HOJA DE METRADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

01.02 SISTEMA DE ALCANTARILLADO SANITARIO


01.02.01 RED DE ALCANTARIILADO
01.02.01.01 TUBERIAS Y ACCESORIOS
01.02.01.01.01 TRABAJOS PRELIMINARES
01.02.01.01.01.01 TRAZO Y REPLANTEO INICIAL DE OBRA M 416.10
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 07 a BP 08 20.30 1.00 20.30
BP 01 a BP 09 11.00 1.00 11.00
BP 09 a BP 10 31.50 1.00 31.50
BP 10 a BP 11 29.60 1.00 29.60
BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 11.80 1.00 11.80
BP 12 a BP 13 19.00 1.00 19.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00
BP 16 a C. REJAS 14.00 1.00 14.00
C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00
C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00
C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

01.02.01.01.01.02 TRAZO Y REPLANTEO FINAL DE OBRA M 416.10

BP 01 a BP 02 16.50 1.00 16.50

BP 02 a BP 03 19.00 1.00 19.00


BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 07 a BP 08 20.30 1.00 20.30
BP 01 a BP 09 11.00 1.00 11.00
BP 09 a BP 10 31.50 1.00 31.50
BP 10 a BP 11 29.60 1.00 29.60
BP 08 a BP 11 20.50 1.00 20.50

BP 11 a BP 12 11.80 1.00 11.80

BP 12 a BP 13 19.00 1.00 19.00


BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00

BP 16 a PTAR 14.00 1.00 14.00

C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00


C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00
C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

01.02.01.01.02 EXCAVACION MANUAL DE ZANJA


EXCAVACION MANUAL DE ZANJAS PARA TUBERIA H=1.20m EN TERRENO
01.02.01.01.02.01 M 180.90
SEMIROCOSO
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 01 a BP 09 11.00 1.00 11.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 14 a BP 15 13.00 1.00 13.00
BP 15 a BP 16 14.00 1.00 14.00

EXCAVACION MANUAL DE ZANJAS PARA TUBERIA H=1.20 a 1.50 m EN


01.02.01.01.02.02 M 55.80
TERRENO SEMIROCOSO
BP 08 a BP 09 20.30 1.00 20.30
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00

EXCAVACION MANUAL DE ZANJAS PARA TUBERIA H=1.51 a 2.50 m EN


01.02.01.01.02.03 M 91.50
TERRENO SEMIROCOSO
BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 41.40 1.00 41.40
BP 10 a BP 11 29.60 1.00 29.60

01.02.01.01.03 REFINES Y NIVELES


01.02.01.01.03.01 REFINE, NIVEL Y FONDOS PARA TUBERIAS M 416.10
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

BP 06 a BP 07 32.00 1.00 32.00


BP 07 a BP 08 20.30 1.00 20.30
BP 01 a BP 09 11.00 1.00 11.00
BP 09 a BP 10 31.50 1.00 31.50
BP 10 a BP 11 29.60 1.00 29.60
BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 11.80 1.00 11.80
BP 12 a BP 13 19.00 1.00 19.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00
BP 16 a PTAR 14.00 1.00 14.00
C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00
C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00
C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00

01.02.01.01.04 CAMAS DE APOYO


01.02.01.01.04.01 PREPARAC. CAMAS DE APOYO P/TUB. E=10CM (ARENA) M 416.10
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 07 a BP 08 20.30 1.00 20.30
BP 01 a BP 09 11.00 1.00 11.00
BP 09 a BP 10 31.50 1.00 31.50
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

BP 10 a BP 11 29.60 1.00 29.60


BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 11.80 1.00 11.80
BP 12 a BP 13 19.00 1.00 19.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00
BP 16 a PTAR 14.00 1.00 14.00
C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00
C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00
C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00

01.02.01.01.05 RELLENOS DE ZANJA

01.02.01.01.05.01 PRIMER RELLENO H=0.30M MATERIAL DE PRESTAMO SELECCIONADO M 416.10

BP 01 a BP 02 16.50 1.00 16.50


BP 02 a BP 03 19.00 1.00 19.00
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 07 a BP 08 20.30 1.00 20.30
BP 01 a BP 09 11.00 1.00 11.00
BP 09 a BP 10 31.50 1.00 31.50
BP 10 a BP 11 29.60 1.00 29.60
BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 11.80 1.00 11.80
BP 12 a BP 13 19.00 1.00 19.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

BP 13 a BP 14 31.50 1.00 31.50


BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00
BP 16 a PTAR 14.00 1.00 14.00
C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00
C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00
C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00

01.02.01.01.05.02 SEGUNDO RELLENO MATERIAL PROPIO H<1.20 m. M 180.90


BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 01 a BP 09 11.00 1.00 11.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00

BP 14 a BP 15 13.00 1.00 13.00

BP 15 a BP 16 14.00 1.00 14.00

01.02.01.01.05.03 SEGUNDO RELLENO MATERIAL PROPIO H=1.20-1.50 m. M 55.80


BP 08 a BP 09 20.30 1.00 20.30
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00

01.02.01.01.05.04 SEGUNDO RELLENO MATERIAL PROPIO H=1.50-2.00 m. M 91.50


BP 08 a BP 11 20.50 1.00 20.50
BP 11 a BP 12 41.40 1.00 41.40
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

BP 10 a BP 11 29.60 1.00 29.60

01.02.01.01.05.07 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA M3 129.82


0.60 416.10 0.40 1.00 99.86

01.02.01.01.06 SUMINISTRO E INSTALACION DE TUBERIAS


SUMINISTRO E INSTALACION DE TUBERIA PVC NORMA ISO 4435
01.02.01.01.06.01 M 143.90
DN=110mm S-20
BP 01 a BP 02 16.50 1.00 16.50
BP 02 a BP 03 19.00 1.00 19.00
BP 03 a BP 04 41.40 1.00 41.40
BP 04 a BP 05 13.00 1.00 13.00
BP 04 a BP 06 11.00 1.00 11.00
BP 06 a BP 07 32.00 1.00 32.00
BP 01 a BP 09 11.00 1.00 11.00

SUMINISTRO E INSTALACION DE TUBERIA PVC NORMA ISO 4435


01.02.01.01.06.02 M 272.20
DN=160mm S-20.
BP 07 a BP 08 20.30 1.00 20.30
BP 08 a BP 11 20.50 1.00 20.50
BP 09 a BP 10 31.50 1.00 31.50
BP 10 a BP 11 29.60 1.00 29.60
BP 11 a BP 12 11.80 1.00 11.80
BP 12 a BP 13 19.00 1.00 19.00
BP 13 a BP 14 31.50 1.00 31.50
BP 14 a BP 15 14.00 1.00 14.00
BP 15 a BP 16 13.00 1.00 13.00
BP 16 a PTAR 14.00 1.00 14.00
C. REJAS a C. DISTRIBUCION 1 2.00 1.00 2.00
C. DISTRIBUCION 1 a T. SEPTICO 1 5.00 1.00 5.00
C. DISTRIBUCION 1 a T. SEPTICO 2 5.00 1.00 5.00
T. SEPTICO 1 a C. DISTRIBUCION 2 5.00 1.00 5.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

T. SEPTICO 1 a C. DISTRIBUCION 3 5.00 1.00 5.00


C. DISTRIBUCION 2 a P. PERCOLACION 1 10.00 1.00 10.00
C. DISTRIBUCION 2 a P. PERCOLACION 2 25.00 1.00 25.00
C. DISTRIBUCION 3 a P. PERCOLACION 3 10.00 1.00 10.00

01.02.01.01.06.03 ALINEAM. Y AJUST DE TUB. PVC ISO 4435 M 416.10


416.10 1.00 416.10

01.02.01.01.07 PRUEBA HIDRAULICA


01.02.01.01.07.01 PRUEBA HIDRAULICA+DESINFECCION TUB. PVC M 416.10
416.10 1.00 416.10

01.02.01.02 BUZONES Y BUZONETAS


01.02.01.02.01 MOVIMIENTO DE TIERRAS
01.02.01.02.01.01 EXCAV. EN T/SEMIROCOSO P/BUZON DE H=1.20 m. UND 11.00
BP 01 1.00 1.00
BP 03 1.00 1.00
BP 04 1.00 1.00
BP 05 1.00 1.00
BP 06 1.00 1.00
BP 07 1.00 1.00
BP 09 1.00 1.00
BP 13 1.00 1.00
BP 14 1.00 1.00
BP 15 1.00 1.00
BP 16 1.00 1.00

01.02.01.02.01.02 EXCAV. EN T/SEMIROCOSO P/BUZON DE H=1.21 A 1.50 m. UND 3.00


BP 02 1.00 1.00
BP 09 1.00 1.00
BP 12 1.00 1.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

01.02.01.02.01.03 EXCAV. EN TSEMIROCOSO P/BUZON DE H=1.51-2.50M UND 2.00


BP 10 1.00 1.00
BP 11 1.00 1.00

01.02.01.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA UND 25.96


Buzon h=1.20m 11.00 14.93 14.93
Buzon h=1.21m a 1.50 3.00 5.94 5.94
Buzon h=1.51m a 2.00 2.00 5.09 5.09

01.02.01.02.02 CONSTRUCCION DE BUZONES


01.02.01.02.02.01 CONST. DE BUZON ESTANDAR TIPO I F´C=210KG/CM2, H=1.20M UND 11.00
BP 01 1.00 1.00
BP 03 1.00 1.00
BP 04 1.00 1.00
BP 05 1.00 1.00
BP 06 1.00 1.00
BP 07 1.00 1.00
BP 09 1.00 1.00
BP 13 1.00 1.00
BP 14 1.00 1.00

BP 15 1.00 1.00

BP 16 1.00 1.00

01.02.01.02.02.02 CONST. DE BUZON ESTANDAR TIPO I F´C=210KG/CM2, H=1.20 A 1.50 M UND 3.00
BP 02 1.00 1.00
BP 09 1.00 1.00
BP 12 1.00 1.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL DISTRITO DE SAN PEDRO DE CHAULAN -
HUÁNUCO - HUANUCO" - ADICIONAL

FECHA :OCTUBRE 2018


LOCALIDAD : COZO TINGO

MEDIDAS SUB-TOTAL
Nº DESCRIPCION UND CANT TOTAL
ANCHO LARGO ALTO LONG. VOLUM AREA UNIDAD KG.

01.02.01.02.02.03 CONST. DE BUZON ESTANDAR TIPO I F´C=210KG/CM2, H=1.51M - 2.00M UND 2.00
BP 10 1.00 1.00
BP 11 1.00 1.00

01.02.01.02.03 VARIOS
01.02.01.02.03.01 PRUEBA DE CALIDAD DEL CONCRETO (COMPRESION) UND 16.00
Prueba a la compresion 16.00 16.00

01.02.01.02.03.02 DISEÑO DE MEZCLA DE CONCRETO UND 1.00


Diseño de Mezcla 1.00 1.00

01.02.01.02.03.03 PRUEBA DE DENSIDAD DE CAMPO UND 6.00


Diseño de Mezcla 6.00 6.00

01.02.01.03 INSTALACIONES DOMICILIARIAS DE DESAGUE


01.02.01.03.01 CONEXIONES DOMICILIARIAS
01.02.01.03.01.01 EXCAVACION DE CONEX. DOMICILIARIAS M 110.00
Excavacion manual de zanja 5.00 22.00 110.00

SUMINISTRO E INSTALACION DE TUBERIA PVC NORMA ISO 4435


01.02.01.03.01.02 M 110.00
DN=110mm S-25
5.00 22.00 110.00

01.02.01.03.01.03 CONEX. DOMICILIARIA DN=110mm,S-25 UND 22.00


22.00 22.00 22.00

01.02.01.03.01.04 RELLENO Y COMP.MAT.PROPIO EN ZANJAS M3 968.00


0.40 110.00 1.00 22.00 968.00 968.00

01.02.01.03.01.05 ELIMINACION DE MATERIAL EXCEDENTE EN CARRETILLA M3 8.80


0.40 110.00 0.20 1.00 8.80 8.80

01.02.01.03.01.06 PRUEBA HIDRAULICA+DESINFECCION TUB. PVC M 110.00


5.00 22.00 110.00
HOJA DE METRADO
PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCIÓN DEL SISTEMA DE ALCANTARILLADO DE 07 LOCALIDADES DEL
DISTRITO DE SAN PEDRO DE CHAULAN - HUÁNUCO - HUANUCO" - ADICIONAL

SUBPRESUPUESTO: SISTEMA DE AGUA POTABLE


FECHA :OCTUBRE 2018

LOCALIDAD : COZO TINGO


ELEMENTO LONGITUD TOTAL (M)
PARCIAL
CODIGO ELEMENTO 6mm 1/4 8mm 3/8 1/2 5/8 3/4 1 TOTAL Kg.
ø (") Cant Long. Kg.
0.222 0.25 0.4 0.56 0.994 1.552 2.24 3.97

#REF! CAPTACION (01 UND)


#REF! OBRAS DE CONCRETO ARMADO
#REF! ACERO FY= 4200 KG/CM2 #VALUE!
Captacion
Laterales 3/8 14 3.20 44.80 #VALUE!
3/8 28 1.50 42.00 #VALUE!

02.01.02 RESERVORIO 6M3 (01 UND)


02.01.02.04 OBRAS DE CONCRETO ARMADO

02.01.02.04.03 LOSA MACIZA 101.64


02.01.02.04.03 ACERO fy=4200 kg/cm2 GRADO 60
LOSA RESERVORIO
Acero Longitudinal 3/8 15 3.2 48.00 26.88
3/8 15 3.1 46.50 26.04
Acero Transversal 3/8 15 2.9 43.50 24.36
3/8 15 2.9 43.50 24.36

02.01.02.04.05 CASETA DE CLORACION


02.01.02.04.05 ACERO fy=4200 kg/cm2 GRADO 60 42.77
LOSA
Acero Longitudinal 3/8 6 1.21 7.26 4.07
estribos 3/8 7 1.1 7.70 4.31

MUROS
Acero Longitudinal 3/8 9 3.2 28.80 16.13
Acero Transversal 3/8 14 2.33 32.62 18.27

#VALUE!