A PEKERJAAN TANAH
PONDASI
1 PEKERJAAN L=P X L M²
PEMBERSIHAN LAHAN =16,5X7
=115,5
2 PEMASANGAN K=2.(P+L) M¹
BOUPLANG =2.(12,5+7)
=2X19,25
=38,5
3 PEKERJAAN GALIAN V=L.PENAMPANG X P.PONDASI M³
TANAH PONDASI 1/2 L.PEN=PXL
=0.55X0,8
=0,44
P.PONDASI=40
V=L.PENXP.PONDASI
=0,44X40
=17,6
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PENAMPANG=PXL
=0,8X0,8
=0,64
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0,64X40
=25,6
JUMLAH TOTAL V=17,6+25,6 M³
=43.2
4 PEKERJAAN URUGAN V=L.PENAMPANG X P.PONDASI M³
BAWAH PONDASI 1/2 L.PENAMPANG=PXL
=5.5X0,05
=0,275
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.275X40
=11
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PEN=PXL
=0,8X0,05
=0,04
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.04X40
=1,6
JUMLAH TOTAL V=11+1,6 M³
=12,6
5 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN L.PEN=PXL
ANSTAMPING1/2 =0,43X0,15
=0,0675
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.0675X40
=2,7
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PEN=PXL
=0,7X0,15
=0,105
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0,105X40
=4,2
JUMLAH TOTAL V=4,2+2,7 M³
=6,9
6 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN BATU 𝑎+𝑏
KALI 1/2
L.PEN= 𝑥𝑡
2
0,4+0,15
= 𝑥 0,6
2
=0,165
P.PONDASI=40
V=L.PENAMPANGXP.PONDASI
=0,165X40
=6.6
PONDASI UTUH V=L.PENAMPANGXP.PONDASI M³
𝑎+𝑏
= 𝑥𝑡
2
0,6+2,25
= 𝑥 0,6
2
=0,855
V=L.PEN X P.PONDASI
=0.045X40
=1,8
JUMLAH TOTAL V=6,6+1,8 M³
=8,4
7 PEKERJAAN URUGAN V=43,2-12,6-6,9-8,4 M³
TANAH KEMBALI =15,3
NO PEKERJAAN VOLUME SATUAN SKETSA
B PEKERJAAN BETON
1 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN SLOOF =0,15X0,2X40
=0,03X40
=1,2
2 PEKERJAAN KOLOM V=L.PENAMPANG X P.PONDASI M³
15/15 =0,15X0,15X40
=0,0225X40
=0,9
JUMLAH KOLOM =25
V=0,9X25
=22,5
KOLOM KI 15/30 V=L.PENAMPANG X JML KOLOM KI M³
=0.15X0,3X3
=0,135
KOLOM K2 V=L.PENAMPANG X JML KOLOM K2 M³
=0,15X0,3X1
=0,045
PEKERJAAN RING BALK V=P X L P.BANGUNAN M³
15/20 =0,15X0,2
=0,03
P.R.BANGUNAN
(40+6,475)
=46,475
V=0,03X46,475
=1,39425
V BALOK=S X S X T
=0,04X0,04X0,15
=0,024
V BALOK=S X S X T
=0,15X0,15X0,6
=0,0135
V LIMAS=L.ALAS+L.ALAS BAWAH X T
V=(0,13X0,15)+(0,4X0,4)
=0,0195+0,6
=0,6195
NO PEKERJAAN VOLUME SATUAN SKETSA
NO PEKERJAAN VOLUME SATUAN SKETSA
C PEKERJAAN PASANGAN
DINDING 1:3
1 DINDING BAGIAN WC V=P X T M²
(A) =2 X 2
=4
2 DINDING BAGIAN WC V=P X T M²
(B) =1,5 X 2
=3
3 DINDING BAGIAN WC V=P X T M²
(C) =2 X 2
=4
4 DINDING BAGIAN WC V=(P X T)-PINTU KM M²
(D) =(1,5X2)-0,75
=3 - 0,75
=2,25
5 DINDING E V=(P X T)-JENDELA KACA M²
=(2,5X0,8) - 1,325
=2 - 1,325
=0,675
6 DINDING (F) V=(PXT) – PINTU M²
=(1,45X0,8) – 0,85
=1,16 – 0,85
=0,31
7 DINDING (G) V=P X T M²
=2,475 X 0,8
=1,98
8 DINDING (H) V=(PXT) – PINTU M²
=(1 X 0,8) – 0,75
=0,8 – 0,75
=0,05
9 DINDING (I) ADA 2 V= (P X T)X2 M²
=(1X0,8)X 2
=0,8 X 2
=1,6
10 DINDING (J) V=P X T M²
=3,90X 0,8
=3,12
11 DINDING (K) V=P X T M²
=3 X 0,8
=2,4
12 DINDING (L) V=P X T M²
=2 X 0,8
=1,6
13 DINDING (M) V=P X T M²
=4,15 X 0,8
=3,32
14 DINDING (N) V=P X T M²
=6 X 0,8
=4,8
15 DINDING (O) V=P X T M²
=2,25 X 0,8
=1,8
16 DINDING (P) V=P X T M²
=3 X 0,8
=2,4
17 DINDING (Q) ADA 2 V= (P X T)X2 M²
=(2,75X0,8)X 2
=2,2 X 2
=4,4
18 DINDING (R) ADA 2 V= (P X T)X2 - PINTU M²
=(3X0,8)X 2 – 0,85
=2,4 X 2 – 0,85
=2,4 X 1,15
=2,76
19 DINDING (S) V=P X T M²
=3 X 0,8
=2,4
20 DINDING (T) V=P X T M²
=7 X 0,8
=5,6
21 JUMLAH KESELURUHAN V= 4+3+4+2,25+0,675+0,31+1,98+0,05 M²
+1,6+3,12+2,4+1,6+3,32+4,8+1,8+
2,4+4,4+2,76+2,4+5,6
=52,465
PEKERJAAN DINDING
1:5
1 KAMAR MANDI Va=P X T X 2 M²
=2 X 1 X 2
=2 X 2
=4
Vb=1,5 X 1
=1,5
Vc=(1,5 – 0,225)X1
=1,275
TOTAL=4+1,5+1,275
=6,775
2 DINDING (A) V=(16,5X2)-1,5X2,2 M²
=33-1,5X2,2
=69,3
3 DINDING (B) V=1,175X2,2 M²
=2,585
4 DINDING (C) V=(3,375-1,5)X2,2 M²
=1,875X2,2
=4,125
5 DINDING (D) V=1X2,2 M²
=2,2
6 DINDING (E) V=0,5X2,2 M²
=1,1
7 DINDING (F) V=2,5X2,2 M²
=5,5
8 DINDING (G) V=3X2,2 M²
=6,6
9 DINDING (H) V=1,525X2,2 M²
=3,355
10 DINDING (I) V=P X T M²
=3X2,2
=6,6
11 DINDING (J) V=(4-0,3-2,25)X2,2 M²
=1,15X2,2
=2,57
12 DINDING (K) V= 2,75X2,2 M²
=6,05
3 PJ 2 V.P=(0,05+0,05+0,15)X2,3 X 2
=0,25 X 2,3 X 2 M²
=1,15
V.PJ=(0,05+0,05+0,15)X1,5 X 2
=0,25 X 1,5 X 2
=0,85
V= (0,05+0,05+0,15)X0.9 X 2
=0,25 X 0,9 X 2
=0,45
V TOTAL V=1,15 +0,75 + 0,85 + 0,45
=3,2
4 PJ 1 V=(0,05+0,05+0,15)X2,3 X 2 M²
=0.25 X 2,3 X 2
=1,15
V.P=(0,05+0,05+0,15)X(2,3+0,6)X 5
(2,3 + 1,5) X 5
=0,25 X 6,9 X 15,2375
=5,534
V TOTAL V=6,3+1,525+3,2+5,534 M²
=16,559
5 J2 V=(0,05+0,05+0,15)X 1,5 X 2 M²
=0,25 X 7,5 X 2
=0,75
V=(0,05+0,05+0,15)X0,9 X 3 M²
=0,25 X 0,9 X 3
=0,675
6 J1 V=(0,05+0,05+0,15)X 0,7 X 3 M²
=0,25 X 0,7 X 3
=0,525
V= (0,05+0,05+0,15)X 1,016 X 3
=0,25 X 1,016 X 3
= 0,762
P PEKERJAAN DAUN
JENDELA
1 J1 V=(0,73 X 0,463) – (0,55 X 0,283) M²
=0,33799 – 0,15565
=0,18234+(0,04 X 0,453 X 2 )
=0,18234 + 0,03704 + 0,0584
=0,27778 X 2 = 1,11112
2 J2 V=(0,093 X 1,18)-(1 X 0,7) M²
=1,0974 X 0,3
=0,32922
V=0,32922 + (0,04 X 0,94 X
2)+(0,04X1,18X2)
=0,3974+0,0752+0,0944
=0,567
3 V TOTAL DAUN PINTU V=0,75075 + 0,6202 + 10,0074 + M²
2,9288
=14,30715
4 V TOTAL DAUN JENDELA V=1,11112 + 0,567 M²
=1,67812
Q PEKERJAAN LISPLAFON
1 R.TIDUR 1 V=(2 X P)+(2 X L) M³
=(2 X 2,85)+(2 X 2,85)
=5,7 + 5,7
=11,4
R PEKERJAAN
GANTUNGAN
1 ENGSEL PINTU 2 X 6 = 18 BUAH
2 HENDEL PINTU 1X6=6 UNIT
3 ENGSEL JENDELA 4X2=8 BUAH
4 HAK JENDELA 4 UNIT
5 SLOT JENDELA 3 BUAH
3 SLOT PINTU 6 BUAH
S PEKERJAAN KACA V=1,11112 + 0,567 M²
=1,67812
1 PJ2 V=L .PENAMPANG M²
V BV=(0,7 + 0,8)X 0,2=0,3
VJ=0,3 + 0,57 =0,87
£=0,3 + 0,57 = 0,87
3 P1 VBV=0,2 X 0,75 M²
=0,15 X 4
=0,6
4 P2 VB=0,2 X 0,65 M²
=0,13
5 J1 V=0,233 X 0,5 X 2 M²
=0,1165 X 2
=0,233
6 J2 V=0,6 X 0,95 M²
=0,57
7 PJ1 VBV=(0,75 + O,6 + 1,32)X0,2 M²
=0,534
VJ1=(0,6 + 1,32)X0,469
=0,4348
VJ2=(0,16 + 1,32)X 0,44
=0,85248 X 3
=2,55744
£=3,52292
V= KACA
=0,87+0,6+0,13+0,233+0,57+3,52292
=5,92592