Contoh Timeline EOT Akibat Constrain Lahan Belum Bebas
Contoh Timeline EOT Akibat Constrain Lahan Belum Bebas
Contoh Timeline EOT Akibat Constrain Lahan Belum Bebas
Update : 21 May 17
27 Nov 17 dan
4 Lahan Diserahterimakan antara 15 Aug 17 s.d 27 Nov 17 13-15, 19-25, 37, 42, 46, 47, 51, 52 210,763 0 210,763 18.83% 14 Nov 17
Surat No. 111 28-Nov-17 22-Feb-18
Sebelum 22 Asumsi
5 Lahan Terkendala di Area Bebas per 21 May 2017 1, 4-10, 12, 17, 18, 43, 50 109,790 0 109,790 9.81% 23-Feb-18 08-Apr-18
Feb 18 WIKA
Lahan Belum Dijadwalkan Bebas Oleh Pertamina - Asumsi Sebelum 08 Asumsi
6 11, 16, 28-32, 41, 48, 49, 54 126,124 0 126,124 11.27% 09-Apr-18 14-Jun-18
Bebas sebelum 22 Feb 18 Apr 18 WIKA
2
7 Area Gunung Sepuluh Step 1 55 cut 36,119 0 36,119 3.23% Done 15-Jun-18 29-Jun-18
8 Lahan Diserahterimakan setelah 22 Feb 18 53 50,527 0 50,527 4.51% 27-Jun-18 Surat No. 111 30-Jun-18 21-Jul-18
9 Lahan Diserahterimakan setelah 21 Jul 18 36 60,844 0 60,844 5.44% 08-Jan-19 Surat No. 111 09-Jan-19 02-Feb-19
3
10 Area Gunung Sepuluh Step 2 55 cut 60,844 0 60,844 5.44% Done 03-Feb-19 28-Feb-19
Project Timeline
Project Started ANDAL Issued End of Project Forecast Finish
12/1/2016 5/25/2017 12/1/2017 2/1/2019
2016 Dec Mar Jun Sep Dec Mar Jun Sep Dec 2019
(No. 8) Area Dijadwalkan Pertamina Bebas pada Surat No.111 (Tahap 2) 6/30/2018 - 7/21/2018
(No. 9) Area Dijadwalkan Pertamina Bebas pada Surat No.111 (Area 36) 1/9/2019 - 2/2/2019
Tahap
Handover 3
(No. 10) Area Gunung Sepuluh (Tahap 2) 2/3/2019 - 2/28/2019