LCPL Standard Program Hierarchy

PROGRAM PROGRAM PROGRAM PURPOSE PROGRAM TYPICALLY


LEVEL TYPE RELATIONSHIPS DEVELOPED BY

1 Summary Dependent on Level 3 Automatically generated


Summarised Master Program to
Program Program from Level 3 program
WBS Level 2

Used for reporting purposes only

2 Summary Dependent on Level 3 Automatically generated


Summarised Master Program to
Program Program from Level 3 program
WBS Level 4

Used for reporting purposes only

3 Integrated Parent relationship. Sets Planner(s), Project


Cross functional strategic program to
Master planning parameters for Manager, C+P Owner
project completion
Program Levels 4 and 5
Developed to clearly articulate
execution strategies. Highlight
project critical path and track key
milestones. Used to support project
wide resource management and to
set planning parameters for detailed
Execution Programs

4 Execution Child Relationship.


Mid Term execution program Design Manager(s)
Program Planning parameters set
Developed to support the co- Procurement Manager(s)
by Level 3 program
ordination and delivery of design,
Construction Manager(s)
procurement and construction
packages

Typically operates on a rolling 3


month look-ahead basis

5 Execution Child Relationship.


Short Term execution program Project Engineer(s), Site
Program Planning parameters set
Engineer(s)
Developed to support the co- by Level 3 and/or Level 4
ordination and delivery of design, program Design Team Leader(s)
procurement and construction
packages

Typically operates on a rolling 4


week look-ahead basis

Title: LCPL Standard Program Hierarchy Template Date Published: 09/07/2012 Page 1 of 1
ID: 001498 Version: 3
Our Way Management System - Uncontrolled Document when Printed
Leighton Contractors Pty. Limited ABN 98 000 893 667 www.leightoncontractors.com.au