Lampiran 1

RENCANA ANGGARAN BIAYA


Renovasi Mushola

KODE HARGA SATUAN HARGA


NO URAIAN PEKERJAAN SAT VOLUME
ANALISA Rp Rp
1 2 3 4 5 6 7
I PEKERJAAN PASANGAN
1 Pasangan bata merah tebal 1/2 bata 1:3:10 M2 100.00 D.5 77,985.00 7,798,500.00
2 Plesteran 1 : 4 M2 120.00 E.1 29,038.30 3,484,596.00
3 Pasang lantai keramik 40 x 40 M2 60.50 L.4.pls 116,987.40 7,077,737.70
SUB TOTAL BAGIAN I : PEKERJAAN PASANGAN 18,360,833.70
II PEKERJAAN BETON
1 Beton bertulang kolom, sloof (175 Kg/m3) M3 3.40 G.14.k.175 3,786,697.00 12,874,769.80
SUB TOTAL BAGIAN II : PEKERJAAN KAYU 12,874,769.80
III PEKERJAAN KAYU
1 Pasang kuda - kuda gording kayu kruing M3 1.50 F.6.kr 8,429,685.00 12,644,527.50
2 Pasang rangka atap kayu kruing M2 80.00 F.8.kr 90,911.25 7,272,900.00
3 Pasang Kusen Pintu dan Jendela Kayu KruingM3 0.80 F.1.kr 9,145,000.00 7,316,000.00
SUB TOTAL BAGIAN III : PEKERJAAN KAYU 27,233,427.50
IV PEKERJAAN ATAP
1 Pasang genting plentong M2 80.00 H.1 58,675.00 4,694,000.00
SUB TOTAL BAGIAN IV : PEKERJAAN ATAP 4,694,000.00
V PEKERJAAN CAT
1 Cat tembok 2 kali M2 120.00 M.5 14,037.00 1,684,440.00
SUB TOTAL BAGIAN V : PEKERJAAN CAT 1,684,440.00
TOTAL BIAYA 64,847,400.00