Anda di halaman 1dari 6

SAP EDUCATION

SAMPLE QUESTIONS: C_TS420_1610

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610)

Disclaimer: These sample questions are for self-evaluation purposes only and do not appear on the
actual certification exams. Answering the sample questions correctly is no guarantee that you will pass
the certification exam. The certification exam covers a much broader spectrum of topics, so do make
sure you have familiarized yourself with all topics listed in the exam competency areas before taking the
certification exam.

Questions

1. How can Production Planning and Detailed Scheduling (PP/DS) enhance the
standard planning functionality ?

Please choose the correct answer.

a) O By providing multilevel material requirements planning

b) O By providing future demands from demand figures in the past

c) O By providing cross-plant planning and deployment

d) O By providing replenishment proposals with exact times

2. Which warehouse management functions are available in SAP EWM but NOT in
SAP WM ?

Note: There are 3 correct answers to this question.

a) O Handling Unit Management

b) O Expected goods receipt

c) O Labor Management

d) O Yard Management

e) O Slotting
3. How can you limit the number of master data objects to be created when the
manufacturing process is the same for many different products?

Please choose the correct answer.

a) O By creating routings with parallel sequences

b) O By assigning the same production version to different materials

c) O By creating routings with alternative sequences

d) O By assigning different materials to the same routing

4. Which technological advances enabled the development of SAP S/4HANA as the


digital core ?

Note: There are 3 correct answers to this question.

a) O Big and affordable memory

b) O Multi core processors enabling parallelism of tasks

c) O Wide adoption of web standards such as Service oriented


architecture

d) O Advances in the three-tier architecture approach

e) O Capability to add to server landscape and scale


5. Which of the following apply to MRP Live ?
Note: There are 2 correct answers to this question.

a) O The BAdIs for classical MRP also apply to MRP Live.

b) O The definition of the planning scope is more flexible.

c) O The sequence of planning materials is calculated across plants.

d) O Planned orders need to be converted to purchase requisitions for


externally procured materials.

6. You want to procure your material components based on a forecast for the
finished material derived from historical sales. When customers order, you
produce the finished product and reserve it for that particular order.

Which is the appropriate planning strategy to use?

Please choose the correct answer.

a) O Planning with final assembly (40)

b) O Make-to-order production (20)

c) O Planning without final assembly (50)

d) O Production by lot size (30)


7. The settings for MRP can be maintained at different levels.
If settings have been maintained in different places, in which sequence does the
system search for the MRP settings?

Please choose the correct answer.

a) O MRP Group –> Material Master –> Plant Settings

b) O Plant Settings –> MRP Group –> Material Master

c) O Material Master –> Plant Settings –> MRP Group

d) O Material Master –> MRP Group –> Plant Settings

8. Which elements are included in the structure of the batch where-used list?

Note: There are 3 correct answers to this question.

a) O Purchase orders

b) O Planned orders

c) O Transfers from batch to batch

d) O Stock transfers

e) O Collective orders
9. The procurement type of your material is set to "E" for In-house production.
Which of the following is valid to determine a source of supply in SAP S/4HANA?

Please choose the correct answer.

a) O Selection Method

b) O Contract

c) O Purchasing Info Record

d) O Production Version

10. A customer is considering switching from order-related settlement to product-


related settlement.

What are capabilities of cost collectors?

Note: There are 2 correct answers to this question.

a) O They can be created automatically during month end process.

b) O They can be applied to make-to-stock production order.

c) O They can be used for manufacturing with collective orders.

d) O They can be used for repetitive manufacturing.


Solutions

1 a) Incorrect 2 a) Incorrect 3 a) Incorrect 4 a) Correct 5 a) Incorrect

1 b) Incorrect 2 b) Correct 3 b) Incorrect 4 b) Correct 5 b) Correct

1 c) Incorrect 2 c) Correct 3 c) Incorrect 4 c) Incorrect 5 c) Correct

1 d) Correct 2 d) Incorrect 3 d) Correct 4 d) Incorrect 5 d) Incorrect

2 e) Correct 4 e) Correct

6 a) Incorrect 7 a) Incorrect 8 a) Correct 9 a) Incorrect 10 a) Incorrect

6 b) Incorrect 7 b) Incorrect 8 b) Incorrect 9 b) Incorrect 10 b) Correct

6 c) Correct 7 c) Incorrect 8 c) Correct 9 c) Incorrect 10 c) Incorrect

6 d) Incorrect 7 d) Correct 8 d) Correct 9 d) Correct 10 d) Correct

8 e) Incorrect

Want to learn more? Contact SAP for more information.