Anda di halaman 1dari 19

NO PEKERJAAN VOLUME SATUAN SKETSA

A PEKERJAAN TANAH
PONDASI
1 PEKERJAAN L=P X L M²
PEMBERSIHAN LAHAN =16,5X7
=115,5
2 PEMASANGAN K=2.(P+L) M¹
BOUPLANG =2.(12,5+7)
=2X19,25
=38,5
3 PEKERJAAN GALIAN V=L.PENAMPANG X P.PONDASI M³
TANAH PONDASI 1/2 L.PEN=PXL
=0.55X0,8
=0,44
P.PONDASI=40
V=L.PENXP.PONDASI
=0,44X40
=17,6
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PENAMPANG=PXL
=0,8X0,8
=0,64
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0,64X40
=25,6
JUMLAH TOTAL V=17,6+25,6 M³
=43.2
4 PEKERJAAN URUGAN V=L.PENAMPANG X P.PONDASI M³
BAWAH PONDASI 1/2 L.PENAMPANG=PXL
=5.5X0,05
=0,275
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.275X40
=11
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PEN=PXL
=0,8X0,05
=0,04
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.04X40
=1,6
JUMLAH TOTAL V=11+1,6 M³
=12,6
5 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN L.PEN=PXL
ANSTAMPING1/2 =0,43X0,15
=0,0675
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0.0675X40
=2,7
PONDASI UTUH V=L.PENAMPANG X P.PONDASI M³
L.PEN=PXL
=0,7X0,15
=0,105
P.PONDASI=40
V=L.PENAMPANG X P.PONDASI
=0,105X40
=4,2
JUMLAH TOTAL V=4,2+2,7 M³
=6,9
6 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN BATU 𝑎+𝑏
KALI 1/2
L.PEN= 𝑥𝑡
2
0,4+0,15
= 𝑥 0,6
2
=0,165
P.PONDASI=40
V=L.PENAMPANGXP.PONDASI
=0,165X40
=6.6
PONDASI UTUH V=L.PENAMPANGXP.PONDASI M³
𝑎+𝑏
= 𝑥𝑡
2
0,6+2,25
= 𝑥 0,6
2
=0,855
V=L.PEN X P.PONDASI
=0.045X40
=1,8
JUMLAH TOTAL V=6,6+1,8 M³
=8,4
7 PEKERJAAN URUGAN V=43,2-12,6-6,9-8,4 M³
TANAH KEMBALI =15,3
NO PEKERJAAN VOLUME SATUAN SKETSA
B PEKERJAAN BETON
1 PEKERJAAN V=L.PENAMPANG X P.PONDASI M³
PEMASANGAN SLOOF =0,15X0,2X40
=0,03X40
=1,2
2 PEKERJAAN KOLOM V=L.PENAMPANG X P.PONDASI M³
15/15 =0,15X0,15X40
=0,0225X40
=0,9
JUMLAH KOLOM =25
V=0,9X25
=22,5
KOLOM KI 15/30 V=L.PENAMPANG X JML KOLOM KI M³
=0.15X0,3X3
=0,135
KOLOM K2 V=L.PENAMPANG X JML KOLOM K2 M³
=0,15X0,3X1
=0,045
PEKERJAAN RING BALK V=P X L P.BANGUNAN M³
15/20 =0,15X0,2
=0,03
P.R.BANGUNAN
(40+6,475)
=46,475
V=0,03X46,475
=1,39425
V BALOK=S X S X T
=0,04X0,04X0,15
=0,024
V BALOK=S X S X T
=0,15X0,15X0,6
=0,0135
V LIMAS=L.ALAS+L.ALAS BAWAH X T
V=(0,13X0,15)+(0,4X0,4)
=0,0195+0,6
=0,6195
NO PEKERJAAN VOLUME SATUAN SKETSA
NO PEKERJAAN VOLUME SATUAN SKETSA
C PEKERJAAN PASANGAN
DINDING 1:3
1 DINDING BAGIAN WC V=P X T M²
(A) =2 X 2
=4
2 DINDING BAGIAN WC V=P X T M²
(B) =1,5 X 2
=3
3 DINDING BAGIAN WC V=P X T M²
(C) =2 X 2
=4
4 DINDING BAGIAN WC V=(P X T)-PINTU KM M²
(D) =(1,5X2)-0,75
=3 - 0,75
=2,25
5 DINDING E V=(P X T)-JENDELA KACA M²
=(2,5X0,8) - 1,325
=2 - 1,325
=0,675
6 DINDING (F) V=(PXT) – PINTU M²
=(1,45X0,8) – 0,85
=1,16 – 0,85
=0,31
7 DINDING (G) V=P X T M²
=2,475 X 0,8
=1,98
8 DINDING (H) V=(PXT) – PINTU M²
=(1 X 0,8) – 0,75
=0,8 – 0,75
=0,05
9 DINDING (I) ADA 2 V= (P X T)X2 M²
=(1X0,8)X 2
=0,8 X 2
=1,6
10 DINDING (J) V=P X T M²
=3,90X 0,8
=3,12
11 DINDING (K) V=P X T M²
=3 X 0,8
=2,4
12 DINDING (L) V=P X T M²
=2 X 0,8
=1,6
13 DINDING (M) V=P X T M²
=4,15 X 0,8
=3,32
14 DINDING (N) V=P X T M²
=6 X 0,8
=4,8
15 DINDING (O) V=P X T M²
=2,25 X 0,8
=1,8
16 DINDING (P) V=P X T M²
=3 X 0,8
=2,4
17 DINDING (Q) ADA 2 V= (P X T)X2 M²
=(2,75X0,8)X 2
=2,2 X 2
=4,4
18 DINDING (R) ADA 2 V= (P X T)X2 - PINTU M²
=(3X0,8)X 2 – 0,85
=2,4 X 2 – 0,85
=2,4 X 1,15
=2,76
19 DINDING (S) V=P X T M²
=3 X 0,8
=2,4
20 DINDING (T) V=P X T M²
=7 X 0,8
=5,6
21 JUMLAH KESELURUHAN V= 4+3+4+2,25+0,675+0,31+1,98+0,05 M²
+1,6+3,12+2,4+1,6+3,32+4,8+1,8+
2,4+4,4+2,76+2,4+5,6
=52,465
PEKERJAAN DINDING
1:5
1 KAMAR MANDI Va=P X T X 2 M²
=2 X 1 X 2
=2 X 2
=4
Vb=1,5 X 1
=1,5
Vc=(1,5 – 0,225)X1
=1,275
TOTAL=4+1,5+1,275
=6,775
2 DINDING (A) V=(16,5X2)-1,5X2,2 M²
=33-1,5X2,2
=69,3
3 DINDING (B) V=1,175X2,2 M²
=2,585
4 DINDING (C) V=(3,375-1,5)X2,2 M²
=1,875X2,2
=4,125
5 DINDING (D) V=1X2,2 M²
=2,2
6 DINDING (E) V=0,5X2,2 M²
=1,1
7 DINDING (F) V=2,5X2,2 M²
=5,5
8 DINDING (G) V=3X2,2 M²
=6,6
9 DINDING (H) V=1,525X2,2 M²
=3,355
10 DINDING (I) V=P X T M²
=3X2,2
=6,6
11 DINDING (J) V=(4-0,3-2,25)X2,2 M²
=1,15X2,2
=2,57
12 DINDING (K) V= 2,75X2,2 M²
=6,05

13 DINDING (L) V= (3-1,5)X2,2 M²


=3,3

14 DINDING (M) V=P X T M²


=7 X 2,2
=15,4
V TOTAL V=6,75+69,3+2,585+4,125+2,2+1,1 M²
+5,5+6,6+3,355+6,6+2,53+6,05+
3,3+15,4
=135,42

NO PEKERJAAN VOLUME SATUAN SKETSA


D PEKERJAAN PLESTERAN
1 DINDING 1:3 V=£ DINDING X 2 M²
=52,465 X 2
=104,93
2 DINDING 1:5 V=£ DINDING X 2 M²
=135,42 X 2
=270,84
3 ROLAG V=P X IP M²
=(1+1,4+2,5+4).(0,3+0,5)
=8,95 X 0,045
=0,40275
NO PEKERJAAN VOLUME SATUAN SKETSA
E PEKERJAAN KUSEN
1 KUSEN P1 V=L.PENAMPANG X P M³
=(0,05 X 0,15)X2,3
=0,0075 X 2,3
=0,01725
V=L.PENAMPANG X P
=(0,05X0,15)X1,05
=0,0075X1,05
=0,01725
V TOTAL=0.01725+0,006375+0,007875
=0,088875X3 KUSEN
=0,266625
2 KUSEN P2 V=L.PENAMPANG X P M³
=(0,05X0,15)X2,3
=0,0075X2,3
=0,01725
V=L.PENAMPANG X P
=(0,05X0,15)X0,75
=0,0075X0,75
=0,005625
V=L.PENEMPANG X P
=(0,05X0,15)X0,95
=0,0075X0,95
=0,007125
V TOTAL=0,01725+0,05625+0,007125
=0,080626
3 KUSEN PJ1 V=L.PENAMPANG X P M³
=(0,05XO,15)X1,3
=0,01725
V=L.PENAMPANG X P
=(0,05X0,15)X2,3X0,75
=0,0075X0,75
=0,005625
V=L.PENAMPANG X P
=(0,05X0,15)0,95
=0,007125
V TOTAL=0.01725+0,05625+0,007125
=0,080625
V=L.PENAMPANG X P
=(0,05X0,15)5,975
=0,0075X5,975
=0,448125
£ KESELULUHAN=0,080625+0,0448125
=0,1254375
4 KUSEN PJ2 V=L.PENAMPANG X P M³
=(0,05 X 0,15)X10,65
=0,079875
5 KUSEN J1 V=L.PENAMAPNG X P M³
=(0,05X0,15)X4,834
=0,0075 X 4,834=0,036255
6 KUSEN J2 V=L.PENAMPANG X P M³
=(0,05X0,15)X6,4 X2
=0,0075X6,2X2
=0,096

NO PEKERJAAN VOLUME SETUAN SKETSA


F PEKERJAAN DAUN
PINTU
1 PJ1 V=PXL M²
=0,78X2,43
=1,5717
2 PJ2 V=P X L M²
=0,78 X 2,015
=1,5717
3 P1 V=P X L M²
=0,78 X 2,015
=1,5717 X 3
=4,7151
4 P2 V=P X L M²
=0,68 X 2,015
=1,3702
5 PJ1 V=(P X L)XPANJANG M²
=(0,05 X 0,03)X5,775
=0,0015X5,775
=0,0086625
6 PJ2 V=(PXL)-V.KACA M²
=(6,83X1,18)-(0,6X0,05)
=0,9794-0,57
=0,4094
7 J1 V=(P X L)-V KACA M²
=(0,73 X 0,46)-(0,35X0,283)
=0,33799-0,15565
=0,18234
8 J2 V=(P X L)-V KACAX2 M²
=(0,93 X 1,18)-(1X0,7)X2
=1,0974-0,7X2
=0,3974X2
=0,7948
NO PEKERJAAN VOLUME SATUAN SKETSA
G PEKERJAAN ATAP
1 BALOK TARIK V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X5
=0,0096 X 5
=0,048 X 5
=0,144
2 BALOK KAKI KUDA- V=L.PENAMPANG X PANJANG BALOK M³
KUDA =(0,08X0,12)X2,8X2X3
=0,0096X2,8X2X3
=0,05376 X 3
=0,16128
3 BALOK SOKONG V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X1,1 X 2 X 3
=0,0098 X 1,1 X 2 X 3
=0,02112 X 3
=0,6336
4 BALOK TEMBOK V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X9 X 2
=0,0098 X 9 X 2
=0,0864 X 2
=0,1728
5 BALOK GORDING V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X10,4 X 2
=0,0098 X 10,4 X 2
=0,19968
6 BALOK NOK V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X8,5
=0,0098 X 8,5
=0,0816
7 BALOK MAKELAR V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X1,75 X 3
=0,0098 X 1,75 X 3
=0,0168 X 3
=0,0504
8 BALOK KUNCI V=L.PENAMPANG X PANJANG BALOK M³
=(0,08X0,12)X 1 X 3
=0,0098 X 1 X 3
=0,0288
9 KASO-KASO V=L.PENAMPANG X PANJANG BALOK M³
=(0,05X0,07)X 3,5
=0,0035 X 3,5
=0,01225
10 PAPAN RUITER V=L.PENAMPANG X PANJANG BALOK M³
=(0,02X0,2)X8,45
=0,004 X 8,45
=0,0338
11 LISPLANG V=L.PENAMPANG X PANJANG M³
=(0,02X0,2)X0,07X4
=0,004X0,07X4
=0,00028 X 4 = 0,00112
12 RENG 3,5 M³
V=COS 35° =
𝑟
=0,81915=3,5/r
R=3,5/0,81915
R=4,2727
P X L=6 X 4,2727
=25,6362
3,5 𝑋 2,5
LϪ= = 4,375
2
X2=8,75
L TOTAL= 25,6362-8,75
=16,8862

NO PEKERJAAN VOLUME SATUAN SKETSA


H PEKERJAAN PLAFON
1 RUANG TIDUR V=P X L M³
=2,84 X 2,85
=8,1225
LIS PLAFON=(2XP)+(2XL)
=(2X2,85)+(2X2,85)
=5,7+5,7
=11,4
2 KAMAR MANDI/WC V=P X L M³
=1,25X1,85
=2,4975
LIS PLAFON=(2XP)+(2XL)
=(2X1,35)+(2X1,85)
=2,7 X 3,7
=6,4
3 RUANG TIDUR 2 V=P X L M³
=2,85 X 2,6
=7,41
LIS PLAFON=(2XP)+(2XL)
=(2X2,85)+(2X2,6)
=5,7+5,2
=10,9
4 DAPUR V=P X L M³
=3,85 X 1,85
=7,1225
LIS PLAFON=3,85 + 1,85
=5,7
5 RUANG TAMU V=P X L M³
=2,35 X 2,85
=6,6975
LIS PLAFON=2,35 + 1,3 + 1,82 + 0,85
=6,32
6 RUANG KELUARGA V=P XL M³
=4,825 X 5,7
=17,8525-1
=16,8525
LIS PLAFON=3,9 + 1,1 + 2,5 + 3=11,4
7 £ RANGKA LANGIT- 8,1225+2,4975+7,41+7,1225+6,6975+ M³
LANGIT 16,8525 = 48,7025
8 £ LIS PLAFON 11,4+6,4+10,9+5,7+6,32+11 M³
= 52,12

NO PEKERJAAN VOLUME SATUAN SKETSA


I PEKERJAAN LANTAI
1 KAMAR MANDI V=URUGAN TANAH M³
=1,5 X 2 X 0,1
=0,3
V=URUGAN PASIR
=1,5 X 2 X0,03
=0,09
V=L.P.LANTAI KERAMIK
V=P X L
=1,5 X 2
=3
V=PLIN LANTAI
V=(1,5+2+1,5)+(1,5-0,75) X 2
(5+0,75) X 2
=11,5
2 RUANG TIDUR 2 V=URUGAN TANAH M³
V=2,75 X 30,15
=1,2375
V=URUGAN PASIR
=2,75 X 3 0,03
=0,2475
L.P.LANTAI KERAMIK
L=P X L
=2,75 X 3
=8,25
PLIN LANTAI KERAMIK
V=(2,75+3+2,75)+(3-0,85)X0,08
=(8,5+2,15)X0,08
=0,852

3 RUANG TIDUR 1 V=URUGAN TANAH M³


=3 X 3 X 0,15
=1,35
V=URUGAN PASIR
=3 X 3 X 0.03
=0,27
L.P.LANTAI KERAMIK
L= P X L
=3 X 3
=9
PLIN LANTAI
(3 + 3 + 3)+(3-0,85)-0,08
=(9+2,15)X0,08
=0,892
4 DAPUR V=URUGAN TANAH M³
=4 X 2 X 0,15
=1,2
V=URUGAN PASIR
=4 X 2 X 0,08
=0,64
L.P LANTAI KERAMIK
V=P X L
=4 X 2
=8
PLIN LANTAI
(2+(4-0,85)+0,85+(4-0,85)X0,08
=0,732
5 RUANG TAMU PEKERJAAN URUGAN TANAH M³
V=2,5 X 3 X 0,75
=1,125
URUGAN PASIR BAWAH LOANTAI
V=2,3 X 3 X 0,03
=0,225
LANTAI KERAMIK
V=P X L
=2,3 X 3
=7,5
PLIN LANTAI
V=2,5(1,45-0,85)+(2,5-0,5)+1
=2,5+0,6+2+1
=6,1
6 RUANG MAKAN URUGAN TANAH BAWAH LANTAI M³
V=4 X 4,9 X 0,15
=2,94
URUGAN PASIR
V=4 X 4,9 X 0,03
=0,588
LANTAI KERAMIK
V=4 X 4,9
=19.6
PLIN LANTAI
V=(4,9
NO PEKERJAAN VOLUME SATUAN SKETSA
J PEKERJAAN INSTALASI M¹
AIR
1 PEKERJAAN AIR BERSIH V=10 + 8,8 M¹
3/4῎ =18,8

2 PEKERJAAN AIR KOTOR V=11,5 + 4,5 M¹


3῎ =16

3 PEKERJAAN AIR KOTOR V=8 + 1,8 M¹


4῎ =9,8

4 KLOSET DUDUK 1 UNIT


5 BAK MANDI 1 BUAH
6 FLOOR DRAIN 1 BUAH
7 KERAN 3 BUAH
8 KITCHEN ZINK 1 UNIT
9 JET PUMP 1 UNIT

NO PEKERJAAN VOLUME SATUAN SKETSA


K PEKERJAAN ELEKTRIKAL
1 PEKERJAAN ARUS 13 TITIK
LISTRIK
2 PEKERJAAN SAKLAR 3 BUAH
TUNGGAL
3 PEKERJAAN SAKLAR 4 BUAH
GANDA
4 PEKERJAAN STOP 6 BUAH
KONTAK
5 PEKERJAAN 4 BUAH
PEMASANGAN LAMPU
PIJAR 25 WATT
6 LAMPU PIJAR 32 WATT 1 BUAH
7 LAMPU PIJAR 40 WATT 6 BUAH
8 LAMPU TAMAN 32 WTT 3 BUAH
9 PEKERJAAN 1 BUAH
PEMASANGAN STOP
KONTAK TELFON
10 PEKERJAAN 1 BUAH
PEMASANGAN ANTENA
TV

NO PEKERJAAN VOLUME SAATUAN SKETSA


L PEKERJAAN FINISHING
1 PEKERJAAN DINDING V=£ DINDING X 2 M³
1:3 =52,465 X 2
=104,93
2 PEKERJAAN DINDING V=£ DINDING X 2 M³
1:5 =135,42 X 2
=270,84
£ DIDNDING V=104,93 + 270,84 M³
=375,77 / 2 = 87,885
M PEKERJAAN PLAFON
1 RUANG TIDUR 1 V=2,85 X 2,85 M³
=8,1225
2 RUANG TIDUR 2 V=2,85 X 2.65 M³
=7,41
3 KAMAR MANDI/WC V=1,35 X 1,85 M³
=2,9475
4 DAPUR V=3,85 X 1,85 M³
=7,1225
4 RUANG TAMU V=2,35 X 2,85 M³
=6,6975
5 RUANG KELUARGA V=4,825 X 3,7 M³
=17,852 – 1 = 16,852
V TOTAL V=8,1225 + 7,4 + 2,4975 + 7,1225 + M³
6,6975 + 16,852 = 48,692
N PEKERJAAN KAYU
1 KUSEN P1 V=(0,05 + 0,05 + 0,15)X 2,3 X 2 M²
=0,25 X 2,3 X 2
=1,15
V.L=(0,05 + 0,05 + 0,15)X 0,85 X 2
=0,25 X 0,85 X 2
=0,425
V KUSEN P1 =1,15 + 0,425 X 4 = 6,3
2 KUSEN P2 V=(0,05 + 0,05 + 0,15)X 2,3 X 2 M²
=0,25 X 2,3 X 2
=1,15
V.L=(0,05 + 0,05 + 0,15)X 0,75 X 2
=0,25 X 0,75 X 2
=0,375
V KUSEN P2=1,15 + 0,375 X 1
=1,525

3 PJ 2 V.P=(0,05+0,05+0,15)X2,3 X 2
=0,25 X 2,3 X 2 M²
=1,15
V.PJ=(0,05+0,05+0,15)X1,5 X 2
=0,25 X 1,5 X 2
=0,85
V= (0,05+0,05+0,15)X0.9 X 2
=0,25 X 0,9 X 2
=0,45
V TOTAL V=1,15 +0,75 + 0,85 + 0,45
=3,2
4 PJ 1 V=(0,05+0,05+0,15)X2,3 X 2 M²
=0.25 X 2,3 X 2
=1,15
V.P=(0,05+0,05+0,15)X(2,3+0,6)X 5
(2,3 + 1,5) X 5
=0,25 X 6,9 X 15,2375
=5,534

V TOTAL V=6,3+1,525+3,2+5,534 M²
=16,559
5 J2 V=(0,05+0,05+0,15)X 1,5 X 2 M²
=0,25 X 7,5 X 2
=0,75
V=(0,05+0,05+0,15)X0,9 X 3 M²
=0,25 X 0,9 X 3
=0,675
6 J1 V=(0,05+0,05+0,15)X 0,7 X 3 M²
=0,25 X 0,7 X 3
=0,525
V= (0,05+0,05+0,15)X 1,016 X 3
=0,25 X 1,016 X 3
= 0,762

V TOTAL PENGECETAN £ PENGECETAN KAYU M²


KAYU KESELURUHAN V=0,435 + 1,525 + 3,2 +16,559 +0,675
+0.762
=23,146
5 RUANG KELUARGA V=4,825 X 3,7 M²
=17,852 – 1 = 16,852
V TOTAL V=8,1225 + 7,4 + 2,4975 + 7,1225 + M²
6,6975 + 16,852 = 48,692
O PEKERJAAN DAUN
PINTU
1 PJ 1 V=(0,05 + 0,05 + 0,03)x 5,775 M²
=0,13 x 5,775
=0,75075

2 PJ2 V=(0,83 x 1,8)-(0,6 x 0,95) M²


=0,9794 + 0,0944 + 0,0664
=0,6202

3 P1 V=(0,78 X 2,015 X 2) + (0,04X 2,015X2) M²


+(0,78 + 0,04)X3
=3,1434 + 0,1612 + 0,0312 X 3
=3,3358 X 3 =10,0074
2 P2 V=(0,68 X 2,015)X2(0,04X0,215)X2 M²
(0,68 X 0,04)
=2,7404+0,1612+0,0212
=2,9288

P PEKERJAAN DAUN
JENDELA
1 J1 V=(0,73 X 0,463) – (0,55 X 0,283) M²
=0,33799 – 0,15565
=0,18234+(0,04 X 0,453 X 2 )
=0,18234 + 0,03704 + 0,0584
=0,27778 X 2 = 1,11112
2 J2 V=(0,093 X 1,18)-(1 X 0,7) M²
=1,0974 X 0,3
=0,32922
V=0,32922 + (0,04 X 0,94 X
2)+(0,04X1,18X2)
=0,3974+0,0752+0,0944
=0,567
3 V TOTAL DAUN PINTU V=0,75075 + 0,6202 + 10,0074 + M²
2,9288
=14,30715
4 V TOTAL DAUN JENDELA V=1,11112 + 0,567 M²
=1,67812
Q PEKERJAAN LISPLAFON
1 R.TIDUR 1 V=(2 X P)+(2 X L) M³
=(2 X 2,85)+(2 X 2,85)
=5,7 + 5,7
=11,4

2 WC / KAMAR MANDI V=(2 X 1,35)+(2 X 1,85) M³


=2,7 + 3,7
=6,4

3 RUANG TIDUR 2 V=(2 X 2,85)+(2 X 2,6) M³


=5,7 + 5,2
=10,9

4 DAPUR V=3,85 + 1,85 M³


=5,7

5 RUANG TAMU V=3,9 + 1,1 + 2,5 + 3 M³


=10,5
6 VOLUME TOTAL LIS V=11,4 + 6,4 + 10,9 + 5,7 + 6,32 + 10,5 M³
PLAFON =51,22

R PEKERJAAN
GANTUNGAN
1 ENGSEL PINTU 2 X 6 = 18 BUAH
2 HENDEL PINTU 1X6=6 UNIT
3 ENGSEL JENDELA 4X2=8 BUAH
4 HAK JENDELA 4 UNIT
5 SLOT JENDELA 3 BUAH
3 SLOT PINTU 6 BUAH
S PEKERJAAN KACA V=1,11112 + 0,567 M²
=1,67812
1 PJ2 V=L .PENAMPANG M²
V BV=(0,7 + 0,8)X 0,2=0,3
VJ=0,3 + 0,57 =0,87
£=0,3 + 0,57 = 0,87
3 P1 VBV=0,2 X 0,75 M²
=0,15 X 4
=0,6

4 P2 VB=0,2 X 0,65 M²
=0,13
5 J1 V=0,233 X 0,5 X 2 M²
=0,1165 X 2
=0,233
6 J2 V=0,6 X 0,95 M²
=0,57
7 PJ1 VBV=(0,75 + O,6 + 1,32)X0,2 M²
=0,534
VJ1=(0,6 + 1,32)X0,469
=0,4348
VJ2=(0,16 + 1,32)X 0,44
=0,85248 X 3
=2,55744
£=3,52292
V= KACA
=0,87+0,6+0,13+0,233+0,57+3,52292
=5,92592