RESUME TARGET DAN PENCAPAIAN PRODUKSI CFK #1, #2, & #3

PERIODE BULAN APRIL 2019

1. CFK #1 DAN #2
Satuan CFK #1 CFK #2 PLANT CFK #1&#2
Target Listrik Terkirim kWh 14,737,499.64 14,737,499.64 29,474,999.28
AFpm % 90.97222
Ea kWh 14,526,187.00 13,734,267.00 28,260,454.00
Qi kWh 28,153,910.00
DCH kWh 2,394,744.00
AFa % 94.28597

KETERANGAN :
@ Target pembebanan harian sesuai dengan Afpm bulan April 2019 sebesar 982,499.98 kWh
@ Tanggal 11 April 2019 Turbin CFK#1 dan CFK#2 Trip Pukul 15:45 WITA karena gangguan jaringan, CFK#1
masuk kembali ke system pukul 18:29 WITA, CFK#2 masuk kembali ke system pukul 18:17 WITA
@ Tanggal 13,14,21,22 April 2019 target tidak tercapai karena penurunan beban oleh PLN
@ Tanggal 27 s.d 30 April Emergency shutdown karena Stock Batubara habis BO#2, TG#2 lepas system tgl 27
pukul 22:02 WITA, synkron ke system tgl 30 Pukul 01:44 WITA dan TG#1 lepas system pukul 02:16 WITA
2. CFK #3
Satuan CFK #3
Target Listrik Terkirim kWh 15,023,998.80
AFpm % 41.73333
Ea kWh 14,556,616.00
Qi kWh 14,463,603.00
DCH kWh 502,885.00
AFa % 41.57358

KETERANGAN :
@ Target pembebanan harian sesuai dengan Afpm bulan April 2019 sebesar 1,073,142.77 kWh
@ Tanggal 01 s.d 16 April 2019 Shutdown lanjut kegiatan Serious Inspection
@ Tanggal 16 April 2019 Start-up dan sinkron Pukul 09:01 WITA dan pukul 15:01 WITA lepas kembali
dari system karena beban tidak bisa maksimal, ada masalah di governor valve.
@ Tanggal 18 April 2019 Start-up dan sinkron Pukul 04:15 WITA dan pukul 12:31 WITA lepas kembali
dari system karena beban tidak bisa maksimal, pengecekan governor valve oleh team china.
@ Tanggal 18 April 2019 Start-up dan sinkron kembali Pukul 15:47 WITA sukses.
3. PEMAKAIAN BATUBARA

Kecukupan (hari)
batubara
berdasarkan rata-
rata pemakaian
harian : 1 Hari

Tanjung Batu, 08 Mei 2019

Rosibel Ompusunggu
Direktur Operasional