PROPOSED: CONSTN. OF 1 UNIT, 2 STORY-2CL SCIENCE LABORATORY BLDG.

LOCATION: DUGMANON NATIONAL HIGH SCHOOL


DUGMANON, HINATUAN, SURIGAO DEL SUR
CONTRACTOR: XEXAMIN2 CORPORATION(Marfore St. Peal Subd. Davao City)
SUB-CON: LARRY T. JABAGATON
ADDRESS: P-6 Tambakan, Sto. Nino, Hianatuan, Surigao del Sur
Cellphone No. 09070454993

BREAKDOWN AND QOUTATION OF LABOR COST

ITEM OF WORKS
A. SITE DEVELOPMENT
1. Clearing and Grubbing
2. Staking and Lay-out
B. EXCAVATION WORKS
1. Manual Excavation of Column (F1,F2,F3)
2. Manual Excavation of FTB and WF
C. EMBANKMENT
1. Backfilling
2. Filling of Slab on fill(Base Preparation)
3. Manual Labor and Hauling
D. SOG – SLAB OR GRADE
1. Structural Steel / Matting
2. Reinforce Concrete
E. COLUMN FOOTING WORKS/ CONCRETE
1. Structural Steel Re-bar of F1C1-F2/F3
2. Tie Beam
3. Wall Footing
4. Forms/ & Scaffolding
F. HALLWAY BLOCK, RAMPS, & STEPS
G. ELECTRICAL & PLUMBING ROUGH-INS
1. Electrical Rough- Ins
2. Plumbing & Downspout Rough-Ins
H. SEPTIC TANK, CATCH BASIN AND DOWNSPOUT
1. Manual Excavation
2. Structural Steel (Re-bars)
3. Reinforce Concrete
4. Forms/Braces/Scaffolding
I. GRAB-BAR (PWD)
1. Railings and Handrails
2. Bending / Welding Works
J. CONCRETE WALL (Ground floor and Second floor)
1. CHB Filling
2. Mortar Wall and Sitting
3. Horizontal and Vertical Steel
4. Plastering and Finishing
K. STAIRWAYS ENTRANCE AND EXIT
1. Cantilever Beam/ Landing
2. Foundation / Column / Reinf. Conc. Stair
3. Welding Works / Railings / Checkered Plate / Handrail
L. STRUCTURAL SECOND FLOOR
1. Re – bar / Structural Steel
2. Con Suspended Slab
3. Metal Deck
4. Scaffolding / Forms
5. Roof Beams / Beams
6. Sun Breaker (RC)
M. CEILING WORKS
1. Installation of metal furrings / framing
2. Installation of ficem board
N. TRUSSES FRAMINGAND WELDING WORKS
1. Truss Framing / CEE Purlins Framing
2. Braces – SOG Rod / 0X – Bracing with Turning Buckle
3. Base Plate, Bolts, Gusset Plate, Nuts
4. Scaffolding
O. ROOFING WORKS
1. Installation Pre – Painted Roof
2. Installation of Pre- Painted Gutter / Flashing
3. Installation of Ridge Roll
4. Installation of Fascia Board
P. PLUMBING WORKS
1. Tiles Works
2. Plumbing Fixtures
3. PWD Grab – Bar / Facial Mirror
Q. ELECTRICAL WORKS
R. DOORS AND WINDOWS
S. PAINTING WORKS
T. FURNITURES
U. EXTRA AND RECTIFICATIONWORKS