On
“CONSTRUCTION OF UNDERGROUND STATION
AT DHANSA, NAJAFGARH”
SESSION 2018-2019
Undertaken at
“DMRC – STEC SUCGIN - JV”
Submitted in partial fulfillment of the requirement
for the award of the degree
BACHELOR OF TECHNOLOGY
in
Civil Engineering
I take this opportunity to express a deep sense of gratitude to Mr. Sanjay Singh and Mr.
Anubhav Triphati, JE Dhansa, DMRC, for his cordial support, valuable information and
guidance, which helped me in completing this task through various stages.
I am also obliged to staff members of DMRC STEC SUCGIN-JV, for the valuable
information provided by them in their respective fields. I am grateful for their cooperation
during the period of my Industrial Training.
I would like to express my sincere gratitude to my Prof. Seema Khan for giving me the
opportunity to complete my industrial training. It would never be possible for us to take this
project to this level without his innovative ideas and his relent less support and encouragement.
SHADAB AHMED
(1603000082)
(CE IV SEM)
Declaration
I hereby declare that the Industrial training report entitled (“CONSTRUCTION
OF UNDERGROUND STATION AT DHANSA, NAJAFGARH”) is an
authentic record of my own work as requirement of Industrial training during
the period of 11 June, 2018 to 06 July, 2018 for the award of degree of B.Tech
(Civil Engineering), INDERPRASTHA ENGINEERING COLLEGE, under
the of Junior Engineer.
Signature
(Shadab Ahmed)
Date: 31-07-2019 (1603000082)
Index
List Of Table ………………………………………………………………………………iii
List Of Figure ……………………………………...………………………………………iv
Chapter 1 Introduction
1.1 General………………………………………………………………………………….1
1.1.2 Project Details…………………………….…………………………….……….2
1.1.3 Site Location……...……………………………….………………….…...….…3
1.1.4 Safety Induction…...………………...….…………………………………….…4
1.2 General Construction Activity………………………………………………….……...4
1.2.1 Precondition Building Survey……………………………………………..…….5
1.2.2 Geotechnical Investigation………………………………………………..……..6
1.2.3 Utility Diversion…………………………………………………………...…….6
Chapter 2 Station
2.1 Guide Wall……………………………………………………………………….…...…8
2.2 Diaphragm Wall………………………………………………………..………………..9
2.2.1 Diaphragm Wall Excavation………………………………….………………..10
2.2.2 Cage Lifting And Placing………………………………………………………12
2.2.3 Placing Of Concrete……………………………………………………………13
2.2.4 Poly Mud Slurry………………………………………………….…………….14
2.3 Plunge Column……………………………………………………….……..………….16
Chapter 5 Conclusion…………………...……………………………………..…..……….52
Chapter 6 Reference………………………………………………………….……….……53
List Of Table
Client DMRC
Contractor STEC-SUCGIN JV
Figure 2 Metro
Project Scope-
1 - Underground Station Tunnel Cut and Cover Tunnel.
Dimension: 200.055 X 33.737 m
Depth : 19.7 m
Construction Methodology: Top Down Method
Location: Dhansa Stand
Exit/Entry:03 No’s
1.1.3 Site Location
In safety induction safety engineer told us about the use of safety equipment and PPE(Personal
Protective Equipment) at construction site.
Figure 5 PPE(Personal Protective Equipment) Figure 6 Colour Code For Lifting Tools
1.2 General Construction Activity
Complete Summary of Steps Involved
A. Survey work
a) Preconditioning Building Survey
b) Geotechnical Investigation
c) Topography and Tunnelling Survey
d) Utility Diversions
B. Construction Work
a) Guide Wall
b) Diaphragm Wall
c) Permanent Columns
d) Top Slab
e) Second Slab Underground Station
f) Third Slab
g) Base Slab
h) Staircase
i) Lifts and Escalators
j) Operational Rooms
k) TBM Launching Shaft
l) Boring Tunnel Underground Tunnel Construction
m) Retrieval Shaft
ZONE OF INFLUENCE
The pre-construction and post construction condition survey will be carried out for structure and
building located within the zone of influence of underground metro tunnel and station.
The purposes of a Geotechnical Investigation are to investigate the soil and geologic conditions
of a property and to provide recommendations and design criteria for construction. The scope of
a Geotechnical Investigation includes review of available literature; conducting on-site
exploration, mapping/logging and sampling; and laboratory testing of samples obtained in the
field. The collected data is analyzed and geotechnical criteria for foundations, retaining walls,
site grading and site drainage are developed. This criterion chiefly consists of the load bearing
capacities and anticipated lateral forces from the onsite soil and rock. The culmination of the
investigation is a report summarizing the field and lab findings; conclusions regarding the
geotechnical impacts of the site; and recommendations for the most geotechnical suitable
construction.
In other words, the Geotechnical Consultant will define the anticipated effects of the earth on
man-made features at the site as well as the impacts the development could impose on the land.
The Geotechnical Consultant along with the client, builder, architect, civil engineer and
structural engineer endeavor to implement the most efficient and cost-effective construction
methods.
The Geotechnical Investigation typically costs a few percent of the total project costs but can
reduce the risk of costly problems during construction and in the future.
Chapter 2
STATION- I
2.1 Guide Wall
Two parallel concrete beams constructed along the side of the wall as a guide to the clamshell.
Guide wall trench excavation will be excavated by manual/JCB excavation for the guide wall of
1.5m depth of existing ground level.
Guide wall will be constructed by inverted L shaped RCC walls forming a support to the earth
and prevents it from collapsing when the boring of the diaphragm wall.
The purpose of guide wall is
To provide a permanent alignment for the grab.
To provide edge protection to the diaphragm wall and to prevent the collapsing of soil
during excavation.
To act as a platform to hang the reinforcement cage and maintain the coupler levels.
Steps involved in construction of guide wall are:
a) Before excavation a valid “Permit for work” must be issued.
b) The trench will be excavated as per set out and indicated alignment.
c) Manual excavation for guide wall trench up to 1.5 m depth from the existing ground
level.
d) Fixing of reinforcement will be done as per the approved drawings.
e) The minimum cover to reinforcement shall be done as per the reinforced drawings.
f) The clear horizontal distance of guide wall i.e diaphragm wall width plus 50mm will be
maintained.
g) Placing of M20 grade of concrete with proper compaction.
h) De-shuttering will be done after concrete gets set and the area will be backfilled for
safety purpose.
i) After concrete gets hardened curing shall be done with clean water.
j) The trench face of the guide wall on the side of the trench nearest to the subsequent main
excavation shall be vertical to within 1:200.
Figure 8 Guide Wall
Najafgarh –Dhansa Bus Stand Metro Extension is estimated to serve the travel needs of
an additional 10,000 passengers per day catering to the needs of people of Nangloi,
Dhansa, Bahadurgarh and the adjoining areas.
As per 2016 estimates, 3.61 lakh vehicle trips are generated at Najafgarh. Since the area
between Najafgarh and Dhansa is densely populated with substantial built up areas,
extension to Dhansa Bus Stand has been made Under Ground.