TIME LINE SCHEDULE

INSTALL IHLA TANK T-202 & T-203


PT. SHELL INDONESIA
Gresik, Jawa Timur
ID Work Description Duration
W1 W2 W3 W4
28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0 TIME LINE SUMMARY (EFFECTIVE 20 days
WORKING DAYS)

1 1 PREPARATION WORKS 6 days

2 1.1 Propose Project Document (Drawing, ITP, Material 6 days


Approval, etc)

3 1.2 Prepare Manpower, Material & Tools 6 days

4 2 CONSTRUCTION WORKS 14 days

5 2.1 TANK T202 9 days

6 2.1.1 Install Scaffolding 2 days

7 2.1.2 Fabrication works 2 days

8 2.1.3 Install on Site 4 days

9 2.1.4 NDT & Inspection 1 day

10 2.1.5 Dismantling Scaffolding & General Cleaning 2 days

11 2.2 TANK T203 14 days

12 2.2.1 Install Scaffolding 2 days

13 2.2.2 Fabrication works 2 days

14 2.2.3 Install on Site 5 days

15 2.2.4 NDT & Inspection 1 day

16 2.2.5 Dismantling Scaffolding & General Cleaning 2 days

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: IHLA
Summary Inactive Summary Critical
Date: Thu 27/06/19
Project Summary Manual Task Critical Split
External Tasks Duration-only Progress
External Milestone Manual Summary Rollup Deadline
by :

ASUKA ENGINEERING INDONESIA, PT