Anda di halaman 1dari 1

REKAPITULASI ESTIMASI BIAYA

PEKERJAAN : REilOVASI PANGKALATII LIIIDUIIIGAN LINGKUNGA}I PERAIRAN {LLP}


IUIARINE REGIOI{ III BALOiIGAN
JANGKA WAKTU : 65 {ENAI{ PULUH Ll[iA] HARI KALEI.IDER
LOKASI : TERHII{AL KHUSUS t6lGAS BALO}IGAN

URAIAN P E K E R J A A N JUMLAH
PEKERJAAIII UMUM
A.{. PEKERJAAil PERSIAPAN Rp. 50,336,9{4.56

PEKERJAAN BANGUNAH GUDANG DA]II KANTOR


B.{. PEKERJAAH STRUKTUR Rp. 189,875,396.49
8.2. PEKERJAAN ARSITEKTUR Rp. {,53{,{70,9{2.55

SUB TOTAL Rp. 1,77'1,383,223.60


Rp. 177,'138,322#
Rp. 1,9fi,521,545.96
DIBULATKAN Rp. 1,98,521,000.00