Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
15. Poor Housekeeping at the site 1. Put barrication around the Immediate
near carpentry yard material or rubbish.
2. Arrange housekeeping team. One day
3. Maintain the record. One month
16. Without LEV Storage of Paint, 1. Remove workers from the store Immediate
No fire extinguisher and 2. Open the doors or window. Immediate
evacuation plans shows in the 3. Install exhaust system One day
store area. 4. Place Fire extinguisher in store. One day
5. Paste evacuation plan in the One day
store.
6. Inspect schedulable. One week
17. Slip & Trips by wires and 1. Put soft barrication around the Immediate
improper placement of poor housekeeping area
scaffolding 2. Remove the obstruction i.e. One day
Wires and Scaffolding material.
3. Tool Box Talk. One week
18. Working Without PPE 1. Stop the work. Immediate
2. Provision of PPE. Immediate
3. Tool Box talk Three days
4. Maintain record of PPE’s One week
5. Apply penalty system. One month
6.
INTERNATIONAL GENERAL
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
20. Open Electrical Connections 1. Shut off the electric supply. Immediate
2. Repair the connection with Immediate
competent electrician.
3. Close Electric boxes. One week
4. Inspection record must be One month
made.
21. Poor Waste Management i.e. 1. Barricade the area and ask the Immediate
wastes area at improper place. vehicles to adopt alternate
Waste collected around the routes.
site. 2. Remove the Waste by some One day
competent subcontractor of
Waste Management.
3. Recycle the waste if possible. One month
4. Maintain one proper waste area One month
away from the work site.
22. Work in Confined Spaces 1. Eliminate the work Immediate
without ventilation equipment 2. Provision of Air blower for air One day
and without portable gas intake and portable multi gas
detector. detector.
3. Maintain the record and inspect One month
before start of work.
23. Sharp Edges found at work 1. Stop the work. Immediate
area. 2. Put barrication. One day
3. Remove the sharp edges. One week
INTERNATIONAL GENERAL
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012
25. Spray paint and Plaster without 1. Stop the work. Immediate
PPE i.e. mask and goggles 2. Tool box talk Immediate
3. Provision of PPE One day
4. Inspection made regularly. One week
26. Contact with buried services 1. Stop the work and evacuate the Immediate
area.
2. Contact emergency services. Immediate
3. Barricade the area. Immediate
4. Inspect the area. After clearance
5. Get permit to work. One week
6. Maintain record. One month
27. First Aid Services 1. Provision of Initial First aid
2. Availability of Ambulatory
services.
3. Maintain Accident, Incident and
Health record,
28. Provision of Worker Welfare 1. Provision of Rest Breaks.
2. Provision of Rest areas.
3. Provision of Medical services
Sheet
Place inspected: Bawabat Al Sharq Phase II Villas Baniyas _ Date of inspection 03 / 09 / 2012