.87 1,152.67 0.84 968.24
462.0000 5.00 2,310.00 2,310.00 0.84 1,940.40
8.0000 1,200.00 9,600.00 9,600.00 0.84 8,064.00
8.0000 1,200.00 9,600.00 9,600.00 0.84 8,064.00
16.0000 55.00 880.00 880.00 0.84 739.20
8.0000 20.00 160.00 160.00 0.84 134.40
4.0000 950.00 3,800.00 3,800.00 0.84 3,192.00
8,542.0300 3.30 28,188.71 28,228.91 0.84 23,712.28
0.1000 80.00 8.00 8.00 0.84 6.72
64.2300 60.00 3,853.84 3,853.59 0.84 3,237.02
122.6400 60.00 7,358.43 7,358.43 0.84 6,181.08
140.9200 80.00 11,273.40 11,273.40 0.84 9,469.66
163.5300 30.00 4,905.90 4,905.90 0.84 4,120.96
26.0000 30.00 780.00 780.00 0.84 655.20
1,904.6800 25.50 48,569.39 48,570.00 0.84 40,798.80
1,768.0000 1.00 1,768.00 1,768.00 0.84 1,485.12
168.0000 10.00 1,680.00 1,680.00 0.84 1,411.20
1,100.0000 7.00 7,700.00 7,700.00 0.84 6,468.00
290.0000 8.00 2,320.00 2,320.00 0.84 1,948.80
230.0000 9.00 2,070.00 2,070.00 0.84 1,738.80
6.4500 10.00 64.53 64.53 0.84 54.21
144.0000 15.00 2,160.00 2,160.00 0.84 1,814.40
3.6100 8.00 28.86 29.52 0.84 24.80
19.3600 45.00 871.18 871.18 0.84 731.79
33.9100 80.00 2,712.64 2,712.64 0.84 2,278.62
2.0000 5.00 10.00 10.00 0.84 8.40
410.0000 80.00 32,800.00 32,800.00 0.84 27,552.00
16.0000 26.00 416.00 416.00 0.84 349.44
2.0000 3.00 6.00 6.00 0.84 5.04
2.0000 2.50 5.00 5.00 0.84 4.20
50.0000 2.00 100.00 100.00 0.84 84.00
1.0000 5,000.00 5,000.00 5,000.00 0.84 4,200.00
1.0000 10,000.00 10,000.00 10,000.00 0.84 8,400.00
244.9300 12.00 2,939.18 2,937.72 0.84 2,467.68
0.0700 90.00 5.90 6.56 0.84 5.51
24.8600 55.00 1,367.30 1,367.30 0.84 1,148.53
82.8900 2.00 165.77 164.64 0.84 138.30
40.6700 6.00 244.00 243.99 0.84 204.95
84.5500 2.00 169.10 169.10 0.84 142.04
50.9500 1.00 50.95 50.96 0.84 42.81
50.0000 1.50 75.00 75.00 0.84 63.00
5.0000 3.00 15.00 15.00 0.84 12.60
4.0000 100.00 400.00 400.00 0.84 336.00
1.0000 35.00 35.00 35.00 0.84 29.40
1.0000 650.00 650.00 650.00 0.84 546.00
50.0000 5.00 250.00 250.00 0.84 210.00
1,490.0000 2.80 4,172.00 4,172.00 0.84 3,504.48
300.0000 2.80 840.00 840.00 0.84 705.60
570.0000 2.80 1,596.00 1,596.00 0.84 1,340.64
250.0000 2.80 700.00 700.00 0.84 588.00
280.0000 2.80 784.00 784.00 0.84 658.56
4,000.0000 2.80 11,200.00 11,200.00 0.84 9,408.00
990.0000 4.00 3,960.00 3,960.00 0.84 3,326.40
48.4000 87.00 4,210.71 4,210.72 0.84 3,537.00
2,243.7700 2.20 4,936.29 4,936.29 0.84 4,146.48
2.0000 1,500.00 3,000.00 3,000.00 0.84 2,520.00
12.4200 22.00 273.26 274.37 0.84 230.47
62.6000 40.00 2,503.83 2,503.83 0.84 2,103.22
14.0900 45.00 634.14 634.14 0.84 532.68
5.6400 45.00 253.66 253.66 0.84 213.07
71.6000 75.00 5,370.00 5,370.00 0.84 4,510.80
3,536.0000 1.00 3,536.00 3,536.00 0.84 2,970.24
55.0000 4.00 220.00 220.00 0.84 184.80
75.0000 7.00 525.00 525.00 0.84 441.00
35.0000 22.00 770.00 770.00 0.84 646.80
90.0000 22.00 1,980.00 1,980.00 0.84 1,663.20
80.0000 5.50 440.00 440.00 0.84 369.60
483.9900 2.70 1,306.77 1,306.78 0.84 1,097.70
1.0000 400.00 400.00 400.00 0.84 336.00
75.0000 5.00 375.00 375.00 0.84 315.00

288,840.53 288,885.76 242,664.04

50.0000 35.00 1,750.00 1,750.00 0.84 1,470.00


50.0000 12.00 600.00 600.00 0.84 504.00
2.0000 150.00 300.00 300.00 0.84 252.00
970.5600 15.00 14,558.40 14,558.40 0.84 12,229.06
10.0000 10.00 100.00 100.00 0.84 84.00
50.0000 25.00 1,250.00 1,250.00 0.84 1,050.00
50.0000 10.00 500.00 500.00 0.84 420.00
50.0000 15.00 750.00 750.00 0.84 630.00
264.6000 8.00 2,116.80 2,116.80 0.84 1,778.11
5.0000 50.00 250.00 250.00 0.84 210.00
970.5600 15.00 14,558.40 14,558.40 0.84 12,229.06
136.4700 5.00 682.36 677.56 0.84 569.15
219.3100 10.00 2,193.08 2,193.08 0.84 1,842.19
154.2800 350.00 53,997.02 53,997.01 0.84 45,357.49
40.0000 20.00 800.00 800.00 0.84 672.00
5.0000 50.00 250.00 250.00 0.84 210.00
5.0000 50.00 250.00 250.00 0.84 210.00
113.3600 20.00 2,267.16 2,267.46 0.84 1,904.67
5.0000 50.00 250.00 250.00 0.84 210.00
1,922.8700 20.00 38,457.45 38,451.96 0.84 32,299.65
81.2800 8.00 650.23 650.58 0.84 546.49
4.0000 1,700.00 6,800.00 6,800.00 0.84 5,712.00
9.4100 10.00 94.14 95.12 0.84 79.90
5.6700 15.00 85.12 85.28 0.84 71.64
965.2800 15.00 14,479.20 14,479.20 0.84 12,162.53
960.0000 5.00 4,800.00 4,800.00 0.84 4,032.00
5.0000 50.00 250.00 250.00 0.84 210.00
5.0000 50.00 250.00 250.00 0.84 210.00
163,289.36 163,280.85 137,155.91

ENTAS MANUALES

2,463.87 2,463.81 0.84 2,069.60


2,463.87 2,463.81 2,069.60
STO DIRECTO 510,725.92 419,268.02

FUENTE
guia de perfil MEF
guia de perfil MEF
guia de perfil MEF
guia de perfil MEF
PRESUPUESTO ALTERNATIVA II

PROYECT: “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION -

UBICACIÓN
SECTOR : HELARES
DISTRITO : KIMRIRI
PROVINCIA : LA CONVENCION
DEPARTAME : CUSCO
ITEM DESCRIPCION UND

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und
01.02 CONSTRUCCION DE ALAMACEN Y CAMPAMENTO PROVISIONAL 12M X 6M GLB
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2
02.02 TRAZO Y REPLANTEO PRELIMINAR m2
02.03 CONTROL TOPOGRAFICO EN PROCESO CONSTRUCTIVO m2
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION MATERIAL CON BOLONERIA BAJO AGUA m3
03.02 EXCAVACION MATERIAL CON BOLONERIA m3
03.03 EXCAVACION CON MAQUINARIA m3
03.04 RELLENO COMPACTADO CON MATERIAL GRANULAR m3
03.05 RELLENO COMPACTADO CON MATERIAL PROPIO m3
03.06 ACARREO DE MATERIAL EXCEDENTE D=30 MT. m3
04 OBRAS DE CONCRETO SIMPLE
04.01 FALZA ZAPATAS, MEZCLA C:H 1:10 + 30%P.G. m3
04.02 CONCRETO F'C=175 KG/CM2 + 40% P.G. m3
04.03 ENCOFRADO Y DESENCOFRADO. m2
04.04 PANTALLA Y ALAS
04.04.01 CONCRETO F'C=175 KG/CM2 + 40% P.G. m3
04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2
05 OBRAS DE CONCRETO ARMADO
05.01 ZAPATA DE ESTRIBO
05.01.01 CONCRETO F'C= 210 KG/CM2 m3
05.01.02 ENCOFRADO Y DESENCOFRADO. m2
05.01.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg
05.02 COLUMNAS EN TORRE DE CONCRETO ARMADO
05.02.01 CONCRETO F'C= 210 KG/CM2 m3
05.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2
05.02.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg
05.03 VIGAS EN TORRE DE CONCRETO ARMADO
05.03.01 CONCRETO F'C= 210 KG/CM2 m3
05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2
05.03.03 ACERO DE REFUERZO FY=4200 KG/CM2 kg
06 SUPERESSTRUCTURA DE PUENTE COLGANTE
06.01 MONTAJE MECANICO DE SUPERESTRUCTURA DE PUENTE COLGANTE. GLB
06.02 COLOCACION DE PENDOLAS. und
06.03 VIGA 4" X 6" und
06.04 TABLERO DE MADERA. GLB
06.05 BARANDA DE MADERA. GLB
06.06 COLOCACION DE CARRILES. und
06.07 ARMADO Y COLOCACION DE TEMPLADORES EN CAMARA DE ANCLAJE. GLB
07 OBRAS DE PROTECCION
07.01 ENCAUSAMIENTO DE CURSOS DE AGUA m3
07.02 PROTECCION DE ESTRIBOS m3
08 PINTURA
08.01 PINTURA ANTICORROSIVO EPOXI ZINCROMATO m
08.02 PINTURA ESMALTE SINTETICO EN SUPERFICIE METALICO (02 MANOS) m
08.03 PINTURA ESMALTE SINTETICO EN SUPERFICIE DE CONCRETO (02 MANOS) m2
08.04 ACABADO EN CARPINTERIA DE MADERA m2
09 CONTROL DE CALIDAD
09.01 ENSAYO DE ROTURA DE PROBETA DE CONCRETO und
09.02 SEGURIDAD PERSONAL
09.02.01 INDUCCION EN SEGURIDAD PERSONAL GLB
09.02.02 EQUIPO DE PROPTECCION PERSONAL GLB
10 PLACA RECORDEATORIA
10.01 PLACA RECORDATORIA ACRILICA und
11 FLETE Y TRANSPORTE TERRESTRE
11.01 FLETE PARA TRASLADO DE ACCESORIOS GLB
12 CONFORMACION DE COMITE DE GESTION
12.01 CONFORMACION DE COMITE DE GESTION GLB
12.02 MANUAL DE CAPACITACION und
01 PROGRAMAS DE CAPACITACION Y SENSIBILIZACION EN TEMAS DE MANTENIMIENTO
01.01 PROGRAMA DE CAPACITACION Y SENSIBILIZACION EN MANTENIMIENTO und
01.02 MATERIALES DE CAPACITACION GLB
14 PLAN DE MANEJO AMBIENTAL
14.01 SENSIBILIZACIÓN Y CAPACITACIÓN EN TEMAS AMBIENTALES
14.01.01 CONSTRUCCION DE MICRO RELLENO SANITARIO m3
14.01.02 RECOLECCION MANUAL DE RESIDUOS DE AREA DE TRABAJO m3
14.01.04 RECUPERACION DE AREA DE BOTADERO E INST. DE COBERTURA VEGETAL M2
14.01.05 SEÑALES INFORMATIVAS (IMPACTO AMBIENTAL) und
14.01.06 LIMPIEZA FINAL DE OBRA m2

COSTO DIRECTO
GASTOS GENERALES (12.30% C.D.)

SUB TOTAL - VALOR REFERENCIAL


COSTO DEL EXPEDIENTE TECNICO (1.74% C.D.)
GASTOS DE SUPERVISION (5.50% V.R.)
GASTOS ADMINISTRATIVOS (1.0% V.R.)

TOTAL PRESUPUESTO
LTERNATIVA II

O DE KIMBIRI- LA CONVENCION - CUSCO”

METRADO C.U. SUB TOTAL TOTALES

4,507.73
1.00 974.21 974.21
1.00 3,533.52 3,533.52
708.48
328.00 0.63 206.64
328.00 0.26 85.28
328.00 1.27 416.56
29,178.67
88.20 69.99 6,173.12
88.00 18.98 1,670.24
600.60 10.36 6,222.22
142.20 50.19 7,137.02
406.07 15.69 6,371.24
211.44 7.59 1,604.83
149,352.45
31.59 200.35 6,329.06
114.24 239.29 27,336.49
114.40 25.49 2,916.06
112,770.84
425.28 239.29 101,765.25
246.10 44.72 11,005.59
62,139.44
46,007.25
67.50 398.27 26,883.23
46.00 25.49 1,172.54
3,945.38 4.55 17,951.48
14,042.07
6.34 398.27 2,525.03
63.36 44.72 2,833.46
1,908.48 4.55 8,683.58
2,090.12
1.58 398.27 629.27
13.20 44.72 590.30
191.33 4.55 870.55
237,680.36
1.00 37,650.98 37,650.98
66.00 211.87 13,983.42
33.00 226.10 7,461.30
1.00 65,296.24 65,296.24
1.00 69,755.74 69,755.74
4.00 1,753.09 7,012.36
1.00 36,520.32 36,520.32
50,046.60
3,000.00 8.10 24,300.00
2,820.00 9.13 25,746.60
14,141.09
571.56 6.84 3,909.47
571.56 6.12 3,497.95
225.82 12.82 2,895.01
281.84 13.62 3,838.66
14,130.00
26.00 30.00 780.00
13,350.00
1.00 1,500.00 1,500.00
1.00 11,850.00 11,850.00
604.27
1.00 604.27 604.27
15,000.00
1.00 15,000.00 15,000.00
1,875.00
1.00 1,500.00 1,500.00
1.00 375.00 375.00
1,581.00
1.00 1,300.00 1,300.00
1.00 281.00 281.00
6,513.99
6,513.99
27.00 193.64 5,228.28
20.00 25.32 506.40
9.00 0.95 8.55
4.00 130.37 521.48
328.00 0.76 249.28

587,459.08
72,257.47

659,716.55
11,479.07
36,284.41
6,597.17

714,077.20
Precios y cantidades de recur

Obra 0801001CONSTRUCCION PUENTE PEATONAL HELARES II ETAPA

Fecha 01/04/2010
Lugar 080907 CUSCO - LA CONVENCION - KIMBIRI

Código Recurso Unidad

MANO DE OBRA CALIFICA

TOPOGRAFO hh
OPERARIO hh
OFICIAL hh
OPERADOR MONTAJISTA hh
OPERARIO CARPINTERO hh
OFICIAL DE OPERARIO MONTAJISTA hh
CAPACITADOR SOCIAL EN TEMAS DE MANTENIMIENTO DE PUENTES PEATONALES und

MANO DE OBRA NO CALIFI

PEON hh

ACEITE PARA MOTOR GRADO 30 gln


CLAVOS PARA MADERA C/C 2 1/2" kg
CLAVOS PARA MADERA C/C 3" kg
CLAVOS PARA MADERA C/C 4" kg
CLAVOS PARA MADERA C/C 5" kg
ABRAZADERA SUPERIOR PARA CABLE 1 3/8", E=1/4", FORJADAS CON MATRICES, NORMA ASME B30.20, INC/TUER und
ABRAZADERA INFERIOR PARA VIGA 4"X6, E=1/4", FORJADA, NORMA ASME B30.20, INC/TUERCAS Y PLATINAS und
DISPOSITIVO DE SUJECION ANTIDESLIZANTE, E=1/4", FORJADA, NORMA ASME B30.20, INC/TUERCAS Y PLATINAS und
BARRA DE ANCLAJE Ø 1 1/2", L=5.0M, LONGITUD DE ROSCA 1.0M, NORMA ASTM A193M/193M-04C und
ALAMBRE NEGRO N°16 kg
ALAMBRE NEGRO N°8 kg
FIERRO LISO DE 5/8" x 6 m. kg
SOCKET CONICO DE ANCLAJE PARA CABLE DE ACERO DE 1 1/4", NORMA ASME B30.20, SEGUN ESPECIFICACION und
SOCKET CILINDRICO DE ANCLAJE PARA CABLE DE ACERO DE 1 1/4", NORMA ASME B30.20, SEGUN ESPECIFICAC und
TUERCAS PARA BARRA DE ANCLAJE DE 1 1/2" ASTM A194M/194M-04a und
ARANDELAS DE PRESION PARA BARRA DE ANCLAJE DE 1 1/2" ASTM F436-86 und
PLACA DE ANCLAJE DE 1" X 20" X 20", ASTM A36, CON 4 AGUJEROS PARA BARRA DE 1 1/2" und
ACERO DE REFUERZO FY=4200 GRADO 60 kg
ARENA FINA m3
PIEDRA GRANDE DE 8" m3
ARENA GRUESA m3
PIEDRA ZARANDEADA DE 3/4" m3
MATERIAL GRANULAR m3
ENSAYO DE ROTURA DE PROBETA DE CONCRETO ENSAYO DE ROTURA Cª und
CEMENTO PORTLAND TIPO I (42.5KG) BOL
TUERCA DE ACERO DE 3/8" und
PERNO DE ACERO DE 3/8" X 14" und
PERNO DE ACERO DE 3/8" X 6" und
PERNO DE ACERO DE 3/8" X 7" und
PERNO DE ACERO DE 3/8" X 9" und
WAYPE kg
SOLDADURA kg
YESO DE 25 Kg BOL
LACA DESMOLDANTE P/MADERA/METAL gln
PINTURA ANTICORROSIVA EPOXI ZINCROMATO gln
ESCOBILLA DE ACERO und
CABLE DE ACERO TIPO BOA 6X19 (9/9/1) RD SEALE, ALMA DE ACERO DE Ø 1 1/4". NORMA: API 9A NACIONAL m
BROCA DIAMANTADA DE 3/8" und
CINTA MASKINTAPE DE 2" rll
PLUMONES JUEGO und
CUADERNO 50 HOJAS und
FLETE ADICIONAL LIMA - KIMBIRI GLB
FLETE LOCAL GLB
GASOLINA 84 OCTANOS gln
WINCHA DE 50 m und
HORMIGON (PREPARADA Y PUESTO EN OBRA) m3
LIJA PAPEL GRANATE ASA 80 plg
HOJA DE SIERRA und
LIJA PARA MADERA und
AGUA m3
LAPICEROS und
PAPEL CANSON m
CARTEL INFORMATIVO AMBIENTAL (SEGUN DISEÑO) und
PAPEL BOND A4 80 GRAMOS mll
CARTEL DE OBRA 3.60Mx2.40M TRANSPORTE E INSTALACION GLB
MADERA ROLLIZO Ø6" und
MADERA TORNILLO DE 3" X 5" X 14' p2
MADERA TORNILLO DE 3" X 4" X 3.5' p2
MADERA TORNILLO DE 3" X 4" X 7.2' p2
MADERA TORNILLO DE 2" X 4" X 4.3' p2
MADERA TORNILLO DE 3" X 2" X 6.9' p2
MADERA TORNILLO DE 1 1/2" X 8" X 7' p2
MADERA QUINACHO DE 4" X 6" X 10' p2
TRIPLAY DE 4'x8'x 12 mm pln
MADERA NACIONAL P/ENCOFRADO p2
AMBIENTALISTA und
THINER gln
PINTURA ESMALTE SINTETICO gln
BARNIZ MARINO gln
SELLADOR gln
PRESERVANTE DE MADERA gln
ARANDELA DE ACERO DE 3/8" und
PLANCHA DE ACERO 3MM X 3" m
PLANCHA DE ACERO 3MM X 4" m
PLANCHA DE ACERO 3MM X 11" m
CALAMINA pza
ARPILLERA m
TUBO PVC AGUA SP C-10 DE 1/2" m
PLACA ACRILICA und
MANUAL DE CAPACITACION und

CASCO AMARILLO und


GUANTES DE CUERINA PAR
GARLOPA hm
GUANTES DE JEBE PAR
BOTAS DE JEBE 38 -40 PAR
MASCARA CONTRA POLVO pza
LENTES DE PROTECCION pza
MOTOBOMBA 10 HP 4" hm
TIRFOR DE 5 TON. DIA
SIERRA CIRCULAR hm
COMPRESORA DE AIRE 4HP hm
COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm
RETROEXCAVADOR S/ORUG 170-250HP 1.1-2.75 hm
MOTOSOLDADORA DE 250 AMP. hm
CANASTILLA DESLIZANTE DE 0.50TN DIA
TECLE DE 5 TN DIA
MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm
SIERRA ELECTRICA DE 7 1/4" DIA
GRUPO ELECTROGENO hm
VIBRADOR DE 4 HP CAP.=1.50" hm
CARRO DE DILATACION PARA 02 CABLE DE 1 1/4", NORMA ASME B30.20, SEGUN PLANO und
NIVEL TOPOGRAFICO hm
TEODOLITO hm
CEPILLADORA ELECTRICA hm
TALADRO ELECTRICO hm
TALADRO ELECTRICO DE 1/2" DE 2 VELOCIDADES DIA
AMOLADORA D=6" DIA

HERRAMIENTAS MANUAL
HERRAMIENTAS MANUALES %MO

COSTO DIRECTO
os y cantidades de recursos requeridos

Cantidad Precio S/. Parcial S/. resupuestado S/.

MANO DE OBRA CALIFICADA

18.7900 9.03 169.71 170.56


1,840.9100 7.22 13,291.39 13,302.70
2,332.1500 5.42 12,640.28 12,673.41
40.0000 7.22 288.80 288.80
305.6000 7.22 2,206.43 2,206.30
40.0000 5.42 216.80 216.80
1.0000 1,300.00 1,300.00 1,300.00
30,113.41 30,158.57

MANO DE OBRA NO CALIFICADA

7,746.9300 4.52 35,016.12 35,022.63


35,016.12 35,022.63

MATERIALES

36.2600 40.00 1,450.57 1,450.56


67.6500 5.50 372.06 373.67
72.8700 5.50 400.80 403.21
26.0000 5.50 143.00 143.00
1.0000 6.00 6.00 6.00
66.0000 45.00 2,970.00 2,970.00
66.0000 75.00 4,950.00 4,950.00
66.0000 35.00 2,310.00 2,310.00
8.0000 1,450.00 11,600.00 11,600.00
362.7100 5.50 1,994.91 1,994.92
209.4300 5.50 1,151.87 1,152.67
462.0000 5.00 2,310.00 2,310.00
8.0000 1,200.00 9,600.00 9,600.00
8.0000 1,200.00 9,600.00 9,600.00
16.0000 55.00 880.00 880.00
8.0000 20.00 160.00 160.00
4.0000 950.00 3,800.00 3,800.00
6,349.5800 3.30 20,953.62 20,983.38
0.1000 80.00 8.00 8.00
298.2300 60.00 17,894.02 17,892.87
210.8800 60.00 12,652.74 12,652.74
240.0000 80.00 19,200.14 19,200.15
163.5300 30.00 4,905.90 4,905.90
26.0000 30.00 780.00 780.00
3,274.0400 25.50 83,488.10 83,490.95
1,768.0000 1.00 1,768.00 1,768.00
168.0000 10.00 1,680.00 1,680.00
1,100.0000 7.00 7,700.00 7,700.00
290.0000 8.00 2,320.00 2,320.00
230.0000 9.00 2,070.00 2,070.00
6.4500 10.00 64.53 64.53
144.0000 15.00 2,160.00 2,160.00
3.6100 8.00 28.86 29.52
19.3600 45.00 871.18 871.18
33.9100 80.00 2,712.64 2,712.64
2.0000 5.00 10.00 10.00
410.0000 80.00 32,800.00 32,800.00
16.0000 26.00 416.00 416.00
2.0000 3.00 6.00 6.00
2.0000 25.00 50.00 50.00
50.0000 2.00 100.00 100.00
1.0000 5,000.00 5,000.00 5,000.00
1.0000 10,000.00 10,000.00 10,000.00
375.0700 12.00 4,500.83 4,500.26
0.0700 90.00 5.90 6.56
28.9900 55.00 1,594.51 1,594.51
82.8900 2.00 165.77 164.64
30.2300 6.00 181.36 181.35
84.5500 2.00 169.10 169.10
37.1600 1.00 37.16 37.17
50.0000 1.50 75.00 75.00
5.0000 3.00 15.00 15.00
4.0000 100.00 400.00 400.00
1.0000 35.00 35.00 35.00
1.0000 650.00 650.00 650.00
50.0000 5.00 250.00 250.00
1,490.0000 2.80 4,172.00 4,172.00
300.0000 2.80 840.00 840.00
570.0000 2.80 1,596.00 1,596.00
250.0000 2.80 700.00 700.00
280.0000 2.80 784.00 784.00
4,000.0000 2.80 11,200.00 11,200.00
990.0000 4.00 3,960.00 3,960.00
48.4000 87.00 4,210.71 4,210.72
2,243.7700 2.20 4,936.29 4,936.29
2.0000 1,500.00 3,000.00 3,000.00
12.4200 22.00 273.26 274.37
62.6000 40.00 2,503.83 2,503.83
14.0900 45.00 634.14 634.14
5.6400 45.00 253.66 253.66
71.6000 75.00 5,370.00 5,370.00
3,536.0000 1.00 3,536.00 3,536.00
55.0000 4.00 220.00 220.00
75.0000 7.00 525.00 525.00
35.0000 22.00 770.00 770.00
90.0000 22.00 1,980.00 1,980.00
80.0000 5.50 440.00 440.00
483.9900 2.70 1,306.77 1,306.78
1.0000 400.00 400.00 400.00
75.0000 5.00 375.00 375.00

345,405.24 345,442.27

EQUIPOS

50.0000 25.00 1,250.00 1,250.00


50.0000 35.00 1,750.00 1,750.00
970.5600 15.00 14,558.40 14,558.40
10.0000 10.00 100.00 100.00
50.0000 150.00 7,500.00 7,500.00
50.0000 10.00 500.00 500.00
50.0000 15.00 750.00 750.00
264.6000 8.00 2,116.80 2,116.80
5.0000 50.00 250.00 250.00
970.5600 15.00 14,558.40 14,558.40
136.4700 5.00 682.36 677.56
219.3100 10.00 2,193.08 2,193.08
154.2800 350.00 53,997.02 53,997.01
40.0000 20.00 800.00 800.00
5.0000 50.00 250.00 250.00
5.0000 50.00 250.00 250.00
261.9600 20.00 5,239.21 5,239.35
5.0000 50.00 250.00 250.00
1,922.8700 20.00 38,457.45 38,451.91
245.2000 8.00 1,961.62 1,961.81
4.0000 1,700.00 6,800.00 6,800.00
9.4100 10.00 94.14 95.12
5.6700 15.00 85.12 85.26
965.2800 15.00 14,479.20 14,479.20
960.0000 5.00 4,800.00 4,800.00
5.0000 50.00 250.00 250.00
5.0000 50.00 250.00 250.00
174,163.90

HERRAMIENTAS MANUALES
2,671.71 2,671.71
2,671.71 2,671.71

COSTO DIRECTO S/. 587,459.08


PRESUPUESTO ALTERNATIVA I

PROYECTO : “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRIT


: “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI-
UBICACIÓN
SECTOR: HELARES
DISTRITO : KIMRIRI
PROVINCIA : LA CONVENCION
DEPARTAMENTO : CUSCO
COSTO A PRECIO DE
DESCRIPCIÓN
MERCADO

1.- CONSTRUCCIÓN DE PUENTE COLGANTE PEATONAL 65 ML 500,800.93


1.1. Mano de Obra Calificada 26,244.55
1.2. Mano de Obra No Calificada 22,632.81
1.3. Materiales 286,374.70
1.4 .Equipos 163,280.85
1.5 .Herramientas Manuales 2,268.02

2.- CONFORMACIÓN DE COMITÉ DE GESTIÓN 1,875.00


1.1. Mano de Obra Calificada -
1.2. Mano de Obra No Calificada -
1.3. Materiales 1,875.00
1.4 .Equipos -
1.5 .Herramientas Manuales -

3.- PROGRAMAS DE CAPACITACIÓN Y SENSIBILIZACIÓN EN TEMAS


MANTENIMIENTO 1,536.00
1.1. Mano de Obra Calificada 1,300.00
1.2. Mano de Obra No Calificada -
1.3. Materiales 236.00
1.4 .Equipos -
1.5 .Herramientas Manuales -

4.- PLAN DE MANEJO AMBIENTAL 6,513.99


1.1. Mano de Obra Calificada 1,214.08
1.2. Mano de Obra No Calificada 4,704.06
1.3. Materiales 400.00
1.4 .Equipos 195.85
1.5 .Herramientas Manuales -

COSTO DIRECTO 510,725.92


GASTOS GENERALES ( 12.30% CD ) 62,819.29

VALOR REFERENCIAL 573,545.21

ELABORACIÓN DE EXPEDIENTE TÉCNICO ( 1.83 % VR ) 10,500.00


GASTOS DE SUPERVISIÓN ( 5.50 % VR ) 31,544.99
GASTOS ADMINISTRATIVOS ( 1.00 % VR ) 5,735.45
TOTAL INVERSIONES 621,325.65
Fuente: Elaboración propia

FACTORES DE CORRECCION A PRECIOS SOCIALES

DESCRIPCION VALOR
MANO DE OBRA CALIFICADA 0.91
MANO DE OBRA NO CALIFICADA 0.41
BIENES NO TRANSABLES 0.84
BIENES TRANSABLES 0.86
PRESUPUESTO ALTERNATIVA II
A PRECIOS DE MERCADO

PROYECTO : “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRIT


: “CONSTRUCCION DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI-
UBICACIÓN
SECTOR: HELARES
DISTRITO : KIMRIRI
PROVINCIA : LA CONVENCION
DEPARTAMENTO : CUSCO
COSTO A PRECIO DE
DESCRIPCIÓN
MERCADO

1.- CONSTRUCCIÓN DE PUENTE COLGANTE PEATONAL 65 ML 577,489.18


1.1. Mano de Obra Calificada 27,644.49
1.2. Mano de Obra No Calificada 30,318.57
1.3. Materiales 342,886.27
1.4 .Equipos 174,163.99
1.5 .Herramientas Manuales 2,475.86

2.- CONFORMACIÓN DE COMITÉ DE GESTIÓN 1,875.00


1.1. Mano de Obra Calificada -
1.2. Mano de Obra No Calificada -
1.3. Materiales 1,875.00
1.4 .Equipos -
1.5 .Herramientas Manuales -
3.- PROGRAMAS DE CAPACITACIÓN Y SENSIBILIZACIÓN EN TEMAS
MANTENIMIENTO 1,581.00
1.1. Mano de Obra Calificada 1,300.00
1.2. Mano de Obra No Calificada -
1.3. Materiales 281.00
1.4 .Equipos -
1.5 .Herramientas Manuales -
4.- PLAN DE MANEJO AMBIENTAL 6,513.99
1.1. Mano de Obra Calificada 1,214.08
1.2. Mano de Obra No Calificada 4,704.06
1.3. Materiales 400.00
1.4 .Equipos 195.85
1.5 .Herramientas Manuales -

COSTO DIRECTO 587,459.17


GASTOS GENERALES ( 12.30% CD ) 72,257.48

VALOR REFERENCIAL 659,716.65

ELABORACIÓN DE EXPEDIENTE TÉCNICO ( 1.74 % VR ) 11,479.07


GASTOS DE SUPERVISIÓN ( 5.50 % VR ) 36,284.42
GASTOS ADMINISTRATIVOS ( 1.00 % VR ) 6,597.17
TOTAL INVERSIONES 714,077.30
ERNATIVA I

N DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION - CUSCO”

CUADRO DE RESUMEN DE OBRA


COSTO A PRECIO
FC PRECIOS SOCIALES
SOCIALES
1.1. Mano de Obra Calificada 26,170.35
412,777.79 1.2. Mano de Obra No Calificada 11,208.12
0.91 23,882.54 1.3. Materiales 242,663.99
0.41 9,279.45 1.4 .Equipos 137,320.43
0.84 240,554.75 1.5 .Herramientas Manuales 1,905.14
0.84 137,155.91 1.6.Costo Directo 419,268.02
0.84 1,905.14 1.7.Gastos Generales 51,569.97
- 1.8.Valor referencial 470,837.99
1,575.00 1.9.Elaboracion de Expediente Tecnioco 8,619.72
0.91 - 1.10.Gastos de Supervision 25,896.09
0.41 - 1.11.Gastos Administrativos 4,708.38
0.84 1,575.00
0.84 - TOTAL INVERSIONES 510,062.18
0.84 -

1,381.24
0.91 1,183.00 CUADRO DE RESUMEN DE OBRA
0.41 - PRECIOS PRIVADOS
0.84 198.24 1.1. Mano de Obra Calificada 28,758.63
0.84 - 1.2. Mano de Obra No Calificada 27,336.87
0.84 - 1.3. Materiales 288,885.70
1.4 .Equipos 163,476.70
3,533.99 1.5 .Herramientas Manuales 2,268.02
0.91 1,104.81 1.6.Costo Directo 510,725.92
0.41 1,928.66 1.7.Gastos Generales 62,819.29
0.84 336.00 1.8.Valor referencial 573,545.21
0.84 164.51 1.9.Elaboracion de Expediente Tecnioco 10,500.00
0.84 - 1.10.Gastos de Supervision 31,544.99
1.11.Gastos Administrativos 5,735.45
419,268.02
51,569.97 TOTAL INVERSIONES 621,325.65

470,837.99

8,619.72
25,896.09
4,708.38
510,062.18

FACTORES DE CORRECCION A PRECIOS SOCIALES

FUENTE DESCRIPCION VALOR FUENTE


guia de perfil MEF MANO DE OBRA CALIFICADA 0.91 guia de perfil MEF
guia de perfil MEF MANO DE OBRA NO CALIFICADA 0.41 guia de perfil MEF
guia de perfil MEF BIENES NO TRANSABLES 0.84 guia de perfil MEF
guia de perfil MEF BIENES TRANSABLES 0.86 guia de perfil MEF
ATIVA II
CADO

N DE PUENTE PEATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION - CUSCO”

COSTO A PRECIO
FC CUADRO DE RESUMEN DE OBRA
SOCIALES
PRECIOS PRIVADOS
473,989.04 1.1. Mano de Obra Calificada 30,158.57
0.91 25,156.49 1.2. Mano de Obra No Calificada 35,022.63
0.41 12,430.61 1.3. Materiales 345,442.27
0.84 288,024.47 1.4 .Equipos 174,359.84
0.84 146,297.75 1.5 .Herramientas Manuales 2,475.86
0.84 2,079.72 1.6.Costo Directo 587,459.17
- 1.7.Gastos Generales 72,257.48
1,575.00 1.8.Valor referencial 470,837.99
0.91 - 1.9.Elaboracion de Expediente Tecnioco 11,479.07
0.41 - 1.10.Gastos de Supervision 36,284.42
0.84 1,575.00 1.11.Gastos Administrativos 6,597.17
0.84 -
0.84 - TOTAL INVERSIONES 714,077.30

1,419.04
0.91 1,183.00 CUADRO DE RESUMEN DE OBRA
0.41 - PRECIOS SOCIALES
0.84 236.04 1.1. Mano de Obra Calificada 27,444.30
0.84 - 1.2. Mano de Obra No Calificada 14,359.28
0.84 - 1.3. Materiales 290,171.51
1.4 .Equipos 146,462.27
3,533.99 1.5 .Herramientas Manuales 2,079.72
0.91 1,104.81 1.6.Costo Directo 480,517.07
0.41 1,928.66 1.7.Gastos Generales 59,103.60
0.84 336.00 1.8.Valor referencial 539,620.67
0.84 164.51 1.9.Elaboracion de Expediente Tecnioco 9,389.40
0.84 - 1.10.Gastos de Supervision 29,679.14
1.11.Gastos Administrativos 5,396.21
480,517.07
12.300% 59,103.60 0.123 TOTAL INVERSIONES 584,085.41

539,620.67

1.740% 9,389.40 1.74%


5.500% 29,679.14 0.055
1.000% 5,396.21 0.01
584,085.41
COSTO TOTAL DEL PROYECTO
NUMERO DE HABITANTES
COSTO POR HABITANTE
S/. 510,062.18
365
S/. 1,397.43
0 1 2 3 4
365 384.505119 389.542136 394.645138 399.814989
95.0520833 100.131541 101.443265 102.772171 104.118487
5 6 7 8 9 10
405.052566 410.358754 415.734454 421.180575 426.698041 432.287785
105.482439 106.864259 108.264181 109.682441 111.119281 112.574944
COSTOS DE MANTENIMIENTO SIN PROYECTO

A PRECIOS DE MERCADO Y SOCIALES ALTERNATIVAS I Y II

Cant. P. Unit. (S/.)

Costos de Mantenimiento
troncos de madera (palotes) und 20.00 30.00
Mano Obra HH 60.00 25.00
Herramientas global 1.00 60.00
Costo Total Anual
Costo Mensual
Costo Mensual Por Familia
Fuente : Elaboracion propia

Factores de Corrección
Bienes Transables 0.86
Bienes No Transables 0.84
Mano de Obra No calificada Rural (Sierra) 0.41
Mano de Obra Calificada 0.91
SIN PROYECTO

ALTERNATIVAS I Y II

Factor de
A Precios de Mercado A Precios Sociales
Conversion
2,160.00 1,169.40
600.00 0.84 504.00
1,500.00 0.41 615.00
60.00 0.84 50.40
2,160.00 1,169.40
180.00 97.45
1.82 0.98
COSTOS DE OPERACIÓN Y MANTENIMIENTO EN LA SITUACION CO
A PRECIOS DE MERCADO Y A PRECIOS SOCIALES ALTERNATIV

(En Nuevos Soles)


CONCEPTO UNIDAD
CANTIDAD

COSTO DE OPERACIÓN
TAREAS DE GESTION Y ADMINISTRACION
GLB 1.00

COSTO DE MANTENIMIENTO
SUPERESTRUCTURA DE PUENTE COLGANTE

TABLERO DE MADERA. GLB 1.00


BARANDA DE MADERA. GLB 1.00
OBRAS DE PROTECCION
ENCAUSAMIENTO DE CURSOS DE AGUA m3 500.00
PROTECCION DE ESTRIBOS m3 300.00
PINTURA
PINTURA ANTICORROSIVO EPOXI ZINCROMATO m 200.00
PINTURA ESMALTE SINTETICO EN SUPERFICIE METALICO (02 MANOS) m 200.00
PRESUPUESTO DEL MANTENIMIENTO
C/ 01 AÑOS

Fuente: elaboracion propia

Recurso Unidad Cantidad

MANO DE OBRA

OPERARIO hh 26.6800
OFICIAL hh 125.2800
PEON hh 37.2000
OPERARIO CARPINTERO hh 120.0000

MATERIALES

CLAVOS PARA MADERA C/C 3" kg 5.0000


CLAVOS PARA MADERA C/C 4" kg 17.0000
TUERCA DE ACERO DE 3/8" und 183.0000
PERNO DE ACERO DE 3/8" X 14" und 50.0000
PERNO DE ACERO DE 3/8" X 6" und 20.0000
PERNO DE ACERO DE 3/8" X 7" und 30.0000
PERNO DE ACERO DE 3/8" X 9" und 20.0000
PINTURA ANTICORROSIVA EPOXI ZINCROMATO gln 12.0000
GASOLINA 84 OCTANOS gln 3.3200
LIJA PAPEL GRANATE ASA 80 plg 13.2000
MADERA TORNILLO DE 3" X 5" X 14' p2 300.0000
MADERA TORNILLO DE 3" X 4" X 3.5' p2 120.0000
MADERA TORNILLO DE 2" X 4" X 4.3' p2 150.0000
MADERA TORNILLO DE 3" X 2" X 6.9' p2 150.0000
MADERA TORNILLO DE 1 1/2" X 8" X 7' p2 300.0000
THINER gln 4.1600
PINTURA ESMALTE SINTETICO gln 18.0000
ARANDELA DE ACERO DE 3/8" und 110.0000
PLANCHA DE ACERO 3MM X 3" m 15.0000
PLANCHA DE ACERO 3MM X 4" m 10.0000
PLANCHA DE ACERO 3MM X 11" m 15.0000

EQUIPOS

HERRAMIENTAS MANUALES %MO


COMPRESORA DE AIRE 4HP hm 26.6800
RETROEXCAVADOR S/ORUG 170-250HP 1.1-2.75 hm 18.6000
GRUPO ELECTROGENO hm 13.3400

COSTO DE OPERACIÓN Y MANTENIMINETO C/AÑO


TO EN LA SITUACION CON PROYECTO
S SOCIALES ALTERNATIVAS I Y II

s Soles)
COSTO PRECIOS F.C. PRECIOS
UNITARIO PRIVADOS SOCIALES
14,970.00 12,076.00

1,160.00 475.60

1,160.00 1,160.00 0.41 475.60

13,810.00 11,600.40

3,276.12 3,276.12 0.84 2,751.94


3,100.88 3,100.88 0.84 2,604.74

6.33 3,165.00 0.84 2,658.60


7.14 2,142.00 0.84 1,799.28

4.51 902.00 0.84 757.68


6.12 1,224.00 0.84 1,028.16
14,970.00 12,076.00

Precio S/. Parcial S/. Presupuestado S/.

7.22 192.63 192.00


5.42 679.02 679.60
4.52 168.14 169.00
7.22 866.40 866.40
1,906.19 1,907.00

5.50 27.50 27.50


5.50 93.50 93.50
1.00 183.00 183.00
10.00 500.00 500.00
7.00 140.00 140.00
8.00 240.00 240.00
9.00 180.00 180.00
60.00 720.00 720.00
12.00 39.84 40.00
2.00 26.40 26.00
2.80 840.00 840.00
2.80 336.00 336.00
2.80 420.00 420.00
2.80 420.00 420.00
2.80 840.00 840.00
22.00 91.52 92.00
40.00 720.00 720.00
1.00 110.00 110.00
4.00 60.00 60.00
7.00 70.00 70.00
22.00 330.00 330.00
6,387.76 6,388.00

97.00 97.00
5.00 133.40 132.00
270.00 5,022.00 5,020.00
20.00 266.80 266.00
5,519.20 5,515.00

13,810.00

Descripción
Situación sin
Proyecto
Alternativa 1
Alternativa 2
Costos Incrementales
Alternativa 1
Alternativa 2
1200

12120.0
Costo de Inversión VP.CO&M VP.Costo Total

0 6,884.51 6,884.51
510,061.74 71,118.37 581,180.10
714,077.30 14,970.00 729,047.30
os Incrementales
510,061.74 64,233.86 574,295.60
714,077.30 8,085.49 722,162.79
COSTOS INCRE

DESCRIPCION VACT AÑOS


0
A.-COSTOS DE PRE- INVERSION 10,500.00
1. Intangibles 10,500.00
1.9.Elaboracion de Expediente Tecnico 10,500.00
B.- COSTOS DE INVERSION 610,825.65
1.1. Mano de Obra Calificada 28,758.63
1.2. Mano de Obra No Calificada 27,336.87
1.3. Materiales 288,885.70
1.4 .Equipos 163,476.70
1.5 .Herramientas Manuales 2,268.02
1.6.Costo Directo 510,725.92
1.7.Gastos Generales 62,819.29
1.10.Gastos de Supervision 31,544.99
1.11.Gastos Administrativos 5,735.45

C.- COSTOS DE POST- INVERSION POR CADA AÑO


D.-COSTOS DE OPERACIÓN Y MANTENIMIENTO -
"CON PROYECTO"
OPERACIÓN
MANTENIMIENTO

E.-COSTO TOTAL "CON PROYECTO" (A+B+C) 621,325.65

F.-COSTOS DE OPERACIÓN Y MANTENIMIENTO


"SIN PROYECTO"
OPERACIÓN
MANTENIMIENTO
TOTAL COSTOS INCREMENTALES 621,325.65

F.A(11%) 1.00
VACT 696,520.35 621,325.65
FUENTE:Equipo formulador
Nota: Según el parámetro del Anexo SNIP 09, se está utilizando el 11% de TSD por lo que los precios estan elab

COSTOS INCRE

DESCRIPCION VACT AÑOS


0
A.-COSTOS DE PRE- INVERSION 8,619.72
1. Intangibles 8,619.72
1.9.Elaboracion de Expediente Tecnico 8,619.72
B.- COSTOS DE INVERSION 501,442.46
1.1. Mano de Obra Calificada 26,170.35
1.2. Mano de Obra No Calificada 11,208.12
1.3. Materiales 242,663.99
1.4 .Equipos 137,320.43
1.5 .Herramientas Manuales 1,905.14
1.6.Costo Directo 419,268.02
1.7.Gastos Generales 51,569.97
1.10.Gastos de Supervision 25,896.09
1.11.Gastos Administrativos 4,708.38

C.- COSTOS DE POST- INVERSION POR CADA AÑO


D.-COSTOS DE OPERACIÓN Y MANTENIMIENTO -
"CON PROYECTO"
OPERACIÓN
MANTENIMIENTO

E.-COSTO TOTAL "CON PROYECTO" (A+B+C) 510,062.18

F.-COSTOS DE OPERACIÓN Y MANTENIMIENTO


"SIN PROYECTO"
OPERACIÓN
MANTENIMIENTO

TOTAL COSTOS INCREMENTALES 510,062.18

F.A(11%) 1.00
VACT 574,083.92 510,062.18
FUENTE:Equipo formulador
Nota: Según el parámetro del Anexo SNIP 09, se está utilizando el 11% de TSD por lo que los precios estan elab

419,268.02

COSTOS INCRE

DESCRIPCION VACT
0
A.-COSTO DE PRE INVERSION 11,479.07
1. Intangibles 11,479.07
1.9.Elaboracion de Expediente Tecnico 11,479.07
B.-COSTO DE INVERSION 702,598.23
1.1. Mano de Obra Calificada 30,158.57
1.2. Mano de Obra No Calificada 35,022.63
1.3. Materiales 345,442.27
1.4 .Equipos 174,359.84
1.5 .Herramientas Manuales 2,475.86
1.6.Costo Directo 587,459.17
1.7.Gastos Generales 72,257.48
1.10.Gastos de Supervision 36,284.42
1.11.Gastos Administrativos 6,597.17

C.-COSTO DE POST INVERSION -


D.-COSTOS DE OPERACIÓN Y MANTENIMIENTO
"CON PROYECTO"
OPERACIÓN
MANTENIMIENTO

E.-COSTO TOTAL "CON PROYECTO" (A+B+C) 714,077.30


F.-COSTOS DE OPERACIÓN Y MANTENIMIENTO -
"SIN PROYECTO"
OPERACIÓN
MANTENIMIENTO

G.-TOTAL COSTOS INCREMENTALES (E-F) 714,077.30

F.A(11%) 1.00
VACT (ExF) 789,272.00 714,077.30
FUENTE:Equipo formulador
Nota: Según el parámetro del Anexo SNIP 09, se está utilizando el 11% de TSD por lo que los precios estan elab

COSTOS INCRE

DESCRIPCION VACT AÑOS


0
A.-COSTOS DE PRE- INVERSION 9,389.40
1. Intangibles 9,389.40
1.9.Elaboracion de Expediente Tecnioco 9,389.40
B.- COSTOS DE INVERSION 574,696.02
1.1. Mano de Obra Calificada 27,444.30
1.2. Mano de Obra No Calificada 14,359.28
1.3. Materiales 290,171.51
1.4 .Equipos 146,462.27
1.5 .Herramientas Manuales 2,079.72
1.6.Costo Directo 480,517.07
1.7.Gastos Generales 59,103.60
1.10.Gastos de Supervision 29,679.14
1.11.Gastos Administrativos 5,396.21

C.-COSTO DE POST INVERSION -


D.-COSTOS DE OPERACIÓN Y MANTENIMIENTO
"CON PROYECTO"
OPERACIÓN
MANTENIMIENTO

E.-COSTO TOTAL "CON PROYECTO" (A+B+C) 584,085.41

F.-COSTOS DE OPERACIÓN Y MANTENIMIENTO -


"SIN PROYECTO"
OPERACIÓN
MANTENIMIENTO

G.-TOTAL COSTOS INCREMENTALES (E-F) 584,085.41

F.A(11%) 1.00
VACT (ExF) 662,490.34 584,085.41
FUENTE:Equipo formulador
Nota: Según el parámetro del Anexo SNIP 09, se está utilizando el 11% de TSD por lo que los precios estan elab

Descripción Costo de Inversión

Situación sin Proyecto 0


Alternativa 1 621,325.65
Alternativa 2 714,077.30

Costos Incrementales

Descripción Costo de Inversión

Alternativa 1 621,325.65
Alternativa 2 714,077.30
COSTOS INCREMENTALES (PRECIOS PRIVADOS)
ALTERNATIVA I

1 2 3 4 5 6

14,970.00 14,970.00 14,970.00 14,970.00 14,970.00 14,970.00

1,160.00 1,160.00 1,160.00 1,160.00 1,160.00 1,160.00


13,810.00 13,810.00 13,810.00 13,810.00 13,810.00 13,810.00

14,970.00 14,970.00 14,970.00 14,970.00 14,970.00 14,970.00

2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00

2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00


12,810.00 12,810.00 12,810.00 12,810.00 12,810.00 12,810.00

0.90 0.81 0.73 0.66 0.59 0.53


11,529.00 10,376.10 9,351.30 8,454.60 7,557.90 6,789.30

or lo que los precios estan elaborados a precio real de mercado

COSTOS INCREMENTALES (PRECIOS SOCIALES)


ALTERNATIVA I
1 2 3 4 5 6
12,076.00 12,076.00 12,076.00 12,076.00 12,076.00 12,076.00

475.60 475.60 475.60 475.60 475.60 475.60


11,600.40 11,600.40 11,600.40 11,600.40 11,600.40 11,600.40

12,076.00 12,076.00 12,076.00 12,076.00 12,076.00 12,076.00

1,169.40 1,169.40 1,169.40 1,169.40 1,169.40 1,169.40

1,169.40 1,169.40 1,169.40 1,169.40 1,169.40 1,169.40

10,906.60 10,906.60 10,906.60 10,906.60 10,906.60 10,906.60

0.90 0.81 0.73 0.66 0.59 0.53


9,815.94 8,834.35 7,961.82 7,198.36 6,434.89 5,780.50

or lo que los precios estan elaborados a precio real de mercado

COSTOS INCREMENTALES (PRECIOS PRIVADOS)


ALTERNATIVA II
AÑOS
1 2 3 4 5 6

17,130.00 17,130.00 17,130.00 17,130.00 17,130.00 17,130.00

1,160.00 1,160.00 1,160.00 1,160.00 1,160.00 1,160.00


13,810.00 13,810.00 13,810.00 13,810.00 13,810.00 13810.00

14,970.00 14,970.00 14,970.00 14,970.00 14,970.00 14,970.00


2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 2160.00

2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00

12,810.00 12,810.00 12,810.00 12,810.00 12,810.00 12,810.00

0.90 0.81 0.73 0.66 0.59 0.53


11,529.00 10,376.10 9,351.30 8,454.60 7,557.90 6,789.30

or lo que los precios estan elaborados a precio real de mercado

COSTOS INCREMENTALES (PRECIOS SOCIALES)


ALTERNATIVA II

1 2 3 4 5 6

13,245.40 13,245.40 13,245.40 13,245.40 13,245.40 13,245.40

475.60 475.60 475.60 475.60 475.60 475.60


11,600.40 11,600.40 11,600.40 11,600.40 11,600.40 11600.40

12,076.00 14,970.00 14,970.00 14,970.00 14,970.00 14,970.00

1,169.40 1,169.40 1,169.40 1,169.40 1,169.40 1169.40

1,169.40 1,169.40 1,169.40 1,169.40 1,169.40 1,169.40

10,906.60 13,800.60 13,800.60 13,800.60 13,800.60 13,800.60

0.90 0.81 0.73 0.66 0.59 0.53


9,815.94 11,178.49 10,074.44 9,108.40 8,142.35 7,314.32
or lo que los precios estan elaborados a precio real de mercado

VP.CO&M VP.Costo Total

2,160.00 6,884.51
14,970.00 636,295.65
14,970.00 729,047.30

VP.CO&M VP.Costo Total

12,810.00 634,135.65
12,810.00 726,887.30
1
7 8 9 10 0.90
0.81

0.73
0.66
0.59
0.53
0.48
0.43
0.39
0.35

14,970.00 14,970.00 14,970.00 14,970.00

1,160.00 1,160.00 1,160.00 1,160.00


13,810.00 13,810.00 13,810.00 13,810.00

14,970.00 14,970.00 14,970.00 14,970.00

2,160.00 2,160.00 2,160.00 2,160.00

2,160.00 2,160.00 2,160.00 2,160.00


12,810.00 12,810.00 12,810.00 12,810.00

0.48 0.43 0.39 0.35


6,148.80 5,508.30 4,995.90 4,483.50

7 8 9 10
12,076.00 12,076.00 12,076.00 12,076.00

475.60 475.60 475.60 475.60


11,600.40 11,600.40 11,600.40 11,600.40

12,076.00 12,076.00 12,076.00 12,076.00

1,169.40 1,169.40 1,169.40 1,169.40

1,169.40 1,169.40 1,169.40 1,169.40

10,906.60 10,906.60 10,906.60 10,906.60

0.48 0.43 0.39 0.35


5,235.17 4,689.84 4,253.57 3,817.31

7 8 9 10

17,130.00 17,130.00 17,130.00 17,130.00

1,160.00 1,160.00 1,160.00 1,160.00


13810.00 13810.00 13810.00 13810.00

14,970.00 14,970.00 14,970.00 14,970.00


2160.00 2160.00 2160.00 2,160.00

2,160.00 2,160.00 2,160.00 2,160.00

12,810.00 12,810.00 12,810.00 12,810.00

0.48 0.43 0.39 0.35


6,148.80 5,508.30 4,995.90 4,483.50

7 8 9 10

13,245.40 13,245.40 13,245.40 13,245.40

475.60 475.60 475.60 475.60


11600.40 11600.40 11600.40 11600.40

14,970.00 14,970.00 14,970.00 14,970.00

1169.40 1169.40 1169.40 1,169.40

1,169.40 1,169.40 1,169.40 1,169.40

13,800.60 13,800.60 13,800.60 13,800.60

0.48 0.43 0.39 0.35


6,624.29 5,934.26 5,382.23 4,830.21
CRONOGRAMA DE EJECUCI

NOMBRE DEL PROYECTO “CONSTRUCCION DE PUENTE PEATONAL HELARES DIST

Cronograma
Alternativa I

Descripción AÑO 0
MES 1- 4 PRIMER MES
Etapa Preinversión
Elaboración de Expediente técnico

Etapa Inversión
2.-EJECUCION DE OBRA
3.-COSTOS DE PLAN DE MANEJO AMBIENTAL
4.-COSTOS DE SEGURIDAD Y ASISTENCIA MEDICA
5.-GASTOS DE SUPERVISION
6.-GASTOS ADMINISTRATIVOS

Fase de Post Inversion


OPERACIÓN Y MANTENIMIENTO

CRONOGRAMA DE EJECUCION
NOMBRE DEL PROYECTO “CONSTRUCCION DE PUENTE PEATONAL HELARES DIST

Cronograma
Alternativa I

Descripción AÑO 0
MES 1- 4 PRIMER MES
Etapa Preinversión
Elaboración de Expediente técnico 50% 50%

Etapa Inversión
2.-EJECUCION DE OBRA 25%
3.-COSTOS DE PLAN DE MANEJO AMBIENTAL 50%
4.-COSTOS DE SEGURIDAD Y ASISTENCIA MEDICA 25%
5.-GASTOS DE SUPERVISION 25%
6.-GASTOS ADMINISTRATIVOS 25%
Fase de Post Inversion
OPERACIÓN Y MANTENIMIENTO
RAMA DE EJECUCION FISICA

EATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION - CUSCO”

ograma

AÑO 0 AÑO 1-10


RIMER MES SEGUNDO MES TERCER MES CUARTO MES POST INVERSIÓN

MA DE EJECUCION FINANCIERA
EATONAL HELARES DISTRITO DE KIMBIRI- LA CONVENCION - CUSCO”

Cronograma

AÑO 0 AÑO 1-10


RIMER MES SEGUNDO MES TERCER MES CUARTO MES POST INVERSIÓN

25% 25% 25% 25%


50% 50%
25% 25% 25% 25%
25% 25% 25% 25%
25% 25% 25% 25%
100%
ESTUDIOS DE PRE-INVERSION A NIVEL DE PERF

PROYECTO : Err:509

UBICACIÓN:
SECTOR: SECTOR: HELARES
DISTRITO: DISTRITO: KIMRIRI
PROVINCIA: PROVINCIA: LA CONVENCION
DEPARTAMENTO: DEPARTAMENTO: CUSCO

INDICE COSTO EFECTIVIDAD A PRECIOS SOCIALES - ALTERNATIVA 01

AÑO COSTOS A PRECIOS SOCIALES POBLACIÓN SERVIDA


INVERSION (S/.) O Y M (S/.) TOTAL (S/.)
0 510,062.18 510,062.18 0
1 12,076.0 12,076.0 385
2 12,076.0 12,076.0 390
3 12,076.0 12,076.0 395
4 12,076.0 12,076.0 400
5 12,076.0 12,076.0 406
6 12,076.0 12,076.0 411
7 12,076.0 12,076.0 416
8 12,076.0 12,076.0 422
9 12,076.0 12,076.0 427
10 12,076.0 12,076.0 433

VAN (Soles)
Resultados de la evaluación
Indicadores Resultados
VAN a precios
sociales (S/.) 581,180.54 S/. 581,180.54
Pob. Promedio (hab 409
ICE (S/./hab.) 1421.33 OK! ICE (S/. Hab)

LINEA DE CORTE PROPUESTA POR EL MEF

1630 S/. Hab.


ON A NIVEL DE PERFIL

ANALISIS DE SENSIBILIDAD -ALTERNATIVA 01

Analisis de sensibilidad
1.30 1.2 1.1 0.9 0.8 0.7
663,080.83 612,074.61 561,068.40 459,055.96 408,049.74 357,043.52
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20
15,698.80 14,491.20 13,283.60 10,868.40 9,660.80 8,453.20

755,534.71 697,416.65 639,298.60 523,062.49 464,944.44 406,826.38

VARIACION DEL ICE

30% 20% 10% -10% -20% -30%


1,847.73 1,705.60 1,563.46 1,279.20 1,137.07 994.93

MAL!
PROYECCION DE LA DEMANDA
Año Poblacion Cobertura Demanda (Hab.) N° de Miem/Fam
(1) (2) (3) (4)=(2)x(3) (5)
0 380 1 380 3.85
1 385 1 385 3.85
2 390 1 390 3.85
N° Familias
(6)=(4)/(5)
99
100
101
Descripción Costo de Inversión VP.CO&M VP.Costo Total

Situación sin Proyecto 0 6,884.51 6,884.51

Alternativa 1 510,061.74 71,118.37 581,180.10

Alternativa 2 714,077.30 14,970.00 729,047.30

Costos Incrementales

Alternativa 1 510,061.74 64,233.86 574,295.60

Alternativa 2 714,077.30 8,085.49 722,162.79