NO URAIAN PEKERJAAN SAT VOLUME ANALISA Rp Rp 1 2 3 4 5 6 7 I PEKERJAAN PASANGAN 1 Pasangan bata merah tebal 1/2 bata 1:3:10 M2 100.00 D.5 77,985.00 7,798,500.00 2 Plesteran 1 : 4 M2 120.00 E.1 29,038.30 3,484,596.00 3 Pasang lantai keramik 40 x 40 M2 60.50 L.4.pls 116,987.40 7,077,737.70 SUB TOTAL BAGIAN I : PEKERJAAN PASANGAN 18,360,833.70 II PEKERJAAN BETON 1 Beton bertulang kolom, sloof (175 Kg/m3) M3 3.40 G.14.k.175 3,786,697.00 12,874,769.80 SUB TOTAL BAGIAN II : PEKERJAAN KAYU 12,874,769.80 III PEKERJAAN KAYU 1 Pasang kuda - kuda gording kayu kruing M3 1.50 F.6.kr 8,429,685.00 12,644,527.50 2 Pasang rangka atap kayu kruing M2 80.00 F.8.kr 90,911.25 7,272,900.00 3 Pasang Kusen Pintu dan Jendela Kayu KruingM3 0.80 F.1.kr 9,145,000.00 7,316,000.00 SUB TOTAL BAGIAN III : PEKERJAAN KAYU 27,233,427.50 IV PEKERJAAN ATAP 1 Pasang genting plentong M2 80.00 H.1 58,675.00 4,694,000.00 SUB TOTAL BAGIAN IV : PEKERJAAN ATAP 4,694,000.00 V PEKERJAAN CAT 1 Cat tembok 2 kali M2 120.00 M.5 14,037.00 1,684,440.00 SUB TOTAL BAGIAN V : PEKERJAAN CAT 1,684,440.00 TOTAL BIAYA 64,847,400.00