PLANILLA DE METRADOS - 1 ALTERNATIVA

PROYECTO CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
ENTIDAD: GOBIERNO REGIONAL DE AREQUIPA
FECHA: FEBRERO DEL 2016

Item Descripción Und. cantidad Largo Ancho Alto Parcial Total

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 X 3.60 M. UND 1 1.00 1.00

01.02 CASETA DE ALMACEN, GUARDIANIA Y OFICINA DEL RESIDENTE M2 1 6.00 10.00 60.00 60.00

01.03 CERCO PROVISIONAL CON MALLA ARPILLERA M 1 170.00 170.00 170.00

01.04 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA GLB 1 1.00 1.00

02 SEGURIDAD, SALUD Y MEDIO AMBIENTE


02.01 PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1 1.00 1.00

02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 80 80.00 80.00

02.03 EQUIPOS DE PROTECCION COLECTIVO glb 1 1.00 1.00

02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1 1.00 1.00

02.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1 1.00 1.00

02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURA glb 1 1.00 1.00

03 MITIGACION Y CONTROL AMBIENTAL


03.01 CAPACITACION PERMANENTE AL PERSONAL SOBRE SALUD AMBIENTAL mes 7 7.00 7.00

03.02 REVISION PERIODICA DEL BUEN FUNCIONAMIENTO DE LOS EQUIPOS mes 7 7.00 7.00

03.03 CONTROL DE PROPAGACION DE PARTICULAS VOLATILES m2 area= 1,106.37 1106.37 1,106.37

03.04 READECUACION AMBIENTAL DE CASETA DE GUARDIANIA,ALMACEN Y OFICINA DEL m2 area= 60.00 60.00 60.00

03.05 ACONDICIONAMIENTO DE DESECHOS Y EXCEDENTES m2 area= 1,106.37 1106.37 1,106.37

04 OBRAS PRELIMINARES
04.01 LIMPIEZA DEL TERRENO EN FORMA MANUAL M2 1,106.37
local 1 area= 1,106.37 1106.37

04.02 TRAZO NIVELES Y REPLANTEO PRELIMINAR M2 1,106.37


local 1 area= 1,106.37 1106.37

04.03 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 90.42


0+050 1 10.00 area= 0.89 8.90
0+060 1 10.00 area= 1.43 14.30
0+070 1 10.00 area= 1.63 16.30
0+080 1 10.00 area= 1.88 18.80
0+090 1 5.50 area= 5.84 32.12

04.04 RELLENO CON MATERIAL PROPIO CON MAQUIANRIA m3 82.60


0+050 1 10.00 area= 2.80 28.00
0+060 1 10.00 area= 2.43 24.30
0+070 1 10.00 area= 1.69 16.90
0+080 1 10.00 area= 1.34 13.40
0+090 1 5.50 area= 0.00 0.00

04.05 COMFORMACION Y COMPACTACION DE SUBRASANTE m2 area= 1,106.37 1106.37 1,106.37

04.06 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO D=5KM M3 1.3 7.82 10.17 10.17
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total

05 SALON DE USOS MULTIPLES


05.01 MOVIMIENTO DE TIERRAS
05.01.01 EXCAVACION PARA CIMIENTOS HASTA 1.00M. TERRENO NORMAL M3 47.73
EJE A, G' 2 11.05 0.50 1.20 13.26
EJE A', F' 2 9.18 0.50 1.20 11.01
EJE B', E' 2 1.80 0.50 1.20 2.16
EJE 11 1 11.05 0.50 1.20 6.63
EJE 11' 1 14.05 0.50 1.20 8.43
EJE 12 2 0.50 0.50 1.20 0.60
EJE 12' 2 1.48 0.50 1.00 1.48
EJE 13 2 0.25 0.50 1.00 0.25
EJE 14 1 5.73 0.50 1.00 2.86
EJE 15 2 1.05 0.50 1.00 1.05

05.01.02 EXCAVACION PARA ZAPATAS DE 1.40M. A 1.70M. DE PROFUNDIDAD M3 101.27


Z-1 4 1.70 1.70 2.00 23.12
Z-2 11 1.00 1.00 2.00 22.00
Z-3 4 2.60 1.40 2.00 29.12
Z-1' 2 2.65 2.55 2.00 27.03

05.01.03 REFINE Y NIVELACION DE ZANJA M2 91.35


EJE A, G' 2 11.05 0.50 11.05
EJE A', F' 2 9.18 0.50 9.18
EJE B', E' 2 1.80 0.50 1.80
EJE 11 1 11.05 0.50 5.53
EJE 11' 1 14.05 0.50 7.03
EJE 12 2 0.50 0.50 0.50
EJE 12' 2 1.48 0.50 1.48
EJE 13 2 0.25 0.50 0.25
EJE 14 1 5.73 0.50 2.86
EJE 15 2 1.05 0.50 1.05

Z-1 4 1.70 1.70 11.56


Z-2 11 1.00 1.00 11.00
Z-3 4 2.60 1.40 14.56
Z-1' 2 2.65 2.55 13.52

05.01.04 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO M3 69.79


EJE A, G' 2 11.05 0.30 0.20 1.33
EJE A', F' 2 9.18 0.45 0.85 7.02
EJE B', E' 2 1.80 0.45 0.85 1.38
EJE 11 1 11.05 0.45 0.85 4.23
EJE 11' 1 14.05 0.45 0.85 5.37
EJE 12 2 0.50 0.45 0.85 0.38
EJE 12' 2 1.48 0.30 0.20 0.18
EJE 13 2 0.25 0.30 0.20 0.03
EJE 14 1 5.73 0.30 0.20 0.34
EJE 15 2 1.05 0.30 0.20 0.13

Z-1 4 1.70 1.70 1.10 12.72


-4 0.60 0.35 1.10 -0.92
Z-2 11 1.00 1.00 1.10 12.10
-11 0.25 0.25 1.10 -0.76
Z-3 4 2.60 1.40 1.10 16.02
-4 1.10 0.35 1.10 -1.69
Z-1' 2 2.65 2.55 1.10 14.87
-2 5.30 0.25 1.10 -2.92

05.01.05 NIVELACION Y COMPACTADO PARA PISOS M2 279.16


SUM 1 area= 198.47 198.47
escenario 1 area= 20.76 20.76
camerino y grupo electrogeno 2 3.85 1.90 14.63
salida de emergencia 2 2.30 1.50 6.90
ss.hh. Varones y damas 2 9.60 2.00 38.40

05.01.06 TERRAPLEN PARA PISOS E=0.10M. M2 279.16


SUM 1 area= 198.47 198.47
escenario 1 area= 20.76 20.76
camerino y grupo electrogeno 2 3.85 1.90 14.63
salida de emergencia 2 2.30 1.50 6.90
ss.hh. Varones y damas 2 9.60 2.00 38.40

Coef. Volumen
05.01.07 ACARREO DE MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO DE 30M M3 1.3 79.21 102.97 102.97

05.01.08 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO M3 1.3 79.21 102.97 102.97

05.02 OBRAS DE CONCRETO SIMPLE


05.02.01 CONCRETO C:H (1:10) + 30% P.G. P/CIMIENTO CORRIDO M3 23.78
EJE A, G' 2 12.18 0.50 0.80 9.74
EJE A', F' 2 10.53 0.50 0.10 1.05
EJE B', E' 2 2.38 0.50 0.10 0.24
EJE 11 1 12.43 0.50 0.10 0.62
EJE 11' 1 15.43 0.50 0.10 0.77
EJE 12 2 1.88 0.50 0.10 0.19
EJE 12' 2 1.48 0.50 0.80 1.18
EJE 13 2 3.18 0.50 0.80 2.54
EJE 14 1 5.73 0.50 0.80 2.29
EJE 15 2 6.45 0.50 0.80 5.16

05.02.02 CONCRETO C:H (1:8) + 25% P.M. PARA SOBRECIMIENTOS M3 4.97


EJE A, G' 2 12.18 0.25 0.65 3.96
EJE B', E' 2 -4.28 0.25 0.50 -1.07
EJE 12' 2 -0.83 0.15 0.50 -0.12
EJE 13 2 3.18 0.25 0.50 0.79
EJE 14 1 5.73 0.25 0.50 0.72
EJE 15 2 4.65 0.15 0.50 0.70

05.02.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS M2 42.83


EJE A, G' 4 12.18 0.65 31.66
EJE B', E' 4 -4.28 0.50 -8.55
EJE 12' 4 -0.83 0.50 -1.65
EJE 13 4 3.18 0.50 6.35
EJE 14 2 5.73 0.50 5.73
EJE 15 4 4.65 0.50 9.30

05.02.04 FALSO PISO DE E=4" CONCRETO 1:10 (C:H) M2 279.16


SUM 1 area= 198.47 198.47
escenario 1 area= 20.76 20.76
camerino y grupo electrogeno 2 3.85 1.90 14.63
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
salida de emergencia 2 2.30 1.50 6.90
ss.hh. Varones y damas 2 9.60 2.00 38.40
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.02.05 SOLADO DE E=4" EN ZAPATAS CON MEZCLA 1:12 CEMENTO HORMIGON M2 50.64
Z-1 4 1.70 1.70 11.56
Z-2 11 1.00 1.00 11.00
Z-3 4 2.60 1.40 14.56
Z-1' 2 2.65 2.55 13.52

05.02.06 GRADERIA DE CEMENTO PULIDO F'C=175 KG/CM2 M3 1.00


graderia 12 1.00 0.25 0.10 0.30
12 1.00 0.15 0.10 0.18
2 1.40 1.00 0.10 0.28
cimiento 2 1.00 0.30 0.40 0.24

05.02.07 ENCOFRADO Y DESENCOFRADO NORMAL EN GRADERIA M2 1.80


graderia 12 1.00 0.15 1.80

05.03 OBRAS DE CONCRETO ARMADO


05.03.01 ZAPATAS
05.03.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 M3 66.91
Z-1 4 1.70 1.70 0.50 5.78
Z-2 11 1.00 1.00 0.50 5.50
Z-3 4 2.60 1.40 1.50 21.84
Z-1' 2 2.65 2.55 2.50 33.79

05.03.01.02 ACERO GRADO 60 EN ZAPATAS KG VER DETALLE DE PLANILLA DE ACERO 718.52 718.52

05.03.02 PLACAS
05.03.02.01 PLACAS: CONCRETO F'C=210 KG/CM2 M3 27.91
PRIMER Y SEGUNDO PISO
P-1 2 0.60 0.35 7.30 3.07
2 2.05 0.25 7.30 7.48
P-1 2 0.60 0.35 7.30 3.07
2 1.50 0.25 7.30 5.48
P-2 2 2.30 0.25 7.30 8.40

05.03.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN PLACAS M2 233.60


PRIMER Y SEGUNDO PISO
P-1 2 6.00 7.30 87.60
P-1 2 4.90 7.30 71.54
P-2 2 5.10 7.30 74.46

05.03.02.03 ACERO GRADO 60 EN PLACAS KG VER DETALLE DE PLANILLA DE ACERO 5270.17 5,270.17

05.03.03 COLUMNAS
05.03.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 17.32
PRIMER Y SEGUNDO NIVEL 17.32
C-1 6 0.60 0.35 7.30 9.20
C-2 2 0.50 0.35 7.30 2.56
C-3 8 0.25 0.25 7.30 3.65
C-4 7 0.25 0.15 7.30 1.92

05.03.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN COLUMNAS M2 191.99


PRIMER Y SEGUNDO NIVEL 191.99
C-1 6 1.90 7.30 83.22
C-2 2 1.70 7.30 24.82
C-3 8 1.00 7.30 58.40
C-4 7 0.50 7.30 25.55

05.03.03.03 ACERO GRADO 60 EN COLUMNAS KG VER DETALLE DE PLANILLA DE ACERO 2390.80 2,390.80

05.03.04 COLUMNAS Y VIGAS DE AMARRE


05.03.04.01 COLUMNAS Y VIGAS DE AMARRE: CONCRETO F'C=175 KG/CM2 M3 6.94
PRIMER PISO 3.61
C-A 0 0.20 0.15 1.00 0.00
C-A 6 0.20 0.15 2.00 0.36
C-A 23 0.20 0.15 3.20 2.21

V-A
EJE A, G' 2 6.45 0.15 0.10 0.19
EJE A', F' 2 11.15 0.15 0.10 0.33
EJE 11 1 11.60 0.15 0.10 0.17
EJE 12' 1 4.60 0.15 0.10 0.07
EJE 13 4 0.90 0.15 0.10 0.05
EJE 14 1 10.75 0.15 0.10 0.16
EJE 15 1 3.50 0.15 0.10 0.05
SEGUNDO PISO 3.33
C-A 0 0.20 0.15 1.00 0.00
C-A 6 0.20 0.15 2.00 0.36
C-A 23 0.20 0.15 2.80 1.93

V-A
EJE A, G' 2 6.45 0.15 0.10 0.19
EJE A', F' 2 11.15 0.15 0.10 0.33
EJE 11 1 11.60 0.15 0.10 0.17
EJE 12' 1 4.60 0.15 0.10 0.07
EJE 13 4 0.90 0.15 0.10 0.05
EJE 14 1 10.75 0.15 0.10 0.16
EJE 15 1 3.50 0.15 0.10 0.05

05.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS DE AMARRE M2 92.50


PRIMER PISO 48.09
C-A 0 0.40 1.00 0.00
C-A 6 0.40 2.00 4.80
C-A 23 0.40 3.20 29.44

V-A
EJE A, G' 2 6.45 0.20 2.58
EJE A', F' 2 11.15 0.20 4.46
EJE 11 1 11.60 0.20 2.32
EJE 12' 1 4.60 0.20 0.92
EJE 13 4 0.90 0.20 0.72
EJE 14 1 10.75 0.20 2.15
EJE 15 1 3.50 0.20 0.70
SEGUNDO PISO 44.41
C-A 0 0.40 1.00 0.00
C-A 6 0.40 2.00 4.80
C-A 23 0.40 2.80 25.76

V-A
EJE A, G' 2 6.45 0.20 2.58
EJE A', F' 2 11.15 0.20 4.46
EJE 11 1 11.60 0.20 2.32
EJE 12' 1 4.60 0.20 0.92
EJE 13 4 0.90 0.20 0.72
EJE 14 1 10.75 0.20 2.15
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
EJE 15 1 3.50 0.20 0.70
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.03.04.03 ACERO GRADO 60 EN COLUMNAS Y VIGAS DE AMARRE KG VER DETALLE DE PLANILLA DE ACERO 897.09 897.09

05.03.05 VIGAS
05.03.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2 M3 61.11
PRIMER PISO 19.66
EJE A VP-102 1 14.75 0.25 0.50 1.84
EJE A' VP-102 1 14.75 0.25 0.50 1.84
EJE F' VP-102 1 14.75 0.25 0.50 1.84
EJE G' VP-102 1 14.75 0.25 0.50 1.84
EJE 11 VP-102 1 3.40 0.25 0.50 0.43
VP-101 1 14.85 0.35 1.10 5.72
EJE 15 VP-102 1 3.40 0.25 0.50 0.43
VP-101 1 14.85 0.35 1.10 5.72
SEGUNDO PISO 41.45
EJE A VP-102 1 14.75 0.25 0.50 1.84
EJE A' VP-102 1 14.75 0.25 0.50 1.84
EJE B', D' V-1 2 4.15 0.30 0.20 0.50
EJE C' VP-102 1 15.50 0.25 0.50 1.94
EJE F' VP-102 1 14.75 0.25 0.50 1.84
EJE G' VP-102 1 14.75 0.25 0.50 1.84
EJE 11 VP-102 1 3.40 0.25 0.50 0.43
VP-101 1 14.85 0.35 1.10 5.72
EJE 12, 13, 14 VP-102 3 3.40 0.25 0.50 1.28
VP-101 3 14.85 0.35 1.10 17.15
EJE 15 VP-102 1 3.40 0.25 0.50 0.43
VP-101 1 14.85 0.35 1.10 5.72
volado VP-103 1 11.60 0.20 0.40 0.93

05.03.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN VIGAS M2 420.37


PRIMER PISO 157.99
EJE A VP-102 1 14.75 1.25 18.44
EJE A' VP-102 1 14.75 1.25 18.44
EJE F' VP-102 1 14.75 1.25 18.44
EJE G' VP-102 1 14.75 1.25 18.44
EJE 11 VP-102 1 3.40 1.25 4.25
0 VP-101 1 14.85 2.55 37.87
EJE 15 VP-102 1 3.40 1.25 4.25
0 VP-101 1 14.85 2.55 37.87
SEGUNDO PISO 262.38
EJE A VP-102 1 14.75 1.05 15.49
EJE A' VP-102 1 14.75 0.85 12.54
EJE B', D' V-1 2 4.15 0.30 2.49
EJE C' VP-102 1 15.50 0.85 13.18
EJE F' VP-102 1 14.75 0.85 12.54
EJE G' VP-102 1 14.75 1.05 15.49
EJE 11 VP-102 1 3.40 1.05 3.57
0 VP-101 1 14.85 2.35 34.90
EJE 12, 13, 14 VP-102 3 3.40 0.85 8.67
0 VP-101 3 14.85 2.15 95.78
EJE 15 VP-102 1 3.40 1.05 3.57
0 VP-101 1 14.85 2.35 34.90
volado VP-103 1 11.60 0.80 9.28

05.03.05.03 ACERO GRADO 60 EN VIGAS KG VER DETALLE DE PLANILLA DE ACERO 7310.45 7,310.45

05.03.06 LOSA ALIGERADA


05.03.06.01 CONCRETO EN LOSA ALIGERADA F'C=210 KG/CM2 M3 Coef. 23.74
PRIMER PISO 2.92
ss.hh. 2 2.22 1.80 0.0875 0.70
2 4.03 1.80 0.0875 1.27
2 3.03 1.80 0.0875 0.95
SEGUNDO PISO 20.82
SUM 2 3.53 6.70 0.0875 4.13
2 3.93 6.70 0.0875 4.60
2 3.93 6.70 0.0875 4.60
ingreso 2 2.88 2.80 0.0875 1.41
2 2.88 3.60 0.0875 1.81
2 2.80 1.25 0.0875 0.61
2 area= 1.35 0.0875 0.24
deposito 2 3.73 1.80 0.0875 1.17
2 1.00 1.50 0.0875 0.26
2 2.25 1.80 0.0875 0.71
2 4.03 1.80 0.0875 1.27

05.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERADA M2 271.30


PRIMER PISO 33.37
ss.hh. 2 2.22 1.80 7.99
0 2 4.03 1.80 14.49
0 2 3.03 1.80 10.89
SEGUNDO PISO 237.93
SUM 2 3.53 6.70 47.24
0 2 3.93 6.70 52.60
0 2 3.93 6.70 52.60
ingreso 2 2.88 2.80 16.10
0 2 2.88 3.60 20.70
0 2 2.80 1.25 7.00
0 2 area= 1.35 2.70
deposito 2 3.73 1.80 13.41
0 2 1.00 1.50 3.00
0 2 2.25 1.80 8.10
0 2 4.03 1.80 14.49

05.03.06.03 ACERO GRADO 60 EN LOSA ALIGERADA KG VER DETALLE DE PLANILLA DE ACERO 2307.85 2,307.85

05.03.06.04 LADRILLO HUECO DE ARCILLA H=15 PARA TECHO ALIGERADO UND 2,260.00
PRIMER PISO 278.00
ss.hh. 2 2.22 1.80 8.33 66.57
0 2 4.03 1.80 8.33 120.70
0 2 3.03 1.80 8.33 90.71
SEGUNDO PISO 1,982.00
SUM 2 3.53 6.70 8.33 393.47
0 2 3.93 6.70 8.33 438.12
0 2 3.93 6.70 8.33 438.12
ingreso 2 2.88 2.80 8.33 134.11
0 2 2.88 3.60 8.33 172.43
0 2 2.80 1.25 8.33 58.31
0 2 area= 1.35 8.33 22.49
deposito 2 3.73 1.80 8.33 111.71
0 2 1.00 1.50 8.33 24.99
0 2 2.25 1.80 8.33 67.47
0 2 4.03 1.80 8.33 120.70

05.03.07 ESCALERA
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.03.07.01 CONCRETO EN ESCALERA F'C=210 KG/CM2 M3 5.09
PRIMER PISO
CIMIENTO 2 0.90 0.50 0.80 0.72
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
LOSA 1 2 3.13 0.90 0.15 0.84
GRADAS 22 area= 0.02 1.60 0.70
DESCANSO 2 3.20 1.50 0.15 1.44
LOSA 2 2 3.13 0.90 0.12 0.68
GRADAS 22 area= 0.02 1.60 0.70

05.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERA M2 34.93


PRIMER PISO
LOSA 1 2 3.13 0.90 5.63
GRADAS 22 0.20 1.60 7.04
DESCANSO 2 3.20 1.50 9.60
LOSA 2 2 3.13 0.90 5.63
GRADAS 22 0.20 1.60 7.04

05.03.07.03 ACERO GRADO 60 EN ESCALERA KG VER DETALLE DE PLANILLA DE ACERO 205.78 205.78

05.03.08 MESON DE CONCRETO


05.03.08.01 CONCRETO EN MESON F'C=175 KG/CM2 M3 1.97
SEGUNDO PISO
M-1
MURO 4 0.65 0.15 1.13 0.44
MESON 2 1.95 0.65 0.12 0.30
M-2
MURO 4 0.65 0.15 1.13 0.44
MESON 2 0.85 0.65 0.12 0.13
M-3
MURO 2 0.65 0.15 1.13 0.22
MESON 1 1.65 0.65 0.12 0.13
M-4
MURO 2 0.65 0.15 1.13 0.22
MESON 1 1.00 0.65 0.12 0.08

05.03.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN MESON M2 22.99


SEGUNDO PISO
M-1
MURO 8 0.65 1.13 5.88
MESON 2 1.95 0.65 2.54
M-2
MURO 8 0.65 1.13 5.88
MESON 2 0.85 0.65 1.11
M-3
MURO 4 0.65 1.13 2.94
MESON 1 1.65 0.65 1.07
M-4
MURO 4 0.65 1.13 2.94
MESON 1 1.00 0.65 0.65

05.03.08.03 ACERO GRADO 60 EN MESON DE CONCRETO KG VER DETALLE DE PLANILLA DE ACERO 75.68 75.68

05.04 ALBAÑILERIA Y TABIQUES


05.04.01 MURO DE LADRILLO DE ARCILLA DE SOGA CON MEZCLA 1:5 X 1.5 CM. M2 292.85
PRIMER NIVEL 146.50
EJE A 1 4.63 2.10 9.71
1 1.05 2.70 2.84
EJE A' 1 9.50 2.70 25.65
EJE B', E' 2 0.80 2.70 4.32
2 1.50 1.00 3.00
EJE F' 1 8.73 2.70 23.56
EJE G' 1 4.63 2.10 9.71
1 1.05 2.70 2.84
EJE 11 1 9.20 1.35 12.42
EJE 12' 1 3.84 2.70 10.37
EJE 13 1 4.50 2.70 12.15
EJE 14 1 9.05 2.20 19.91
EJE 14' 1 2.00 2.70 5.40
EJE 15 1 1.30 1.30 1.69
1 1.40 2.10 2.94
SEGUNDO NIVEL 146.35
EJE A 1 4.63 2.90 13.41
1 1.05 2.90 3.05
EJE A' 1 9.50 2.90 27.55
EJE B', E' 2 0.80 2.90 4.64
EJE F' 1 8.73 2.90 25.30
EJE G' 1 4.63 2.90 13.41
1 1.05 2.90 3.05
EJE 11 1 12.75 2.90 36.98
EJE 12' 1 3.84 2.90 11.14
EJE 15 1 1.30 2.90 3.77
1 1.40 2.90 4.06

05.04.02 MURO DE LADRILLO DE ARCILLA DE CABEZA CON MEZCLA 1:5 X 1.5 CM. M2 78.30
PRIMER NIVEL 37.80
EJE A 1 6.75 2.80 18.90
EJE G' 1 6.75 2.80 18.90
SEGUNDO NIVEL 40.50
EJE A 1 6.75 3.00 20.25
EJE G' 1 6.75 3.00 20.25

05.05 CUBIERTAS
05.05.01 CUBIERTA LADRILLO PASTELERO DE 20X20CM+FRAGUA MORTERO 1:5 M2 102.31
AZOTEA
terraza area= 102.31 102.31

05.05.02 IMPERMEABILIZACION DE LADRILLO PASTELERO CON ASFALTO M2 102.31


AZOTEA
terraza area= 102.31 102.31

05.06 REVOQUES, ENLUCIDOS Y MOLDURAS


05.06.01 TARRAJEO PRIMARIO O RAYADO CON CEMENTO-ARENA 1:5 E=1.5CM. M2 85.41
PRIMER NIVEL 58.11
ss.hh. Varones 1 16.60 1.30 21.58
ss.hh. Damas 1 16.60 1.30 21.58
ss.hh. Discapacitados 2 5.75 1.30 14.95
SEGUNDO NIVEL 27.30
ss.hh. Varones 1 10.50 1.30 13.65
ss.hh. Damas 1 10.50 1.30 13.65

05.06.02 TARRAJEO EN MURO INTERIOR Y EXTERIOR M2 656.89


PRIMER NIVEL 310.49
EJE A 2 4.63 2.10 19.43
2 1.05 2.70 5.67
EJE A' 2 9.50 2.70 51.30
EJE B', E' 4 0.80 2.70 8.64
4 1.50 1.00 6.00
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
EJE F' 2 8.73 2.70 47.12
EJE G' 2 4.63 2.10 19.43
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
2 1.05 2.70 5.67
EJE 11 2 9.20 1.35 24.84
EJE 12' 2 3.84 2.70 20.74
EJE 13 2 4.50 2.70 24.30
EJE 14 2 9.05 2.20 39.82
EJE 14' 2 2.00 2.70 10.80
EJE 15 2 1.30 1.30 3.38
2 1.40 2.10 5.88

EJE A 2 6.75 2.80 37.80


EJE G' 2 6.75 2.80 37.80

Tarrajeo primario -1 area= 58.11 -58.11


SEGUNDO NIVEL 373.70
EJE A 2 4.63 2.90 26.83
2 1.05 2.90 6.09
EJE A' 2 9.50 2.90 55.10
EJE B', E' 4 0.80 2.90 9.28
EJE F' 2 8.73 2.90 50.61
EJE G' 2 4.63 2.90 26.83
2 1.05 2.90 6.09
EJE 11 2 12.75 2.90 73.95
EJE 12' 2 3.84 2.90 22.27
EJE 15 2 1.30 2.90 7.54
2 1.40 2.90 8.12

EJE A 2 6.75 3.00 40.50


EJE G' 2 6.75 3.00 40.50

Tarrajeo primario -1 area= 27.30 -27.30

05.06.03 SOLAQUEO EN COLUMNAS CARAVISTA M2 355.63


PRIMER Y SEGUNDO NIVEL 355.63
P-1 2 6.00 6.10 73.20
P-1 2 4.90 6.10 59.78
P-2 2 5.10 6.10 62.22

C-1 6 1.90 6.10 69.54


C-2 2 1.70 6.10 20.74
C-3 8 1.00 6.10 48.80
C-4 7 0.50 6.10 21.35

05.06.04 SOLAQUEO EN VIGAS CARAVISTA M2 420.37


PRIMER PISO 157.99
EJE A 1 14.75 1.25 18.44
EJE A' 1 14.75 1.25 18.44
EJE F' 1 14.75 1.25 18.44
EJE G' 1 14.75 1.25 18.44
EJE 11 1 3.40 1.25 4.25
0 1 14.85 2.55 37.87
EJE 15 1 3.40 1.25 4.25
0 1 14.85 2.55 37.87
SEGUNDO PISO 262.38
EJE A 1 14.75 1.05 15.49
EJE A' 1 14.75 0.85 12.54
EJE B', D' 2 4.15 0.30 2.49
EJE C' 1 15.50 0.85 13.18
EJE F' 1 14.75 0.85 12.54
EJE G' 1 14.75 1.05 15.49
EJE 11 1 3.40 1.05 3.57
0 1 14.85 2.35 34.90
EJE 12, 13, 14 3 3.40 0.85 8.67
0 3 14.85 2.15 95.78
EJE 15 1 3.40 1.05 3.57
0 1 14.85 2.35 34.90
volado 1 11.60 0.80 9.28

05.06.05 VESTIDURA DE DERRAMES PARA VENTANAS Y PUERTAS ML (2 anch+2 alto)xcant 220.00


PRIMER PISO
V-1 2 2.10 0.80 11.60
V-2 2 2.70 0.80 14.00
V-3 2 1.30 0.80 8.40
SEGUNDO PISO
V-4 2 2.10 0.80 11.60
V-5 2 2.70 0.80 14.00
V-6 2 1.20 2.00 12.80
V-7 1 3.05 2.00 10.10
V-8 1 1.45 2.00 6.90
V-9 2 1.80 2.00 15.20
PRIMER PISO ((altox2lados)+ancho)x cant
P-1 2 1.50 3.00 15.00
P-2 2 1.20 2.40 12.00
P-3 1 1.00 3.00 7.00
P-4 1 1.00 2.40 5.80
SEGUNDO PISO
P-5 2 1.00 3.30 15.20
PRIMER PISO
P-6 4 1.00 3.25 30.00
SEGUNDO PISO
P-7 4 1.00 3.30 30.40

05.07 CIELO RASO


05.07.01 TARRAJEO DE CIELO RASO M2 72.37
PRIMER PISO 33.37
ss.hh. 2 2.22 1.80 7.99
0 2 4.03 1.80 14.49
0 2 3.03 1.80 10.89
SEGUNDO PISO 39.00
deposito 2 3.73 1.80 13.41
0 2 1.00 1.50 3.00
0 2 2.25 1.80 8.10
0 2 4.03 1.80 14.49

05.08 PISOS Y PAVIMENTOS


05.08.01 CONTRAPISO DE 48MM. M2 118.72
PRIMER PISO 53.10
deposito 2 3.725 1.80 13.41
2 3.975 1.80 14.31
2 4.025 1.80 14.49
2 3.025 1.80 10.89
SEGUNDO PISO 65.62
archivo 2 area= 7.50 15.00
ss.hh. 2 area= 13.70 27.40
liquidaciones y patrocinio 2 area= 11.61 23.22
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.08.02 PISO DE CERAMICA 40X40CM. C/PEGAMENTO M2 80.48
PRIMER PISO 53.08
grupo electrogeno 1 area= 7.39 7.39
camerino 1 area= 7.29 7.29
ss.hh. 2 area= 19.20 38.40
SEGUNDO PISO 27.40
ss.hh. 2 area= 13.70 27.40

05.08.03 PISO DE PORCELANATO 60X60CM. ANTIDESLIZANTE M2 242.15


PRIMER PISO 101.91
ingreso y auditorio 1 area= 98.46 98.46
salida emergencia 1 2.30 1.50 3.45
SEGUNDO PISO 140.24
archivo 1 area= 7.50 7.50
liquidaciones y patrocinio 1 area= 11.61 11.61
sala central 1 area= 121.13 121.13

05.09 ZOCALOS Y CONTRAZOCALOS


05.09.01 ZOCALO DE CERAMICA DE 20x30CM. DE 1ERA H=1.30M. M2 85.41
PRIMER NIVEL 58.11
ss.hh. Varones 1 16.60 1.30 21.58
ss.hh. Damas 1 16.60 1.30 21.58
ss.hh. Discapacitados 2 5.75 1.30 14.95
SEGUNDO NIVEL 27.30
ss.hh. Varones 1 10.50 1.30 13.65
ss.hh. Damas 1 10.50 1.30 13.65

05.09.02 CONTRAZOCALO DE CERAMICA H=0.10M. DE 1ERA M 21.50


PRIMER PISO 21.50
grupo electrogeno 1 10.75 10.75
camerino 1 10.75 10.75

05.09.03 CONTRAZOCALO DE PORCELANATO DE H=0.10 M. DE 1ERA M 170.82


PRIMER PISO 73.55
ingreso y auditorio 1 64.35 64.35
salida emergencia 4 2.30 9.20
SEGUNDO NIVEL 97.27
archivo 2 10.95 21.90
liquidaciones y patrocinio 2 13.00 26.00
sala central 1 49.37 49.37

05.09.04 CERAMICO DE 20X30CM. EN MESON DE CONCRETO M2 4.40


PRIMER PISO
ss.hh. Varones 1 2.00 0.50 1.00
ss.hh. Damas 1 2.45 0.50 1.23
s.h. discapacitados 2 0.85 0.50 0.85
SEGUNDO NIVEL
ss.hh. Varones 1 1.00 0.50 0.50
ss.hh. Damas 1 1.65 0.50 0.83

05.10 CARPINTERIA DE MADERA


05.10.01 PUERTA INTERIOR DE MELAMINA DE E=10MM. M2 52.96
PRIMER PISO
P-1 2 1.50 3.00 9.00
P-2 2 1.20 2.40 5.76
P-3 1 1.00 3.00 3.00
P-4 1 1.00 2.40 2.40
P-6 4 1.00 3.25 13.00
SEGUNDO PISO
P-5 2 1.00 3.30 6.60
P-7 4 1.00 3.30 13.20

05.11 CARPINTERIA METALICA


05.11.01 BARANDA METALICA M 4.00
PRIMER NIVEL
ss.hh. Minusvalidos 2 2.00 4.00

05.11.02 DIVISION DE ALUMINIO CON PANELES DE MELAMINA M2 25.74


PRIMER NIVEL
ss.hh. 5 1.30 1.80 11.70
2 0.60 1.80 2.16
SEGUNDO NIVEL
ss.hh. 2 3.30 1.80 11.88

05.12 CERRAJERIA
05.12.01 CERRADURA TIPO PARCHE TRES GOLPES PZA 8.00
PRIMER PISO
P-1 2 2.00
P-2 2 2.00
P-3 1 1.00
P-4 1 1.00
SEGUNDO PISO
P-5 2 2.00

05.12.02 CERRADURA TIPO PERILLA PZA 8.00


PRIMER PISO
P-6 4 4.00
SEGUNDO PISO
P-7 4 4.00

05.12.03 BISAGRA ALUMINIZADA DE 4" X 2" PZA Nº BISAGRA 72.00


PRIMER PISO
P-1 2 8 16.00
P-2 2 8 16.00
P-3 1 4 4.00
P-4 1 4 4.00
P-6 4 3 12.00
SEGUNDO PISO
P-5 2 4 8.00
P-7 4 3 12.00

05.13 VIDRIOS, CRISTALES Y SIMILARES Coef.


05.13.01 VENTANA SISTEMA CON VIDRIO DOBLE INCOLORO Y MARCO DE ALUMINIO M2 38.44
PRIMER PISO
V-1 2 2.10 0.80 3.36
V-2 2 2.70 0.80 4.32
V-3 2 1.30 0.80 2.08
SEGUNDO PISO
V-4 2 2.10 0.80 3.36
V-5 2 2.70 0.80 4.32
V-6 2 1.20 2.00 4.80
V-7 1 3.05 2.00 6.10
V-8 1 1.45 2.00 2.90
V-9 2 1.80 2.00 7.20
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.14 PINTURAS Y BARNICES
05.14.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES M2 656.89
PRIMER NIVEL 310.49
EJE A 2 4.63 2.10 19.43
0 2 1.05 2.70 5.67
EJE A' 2 9.50 2.70 51.30
EJE B', E' 4 0.80 2.70 8.64
0 4 1.50 1.00 6.00
EJE F' 2 8.73 2.70 47.12
EJE G' 2 4.63 2.10 19.43
0 2 1.05 2.70 5.67
EJE 11 2 9.20 1.35 24.84
EJE 12' 2 3.84 2.70 20.74
EJE 13 2 4.50 2.70 24.30
EJE 14 2 9.05 2.20 39.82
EJE 14' 2 2.00 2.70 10.80
EJE 15 2 1.30 1.30 3.38
0 2 1.40 2.10 5.88

EJE A 2 6.75 2.80 37.80


EJE G' 2 6.75 2.80 37.80

Tarrajeo primario -1 area= 58.11 -58.11


SEGUNDO NIVEL 346.40
EJE A 2 4.63 2.90 26.83
0 2 1.05 2.90 6.09
EJE A' 2 9.50 2.90 55.10
EJE B', E' 4 0.80 2.90 9.28
EJE F' 2 8.73 2.90 50.61
EJE G' 2 4.63 2.90 26.83
0 2 1.05 2.90 6.09
EJE 11 2 12.75 2.90 73.95
EJE 12' 2 3.84 2.90 22.27
EJE 15 2 1.30 2.90 7.54
0 2 1.40 2.90 8.12

EJE A 2 6.75 3.00 40.50


EJE G' 2 6.75 3.00 40.50

Tarrajeo primario -1 area= 27.30 -27.30

05.14.02 PINTURA LATEX EN VIGAS Y COLUMNAS M2 776.00


PRIMER Y SEGUNDO NIVEL 776.00
P-1 2 6.00 6.10 73.20
P-1 2 4.90 6.10 59.78
P-2 2 5.10 6.10 62.22
P-4 0 2.20 3.10 0.00
P-5 0 1.95 3.10 0.00

C-1 6 1.90 6.10 69.54


C-2 2 1.70 6.10 20.74
C-3 8 1.00 6.10 48.80
C-4 7 0.50 6.10 21.35
VIGAS
PRIMER PISO
EJE A 1 14.75 1.25 18.44
EJE A' 1 14.75 1.25 18.44
EJE F' 1 14.75 1.25 18.44
EJE G' 1 14.75 1.25 18.44
EJE 11 1 3.40 1.25 4.25
0 1 14.85 2.55 37.87
EJE 15 1 3.40 1.25 4.25
0 1 14.85 2.55 37.87
SEGUNDO PISO
EJE A 1 14.75 1.05 15.49
EJE A' 1 14.75 0.85 12.54
EJE B', D' 2 4.15 0.30 2.49
EJE C' 1 15.50 0.85 13.18
EJE F' 1 14.75 0.85 12.54
EJE G' 1 14.75 1.05 15.49
EJE 11 1 3.40 1.05 3.57
0 1 14.85 2.35 34.90
EJE 12, 13, 14 3 3.40 0.85 8.67
0 3 14.85 2.15 95.78
EJE 15 1 3.40 1.05 3.57
0 1 14.85 2.35 34.90
volado 1 11.60 0.80 9.28

05.14.03 PINTURA LATEX EN DERRAMES DE VANOS ML (anch+alto)xcant 220.00


PRIMER PISO
V-1 2 2.10 0.80 11.60
V-2 2 2.70 0.80 14.00
V-3 2 1.30 0.80 8.40
SEGUNDO PISO
V-4 2 2.10 0.80 11.60
V-5 2 2.70 0.80 14.00
V-6 2 1.20 2.00 12.80
V-7 1 3.05 2.00 10.10
V-8 1 1.45 2.00 6.90
V-9 2 1.80 2.00 15.20
PRIMER PISO
P-1 2 1.50 3.00 15.00
P-2 2 1.20 2.40 12.00
P-3 1 1.00 3.00 7.00
P-4 1 1.00 2.40 5.80
SEGUNDO PISO
P-5 2 1.00 3.30 15.20
PRIMER PISO
P-6 4 1.00 3.25 30.00
SEGUNDO PISO
P-7 4 1.00 3.30 30.40

05.14.04 PINTURA LATEX EN CIELO RASO M2 72.37


PRIMER PISO 33.37
ss.hh. 2 2.22 1.80 7.99
0 2 4.03 1.80 14.49
0 2 3.03 1.80 10.89
SEGUNDO PISO 39.00
deposito 2 3.73 1.80 13.41
0 2 1.00 1.50 3.00
0 2 2.25 1.80 8.10
0 2 4.03 1.80 14.49
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total
05.15 VARIOS
05.15.01 CURADO DE ELEMENTOS HORIZONTALES Y VERTICALES M2 1,531.74
SOBRECIMIENTOS 42.83
FALSO PISO 279.16
PLACAS 233.60
COLUMNAS 191.99
COLUMNAS Y VIGAS AMARRE 92.50
VIGAS 420.37
LOSA ALIGERADA 271.30

05.15.02 JUNTA DE CONSTRUCCION CON TECKNOPORT M2 22.65


COLUMNETAS 26 0.15 2.00 7.80
33 0.15 3.00 14.85

05.15.03 JUNTA DE CONSTRUCCION CON ESPUMA PLASTICA + JEBE MICROPOROSO M 151.00


COLUMNETAS 26 2.00 52.00
33 3.00 99.00

05.15.04 LIMPIEZA FINAL DE OBRA M2 area= 441.35 441.35 441.35


PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO

05.03.01.02 ACERO GRADO 60 EN ZAPATAS Z-1 4 9 1.55 52.70


SUM 4 9 1.55 52.70

Z-2 11 5 0.85 46.75


11 5 0.85 46.75

Z-3 4 7 2.45 68.60


4 13 1.25 65.00

Z-1' 2 13 2.50 63.75


2 13 2.40 63.60

TOTAL ML : 459.85 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25

TOTAL KG : 718.52 0.00

TOTAL VAR : 51 0

TOTAL KG 718.52
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO

05.03.02.03 ACERO GRADO 60 EN PLACAS C-1 2 8 10.30 164.80


Est. 2 66 1.50 198.00
2 66 1.50 198.00
SUM P-1 2 4 10.30 82.40
2 18 10.30 370.80
Estribo 2 66 1.20 158.40
Var. Horiz. 2 52 2.60 267.80
2 52 2.60 267.80

C-1 2 8 10.30 164.80


Est. 2 66 1.50 198.00
2 66 1.50 198.00
P-1 2 4 10.30 82.40
2 14 10.30 288.40
Estribo 2 66 1.20 158.40
Var. Horiz. 2 52 2.60 267.80
2 52 2.60 267.80

P-2 2 8 10.30 164.80


2 16 10.30 329.60
Estribo 2 66 1.20 158.40
2 66 1.20 158.40
Var. Horiz. 2 52 2.25 231.75
2 52 2.25 231.75

TOTAL ML : 329.60 329.60 988.80 0.00 1534.70 1425.60 0.00

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25

TOTAL KG : 1318.40 741.60 1545.00 0.00 863.27 801.90 0.00

TOTAL VAR : 37 37 110 0 171 158


TOTAL KG 5,270.17
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO

05.03.03.03 ACERO GRADO 60 EN COLUMNAS

SUM

C-1 6 8 10.30 494.40


Est. 6 66 1.50 594.00
6 66 1.50 594.00

C-2 2 6 10.30 123.60


2 2 10.30 41.20
Est. 2 66 1.30 171.60
2 66 1.30 171.60

C-3 8 4 10.30 329.60


Est. 8 66 1.00 528.00

C-4 7 4 10.30 288.40


Est. 7 66 0.75 346.50

TOTAL ML : 123.60 370.80 288.40 0.00 2059.20 346.50

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25

TOTAL KG : 278.10 579.38 288.40 0.00 1158.30 86.63

TOTAL VAR : 14 41 32 0 229


TOTAL KG 2,390.80
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO
1º PISO CA 0 4 1.60 0.00
05.03.04.03 ACERO GRADO 60 EN COLUMNAS Y VIGAS DE AMARRE Est. 0 10 0.65 0.00
SUM CA 6 4 2.60 62.40
Est. 6 16 0.65 62.40
CA 23 4 3.80 349.60
Est. 23 26 0.65 388.70

V-A 2 2 6.85 27.40


Est. 2 34 0.20 13.70
V-A 2 2 11.55 46.20
Est. 2 58 0.20 23.10
V-A 1 2 12.40 24.80
Est. 1 62 0.20 12.40
V-A 1 2 5.00 10.00
Est. 1 25 0.20 5.00
V-A 4 2 1.30 10.40
Est. 4 7 0.20 5.20
V-A 1 2 11.15 22.30
Est. 1 56 0.20 11.15
V-A 1 2 3.90 7.80
Est. 1 20 0.20 3.90

2º PISO CA 0 4 1.60 0.00


Est. 0 10 0.65 0.00
CA 6 4 2.60 62.40
Est. 6 16 0.65 62.40
CA 23 4 3.80 349.60
Est. 23 26 0.65 388.70

V-A 2 2 6.85 27.40


Est. 2 34 0.20 13.70
V-A 2 2 11.55 46.20
Est. 2 58 0.20 23.10
V-A 1 2 12.00 24.00
Est. 1 60 0.20 12.00
V-A 1 2 5.40 10.80
Est. 1 27 0.20 5.40
V-A 4 2 1.70 13.60
Est. 4 9 0.20 6.80
V-A 1 2 11.55 23.10
Est. 1 58 0.20 11.55
V-A 1 2 4.30 8.60
Est. 1 22 0.20 4.30

TOTAL ML : 0.00 0.00 0.00 1126.60 0.00 1,053.50


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 0.00 0.00 0.00 633.71 0.00 263.38
TOTAL VAR : 0 0 0 125 0
TOTAL KG 897.09
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO
1º PISO
05.03.05.03 ACERO GRADO 60 EN VIGAS EJE A, A' VP-102
SUM (+) 2 3 16.85 101.10
(-) 2 3 16.85 101.10
Est. 2 144 1.50 432.00
EJE F', G' VP-102
(+) 2 3 16.85 101.10
(-) 2 3 16.85 101.10
Est. 2 144 1.50 432.00
EJE 11, 15 VP-101
(+) 2 5 15.85 158.50
2 2 5.30 21.20
2 3 2.50 15.00
2 4 15.85 126.80
2 3 2.50 15.00
(-) 2 2 5.30 21.20
2 5 15.85 158.50
Est. 2 95 2.80 532.00
2 14 1.50 42.00
2 14 1.50 42.00
2º PISO
EJE A, A' VP-102
(+) 2 3 16.85 101.10
(-) 2 3 16.85 101.10
Est. 2 144 1.50 432.00
EJE F', G' VP-102
(+) 2 3 16.85 101.10
(-) 2 3 16.85 101.10
Est. 2 144 1.50 432.00
EJE B', D' V-1
(+) 2 2 5.55 22.20
(-) 2 2 5.55 22.20
Est. 2 36 1.10 79.20
EJE C' (+) 1 3 18.30 54.90
(-) 1 3 18.30 54.90
Est. 1 144 1.50 216.00
EJE 11,12,13,14,15 VP-101
(+) 5 5 15.85 396.25
5 2 5.30 53.00
5 3 2.50 37.50
5 4 15.85 317.00
5 3 2.50 37.50
(-) 5 2 5.30 53.00
5 5 15.85 396.25
Est. 5 95 2.80 1330.00
5 14 1.50 105.00
5 14 1.50 105.00
volado VP-103
(+) 1 2 13.40 26.80
(-) 1 2 13.40 26.80
Est. 1 52 1.20 62.40

TOTAL ML : 1109.50 1270.00 443.80 0.00 4241.60 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25
TOTAL KG : 2496.38 1984.38 443.80 0.00 2385.90 0.00
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016
TOTAL VAR : 123 141 49 0 471
TOTAL KG 7,310.45
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO PRIMER NIVEL
TIPO A As(-) 2 23 2.45 112.70
05.03.06.03 ACERO GRADO 60 EN LOSA ALIGERADA As(+) 2 23 2.45 112.70
As(t) 2 10 16.13 316.05
SUM
SEGUNDO NIVEL
TIPO A As(-) 2 27 2.45 132.30
As(+) 2 27 2.45 132.30
As(t) 2 10 16.13 316.05
TIPO A As(-) 2 4 1.60 12.80
2 4 2.85 22.80
2 4 2.95 23.60
2 4 2.60 20.80
2 4 1.35 10.80
As(+) 2 4 16.60 132.80
As(t) 2 66 2.13 282.20
TIPO A As(-) 2 12 1.60 38.40
2 12 2.85 68.40
2 12 2.95 70.80
2 12 2.60 62.40
2 12 2.85 68.40
As(+) 2 12 18.65 447.60
As(t) 2 75 10.33 1,540.49

TOTAL ML : 399.20 1070.40 0.00 2,454.79


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25
TOTAL KG : 623.75 1070.40 0.00 613.70
TOTAL VAR : 44 119 0
TOTAL KG 2,307.85
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO

05.03.07.03 ACERO GRADO 60 EN ESCALERA

SUM PRIMER NIVEL


1° TRAMO As(-) 1 6 1.25 7.50
1 5 1.50 7.50
As(-) 1 6 0.90 5.40
1 4 1.50 5.40
As(-) 1 6 1.65 9.90
1 7 1.50 9.90

As(+) 1 6 0.95 5.70


1 4 1.50 5.70
As(+) 1 6 2.35 14.10
1 9 1.50 14.10
As(+) 1 6 1.80 10.80
1 7 1.50 10.80

2° TRAMO As(-) 1 6 2.20 13.20


1 9 1.50 13.20
As(-) 1 6 3.55 21.30
1 14 1.50 21.30

As(+) 1 6 1.80 10.80


1 7 1.50 10.80
As(+) 1 6 3.25 19.50
1 13 1.50 19.50
As(+) 1 6 2.25 13.50
1 9 1.50 13.50

TOTAL ML : 131.70 131.70 0.00 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25
TOTAL KG : 131.70 74.08 0.00 0.00
TOTAL VAR : 15 15 0

TOTAL KG 205.78
PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
05.03 OBRAS DE CONCRETO ARMADO

05.03.08.03 ACERO GRADO 60 EN MESON DE CONCRETO SUM

M-1
MURO H 4 3 1.90 22.80
V 4 10 0.60 22.80

MESON 2 3 1.95 11.70


2 10 0.60 11.70

M-2
.10 MURO
.10 H 4 3 1.90 22.80
V 4 10 0.60 22.80

MESON 2 3 0.85 5.10


2 4 0.60 5.10

M-3
MURO H 2 3 1.90 11.40
V 2 10 0.60 11.40

MESON 1 3 1.65 4.95


1 8 0.60 4.95

M-4
MURO H 2 3 1.90 11.40
V 2 10 0.60 11.40

MESON 1 3 1.00 3.00


1 5 0.60 3.00
.10

TOTAL ML : 93.15 0.00 93.15

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 ### 0.56 0.25

TOTAL KG : 52.40 0.00 23.29

TOTAL VAR : 10 0

TOTAL KG 75.68
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total

06 OFICINAS
06.01 MOVIMIENTO DE TIERRAS
06.01.01 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL M3 71.10
EJE A, ENTRE EJES 1-8 1 7.09 0.60 1.40 5.96
EJE B, ENTRE EJES 1-8 1 8.54 0.60 1.40 7.17
EJE C, ENTRE EJES 1-8 1 0.78 0.60 1.40 0.66
EJE D, ENTRE EJES 1-8 1 0.78 0.60 1.40 0.66
EJE E, ENTRE EJES 1-8 1 8.54 0.60 1.40 7.17
EJE F, ENTRE EJES 1-8 1 9.29 0.60 1.40 7.80
EJE G', ENTRE EJES 1-8 (CC-1) 1 3.50 0.60 0.90 1.89
EJE H, ENTRE EJES 1-8 (CC-2) 1 9.19 0.50 0.90 4.14
EJE H, ENTRE EJES 1-8 (CC-3) 1 6.50 0.60 0.90 3.51
EJE 1, ENTRE EJES A-H 1 5.95 0.60 1.40 5.00
EJE 2, ENTRE EJES A-F 1 3.35 0.60 1.40 2.81
EJE 3, ENTRE EJES A-F 1 3.00 0.60 1.40 2.52
EJE 4, ENTRE EJES A-F 1 3.00 0.60 1.40 2.52
EJE 5, ENTRE EJES A-F 1 3.00 0.60 1.40 2.52
EJE 5, ENTRE EJES G-H (CC-1) 1 0.30 0.60 1.40 0.25
EJE 6, ENTRE EJES A-F 1 3.00 0.60 1.40 2.52
EJE 6, ENTRE EJES G-H (CC-1) 1 2.50 0.60 1.40 2.10
EJE 7, ENTRE EJES A-F 1 3.80 0.60 1.40 3.19
EJE 8, ENTRE EJES A-B 1 1.05 0.60 1.40 0.88
EJE 8, ENTRE EJES B-E 1 4.60 1.02 1.40 6.57
EJE 8, ENTRE EJES E-F 1 1.50 0.60 1.40 1.26

06.01.02 EXCAVACION PARA ZAPATAS DE 1.40 MT A 1.70 M DE PROFUNDIDAD M3 446.61


Z-1 6 2.40 2.15 2.00 61.92
Z-2 3 2.00 2.30 2.00 27.60
Z-2' 2 2.00 2.75 2.00 22.00
Z-3 2 2.17 2.40 2.00 20.83
Z-4 1 2.40 2.65 2.00 12.72
Z-5 2 1.60 1.30 2.00 8.32
Z-5' 1 1.05 1.30 2.00 2.73
Z-6 1 1.20 1.20 2.00 2.88
ZC-1 6 1.40 4.25 2.00 71.40
ZC-2 1 4.10 2.60 2.00 21.32
ZC-2' 1 3.90 2.30 2.00 17.94
ZC-3 1 Area: 3.02 2.00 6.03
ZP-1 4 5.40 2.80 2.00 120.96
ZP-2 1 Area: 24.98 2.00 49.96

06.01.03 REFINE Y NIVELACION DE ZANJA M2 269.29


EJE A, ENTRE EJES 1-8 1 7.09 0.60 4.25
EJE B, ENTRE EJES 1-8 1 8.54 0.60 5.12
EJE C, ENTRE EJES 1-8 1 0.78 0.60 0.47
EJE D, ENTRE EJES 1-8 1 0.78 0.60 0.47
EJE E, ENTRE EJES 1-8 1 8.54 0.60 5.12
EJE F, ENTRE EJES 1-8 1 9.29 0.60 5.57
EJE G', ENTRE EJES 1-8 (CC-1) 1 3.50 0.60 2.10
EJE H, ENTRE EJES 1-8 (CC-2) 1 9.19 0.50 4.60
EJE H, ENTRE EJES 1-8 (CC-3) 1 6.50 0.60 3.90
EJE 1, ENTRE EJES A-H 1 5.95 0.60 3.57
EJE 2, ENTRE EJES A-F 1 3.35 0.60 2.01
EJE 3, ENTRE EJES A-F 1 3.00 0.60 1.80
EJE 4, ENTRE EJES A-F 1 3.00 0.60 1.80
EJE 5, ENTRE EJES A-F 1 3.00 0.60 1.80
EJE 5, ENTRE EJES G-H (CC-1) 1 0.30 0.60 0.18
EJE 6, ENTRE EJES A-F 1 3.00 0.60 1.80
EJE 6, ENTRE EJES G-H (CC-1) 1 2.50 0.60 1.50
EJE 7, ENTRE EJES A-F 1 3.80 0.60 2.28
EJE 8, ENTRE EJES A-B 1 1.05 0.60 0.63
EJE 8, ENTRE EJES B-E 1 4.60 1.02 4.69
EJE 8, ENTRE EJES E-F 1 1.50 0.60 0.90

Z-1 6 Área: 2.97 1.40 24.95


Z-2 3 Área: 2.83 1.40 11.87
Z-2' 2 Área: 3.73 1.40 10.43
Z-3 2 Área: 2.71 1.40 7.59
Z-4 1 Área: 4.59 1.40 6.43
Z-5 2 Área: 1.28 1.40 3.58
Z-5' 1 Área: 0.52 1.40 0.73
Z-6 1 Área: 0.74 1.40 1.03
ZC-1 6 Área: 4.57 1.40 38.39
ZC-2 1 Área: 6.30 1.40 8.82
ZC-2' 1 Área: 3.73 1.40 5.22
ZC-3 1 Área: 1.85 1.40 2.59
ZP-1 4 Área: 10.83 1.40 60.65
ZP-2 1 Área: 23.18 1.40 32.46

06.01.04 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO M3 174.35


EJE A, ENTRE EJES 1-8 1 7.09 Área: 0.41 2.91
EJE B, ENTRE EJES 1-8 1 8.54 Área: 0.41 3.50
EJE C, ENTRE EJES 1-8 1 0.78 Área: 0.48 0.37
EJE D, ENTRE EJES 1-8 1 0.78 Área: 0.48 0.37
EJE E, ENTRE EJES 1-8 1 8.54 Área: 0.41 3.50
EJE F, ENTRE EJES 1-8 1 9.29 Área: 0.41 3.81
EJE 1, ENTRE EJES A-H 1 5.95 Área: 0.41 2.44
EJE 2, ENTRE EJES A-F 1 3.35 Área: 0.41 1.37
EJE 3, ENTRE EJES A-F 1 3.00 Área: 0.41 1.23
EJE 4, ENTRE EJES A-F 1 3.00 Área: 0.41 1.23
EJE 5, ENTRE EJES A-F 1 3.00 Área: 0.41 1.23
EJE 6, ENTRE EJES A-F 1 3.00 Área: 0.41 1.23
EJE 7, ENTRE EJES A-F 1 3.80 Área: 0.41 1.56
EJE 8, ENTRE EJES A-B 1 1.05 Área: 0.41 0.43
EJE 8, ENTRE EJES B-E 1 4.60 Área: 0.84 3.85
EJE 8, ENTRE EJES E-F 1 1.50 Área: 0.41 0.62

Z-1 6 Área: 4.74 0.70 19.89


Z-2 3 Área: 4.18 0.70 8.77
Z-2' 2 Área: 4.90 0.70 6.85
Z-3 2 Área: 4.44 0.70 6.21
Z-4 1 Área: 5.84 0.70 4.08
Z-5 2 Área: 1.93 0.70 2.70
Z-5' 1 Área: 1.20 0.70 0.84
Z-6 1 Área: 1.23 0.70 0.86
ZC-1 4 Área: 5.56 0.70 15.57
ZC-1 2 Área: 5.40 0.70 7.56
ZC-2 1 Área: 9.86 0.70 6.90
ZC-2' 1 Área: 9.58 0.70 6.71
ZC-3 1 Área: 2.77 0.70 1.94
ZP-1 4 Área: 14.07 0.70 39.39
ZP-2 1 Área: 23.47 0.70 16.43

06.01.05 NIVELACION INTERIOR Y COMPACTADO FINAL DEL TERRENO PREVIO AL PISO M2 595.88
interiores - piso porcelanato 1 Área= 465.82 465.82
piso - adoquinado 1 Área= 93.24 93.24
piso - cemento bruñado 1 Área= 36.82 36.82

06.01.06 TERRAPLEN PARA PISO E=0.10M. M2 595.88


interiores - piso porcelanato 1 Área= 465.82 465.82
piso - adoquinado 1 Área= 93.24 93.24
piso - cemento bruñado 1 Área= 36.82 36.82

Coef. Volumen
06.01.07 ACARREO DE MATERIAL EXCEDENTE HASTA UNA DISTANCIA DE 30M M3 1.3 343.36 446.37 446.37

06.01.08 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO M3 1.3 343.36 446.37 446.37

06.02 OBRAS DE CONCRETO SIMPLE


06.02.01 CONCRETO C:H (1:10) + 30% P.G. P/CIMIENTO CORRIDO M3 13.58
EJE E', ENTRE EJES 3-4 (CC-1) 1 2.86 0.60 0.80 1.37
EJE G', ENTRE EJES 1-8 (CC-1) 1 3.73 0.60 0.80 1.79
EJE H, ENTRE EJES 1-8 (CC-2) 1 12.97 0.50 0.80 5.19
EJE H, ENTRE EJES 1-8 (CC-3) 1 6.75 0.60 0.80 3.24
EJE 4, ENTRE EJES G-H (CC-2) 1 1.15 0.50 0.80 0.46
EJE 5, ENTRE EJES G-H (CC-1) 1 0.70 0.60 0.80 0.34
EJE 6, ENTRE EJES G-H (CC-1) 1 2.50 0.60 0.80 1.20

06.02.02 CONCRETO C:H (1:8) + 25% P.M. PARA SOBRECIMIENTOS M3 14.42


EJE A, ENTRE EJES 1-2 (1a-1a) 1 1.88 0.15 1.00 0.28
EJE A, ENTRE EJES 2-3 (1-1) 1 3.25 0.15 1.00 0.49
EJE A, ENTRE EJES 3-4 (1-1) 1 2.36 0.15 1.00 0.35
EJE A, ENTRE EJES 4-5 (1-1) 1 3.50 0.15 1.00 0.53
EJE A, ENTRE EJES 5-6 (1-1) 1 2.60 0.15 1.00 0.39
EJE A, ENTRE EJES 6-7 (1-1) 1 2.85 0.15 1.00 0.43
EJE A, ENTRE EJES 7-8 (1-1) 1 2.10 0.15 1.00 0.32
EJE B, ENTRE EJES 1-2 (2b-2b) 1 2.23 0.15 1.00 0.33
EJE B, ENTRE EJES 2-3 (2c-2c) 1 3.75 0.00 0.00 0.00
EJE B, ENTRE EJES 4-4' (2c-2c) 1 2.00 0.00 0.00 0.00
EJE B, ENTRE EJES 4'-5 (2b-2b) 1 2.00 0.15 1.00 0.30
EJE B, ENTRE EJES 6-7 (2c-2c) 1 3.35 0.00 0.00 0.00
EJE B, ENTRE EJES 7-8 (2c-2c) 1 2.55 0.00 0.00 0.00
EJE C, ENTRE EJES 1-2 (3-3) 1 2.23 0.15 1.00 0.33
EJE D, ENTRE EJES 1-2 (3-3) 1 2.23 0.15 1.00 0.33
EJE E, ENTRE EJES 1-2 (2b-2b) 1 2.23 0.15 1.00 0.33
EJE E, ENTRE EJES 2-3' (2b-2b) 1 2.10 0.15 1.00 0.32
EJE E, ENTRE EJES 3'-4 (2c-2c) 1 1.65 0.00 0.00 0.00
EJE E, ENTRE EJES 4-5 (2c-2c) 1 4.00 0.00 0.00 0.00
EJE E, ENTRE EJES 6-7 (2c-2c) 1 3.35 0.00 0.00 0.00
EJE A, ENTRE EJES 7-8 (2b-2b) 1 2.45 0.15 1.00 0.37
EJE F, ENTRE EJES 1-2 (1a'-1a') 1 1.88 0.15 1.00 0.28
EJE F, ENTRE EJES 2-3 (1c-1c) 1 3.25 0.00 0.00 0.00
EJE F, ENTRE EJES 3-4 (1-1) 1 2.36 0.15 1.00 0.35
EJE F, ENTRE EJES 4-5 (1c-1c) 1 3.50 0.00 0.00 0.00
EJE F, ENTRE EJES 5-6 (1-1) 1 2.60 0.15 1.00 0.39
EJE F, ENTRE EJES 6-7 (1-1) 1 2.85 0.15 1.00 0.43
EJE F, ENTRE EJES 7-8 (1-1) 1 2.10 0.15 1.00 0.32
EJE E', ENTRE EJES 3-4 (CC-1) 1 2.86 0.15 0.40 0.17
EJE G', ENTRE EJES 1-8 (CC-1) 1 3.73 0.15 0.40 0.22
EJE H, ENTRE EJES 1-8 (CC-2) 1 12.97 0.15 0.40 0.78
EJE H, ENTRE EJES 1-8 (CC-3) 1 6.75 0.15 0.40 0.41
EJE 1, ENTRE EJES A-B (2-2) 1 2.90 0.15 1.00 0.44
EJE 1, ENTRE EJES B-C (1a-1a) 1 1.90 0.15 1.00 0.29
EJE 1, ENTRE EJES C-D (1-1) 1 1.40 0.15 1.00 0.21
EJE 1, ENTRE EJES D-E (1a-1a) 1 1.90 0.15 1.00 0.29
EJE 1, ENTRE EJES E-F (1-1) 1 3.00 0.15 1.00 0.45
EJE 1, ENTRE EJES G-H (1-1) 1 3.85 0.15 1.00 0.58
EJE 2 ENTRE EJES A-B (2c-2c) 1 3.10 0.00 0.00 0.00
EJE 2, ENTRE EJES C-D (3a-3a) 1 1.40 0.00 0.00 0.00
EJE 2, ENTRE EJES E-F (3-3) 1 3.20 0.15 1.00 0.48
EJE 3 ENTRE EJES A-B (2-2) 1 3.10 0.15 1.00 0.47
EJE 3, ENTRE EJES E-F (3-3) 1 1.25 0.15 1.00 0.19
EJE 3, ENTRE EJES E-F (3a-3a) 1 1.95 0.00 0.00 0.00
EJE 4 ENTRE EJES A-B (2c-2c) 1 3.10 0.00 0.00 0.00
EJE 4, ENTRE EJES E-F (3-3) 1 2.10 0.15 1.00 0.32
EJE 4, ENTRE EJES E-F (3a-3a) 1 1.10 0.00 0.00 0.00
EJE 5 ENTRE EJES A-B (2-2) 1 3.10 0.15 1.00 0.47
EJE 5, ENTRE EJES E-F (3-3) 1 2.30 0.15 1.00 0.35
EJE 5, ENTRE EJES E-F (3a-3a) 1 0.90 0.00 0.00 0.00
EJE 4 ENTRE EJES A-B (2c-2c) 1 3.10 0.00 0.00 0.00
EJE 4, ENTRE EJES E-F (3-3) 1 3.20 0.15 1.00 0.48
EJE 7 ENTRE EJES A-B (2c-2c) 1 3.10 0.00 0.00 0.00
EJE 7, ENTRE EJES C-D (3a-3a) 1 2.00 0.00 0.00 0.00
EJE 7, ENTRE EJES E-F (3a-3a) 1 3.20 0.00 0.00 0.00
EJE 1, ENTRE EJES A-B (2-2) 1 2.40 0.15 1.00 0.36
EJE 1, ENTRE EJES B-E (4-4) 1 6.20 0.00 0.00 0.00
EJE 1, ENTRE EJES E-F (1-1) 1 2.50 0.15 1.00 0.38
EJE 4, ENTRE EJES G-H (CC-2) 1 1.15 0.15 0.40 0.07
EJE 5, ENTRE EJES G-H (CC-1) 1 0.70 0.15 0.40 0.04
EJE 6, ENTRE EJES G-H (CC-1) 1 2.50 0.15 0.40 0.15

06.02.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS M2 192.32


EJE A, ENTRE EJES 1-2 (1a-1a) 2 1.88 1.00 3.76
EJE A, ENTRE EJES 2-3 (1-1) 2 3.25 1.00 6.50
EJE A, ENTRE EJES 3-4 (1-1) 2 2.36 1.00 4.72
EJE A, ENTRE EJES 4-5 (1-1) 2 3.50 1.00 7.00
EJE A, ENTRE EJES 5-6 (1-1) 2 2.60 1.00 5.20
EJE A, ENTRE EJES 6-7 (1-1) 2 2.85 1.00 5.70
EJE A, ENTRE EJES 7-8 (1-1) 2 2.10 1.00 4.20
EJE B, ENTRE EJES 1-2 (2b-2b) 2 2.23 1.00 4.46
EJE B, ENTRE EJES 2-3 (2c-2c) 2 3.75 0.00 0.00
EJE B, ENTRE EJES 4-4' (2c-2c) 2 2.00 0.00 0.00
EJE B, ENTRE EJES 4'-5 (2b-2b) 2 2.00 1.00 4.00
EJE B, ENTRE EJES 6-7 (2c-2c) 2 3.35 0.00 0.00
EJE B, ENTRE EJES 7-8 (2c-2c) 2 2.55 0.00 0.00
EJE C, ENTRE EJES 1-2 (3-3) 2 2.23 1.00 4.46
EJE D, ENTRE EJES 1-2 (3-3) 2 2.23 1.00 4.46
EJE E, ENTRE EJES 1-2 (2b-2b) 2 2.23 1.00 4.46
EJE E, ENTRE EJES 2-3' (2b-2b) 2 2.10 1.00 4.20
EJE E, ENTRE EJES 3'-4 (2c-2c) 2 1.65 0.00 0.00
EJE E, ENTRE EJES 4-5 (2c-2c) 2 4.00 0.00 0.00
EJE E, ENTRE EJES 6-7 (2c-2c) 2 3.35 0.00 0.00
EJE A, ENTRE EJES 7-8 (2b-2b) 2 2.45 1.00 4.90
EJE F, ENTRE EJES 1-2 (1a'-1a') 2 1.88 1.00 3.76
EJE F, ENTRE EJES 2-3 (1c-1c) 2 3.25 0.00 0.00
EJE F, ENTRE EJES 3-4 (1-1) 2 2.36 1.00 4.72
EJE F, ENTRE EJES 4-5 (1c-1c) 2 3.50 0.00 0.00
EJE F, ENTRE EJES 5-6 (1-1) 2 2.60 1.00 5.20
EJE F, ENTRE EJES 6-7 (1-1) 2 2.85 1.00 5.70
EJE F, ENTRE EJES 7-8 (1-1) 2 2.10 1.00 4.20
EJE E', ENTRE EJES 3-4 (CC-1) 2 2.86 0.40 2.29
EJE G', ENTRE EJES 1-8 (CC-1) 2 3.73 0.40 2.98
EJE H, ENTRE EJES 1-8 (CC-2) 2 12.97 0.40 10.37
EJE H, ENTRE EJES 1-8 (CC-3) 2 6.75 0.40 5.40
EJE 1, ENTRE EJES A-B (2-2) 2 2.90 1.00 5.80
EJE 1, ENTRE EJES B-C (1a-1a) 2 1.90 1.00 3.80
EJE 1, ENTRE EJES C-D (1-1) 2 1.40 1.00 2.80
EJE 1, ENTRE EJES D-E (1a-1a) 2 1.90 1.00 3.80
EJE 1, ENTRE EJES E-F (1-1) 2 3.00 1.00 6.00
EJE 1, ENTRE EJES G-H (1-1) 2 3.85 1.00 7.70
EJE 2 ENTRE EJES A-B (2c-2c) 2 3.10 0.00 0.00
EJE 2, ENTRE EJES C-D (3a-3a) 2 1.40 0.00 0.00
EJE 2, ENTRE EJES E-F (3-3) 2 3.20 1.00 6.40
EJE 3 ENTRE EJES A-B (2-2) 2 3.10 1.00 6.20
EJE 3, ENTRE EJES E-F (3-3) 2 1.25 1.00 2.50
EJE 3, ENTRE EJES E-F (3a-3a) 2 1.95 0.00 0.00
EJE 4 ENTRE EJES A-B (2c-2c) 2 3.10 0.00 0.00
EJE 4, ENTRE EJES E-F (3-3) 2 2.10 1.00 4.20
EJE 4, ENTRE EJES E-F (3a-3a) 2 1.10 0.00 0.00
EJE 5 ENTRE EJES A-B (2-2) 2 3.10 1.00 6.20
EJE 5, ENTRE EJES E-F (3-3) 2 2.30 1.00 4.60
EJE 5, ENTRE EJES E-F (3a-3a) 2 0.90 0.00 0.00
EJE 4 ENTRE EJES A-B (2c-2c) 2 3.10 0.00 0.00
EJE 4, ENTRE EJES E-F (3-3) 2 3.20 1.00 6.40
EJE 7 ENTRE EJES A-B (2c-2c) 2 3.10 0.00 0.00
EJE 7, ENTRE EJES C-D (3a-3a) 2 2.00 0.00 0.00
EJE 7, ENTRE EJES E-F (3a-3a) 2 3.20 0.00 0.00
EJE 1, ENTRE EJES A-B (2-2) 2 2.40 1.00 4.80
EJE 1, ENTRE EJES B-E (4-4) 2 6.20 0.00 0.00
EJE 1, ENTRE EJES E-F (1-1) 2 2.50 1.00 5.00
EJE 4, ENTRE EJES G-H (CC-2) 2 1.15 0.40 0.92
EJE 5, ENTRE EJES G-H (CC-1) 2 0.70 0.40 0.56
EJE 6, ENTRE EJES G-H (CC-1) 2 2.50 0.40 2.00

06.02.04 FALSO PISO DE E=4" CONCRETO 1:10 (C:H) M2 595.88


interiores - piso porcelanato 1 Área= 465.82 465.82
piso - adoquinado 1 Área= 93.24 93.24
piso - cemento bruñado 1 Área= 36.82 36.82

06.02.05 SOLADO DE 4" EN ZAPATAS CON MEZCLA 1:12 CEMENTO HORMIGON M2 305.52
EJE A, ENTRE EJES 1-2 (1a-1a) 1 1.88 0.00 0.00
EJE A, ENTRE EJES 2-3 (1-1) 1 3.25 0.60 1.95
EJE A, ENTRE EJES 3-4 (1-1) 1 2.36 0.60 1.42
EJE A, ENTRE EJES 4-5 (1-1) 1 3.50 0.60 2.10
EJE A, ENTRE EJES 5-6 (1-1) 1 2.60 0.60 1.56
EJE A, ENTRE EJES 6-7 (1-1) 1 2.85 0.60 1.71
EJE A, ENTRE EJES 7-8 (1-1) 1 2.10 0.60 1.26
EJE B, ENTRE EJES 1-2 (2b-2b) 1 2.23 0.60 1.34
EJE B, ENTRE EJES 2-3 (2c-2c) 1 3.75 0.60 2.25
EJE B, ENTRE EJES 4-4' (2c-2c) 1 2.00 0.60 1.20
EJE B, ENTRE EJES 4'-5 (2b-2b) 1 2.00 0.60 1.20
EJE B, ENTRE EJES 6-7 (2c-2c) 1 3.35 0.60 2.01
EJE B, ENTRE EJES 7-8 (2c-2c) 1 2.55 0.60 1.53
EJE C, ENTRE EJES 1-2 (3-3) 1 2.23 0.60 1.34
EJE D, ENTRE EJES 1-2 (3-3) 1 2.23 0.60 1.34
EJE E, ENTRE EJES 1-2 (2b-2b) 1 2.23 0.60 1.34
EJE E, ENTRE EJES 2-3' (2b-2b) 1 2.10 0.60 1.26
EJE E, ENTRE EJES 3'-4 (2c-2c) 1 1.65 0.60 0.99
EJE E, ENTRE EJES 4-5 (2c-2c) 1 4.00 0.60 2.40
EJE E, ENTRE EJES 6-7 (2c-2c) 1 3.35 0.60 2.01
EJE A, ENTRE EJES 7-8 (2b-2b) 1 2.45 0.60 1.47
EJE F, ENTRE EJES 1-2 (1a'-1a') 1 1.88 0.00 0.00
EJE F, ENTRE EJES 2-3 (1c-1c) 1 3.25 0.60 1.95
EJE F, ENTRE EJES 3-4 (1-1) 1 2.36 0.60 1.42
EJE F, ENTRE EJES 4-5 (1c-1c) 1 3.50 0.60 2.10
EJE F, ENTRE EJES 5-6 (1-1) 1 2.60 0.60 1.56
EJE F, ENTRE EJES 6-7 (1-1) 1 2.85 0.60 1.71
EJE F, ENTRE EJES 7-8 (1-1) 1 2.10 0.60 1.26
EJE E', ENTRE EJES 3-4 (CC-1) 1 2.86 0.00 0.00
EJE G', ENTRE EJES 1-8 (CC-1) 1 3.73 0.00 0.00
EJE H, ENTRE EJES 1-8 (CC-2) 1 12.97 0.00 0.00
EJE H, ENTRE EJES 1-8 (CC-3) 1 6.75 0.00 0.00
EJE 1, ENTRE EJES A-B (2-2) 1 2.90 0.60 1.74
EJE 1, ENTRE EJES B-C (1a-1a) 1 1.90 0.00 0.00
EJE 1, ENTRE EJES C-D (1-1) 1 1.40 0.60 0.84
EJE 1, ENTRE EJES D-E (1a-1a) 1 1.90 0.00 0.00
EJE 1, ENTRE EJES E-F (1-1) 1 3.00 0.60 1.80
EJE 1, ENTRE EJES G-H (1-1) 1 3.85 0.60 2.31
EJE 2 ENTRE EJES A-B (2c-2c) 1 3.10 0.60 1.86
EJE 2, ENTRE EJES C-D (3a-3a) 1 1.40 0.60 0.84
EJE 2, ENTRE EJES E-F (3-3) 1 3.20 0.60 1.92
EJE 3 ENTRE EJES A-B (2-2) 1 3.10 0.60 1.86
EJE 3, ENTRE EJES E-F (3-3) 1 1.25 0.60 0.75
EJE 3, ENTRE EJES E-F (3a-3a) 1 1.95 0.60 1.17
EJE 4 ENTRE EJES A-B (2c-2c) 1 3.10 0.60 1.86
EJE 4, ENTRE EJES E-F (3-3) 1 2.10 0.60 1.26
EJE 4, ENTRE EJES E-F (3a-3a) 1 1.10 0.60 0.66
EJE 5 ENTRE EJES A-B (2-2) 1 3.10 0.60 1.86
EJE 5, ENTRE EJES E-F (3-3) 1 2.30 0.60 1.38
EJE 5, ENTRE EJES E-F (3a-3a) 1 0.90 0.60 0.54
EJE 4 ENTRE EJES A-B (2c-2c) 1 3.10 0.60 1.86
EJE 4, ENTRE EJES E-F (3-3) 1 3.20 0.60 1.92
EJE 7 ENTRE EJES A-B (2c-2c) 1 3.10 0.60 1.86
EJE 7, ENTRE EJES C-D (3a-3a) 1 2.00 0.60 1.20
EJE 7, ENTRE EJES E-F (3a-3a) 1 3.20 0.60 1.92
EJE 1, ENTRE EJES A-B (2-2) 1 2.40 0.60 1.44
EJE 1, ENTRE EJES B-E (4-4) 1 6.20 1.00 6.20
EJE 1, ENTRE EJES E-F (1-1) 1 2.50 0.60 1.50
EJE 4, ENTRE EJES G-H (CC-2) 1 1.15 0.00 0.00
EJE 5, ENTRE EJES G-H (CC-1) 1 0.70 0.00 0.00
EJE 6, ENTRE EJES G-H (CC-1) 1 2.50 0.00 0.00
Z-1 6 2.40 2.15 30.96
Z-2 3 2.00 2.30 13.80
Z-2' 2 2.00 2.75 11.00
Z-3 2 2.17 2.40 10.42
Z-4 1 2.40 2.65 6.36
Z-5 2 1.60 1.30 4.16
Z-5' 1 1.05 1.30 1.37
Z-6 1 1.20 1.20 1.44
ZC-1 6 1.40 4.25 35.70
ZC-2 1 4.10 2.60 10.66
ZC-2' 1 3.90 2.30 8.97
ZC-3 1 Area: 3.02 3.02
ZP-1 4 5.40 2.80 60.48
ZP-2 1 Area: 24.98 24.98

06.02.06 PISO DE 4" CONCRETO F'C 140 KG/CM2 X 4 CM. + PULIDO 1:2 X BRUÑADO:1CM M2 36.82
piso - cemento bruñado 1 Área= 36.82 36.82

06.03 OBRAS DE CONCRETO ARMADO


06.03.01 ZAPATAS
06.03.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 M3 111.65
Z-1 6 2.40 2.15 0.50 15.48
Z-2 3 2.00 2.30 0.50 6.90
Z-2' 2 2.00 2.75 0.50 5.50
Z-3 2 2.17 2.40 0.50 5.21
Z-4 1 2.40 2.65 0.50 3.18
Z-5 2 1.60 1.30 0.50 2.08
Z-5' 1 1.05 1.30 0.50 0.68
Z-6 1 1.20 1.20 0.50 0.72
ZC-1 6 1.40 4.25 0.50 17.85
ZC-2 1 4.10 2.60 0.50 5.33
ZC-2' 1 3.90 2.30 0.50 4.49
ZC-3 1 Area: 3.02 0.50 1.51
ZP-1 4 5.40 2.80 0.50 30.24
ZP-2 1 Area: 24.98 0.50 12.49

06.03.01.02 ACERO GRADO 60 EN ZAPATAS KG VER DETALLE DE PLANILLA DE ACERO 6284.13 6,284.13

06.03.02 VIGA DE CIMENTACION


06.03.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C=210 KG/CM2 M3 37.38
VC-101
EJE 1 1 14.95 0.40 0.70 4.19
EJE 2 1 3.10 0.40 0.70 0.87
EJE 3 1 3.10 0.40 0.70 0.87
EJE 4 1 3.10 0.40 0.70 0.87
EJE 5 1 3.10 0.40 0.70 0.87
EJE 6 1 3.10 0.40 0.70 0.87
EJE 7 1 3.10 0.40 0.70 0.87
EJE 8 1 11.10 0.40 0.70 3.11
EJE A 1 18.54 0.40 0.70 5.19
EJE B 1 15.78 0.40 0.70 4.42
EJE E 1 15.78 0.40 0.70 4.42
EJE F 1 18.54 0.40 0.70 5.19
VC-102
EJE C 1 2.23 0.30 0.70 0.47
EJE D 1 2.23 0.30 0.70 0.47
EJE 2 1 6.50 0.30 0.70 1.37
EJE 3 1 3.20 0.30 0.70 0.67
EJE 4 1 3.20 0.30 0.70 0.67
EJE 5 1 3.20 0.30 0.70 0.67
EJE 6 1 3.20 0.30 0.70 0.67
EJE 7 1 3.20 0.30 0.70 0.67

06.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS DE CIMENTACION M2 196.35


VC-101
EJE 1 2.00 14.95 0.70 20.93
EJE 2 2.00 3.10 0.70 4.34
EJE 3 2.00 3.10 0.70 4.34
EJE 4 2.00 3.10 0.70 4.34
EJE 5 2.00 3.10 0.70 4.34
EJE 6 2.00 3.10 0.70 4.34
EJE 7 2.00 3.10 0.70 4.34
EJE 8 2.00 11.10 0.70 15.54
EJE A 2.00 18.54 0.70 25.96
EJE B 2.00 15.78 0.70 22.09
EJE E 2.00 15.78 0.70 22.09
EJE F 2.00 18.54 0.70 25.96
VC-102
EJE C 2.00 2.23 0.70 3.12
EJE D 2.00 2.23 0.70 3.12
EJE 2 2.00 6.50 0.70 9.10
EJE 3 2.00 3.20 0.70 4.48
EJE 4 2.00 3.20 0.70 4.48
EJE 5 2.00 3.20 0.70 4.48
EJE 6 2.00 3.20 0.70 4.48
EJE 7 2.00 3.20 0.70 4.48

06.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION KG VER DETALLE DE PLANILLA DE ACERO 3115.35 3,115.35

06.03.04 COLUMNAS
06.03.04.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 135.52
PRIMER PISO 57.75
C-1 2 Área: 0.38 5.00 3.75
C-1' 6 Área: 0.35 5.00 10.50
C-2 12 Área: 0.43 5.00 25.50
C-3 2 Área: 0.20 5.00 2.00
C-4 4 Área: 0.24 5.00 4.80
C-5 12 Área: 0.15 5.00 9.00
CP-1 2 0.30 0.40 3.60 0.86
CA-1A 4 0.15 0.15 3.60 0.32
CA-2 3 0.20 0.20 3.60 0.43
CB-1 1 0.20 0.20 3.60 0.14
CB-2 3 0.20 0.20 3.60 0.43
SEGUNDO PISO 38.89
C-1 2 Área: 0.38 3.50 2.63
C-1' 6 Área: 0.35 3.50 7.35
C-2 12 Área: 0.43 3.50 17.85
C-3 2 Área: 0.20 3.50 1.40
C-4 4 Área: 0.24 3.50 3.36
C-5 12 Área: 0.15 3.50 6.30
TERCER PISO 38.89
C-1 2 Área: 0.38 3.50 2.63
C-1' 6 Área: 0.35 3.50 7.35
C-2 12 Área: 0.43 3.50 17.85
C-3 2 Área: 0.20 3.50 1.40
C-4 4 Área: 0.24 3.50 3.36
C-5 12 Área: 0.15 3.50 6.30

06.03.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN COLUMNAS M2 1,238.04


PRIMER PISO 540.84
C-1 2 Perímetro: 3.20 5.00 32.00
C-1' 6 Perímetro: 3.00 5.00 90.00
C-2 12 Perímetro: 3.60 5.00 216.00
C-3 2 Perímetro: 2.00 5.00 20.00
C-4 4 Perímetro: 2.20 5.00 44.00
C-5 12 Perímetro: 1.60 5.00 96.00
CP-1 2 Perímetro: 1.40 3.60 10.08
CA-1A 4 Perímetro: 0.70 3.60 10.08
CA-2 3 Perímetro: 0.90 3.60 9.72
CB-1 1 Perímetro: 1.20 3.60 4.32
CB-2 3 Perímetro: 0.80 3.60 8.64
SEGUNDO PISO 348.60
C-1 2 Perímetro: 3.20 3.50 22.40
C-1' 6 Perímetro: 3.00 3.50 63.00
C-2 12 Perímetro: 3.60 3.50 151.20
C-3 2 Perímetro: 2.00 3.50 14.00
C-4 4 Perímetro: 2.20 3.50 30.80
C-5 12 Perímetro: 1.60 3.50 67.20
TERCER PISO 348.60
C-1 2 Perímetro: 3.20 3.50 22.40
C-1' 6 Perímetro: 3.00 3.50 63.00
C-2 12 Perímetro: 3.60 3.50 151.20
C-3 2 Perímetro: 2.00 3.50 14.00
C-4 4 Perímetro: 2.20 3.50 30.80
C-5 12 Perímetro: 1.60 3.50 67.20

06.03.04.03 ACERO GRADO 60 EN COLUMNAS KG VER DETALLE DE PLANILLA DE ACERO 16983.88 16,983.88

06.03.05 COLUMNAS Y VIGAS DE AMARRE


06.03.05.01 COLUMNAS Y VIGAS DE AMARRE CONCRETO F'C=175 KG/CM2 M3 12.81
PRIMER PISO 6.23
EJE A CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-2 3 0.20 0.15 2.88 0.26
EJE B CA-1 2 0.20 0.15 2.88 0.17
EJE E CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 1.00 0.06
EJE F CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE H CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE 1 CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-2 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE 3 CA-1 2 0.20 0.15 2.88 0.17
EJE 4 CA-1 2 0.20 0.15 2.88 0.17
EJE 5 CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE 6 CA-1 2 0.20 0.15 2.88 0.17
EJE 8 CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06

V-A
EJE 1 1 12.39 0.15 0.10 0.19
EJE 3 1 2.65 0.15 0.10 0.04
EJE 4 1 1.50 0.15 0.10 0.02
EJE 5 1 4.53 0.15 0.10 0.07
EJE 6 1 4.23 0.15 0.10 0.06
EJE 8 1 4.00 0.15 0.10 0.06
EJE A 1 15.39 0.15 0.10 0.23
EJE B 1 1.57 0.15 0.10 0.02
EJE E 1 3.68 0.15 0.10 0.06
EJE F 1 9.54 0.15 0.10 0.14
EJE G' 1 2.20 0.15 0.10 0.03
EJE H 1 13.63 0.15 0.10 0.20
SEGUNDO PISO 3.24
EJE A CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE F CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 2.88 0.17
EJE 1 CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.00 0.12
CA-2 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.00 0.12
CA-1 2 0.20 0.15 2.88 0.17
EJE 4 CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE 8 CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06

V-A
EJE 1 1 2.55 0.15 0.10 0.04
EJE 4 1 1.53 0.15 0.10 0.02
EJE 8 1 4.00 0.15 0.10 0.06
EJE A 1 13.00 0.15 0.10 0.20
EJE F 1 13.00 0.15 0.10 0.20
TERCER PISO 3.34
EJE A CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE B CA-1 2 0.20 0.15 1.00 0.06
EJE F CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 2.35 0.14
EJE 1 CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 2.88 0.17
CA-2 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
CA-1 2 0.20 0.15 2.88 0.17
EJE 8 CA-1 2 0.20 0.15 1.00 0.06
CA-1 2 0.20 0.15 1.00 0.06
CA-1 1 0.20 0.15 2.88 0.09

V-A
EJE 1 1 8.85 0.15 0.10 0.13
EJE 5 1 4.53 0.15 0.10 0.07
EJE 7 1 1.25 0.15 0.10 0.02
EJE 8 1 4.00 0.15 0.10 0.06
EJE A 1 13.00 0.15 0.10 0.20
EJE B 1 5.55 0.15 0.10 0.08
EJE F 1 3.08 0.15 0.10 0.05
EJE F' 1 5.20 0.15 0.10 0.08

06.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Y VIGAS DE AMARRE M2 170.75


PRIMER PISO 83.01
EJE A CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-2 3 Perímetro: 0.40 2.88 3.45
EJE B CA-1 2 Perímetro: 0.40 2.88 2.30
EJE E CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 1.00 0.80
EJE F CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE H CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 1 CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-2 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 3 CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 4 CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 5 CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 6 CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 8 CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80

V-A
EJE 1 1 12.39 Perímetro: 0.20 2.48
EJE 3 1 2.65 Perímetro: 0.20 0.53
EJE 4 1 1.50 Perímetro: 0.20 0.30
EJE 5 1 4.53 Perímetro: 0.20 0.91
EJE 6 1 4.23 Perímetro: 0.20 0.85
EJE 8 1 4.00 Perímetro: 0.20 0.80
EJE A 1 15.39 Perímetro: 0.20 3.08
EJE B 1 1.57 Perímetro: 0.20 0.31
EJE E 1 3.68 Perímetro: 0.20 0.74
EJE F 1 9.54 Perímetro: 0.20 1.91
EJE G' 1 2.20 Perímetro: 0.20 0.44
EJE H 1 13.63 Perímetro: 0.20 2.73
SEGUNDO PISO 43.22
EJE A CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE F CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 1 CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.00 1.60
CA-2 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.00 1.60
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 4 CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 8 CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80

V-A
EJE 1 1 2.55 Perímetro: 0.20 0.51
EJE 4 1 1.53 Perímetro: 0.20 0.31
EJE 8 1 4.00 Perímetro: 0.20 0.80
EJE A 1 13.00 Perímetro: 0.20 2.60
EJE F 1 13.00 Perímetro: 0.20 2.60
TERCER PISO 44.53
EJE A CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE B CA-1 2 Perímetro: 0.40 1.00 0.80
EJE F CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 2.35 1.88
EJE 1 CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-2 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
CA-1 2 Perímetro: 0.40 2.88 2.30
EJE 8 CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 2 Perímetro: 0.40 1.00 0.80
CA-1 1 Perímetro: 0.40 2.88 1.15

V-A
EJE 1 1 8.85 Perímetro: 0.20 1.77
EJE 5 1 4.53 Perímetro: 0.20 0.91
EJE 7 1 1.25 Perímetro: 0.20 0.25
EJE 8 1 4.00 Perímetro: 0.20 0.80
EJE A 1 13.00 Perímetro: 0.20 2.60
EJE B 1 5.55 Perímetro: 0.20 1.11
EJE F 1 3.08 Perímetro: 0.20 0.62
EJE F' 1 5.20 Perímetro: 0.20 1.04

06.03.05.03 ACERO GRADO 60 EN COLUMNAS Y VIGAS DE AMARRE KG VER DETALLE DE PLANILLA DE ACERO 1578.78 1,578.78

06.03.06 VIGAS
06.03.06.01 CONCRETO EN VIGAS F'C=210 KG/CM2 M3 94.28
PRIMER PISO 33.15
EJE 1 VP-101 1 14.95 0.30 0.50 2.24
EJE 2 VP-101 1 15.45 0.30 0.50 2.32
EJE 3 VP-101 1 16.45 0.30 0.50 2.47
EJE 4 VP-101 1 13.35 0.30 0.50 2.00
EJE 5 VP-101 1 9.50 0.30 0.50 1.43
EJE 6 VP-101 1 10.10 0.30 0.50 1.52
EJE 7 VP-101 1 12.40 0.30 0.50 1.86
EJE 8 VP-101 1 11.10 0.30 0.50 1.67
EJE 9 VP-101 1 6.20 0.30 0.50 0.93
EJE 9' VP-101 1 1.15 0.30 0.50 0.17
EJE 10 VP-101 1 6.20 0.30 0.50 0.93
EJE 5 VS-103 1 1.00 0.20 0.30 0.06
EJE 6 VS-103 1 1.20 0.20 0.30 0.07
EJE 9' VB-101 1 3.90 0.20 0.20 0.16
EJE 9'' VB-101 1 3.90 0.20 0.20 0.16
EJE A' VB-102 1 6.21 0.20 0.50 0.62
EJE A VS-101 1 18.54 0.25 0.40 1.85
EJE B VS-101 1 15.78 0.25 0.40 1.58
EJE B VS-102 1 5.39 0.25 0.50 0.67
EJE C VCH-101 1 5.08 0.75 0.20 0.76
EJE C VB-101 1 20.50 0.20 0.20 0.82
EJE D VCH-101 1 5.08 0.75 0.20 0.76
EJE D VB-101 1 20.50 0.20 0.20 0.82
EJE E VS-101 1 15.78 0.25 0.40 1.58
EJE E VS-102 1 5.39 0.25 0.50 0.67
EJE E' VCH-102 1 2.86 0.25 0.20 0.14
EJE F VS-101 1 18.54 0.25 0.40 1.85
EJE G VS-101 1 12.39 0.25 0.40 1.24
EJE G' VP-101 1 3.35 0.30 0.50 0.50
EJE G' VS-103 1 3.30 0.20 0.30 0.20
EJE H VS-101 1 9.04 0.25 0.40 0.90
EJE H VS-103 1 3.30 0.20 0.30 0.20
SEGUNDO PISO 30.56
EJE 1 VP-101 1 11.05 0.30 0.50 1.66
EJE 2 VP-101 1 12.40 0.30 0.50 1.86
EJE 3 VP-101 1 13.40 0.30 0.50 2.01
EJE 4 VP-101 1 10.40 0.30 0.50 1.56
EJE 5 VP-101 1 10.40 0.30 0.50 1.56
EJE 6 VP-101 1 11.00 0.30 0.50 1.65
EJE 7 VP-101 1 13.30 0.30 0.50 2.00
EJE 8 VP-101 1 11.10 0.30 0.50 1.67
EJE 9 VP-101 1 6.20 0.30 0.50 0.93
EJE 9' VP-101 1 1.15 0.30 0.50 0.17
EJE 10 VP-101 1 6.20 0.30 0.50 0.93
EJE 9' VB-101 1 3.90 0.20 0.20 0.16
EJE 9'' VB-101 1 3.90 0.20 0.20 0.16
EJE A' VB-102 1 6.21 0.20 0.50 0.62
EJE A VS-101 1 18.54 0.25 0.40 1.85
EJE B VS-101 1 15.78 0.25 0.40 1.58
EJE B VS-102 1 5.39 0.25 0.50 0.67
EJE C VCH-101 1 5.08 0.75 0.20 0.76
EJE C VB-101 1 20.50 0.20 0.20 0.82
EJE D VCH-101 1 5.08 0.75 0.20 0.76
EJE D VB-101 1 20.50 0.20 0.20 0.82
EJE E VS-101 1 15.78 0.25 0.40 1.58
EJE E VS-102 1 5.39 0.25 0.50 0.67
EJE E' VCH-102 1 2.65 0.25 0.20 0.13
EJE F VS-101 1 18.54 0.25 0.40 1.85
EJE F' VB-102 1 17.06 0.25 0.50 2.13
TERCER PISO 30.56
EJE 1 VP-101 1 11.05 0.30 0.50 1.66
EJE 2 VP-101 1 12.40 0.30 0.50 1.86
EJE 3 VP-101 1 13.40 0.30 0.50 2.01
EJE 4 VP-101 1 10.40 0.30 0.50 1.56
EJE 5 VP-101 1 10.40 0.30 0.50 1.56
EJE 6 VP-101 1 11.00 0.30 0.50 1.65
EJE 7 VP-101 1 13.30 0.30 0.50 2.00
EJE 8 VP-101 1 11.10 0.30 0.50 1.67
EJE 9 VP-101 1 6.20 0.30 0.50 0.93
EJE 9' VP-101 1 1.15 0.30 0.50 0.17
EJE 10 VP-101 1 6.20 0.30 0.50 0.93
EJE 9' VB-101 1 3.90 0.20 0.20 0.16
EJE 9'' VB-101 1 3.90 0.20 0.20 0.16
EJE A' VB-102 1 6.21 0.20 0.50 0.62
EJE A VS-101 1 18.54 0.25 0.40 1.85
EJE B VS-101 1 15.78 0.25 0.40 1.58
EJE B VS-102 1 5.39 0.25 0.50 0.67
EJE C VCH-101 1 5.08 0.75 0.20 0.76
EJE C VB-101 1 20.50 0.20 0.20 0.82
EJE D VCH-101 1 5.08 0.75 0.20 0.76
EJE D VB-101 1 20.50 0.20 0.20 0.82
EJE E VS-101 1 15.78 0.25 0.40 1.58
EJE E VS-102 1 5.39 0.25 0.50 0.67
EJE E' VCH-102 1 2.65 0.25 0.20 0.13
EJE F VS-101 1 18.54 0.25 0.40 1.85
EJE F' VB-102 1 17.06 0.25 0.50 2.13

06.03.06.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN VIGAS M2 692.44


PRIMER PISO 225.03
EJE 1 VP-101 1 14.95 Perímetro 1.10 16.45
EJE 2 VP-101 1 15.45 Perímetro 0.90 13.91
EJE 3 VP-101 1 16.45 Perímetro 0.90 14.81
EJE 4 VP-101 1 13.35 Perímetro 0.90 12.02
EJE 5 VP-101 1 9.50 Perímetro 0.90 8.55
EJE 6 VP-101 1 10.10 Perímetro 0.90 9.09
EJE 7 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.10 6.82
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 0.90 5.58
EJE 5 VS-103 1 1.00 Perímetro 0.60 0.60
EJE 6 VS-103 1 1.20 Perímetro 0.60 0.72
EJE 9' VB-101 1 3.90 Perímetro 0.20 0.78
EJE 9'' VB-101 1 3.90 Perímetro 0.20 0.78
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.86 Perímetro 0.25 0.72
EJE F VS-101 1 18.54 Perímetro 0.85 15.76
EJE G VS-101 1 12.39 Perímetro 0.85 10.53
EJE G' VP-101 1 3.35 Perímetro 1.30 4.36
EJE G' VS-103 1 3.30 Perímetro 0.50 1.65
EJE H VS-101 1 9.04 Perímetro 0.85 7.68
EJE H VS-103 1 3.30 Perímetro 0.50 1.65
SEGUNDO PISO 233.70
EJE 1 VP-101 1 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.65 Perímetro 0.25 0.66
EJE F VS-101 1 3.98 Perímetro 0.85 3.38
EJE F VS-101 1 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1 17.06 Perímetro 1.00 17.06
TERCER PISO 233.70
EJE 1 VP-101 1 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.65 Perímetro 0.25 0.66
EJE F VS-101 1 3.98 Perímetro 0.85 3.38
EJE F VS-101 1 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1 17.06 Perímetro 1.00 17.06

06.03.06.03 ACERO GRADO 60 EN VIGAS KG VER DETALLE DE PLANILLA DE ACERO 16629.78 16,629.78

06.03.07 LOSA ALIGERADA


06.03.07.01 CONCRETO EN LOSA ALIGERADA F'C=210 KG/CM2 M3 Coef. 71.29
PRIMER PISO 24.65
ENTRE EJES 1-2 1 Área: 32.44 0.0875 2.84
ENTRE EJES 2-3 1 Área: 50.06 0.0875 4.38
ENTRE EJES 3-4 1 Área: 43.47 0.0875 3.80
ENTRE EJES 4-5 1 Área: 46.80 0.0875 4.10
ENTRE EJES 5-6 1 Área: 40.52 0.0875 3.55
ENTRE EJES 6-7 1 Área: 42.88 0.0875 3.75
ENTRE EJES 7-8 1 Área: 25.59 0.0875 2.24
SEGUNDO PISO 23.32
ENTRE EJES 1-2 1 Área: 21.63 0.0875 1.89
ENTRE EJES 2-3 1 Área: 33.38 0.0875 2.92
ENTRE EJES 3-4 1 Área: 36.89 0.0875 3.23
ENTRE EJES 4-5 1 Área: 56.20 0.0875 4.92
ENTRE EJES 5-6 1 Área: 49.92 0.0875 4.37
ENTRE EJES 6-7 1 Área: 42.88 0.0875 3.75
ENTRE EJES 7-8 1 Área: 25.59 0.0875 2.24
TERCER PISO 23.32
ENTRE EJES 1-2 1 Área: 21.63 0.0875 1.89
ENTRE EJES 2-3 1 Área: 33.38 0.0875 2.92
ENTRE EJES 3-4 1 Área: 36.89 0.0875 3.23
ENTRE EJES 4-5 1 Área: 56.20 0.0875 4.92
ENTRE EJES 5-6 1 Área: 49.92 0.0875 4.37
ENTRE EJES 6-7 1 Área: 42.88 0.0875 3.75
ENTRE EJES 7-8 1 Área: 25.59 0.0875 2.24

06.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERADA M2 814.72


PRIMER PISO 281.76
ENTRE EJES 1-2 1 Área: 32.44 32.44
ENTRE EJES 2-3 1 Área: 50.06 50.06
ENTRE EJES 3-4 1 Área: 43.47 43.47
ENTRE EJES 4-5 1 Área: 46.80 46.80
ENTRE EJES 5-6 1 Área: 40.52 40.52
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59
SEGUNDO PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59
TERCER PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59

06.03.07.03 ACERO GRADO 60 EN LOSA ALIGERADA KG VER DETALLE DE PLANILLA DE ACERO 4167.64 4,167.64

06.03.07.04 LADRILLO HUECO DE ARCILLA H=15 PARA TECHO ALIGERADO UND 6,787.00
PRIMER PISO 2,347.06
ENTRE EJES 1-2 1 Área: 32.44 8.33 270.23
ENTRE EJES 2-3 1 Área: 50.06 8.33 417.02
ENTRE EJES 3-4 1 Área: 43.47 8.33 362.12
ENTRE EJES 4-5 1 Área: 46.80 8.33 389.84
ENTRE EJES 5-6 1 Área: 40.52 8.33 337.53
ENTRE EJES 6-7 1 Área: 42.88 8.33 357.19
ENTRE EJES 7-8 1 Área: 25.59 8.33 213.12
SEGUNDO PISO 2,219.79
ENTRE EJES 1-2 1 Área: 21.63 8.33 180.15
ENTRE EJES 2-3 1 Área: 33.38 8.33 278.01
ENTRE EJES 3-4 1 Área: 36.89 8.33 307.33
ENTRE EJES 4-5 1 Área: 56.20 8.33 468.15
ENTRE EJES 5-6 1 Área: 49.92 8.33 415.83
ENTRE EJES 6-7 1 Área: 42.88 8.33 357.19
ENTRE EJES 7-8 1 Área: 25.59 8.33 213.12
TERCER PISO 2,219.79
ENTRE EJES 1-2 1 Área: 21.63 8.33 180.15
ENTRE EJES 2-3 1 Área: 33.38 8.33 278.01
ENTRE EJES 3-4 1 Área: 36.89 8.33 307.33
ENTRE EJES 4-5 1 Área: 56.20 8.33 468.15
ENTRE EJES 5-6 1 Área: 49.92 8.33 415.83
ENTRE EJES 6-7 1 Área: 42.88 8.33 357.19
ENTRE EJES 7-8 1 Área: 25.59 8.33 213.12

06.03.08 MESON DE CONCRETO


06.03.08.01 CONCRETO F'C=175 KG/CM2 M3 0.64
PRIMER PISO
mesa de partes 1 Área: 1.05 0.10 0.11
SEGUNDO PISO
vestidor varones 1 Área: 1.08 0.10 0.11
vestidor damas 1 Área: 1.17 0.10 0.12
cafetería 2 0.50 3.10 0.10 0.31

06.03.08.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 10.52


PRIMER PISO
mesa de partes 1 1.80 0.50 0.90
2 0.50 0.80 0.80
SEGUNDO PISO
vestidor varones 1 2.43 0.50 1.22
2 0.50 0.80 0.80
vestidor damas 1 2.60 0.50 1.30
2 0.50 0.80 0.80
cafetería 2 3.10 0.50 3.10
4 0.50 0.80 1.60

06.03.08.03 ACERO ESTRUCTURAL F'Y=4200 KG/CM2 KG VER DETALLE DE PLANILLA DE ACERO 87.64 87.64
Item Descripción Und. cantidad Largo Ancho Alto Parcial Total

06.04 ALBAÑILERÍA Y TABIQUES


06.04.01 MURO DE LADRILLO DE ARCILLA DE SOGA MEZCLA 1:5 X 1.5 CM. M2 607.81
PRIMER PISO 253.64
EJE A 1 1.43 2.88 4.11
1 2.80 2.88 8.05
1 1.91 2.88 5.49
1 3.05 2.88 8.77
1 2.15 2.88 6.18
1 2.40 2.88 6.90
1 1.65 2.88 4.74
EJE B 1 1.83 2.88 5.26
1 1.58 0.90 1.42
EJE C 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE D 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE E 1 1.78 2.88 5.12
1 1.69 0.90 1.52
1 0.75 2.88 2.16
1 2.00 2.88 5.75
EJE E' 1 3.06 2.88 8.80
EJE F 1 1.43 2.88 4.11
1 1.91 2.88 5.49
1 2.15 2.88 6.18
1 2.40 2.88 6.90
1 1.65 2.88 4.74
EJE G' 1 2.20 2.88 6.33
EJE H 1 1.98 2.88 5.69
1 3.30 2.88 9.49
1 2.41 2.88 6.93
1 1.58 2.88 4.53
1 1.53 2.88 4.38
1 2.99 2.88 8.59
1 2.99 2.88 8.59
EJE 1 1 2.45 2.88 7.04
1 1.45 2.88 4.17
1 1.45 2.88 4.17
1 2.55 2.88 7.33
1 3.40 2.88 9.78
EJE 2 1 0.90 2.88 2.59
1 0.90 2.88 2.59
EJE 3 1 2.65 2.88 7.62
1 0.90 2.25 2.03
EJE 4 1 1.50 2.88 4.31
1 0.95 2.88 2.73
EJE 5 1 2.65 2.88 7.62
1 1.88 2.88 5.39
1 1.00 1.00 1.00
EJE 6 1 2.75 2.88 7.91
1 1.48 2.88 4.24
1 1.20 2.88 3.45
EJE 8 1 1.95 1.00 1.95
1 2.05 1.00 2.05
SEGUNDO NIVEL 178.03
EJE A 1 1.43 2.88 4.11
1 2.80 2.88 8.05
1 3.16 1.00 3.16
1 3.05 2.88 8.77
1 2.15 2.88 6.18
1 3.65 1.00 3.65
1 1.65 2.88 4.74
EJE B 1 1.83 2.88 5.26
1 2.00 1.00 2.00
EJE C 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE D 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE E 1 1.78 2.88 5.12
1 2.90 2.88 8.34
1 1.90 1.00 1.90
EJE E' 1 3.11 2.88 8.94
EJE F 1 1.43 2.88 4.11
1 2.80 2.88 8.05
1 1.91 1.00 1.91
1 3.05 1.00 3.05
1 2.15 1.00 2.15
1 3.55 2.88 10.21
1 1.65 2.88 4.74
EJE 1 1 2.45 2.88 7.04
1 1.45 2.88 4.17
1 1.45 2.88 4.17
1 2.55 2.88 7.33
EJE 2 1 0.90 2.88 2.59
1 0.90 2.88 2.59
1 0.75 2.88 2.16
EJE 3 1 2.65 2.88 7.62
1 0.80 2.88 2.30
EJE 4 1 0.45 2.88 1.29
1 2.55 2.88 7.33
EJE 5 1 1.62 2.88 4.64
EJE 6 1 0.45 2.88 1.29
1 0.75 2.88 2.16
EJE 7 1 0.45 2.88 1.29
1 0.75 2.88 2.16
EJE 8 1 1.95 1.00 1.95
1 2.05 1.00 2.05
TERCER NIVEL 176.14
EJE A 1 1.43 2.88 4.11
1 2.80 2.88 8.05
1 3.01 1.00 3.01
1 3.05 2.88 8.77
1 2.15 2.88 6.18
1 3.65 1.00 3.65
1 1.65 2.88 4.74
EJE B 1 1.78 2.88 5.12
1 3.55 1.00 3.55
1 2.00 2.88 5.75
EJE C 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE D 1 0.85 2.25 1.91
1 0.98 2.88 2.82
EJE E 1 1.78 2.88 5.12
1 2.00 2.88 5.75
1 1.90 2.88 5.46
EJE E' 1 2.68 2.88 7.69
EJE F 1 1.43 2.88 4.11
1 4.15 2.88 11.93
1 3.75 2.88 10.78
1 1.65 2.88 4.74
EJE 1 1 0.90 1.00 0.90
1 0.65 2.88 1.87
1 0.90 1.00 0.90
1 1.45 2.88 4.17
1 1.45 2.88 4.17
1 2.55 2.88 7.33
EJE 2 1 0.90 2.88 2.59
1 0.90 2.88 2.59
1 0.75 2.88 2.16
EJE 3 1 0.43 2.88 1.22
1 0.73 2.88 2.08
EJE 4 1 0.45 2.88 1.29
EJE 5 1 2.65 2.88 7.62
1 1.88 2.88 5.39
EJE 6 1 0.45 2.88 1.29
1 0.75 2.88 2.16
EJE 7 1 0.45 2.88 1.29
1 1.17 2.88 3.36
1 0.75 2.88 2.16
EJE 8 1 1.95 1.00 1.95
1 1.67 1.00 1.67

06.04.02 MURO DE LADRILLO KING KONG DE ARCILLA DE CABEZA MEZCLA 1:4 X 1.5 CM. M2 8.19
PRIMER NIVEL 2.73
EJE 1 1 0.95 2.88 2.73
SEGUNDO NIVEL 2.73
EJE 1 1 0.95 2.88 2.73
TERCER NIVEL 2.73
EJE 1 1 0.95 2.88 2.73

06.04.03 TABIQUERIA DE SISTEMA DRYWALL M2 21.15


SEGUNDO NIVEL 6.60
EJE 2 1 2.20 3.00 6.60
TERCER NIVEL 14.55
EJE 2 1 1.95 3.00 5.85
EJE E' 1 2.90 3.00 8.70

06.05 CUBIERTAS
06.05.01 CUBIERTA LADRILLO PASTELERO DE 20X20CM.+FRAGUA CON MORTERO 1:5 M2 379.84
AZOTEA
terraza area= 379.84 379.84

06.05.02 IMPERMEABILIZACION DE LADRILLO PASTELERO CON ASFALTO M2 379.84


AZOTEA
terraza area= 379.84 379.84

06.06 REVOQUES Y ENLUCIDOS


06.06.01 TARRAJEO PRIMARIO O RAYADO CON CEMENTO ARENA 1:5 E=1.5CM. M2 98.15
PRIMER NIVEL 32.80
ss.hh. Damas 1 8.51 1.30 11.06
ss.hh. Varones 1 8.51 1.30 11.06
ss.hh. Discapacitados 1 8.21 1.30 10.67
SEGUNDO NIVEL 32.80
ss.hh. Damas 1 8.51 1.30 11.06
ss.hh. Varones 1 8.51 1.30 11.06
ss.hh. Discapacitados 1 8.21 1.30 10.67
TERCER NIVEL 32.55
ss.hh. Damas 1 8.51 1.30 11.06
ss.hh. Varones 1 8.51 1.30 11.06
ss.hh. 1 8.02 1.30 10.43

06.06.02 TARRAJEO EN MUROS INTERIOR Y EXTERIOR M2 517.86


MURO DE SOGA
PRIMER PISO 253.64
EJE A 2 1.43 2.88 4.11
2 2.80 2.88 8.05
2 1.91 2.88 5.49
2 3.05 2.88 8.77
2 2.15 2.88 6.18
2 2.40 2.88 6.90
2 1.65 2.88 4.74
EJE B 2 1.83 2.88 5.26
2 1.58 0.90 1.42
EJE C 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE D 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE E 2 1.78 2.88 5.12
2 1.69 0.90 1.52
2 0.75 2.88 2.16
2 2.00 2.88 5.75
EJE E' 2 3.06 2.88 8.80
EJE F 2 1.43 2.88 4.11
2 1.91 2.88 5.49
2 2.15 2.88 6.18
2 2.40 2.88 6.90
2 1.65 2.88 4.74
EJE G' 2 2.20 2.88 6.33
EJE H 2 1.98 2.88 5.69
2 3.30 2.88 9.49
2 2.41 2.88 6.93
2 1.58 2.88 4.53
2 1.53 2.88 4.38
2 2.99 2.88 8.59
2 2.99 2.88 8.59
EJE 1 2 2.45 2.88 7.04
2 1.45 2.88 4.17
2 1.45 2.88 4.17
2 2.55 2.88 7.33
2 3.40 2.88 9.78
EJE 2 2 0.90 2.88 2.59
2 0.90 2.88 2.59
EJE 3 2 2.65 2.88 7.62
2 0.90 2.25 2.03
EJE 4 2 1.50 2.88 4.31
2 0.95 2.88 2.73
EJE 5 2 2.65 2.88 7.62
2 1.88 2.88 5.39
2 1.00 1.00 1.00
EJE 6 2 2.75 2.88 7.91
2 1.48 2.88 4.24
2 1.20 2.88 3.45
EJE 8 2 1.95 1.00 1.95
2 2.05 1.00 2.05
SEGUNDO NIVEL 178.03
EJE A 2 1.43 2.88 4.11
2 2.80 2.88 8.05
2 3.16 1.00 3.16
2 3.05 2.88 8.77
2 2.15 2.88 6.18
2 3.65 1.00 3.65
2 1.65 2.88 4.74
EJE B 2 1.83 2.88 5.26
2 2.00 1.00 2.00
EJE C 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE D 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE E 2 1.78 2.88 5.12
2 2.90 2.88 8.34
2 1.90 1.00 1.90
EJE E' 2 3.11 2.88 8.94
EJE F 2 1.43 2.88 4.11
2 2.80 2.88 8.05
2 1.91 1.00 1.91
2 3.05 1.00 3.05
2 2.15 1.00 2.15
2 3.55 2.88 10.21
2 1.65 2.88 4.74
EJE 1 2 2.45 2.88 7.04
2 1.45 2.88 4.17
2 1.45 2.88 4.17
2 2.55 2.88 7.33
EJE 2 2 0.90 2.88 2.59
2 0.90 2.88 2.59
2 0.75 2.88 2.16
EJE 3 2 2.65 2.88 7.62
2 0.80 2.88 2.30
EJE 4 2 0.45 2.88 1.29
2 2.55 2.88 7.33
EJE 5 2 1.62 2.88 4.64
EJE 6 2 0.45 2.88 1.29
2 0.75 2.88 2.16
EJE 7 2 0.45 2.88 1.29
2 0.75 2.88 2.16
EJE 8 2 1.95 1.00 1.95
2 2.05 1.00 2.05
TERCER NIVEL 176.14
EJE A 2 1.43 2.88 4.11
2 2.80 2.88 8.05
2 3.01 1.00 3.01
2 3.05 2.88 8.77
2 2.15 2.88 6.18
2 3.65 1.00 3.65
2 1.65 2.88 4.74
EJE B 2 1.78 2.88 5.12
2 3.55 1.00 3.55
2 2.00 2.88 5.75
EJE C 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE D 2 0.85 2.25 1.91
2 0.98 2.88 2.82
EJE E 2 1.78 2.88 5.12
2 2.00 2.88 5.75
2 1.90 2.88 5.46
EJE E' 2 2.68 2.88 7.69
EJE F 2 1.43 2.88 4.11
2 4.15 2.88 11.93
2 3.75 2.88 10.78
2 1.65 2.88 4.74
EJE 1 2 0.90 1.00 0.90
2 0.65 2.88 1.87
2 0.90 1.00 0.90
2 1.45 2.88 4.17
2 1.45 2.88 4.17
2 2.55 2.88 7.33
EJE 2 2 0.90 2.88 2.59
2 0.90 2.88 2.59
2 0.75 2.88 2.16
EJE 3 2 0.43 2.88 1.22
2 0.73 2.88 2.08
EJE 4 2 0.45 2.88 1.29
EJE 5 2 2.65 2.88 7.62
2 1.88 2.88 5.39
EJE 6 2 0.45 2.88 1.29
2 0.75 2.88 2.16
EJE 7 2 0.45 2.88 1.29
2 1.17 2.88 3.36
2 0.75 2.88 2.16
EJE 8 2 1.95 1.00 1.95
2 1.67 1.00 1.67
MURO DE CABEZA 8.19
PRIMER NIVEL
EJE 1 2 0.95 0.00 2.88 2.73
SEGUNDO NIVEL
EJE 1 2 0.95 0.00 2.88 2.73
TERCER NIVEL
EJE 1 2 0.95 0.00 2.88 2.73

DESCUENTO (Tarrajeo primario) -1 area= 98.15 -98.15 -98.15

06.06.03 SOLAQUEO EN COLUMNAS CARAVISTA M2 1,377.24


COLUMNAS
PRIMER PISO 598.84
C-1 6 Perímetro: 3.20 5.00 96.00
C-1' 2 Perímetro: 3.00 5.00 30.00
C-2 15 Perímetro: 3.60 5.00 270.00
C-3 2 Perímetro: 2.00 5.00 20.00
C-4 4 Perímetro: 2.20 5.00 44.00
C-5 12 Perímetro: 1.60 5.00 96.00
CP-1 2 Perímetro: 1.40 3.60 10.08
CA-1A 4 Perímetro: 0.70 3.60 10.08
CA-2 3 Perímetro: 0.90 3.60 9.72
CB-1 1 Perímetro: 1.20 3.60 4.32
CB-2 3 Perímetro: 0.80 3.60 8.64
SEGUNDO PISO 389.20
C-1 6 Perímetro: 3.20 3.50 67.20
C-1' 2 Perímetro: 3.00 3.50 21.00
C-2 15 Perímetro: 3.60 3.50 189.00
C-3 2 Perímetro: 2.00 3.50 14.00
C-4 4 Perímetro: 2.20 3.50 30.80
C-5 12 Perímetro: 1.60 3.50 67.20
TERCER PISO 389.20
C-1 6 Perímetro: 3.20 3.50 67.20
C-1' 2 Perímetro: 3.00 3.50 21.00
C-2 15 Perímetro: 3.60 3.50 189.00
C-3 2 Perímetro: 2.00 3.50 14.00
C-4 4 Perímetro: 2.20 3.50 30.80
C-5 12 Perímetro: 1.60 3.50 67.20

06.06.04 SOLAQUEO EN VIGAS CARAVISTA M2 692.44


PRIMER PISO 225.03
EJE 1 VP-101 1 14.95 Perímetro 1.10 16.45
EJE 2 VP-101 1 15.45 Perímetro 0.90 13.91
EJE 3 VP-101 1 16.45 Perímetro 0.90 14.81
EJE 4 VP-101 1 13.35 Perímetro 0.90 12.02
EJE 5 VP-101 1 9.50 Perímetro 0.90 8.55
EJE 6 VP-101 1 10.10 Perímetro 0.90 9.09
EJE 7 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.10 6.82
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 0.90 5.58
EJE 5 VS-103 1 1.00 Perímetro 0.60 0.60
EJE 6 VS-103 1 1.20 Perímetro 0.60 0.72
EJE 9' VB-101 1 3.90 Perímetro 0.20 0.78
EJE 9'' VB-101 1 3.90 Perímetro 0.20 0.78
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.86 Perímetro 0.25 0.72
EJE F VS-101 1 18.54 Perímetro 0.85 15.76
EJE G VS-101 1 12.39 Perímetro 0.85 10.53
EJE G' VP-101 1 3.35 Perímetro 1.30 4.36
EJE G' VS-103 1 3.30 Perímetro 0.50 1.65
EJE H VS-101 1 9.04 Perímetro 0.85 7.68
EJE H VS-103 1 3.30 Perímetro 0.50 1.65
SEGUNDO PISO 233.70
EJE 1 VP-101 1 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.65 Perímetro 0.25 0.66
EJE F VS-101 1 3.98 Perímetro 0.85 3.38
EJE F VS-101 1 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1 17.06 Perímetro 1.00 17.06
TERCER PISO 233.70
EJE 1 VP-101 1 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1 6.21 Perímetro 1.00 6.21
EJE A VS-101 1 18.54 Perímetro 0.85 15.76
EJE B VS-101 1 15.78 Perímetro 0.70 11.05
EJE B VS-102 1 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1 5.08 Perímetro 0.75 3.81
EJE C VB-101 1 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1 5.08 Perímetro 0.75 3.81
EJE D VB-101 1 20.50 Perímetro 0.20 4.10
EJE E VS-101 1 15.78 Perímetro 0.65 10.26
EJE E VS-102 1 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1 2.65 Perímetro 0.25 0.66
EJE F VS-101 1 3.98 Perímetro 0.85 3.38
EJE F VS-101 1 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1 17.06 Perímetro 1.00 17.06

06.06.05 VESTIDURA DE DERRAMES PARA VENTANAS Y PUERTAS ML (2 anch+2 alto)xcant 531.68


VENTANAS
PRIMER PISO 49.86
V-1 1 1.80 1.00 5.60
V-2 2 2.10 2.00 16.40
V-3 1 0.75 1.10 3.70
V-4 1 2.00 2.48 8.96
V-6 2 0.75 0.85 6.40
V-7 1 2.00 2.40 8.80
SEGUNDO PISO 120.88
V-4 1 2.00 2.48 8.96
V-6 2 0.75 0.85 6.40
V-7 1 2.00 2.40 8.80
V-8 1 3.00 3.16 12.32
V-9 2 2.10 3.35 21.80
V-10 1 3.00 3.65 13.30
V-11 1 2.00 3.25 10.50
V-12 1 2.10 2.30 8.80
V-13 1 2.10 3.45 11.10
V-14 1 2.10 2.55 9.30
V-15 1 2.00 2.80 9.60
TERCER PISO 120.48
V-3 2 0.75 1.10 7.40
V-6 2 0.75 0.85 6.40
V-7 1 2.00 2.40 8.80
V-8 1 3.00 3.16 12.32
V-10 1 3.00 3.65 13.30
V-11 1 2.00 3.25 10.50
V-15 1 2.00 2.80 9.60
V-16 1 2.10 4.00 12.20
V-17 1 2.00 2.08 8.16
V-18 1 0.75 2.10 5.70
V-19 1 3.00 10.05 26.10
PUERTAS ((altox2lados)+ancho)x cant
PRIMER PISO 86.10
P-1 1 3.10 3.05 9.20
P-2 1 3.00 0.90 4.80
P-3 1 3.00 1.10 5.20
P-4 1 3.00 1.95 6.90
P-5 1 3.00 2.80 8.60
P-6 2 3.10 2.40 15.80
P-7 1 3.00 1.40 5.80
P-8 2 3.00 0.80 9.20
P-9 1 3.10 3.75 10.60
P-10 2 3.00 1.00 10.00
SEGUNDO PISO 68.20
P-3 1 3.00 1.10 5.20
P-6 1 3.10 2.40 7.90
P-8 2 3.00 0.80 9.20
P-9 1 3.10 3.75 10.60
P-10 3 3.00 1.00 15.00
P-11 1 3.00 3.10 9.20
P-12 1 3.10 4.00 11.10
TERCER PISO 86.16
P-2 3 3.00 0.90 14.40
P-8 2 3.00 0.80 9.20
P-9 1 3.10 3.75 10.60
P-10 3 3.00 1.00 15.00
P-12 1 3.10 4.00 11.10
P-13 1 3.10 1.75 6.60
P-14 1 3.10 1.00 5.10
P-15 1 3.00 0.73 4.46
P-31 1 3.00 3.35 9.70

06.07 CIELOS RASOS


06.07.01 TARRAJEO DE CIELO RASO M2 814.72
LOSA ALIGERADA
PRIMER PISO 281.76
ENTRE EJES 1-2 1 Área: 32.44 32.44
ENTRE EJES 2-3 1 Área: 50.06 50.06
ENTRE EJES 3-4 1 Área: 43.47 43.47
ENTRE EJES 4-5 1 Área: 46.80 46.80
ENTRE EJES 5-6 1 Área: 40.52 40.52
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59
SEGUNDO PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59
TERCER PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92
ENTRE EJES 6-7 1 Área: 42.88 42.88
ENTRE EJES 7-8 1 Área: 25.59 25.59

06.08 PISOS Y PAVIMENTOS


06.08.01 CONTRAPISO DE 4MM. M2 246.96
SEGUNDO PISO 129.51
interiores - piso porcelanato 1 Área= 123.97 123.97
interiores- pocelanato antideslizante 1 Área= 16.26 5.54
TECER PISO 117.45
interiores - piso porcelanato 1 Área= 113.08 113.08
interiores- pocelanato antideslizante 1 Área= 19.50 4.37

06.08.02 PISO DE PORCELANATO 60X60CM. 1ERA ANTIDESLIZANTE M2 399.95


PRIMER PISO 162.90
interiores - piso porcelanato 1 Área= 162.90 162.90
SEGUNDO PISO 123.97
interiores - piso porcelanato 1 Área= 123.97 123.97
TECER PISO 113.08
interiores - piso porcelanato 1 Área= 113.08 113.08

06.08.03 PISO DE PORCELANATO 40X40CM. 1ERA ANTIDESLIZANTE M2 56.39


PRIMER PISO 16.26
sshh damas 1 Área= 5.54 5.54
sshh varones 1 Área= 5.53 5.53
cocineta 1 Área= 5.19 5.19
SEGUNDO PISO 16.26
sshh damas 1 Área= 5.54 5.54
sshh varones 1 Área= 5.53 5.53
cocineta 1 Área= 5.19 5.19
TECER PISO 19.50
sshh damas 1 Área= 5.54 5.54
sshh varones 1 Área= 5.53 5.53
cocineta 1 Área= 8.43 8.43
sshh 1 Área= 4.37 4.37

06.08.04 PISO DE 4" CONCRETO F'C=140KG/CM2X4CM+PULIDO 1:2 X BRUÑADO M2 36.82


PRIMER PISO 36.82
ingreso 1 area= 36.82 36.82

06.09 ZOCALO Y CONTRA ZOCALO


06.09.01 ZOCALO DE PORCELANATO 40x40CM. DE 1ERA H=1.30M. M2 66.38
PRIMER NIVEL 22.13
ss.hh. Damas 1 8.51 1.3 11.063
ss.hh. Varones 1 8.51 1.3 11.063
SEGUNDO NIVEL 22.13
ss.hh. Damas 1 8.51 1.3 11.063
ss.hh. Varones 1 8.51 1.3 11.063
TERCER NIVEL 22.13
ss.hh. Damas 1 8.51 1.3 11.063
ss.hh. Varones 1 8.51 1.3 11.063

06.09.02 CONTRAZOCALO DE PORCELANATO DE H=0.10 M. M 418.76


PRIMER PISO 168.09
interiores - piso porcelanato 1 Área= 162.9 162.90
cocineta 1 Área= 5.19 5.19
SEGUNDO PISO 129.16
interiores - piso porcelanato 1 Área= 123.97 123.97
cocineta 1 Área= 5.19 5.19
TECER PISO 113.08
interiores - piso porcelanato 1 Área= 113.08 113.08
cocineta 1 Área= 8.43 8.43

06.09.03 CERAMICO DE 20X30CM. EN MESON DE CONCRETO M2 6.40


PRIMER PISO
mesa de partes 1 Área: 1.05 1.05
SEGUNDO PISO
vestidor varones 1 Área: 1.08 1.08
vestidor damas 1 Área: 1.17 1.17
cafetería 2 0.50 3.10 3.10

06.10 CARPINTERIA DE MADERA


06.10.01 PUERTA INTERIOR DE MELAMINA DE E=10MM. M2 37.09
PRIMER PISO 10.80
P-2 1 3.00 0.90 2.70
P-3 1 3.00 1.10 3.30
P-8 2 3.00 0.80 4.80
SEGUNDO PISO 8.10
P-3 1 3.00 1.10 3.30
P-8 2 3.00 0.80 4.80
TERCER PISO 18.19
P-2 3 3.00 0.90 8.10
P-8 2 3.00 0.80 4.80
P-14 1 3.10 1.00 3.10
P-15 1 3.00 0.73 2.19

06.11 CARPINTERIA METALICA


06.11.01 CORTA SOL PARA VENTANA M2 64.00
SEGUNDO PISO
fachada 1 10.00 3.20 32.00
TERCER NIVEL
fachada 1 10.00 3.20 32.00

06.11.02 BARANDA METALICA M 10.00


PRIMER NIVEL
1 5.00 5.00
SEGUNDO NIVEL
1 5.00 5.00

06.11.03 LETRAS EN ALTO RELIEVE CON MDF UND 48 48.00 48.00

06.12 CERRAJERIA
06.12.01 CERRADURA TIPO PARCHE DE TRES GOLPES PZA 5.00
PRIMER PISO
P-7 1 1.00
SEGUNDO PISO
P-31 1 1.00
TERCER PISO
P-18 2 2.00
P-20 1 1.00

06.12.02 CERRADURA TIPO PERILLA PZA 14.00


PRIMER PISO
P-2 1 1.00
P-3 1 1.00
P-8 2 2.00
SEGUNDO PISO
P-3 1 1.00
P-8 2 2.00
TERCER PISO
P-2 3 3.00
P-8 2 2.00
P-14 1 1.00
P-15 1 1.00

06.12.03 CERRADURA TIPO PICAPORTE PZA 5.00


SEGUNDO PISO
P-17 5 5.00

06.12.04 BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4" PZA Nº BISAGRA 56.00


PRIMER PISO
P-2 1 4 4.00
P-3 1 4 4.00
P-8 2 4 8.00
SEGUNDO PISO
P-3 1 4 4.00
P-8 2 4 8.00
TERCER PISO
P-2 3 4 12.00
P-8 2 4 8.00
P-14 1 4 4.00
P-15 1 4 4.00

06.13 VIDRIOS, CRISTALES Y SIMILARES


06.13.01 VENTANA SISTEMA CON VIDRIO INCOLORO Y MARCO DE ALUMINIO M2 181.67
PRIMER PISO
V-1 1 1.80 1.00 1.80
V-2 2 2.10 2.00 8.40
V-3 1 0.75 1.10 0.83
V-4 1 2.00 2.48 4.96
V-6 2 0.75 0.85 1.28
V-7 1 2.00 2.40 4.80
SEGUNDO PISO
V-4 1 2.00 2.48 4.96
V-6 2 0.75 0.85 1.28
V-7 1 2.00 2.40 4.80
V-8 1 3.00 3.16 9.48
V-9 2 2.10 3.35 14.07
V-10 1 3.00 3.65 10.95
V-11 1 2.00 3.25 6.50
V-12 1 2.10 2.30 4.83
V-13 1 2.10 3.45 7.25
V-14 1 2.10 2.55 5.36
V-15 1 2.00 2.80 5.60
TERCER PISO
V-3 2 0.75 1.10 1.65
V-6 2 0.75 0.85 1.28
V-7 1 2.00 2.40 4.80
V-8 1 3.00 3.16 9.48
V-10 1 3.00 3.65 10.95
V-11 1 2.00 3.25 6.50
V-15 1 2.00 2.80 5.60
V-16 1 2.10 4.00 8.40
V-17 1 2.00 2.08 4.16
V-18 1 0.75 2.10 1.58
V-19 1 3.00 10.05 30.15

06.14 PINTURAS Y BARNICES


06.14.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 517.86
MURO DE SOGA
PRIMER PISO 253.64
EJE A 2.00 1.43 2.88 4.11
2.00 2.80 2.88 8.05
2.00 1.91 2.88 5.49
2.00 3.05 2.88 8.77
2.00 2.15 2.88 6.18
2.00 2.40 2.88 6.90
2.00 1.65 2.88 4.74
EJE B 2.00 1.83 2.88 5.26
2.00 1.58 0.90 1.42
EJE C 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE D 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE E 2.00 1.78 2.88 5.12
2.00 1.69 0.90 1.52
2.00 0.75 2.88 2.16
2.00 2.00 2.88 5.75
EJE E' 2.00 3.06 2.88 8.80
EJE F 2.00 1.43 2.88 4.11
2.00 1.91 2.88 5.49
2.00 2.15 2.88 6.18
2.00 2.40 2.88 6.90
2.00 1.65 2.88 4.74
EJE G' 2.00 2.20 2.88 6.33
EJE H 2.00 1.98 2.88 5.69
2.00 3.30 2.88 9.49
2.00 2.41 2.88 6.93
2.00 1.58 2.88 4.53
2.00 1.53 2.88 4.38
2.00 2.99 2.88 8.59
2.00 2.99 2.88 8.59
EJE 1 2.00 2.45 2.88 7.04
2.00 1.45 2.88 4.17
2.00 1.45 2.88 4.17
2.00 2.55 2.88 7.33
2.00 3.40 2.88 9.78
EJE 2 2.00 0.90 2.88 2.59
2.00 0.90 2.88 2.59
EJE 3 2.00 2.65 2.88 7.62
2.00 0.90 2.25 2.03
EJE 4 2.00 1.50 2.88 4.31
2.00 0.95 2.88 2.73
EJE 5 2.00 2.65 2.88 7.62
2.00 1.88 2.88 5.39
2.00 1.00 1.00 1.00
EJE 6 2.00 2.75 2.88 7.91
2.00 1.48 2.88 4.24
2.00 1.20 2.88 3.45
EJE 8 2.00 1.95 1.00 1.95
2.00 2.05 1.00 2.05
SEGUNDO NIVEL 178.03
EJE A 2.00 1.43 2.88 4.11
2.00 2.80 2.88 8.05
2.00 3.16 1.00 3.16
2.00 3.05 2.88 8.77
2.00 2.15 2.88 6.18
2.00 3.65 1.00 3.65
2.00 1.65 2.88 4.74
EJE B 2.00 1.83 2.88 5.26
2.00 2.00 1.00 2.00
EJE C 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE D 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE E 2.00 1.78 2.88 5.12
2.00 2.90 2.88 8.34
2.00 1.90 1.00 1.90
EJE E' 2.00 3.11 2.88 8.94
EJE F 2.00 1.43 2.88 4.11
2.00 2.80 2.88 8.05
2.00 1.91 1.00 1.91
2.00 3.05 1.00 3.05
2.00 2.15 1.00 2.15
2.00 3.55 2.88 10.21
2.00 1.65 2.88 4.74
EJE 1 2.00 2.45 2.88 7.04
2.00 1.45 2.88 4.17
2.00 1.45 2.88 4.17
2.00 2.55 2.88 7.33
EJE 2 2.00 0.90 2.88 2.59
2.00 0.90 2.88 2.59
2.00 0.75 2.88 2.16
EJE 3 2.00 2.65 2.88 7.62
2.00 0.80 2.88 2.30
EJE 4 2.00 0.45 2.88 1.29
2.00 2.55 2.88 7.33
EJE 5 2.00 1.62 2.88 4.64
EJE 6 2.00 0.45 2.88 1.29
2.00 0.75 2.88 2.16
EJE 7 2.00 0.45 2.88 1.29
2.00 0.75 2.88 2.16
EJE 8 2.00 1.95 1.00 1.95
2.00 2.05 1.00 2.05
TERCER NIVEL 176.14
EJE A 2.00 1.43 2.88 4.11
2.00 2.80 2.88 8.05
2.00 3.01 1.00 3.01
2.00 3.05 2.88 8.77
2.00 2.15 2.88 6.18
2.00 3.65 1.00 3.65
2.00 1.65 2.88 4.74
EJE B 2.00 1.78 2.88 5.12
2.00 3.55 1.00 3.55
2.00 2.00 2.88 5.75
EJE C 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE D 2.00 0.85 2.25 1.91
2.00 0.98 2.88 2.82
EJE E 2.00 1.78 2.88 5.12
2.00 2.00 2.88 5.75
2.00 1.90 2.88 5.46
EJE E' 2.00 2.68 2.88 7.69
EJE F 2.00 1.43 2.88 4.11
2.00 4.15 2.88 11.93
2.00 3.75 2.88 10.78
2.00 1.65 2.88 4.74
EJE 1 2.00 0.90 1.00 0.90
2.00 0.65 2.88 1.87
2.00 0.90 1.00 0.90
2.00 1.45 2.88 4.17
2.00 1.45 2.88 4.17
2.00 2.55 2.88 7.33
EJE 2 2.00 0.90 2.88 2.59
2.00 0.90 2.88 2.59
2.00 0.75 2.88 2.16
EJE 3 2.00 0.43 2.88 1.22
2.00 0.73 2.88 2.08
EJE 4 2.00 0.45 2.88 1.29
EJE 5 2.00 2.65 2.88 7.62
2.00 1.88 2.88 5.39
EJE 6 2.00 0.45 2.88 1.29
2.00 0.75 2.88 2.16
EJE 7 2.00 0.45 2.88 1.29
2.00 1.17 2.88 3.36
2.00 0.75 2.88 2.16
EJE 8 2.00 1.95 1.00 1.95
2.00 1.67 1.00 1.67
MURO DE CABEZA 8.19
PRIMER NIVEL
EJE 1 2.00 0.95 2.88 2.73
SEGUNDO NIVEL
EJE 1 2.00 0.95 2.88 2.73
TERCER NIVEL
EJE 1 2.00 0.95 2.88 2.73

DESCUENTO (Tarrajeo primario) -1.00 area= 98.15 -98.15 -98.15

06.14.02 PINTURA LATEX EN VIGAS Y COLUMNAS M2 2,069.68


COLUMNAS
PRIMER PISO 598.84
C-1 6.00 Perímetro: 3.20 5.00 96.00
C-1' 2.00 Perímetro: 3.00 5.00 30.00
C-2 15.00 Perímetro: 3.60 5.00 270.00
C-3 2.00 Perímetro: 2.00 5.00 20.00
C-4 4.00 Perímetro: 2.20 5.00 44.00
C-5 12.00 Perímetro: 1.60 5.00 96.00
CP-1 2.00 Perímetro: 1.40 3.60 10.08
CA-1A 4.00 Perímetro: 0.70 3.60 10.08
CA-2 3.00 Perímetro: 0.90 3.60 9.72
CB-1 1.00 Perímetro: 1.20 3.60 4.32
CB-2 3.00 Perímetro: 0.80 3.60 8.64
SEGUNDO PISO 389.20
C-1 6.00 Perímetro: 3.20 3.50 67.20
C-1' 2.00 Perímetro: 3.00 3.50 21.00
C-2 15.00 Perímetro: 3.60 3.50 189.00
C-3 2.00 Perímetro: 2.00 3.50 14.00
C-4 4.00 Perímetro: 2.20 3.50 30.80
C-5 12.00 Perímetro: 1.60 3.50 67.20
TERCER PISO 389.20
C-1 6.00 Perímetro: 3.20 3.50 67.20
C-1' 2.00 Perímetro: 3.00 3.50 21.00
C-2 15.00 Perímetro: 3.60 3.50 189.00
C-3 2.00 Perímetro: 2.00 3.50 14.00
C-4 4.00 Perímetro: 2.20 3.50 30.80
C-5 12.00 Perímetro: 1.60 3.50 67.20
VIGAS
PRIMER PISO 225.03
EJE 1 VP-101 1.00 14.95 Perímetro 1.10 16.45
EJE 2 VP-101 1.00 15.45 Perímetro 0.90 13.91
EJE 3 VP-101 1.00 16.45 Perímetro 0.90 14.81
EJE 4 VP-101 1.00 13.35 Perímetro 0.90 12.02
EJE 5 VP-101 1.00 9.50 Perímetro 0.90 8.55
EJE 6 VP-101 1.00 10.10 Perímetro 0.90 9.09
EJE 7 VP-101 1.00 12.40 Perímetro 0.90 11.16
EJE 8 VP-101 1.00 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1.00 6.20 Perímetro 1.10 6.82
EJE 9' VP-101 1.00 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1.00 6.20 Perímetro 0.90 5.58
EJE 5 VS-103 1.00 1.00 Perímetro 0.60 0.60
EJE 6 VS-103 1.00 1.20 Perímetro 0.60 0.72
EJE 9' VB-101 1.00 3.90 Perímetro 0.20 0.78
EJE 9'' VB-101 1.00 3.90 Perímetro 0.20 0.78
EJE A' VB-102 1.00 6.21 Perímetro 1.00 6.21
EJE A VS-101 1.00 18.54 Perímetro 0.85 15.76
EJE B VS-101 1.00 15.78 Perímetro 0.70 11.05
EJE B VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE C VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE D VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE E VS-101 1.00 15.78 Perímetro 0.65 10.26
EJE E VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1.00 2.86 Perímetro 0.25 0.72
EJE F VS-101 1.00 18.54 Perímetro 0.85 15.76
EJE G VS-101 1.00 12.39 Perímetro 0.85 10.53
EJE G' VP-101 1.00 3.35 Perímetro 1.30 4.36
EJE G' VS-103 1.00 3.30 Perímetro 0.50 1.65
EJE H VS-101 1.00 9.04 Perímetro 0.85 7.68
EJE H VS-103 1.00 3.30 Perímetro 0.50 1.65
SEGUNDO PISO
EJE 1 VP-101 1.00 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1.00 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1.00 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1.00 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1.00 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1.00 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1.00 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1.00 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1.00 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1.00 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1.00 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1.00 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1.00 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1.00 6.21 Perímetro 1.00 6.21
EJE A VS-101 1.00 18.54 Perímetro 0.85 15.76
EJE B VS-101 1.00 15.78 Perímetro 0.70 11.05
EJE B VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE C VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE D VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE E VS-101 1.00 15.78 Perímetro 0.65 10.26
EJE E VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1.00 2.65 Perímetro 0.25 0.66
EJE F VS-101 1.00 3.98 Perímetro 0.85 3.38
EJE F VS-101 1.00 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1.00 17.06 Perímetro 1.00 17.06
TERCER PISO
EJE 1 VP-101 1.00 11.05 Perímetro 1.10 12.16
EJE 2 VP-101 1.00 12.40 Perímetro 0.90 11.16
EJE 3 VP-101 1.00 13.40 Perímetro 0.90 12.06
EJE 4 VP-101 1.00 10.40 Perímetro 0.90 9.36
EJE 5 VP-101 1.00 10.40 Perímetro 0.90 9.36
EJE 6 VP-101 1.00 11.00 Perímetro 0.90 9.90
EJE 7 VP-101 1.00 13.30 Perímetro 0.90 11.97
EJE 8 VP-101 1.00 11.10 Perímetro 0.90 9.99
EJE 9 VP-101 1.00 6.20 Perímetro 1.00 6.20
EJE 9' VP-101 1.00 1.15 Perímetro 0.90 1.04
EJE 10 VP-101 1.00 6.20 Perímetro 1.00 6.20
EJE 9' VB-101 1.00 3.90 Perímetro 3.90 15.21
EJE 9'' VB-101 1.00 3.90 Perímetro 3.90 15.21
EJE A' VB-102 1.00 6.21 Perímetro 1.00 6.21
EJE A VS-101 1.00 18.54 Perímetro 0.85 15.76
EJE B VS-101 1.00 15.78 Perímetro 0.70 11.05
EJE B VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE C VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE C VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE D VCH-101 1.00 5.08 Perímetro 0.75 3.81
EJE D VB-101 1.00 20.50 Perímetro 0.20 4.10
EJE E VS-101 1.00 15.78 Perímetro 0.65 10.26
EJE E VS-102 1.00 5.39 Perímetro 1.05 5.66
EJE E' VCH-102 1.00 2.65 Perímetro 0.25 0.66
EJE F VS-101 1.00 3.98 Perímetro 0.85 3.38
EJE F VS-101 1.00 14.56 Perímetro 0.85 12.38
EJE F' VB-102 1.00 17.06 Perímetro 1.00 17.06

06.14.03 PINTURA LATEX EN DERRAMES DE VANOS ML (anch+alto)xcant 531.68


VENTANAS
PRIMER PISO 49.86
V-1 1.00 1.80 1.00 5.60
V-2 2.00 2.10 2.00 16.40
V-3 1.00 0.75 1.10 3.70
V-4 1.00 2.00 2.48 8.96
V-6 2.00 0.75 0.85 6.40
V-7 1.00 2.00 2.40 8.80
SEGUNDO PISO 120.88
V-4 1.00 2.00 2.48 8.96
V-6 2.00 0.75 0.85 6.40
V-7 1.00 2.00 2.40 8.80
V-8 1.00 3.00 3.16 12.32
V-9 2.00 2.10 3.35 21.80
V-10 1.00 3.00 3.65 13.30
V-11 1.00 2.00 3.25 10.50
V-12 1.00 2.10 2.30 8.80
V-13 1.00 2.10 3.45 11.10
V-14 1.00 2.10 2.55 9.30
V-15 1.00 2.00 2.80 9.60
TERCER PISO 120.48
V-3 2.00 0.75 1.10 7.40 0.00
V-6 2.00 0.75 0.85 6.40 0.00
V-7 1.00 2.00 2.40 8.80 0.00
V-8 1.00 3.00 3.16 12.32 0.00
V-10 1.00 3.00 3.65 13.30 0.00
V-11 1.00 2.00 3.25 10.50 0.00
V-15 1.00 2.00 2.80 9.60 0.00
V-16 1.00 2.10 4.00 12.20 0.00
V-17 1.00 2.00 2.08 8.16 0.00
V-18 1.00 0.75 2.10 5.70 0.00
V-19 1.00 3.00 10.05 26.10 0.00
PUERTAS ((altox2lados)+ancho)x cant
PRIMER PISO 86.10
P-1 1.00 3.10 3.05 9.20
P-2 1.00 3.00 0.90 4.80
P-3 1.00 3.00 1.10 5.20
P-4 1.00 3.00 1.95 6.90
P-5 1.00 3.00 2.80 8.60
P-6 2.00 3.10 2.40 15.80
P-7 1.00 3.00 1.40 5.80
P-8 2.00 3.00 0.80 9.20
P-9 1.00 3.10 3.75 10.60
P-10 2.00 3.00 1.00 10.00
SEGUNDO PISO 68.20
P-3 1.00 3.00 1.10 5.20
P-6 1.00 3.10 2.40 7.90
P-8 2.00 3.00 0.80 9.20
P-9 1.00 3.10 3.75 10.60
P-10 3.00 3.00 1.00 15.00
P-11 1.00 3.00 3.10 9.20
P-12 1.00 3.10 4.00 11.10
TERCER PISO 86.16
P-2 3.00 3.00 0.90 14.40
P-8 2.00 3.00 0.80 9.20
P-9 1.00 3.10 3.75 10.60
P-10 3.00 3.00 1.00 15.00
P-12 1.00 3.10 4.00 11.10
P-13 1.00 3.10 1.75 6.60
P-14 1.00 3.10 1.00 5.10
P-15 1.00 3.00 0.73 4.46
P-31 1.00 3.00 3.35 9.70

06.14.04 PINTURA LATEX EN CIELORASO 609.33


LOSA ALIGERADA
PRIMER PISO 281.76
ENTRE EJES 1-2 1 Área: 32.44 32.44
ENTRE EJES 2-3 1 Área: 50.06 50.06
ENTRE EJES 3-4 1 Área: 43.47 43.47
ENTRE EJES 4-5 1 Área: 46.80 46.80
ENTRE EJES 5-6 1 Área: 40.52 40.52
SEGUNDO PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92
TERCER PISO 266.48
ENTRE EJES 1-2 1 Área: 21.63 21.63
ENTRE EJES 2-3 1 Área: 33.38 33.38
ENTRE EJES 3-4 1 Área: 36.89 36.89
ENTRE EJES 4-5 1 Área: 56.20 56.20
ENTRE EJES 5-6 1 Área: 49.92 49.92

06.15 VARIOS
06.15.01 CURADO DE ELEMENTOS HORIZONTALES Y VERTICALES M2 5,481.76
SOBRECIMIENTOS 192.32
FALSO PISO 595.88
PLACAS 373.86
COLUMNAS 1766.44
COLUMNAS Y VIGAS AMARRE 545.92
VIGAS 926.14
LOSA ALIGERADA 1081.20

06.15.02 JUNTA DE CONSTRUCCION CON TECKNOPORT M2 60.72


COLUMNETAS 120 0.15 2.87 51.71
6 0.15 2.35 2.12
46 0.15 1.00 6.90

06.15.03 JUNTA DE CONSTRUCCION CON JEBE MICROPOROSO M 404.80


COLUMNETAS 120 2.87 344.70
6 2.35 14.10
46 1.00 46.00

06.15.04 LIMPIEZA FINAL DE OBRA M2 area= 215.98 215.98 215.98


PLANILLA DE METRADOS DE ACERO

OBRA CONSTRUCCIÓN DE LA INFRAESTRUCTURA DE LA UNIDAD DE GESTIÓN EDUCATIVA DE LA PROVINCIA DE CONDESUYOS, REGIÓN DE AREQUIPA
PROPIETARIO GOBIERNO REGIONAL DE AREQUIPA
FECHA FEBRERO DEL 2016

DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO

06.03.01.02 ACERO GRADO 60 EN ZAPATAS Z-1 6 11 2.25 145.13


BLOCK "B" 6 12 2.00 144.00
6 9 2.25 116.10
6 12 2.00 144.00

Z-2 3 12 1.85 63.83


3 10 2.15 64.50

Z-2' 2 14 1.85 50.88


2 10 2.60 52.00

Z-3 2 12 2.02 48.48


2 11 2.25 48.83

Z-4 1 11 2.25 23.85


1 12 2.50 30.00

Z-5 2 5 1.45 15.08


2 6 1.15 14.72

Z-5' 1 7 0.90 5.85


1 5 1.15 6.04

Z-6 1 6 1.05 6.30


1 6 1.05 6.30

ZC-1 6 17 1.25 127.50


6 7 4.10 172.20
6 17 1.25 127.50
6 6 4.10 137.76

ZC-2 1 13 3.95 51.35


1 21 2.45 50.23
1 13 3.95 51.35
1 21 2.45 50.23

ZC-2' 1 9 3.75 34.50


1 20 2.15 41.93
1 9 3.75 34.50
1 16 2.15 33.54
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

ZC-3 1 7 1.55 10.66


1 2 1.23 2.70
1 3 1.08 3.01
1 5 1.85 8.51

ZP-1 4 14 5.25 294.00


4 27 2.65 286.20
4 11 5.25 235.20
4 27 2.65 286.20
4 11 1.70 76.16
4 6 1.70 38.08

ZP-2 1 11 5.15 58.71


1 14 5.15 73.39
1 14 5.58 79.52
1 11 5.10 58.14
1 14 5.10 72.68
1 14 5.53 78.80
1 5 1.05 5.04
1 6 1.05 6.30
1 5 1.05 5.04
1 6 1.05 6.30
1 5 1.05 5.04
1 6 1.05 6.30
1 5 1.05 5.04
1 6 1.05 6.30

TOTAL ML : 945.69 2660.06 0.00 0.00 0.00 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25

TOTAL KG : 2127.80 4156.34 0.00 0.00 0.00 0.00

TOTAL VAR : 105 296 0 0 0 0

TOTAL KG 6,284.13
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO
06.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACION
VC-101 EJE 1 1 8 14.95 119.60
1 60 1.93 115.41
EJE 2 1 8 4.10 32.80
1 16 1.93 31.65
EJE 3 1 8 4.10 32.80
1 16 1.93 31.65
EJE 4 1 8 4.10 32.80
1 16 1.93 31.65
EJE 5 1 8 4.10 32.80
1 16 1.93 31.65
EJE 6 1 8 4.10 32.80
1 16 1.93 31.65
EJE 7 1 8 4.10 32.80
1 16 1.93 31.65
EJE 8 1 8 11.10 88.80
1 44 1.93 85.69
EJE A 1 8 18.54 148.32
1 74 1.93 143.13
EJE B 1 8 15.78 126.24
1 63 1.93 121.82
EJE E 1 8 15.78 126.24
1 63 1.93 121.82
EJE F 1 8 18.54 148.32
1 74 1.93 143.13
VC-102 1
EJE C 1 8 2.23 17.84
1 9 1.73 15.43
EJE D 1 8 2.23 17.84
1 9 1.73 15.43
EJE 2 1 8 6.50 52.00
1 26 1.73 44.98
EJE 3 1 8 3.20 25.60
1 13 1.73 22.14
EJE 4 1 8 3.20 25.60
1 13 1.73 22.14
EJE 5 1 8 3.20 25.60
1 13 1.73 22.14

TOTAL ML : 1118.80 0.00 0.00 0.00 1063.19 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 2517.30 0.00 0.00 0.00 598.05 0.00
TOTAL VAR : 124 0 0 0 118 0
TOTAL KG 3,115.35
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

06.03 OBRAS DE CONCRETO ARMADO

06.03.03.03 ACERO GRADO 60 EN PLACAS


PRIMER PISO
PL-1 2 22 3.50 154.00
2 35 0.78 54.60
2 58 1.24 143.84
2 29 1.49 86.42
2 29 0.37 21.46
PL-2 2 20 3.50 140.00
2 22 3.50 154.00
2 35 3.53 247.10
2 58 1.99 230.84
2 35 0.37 25.90
2 123 0.27 66.15
PL-3 2 20 3.50 140.00
2 24 3.50 168.00
2 35 3.77 263.90
2 58 1.99 230.84
2 58 0.37 42.92
2 232 0.27 125.28

SEGUNDO PISO 0.00


PL-1 2 22 3.50 154.00
2 35 0.78 54.60
2 58 1.24 143.84
2 29 1.49 86.42
2 29 0.37 21.46
PL-2 2 20 3.50 140.00
2 22 3.50 154.00
2 35 3.53 247.10
2 58 1.99 230.84
2 35 0.37 25.90
2 123 0.27 66.15
PL-3 2 20 3.50 140.00
2 24 3.50 168.00
2 35 3.77 263.90
2 58 1.99 230.84
2 58 0.37 42.92
2 232 0.27 125.28
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

TERCER PISO
PL-1 2 22 3.50 154.00
2 35 0.78 54.60
2 58 1.24 143.84
2 29 1.49 86.42
2 29 0.37 21.46
PL-2 2 20 3.50 140.00
2 22 3.50 154.00
2 35 3.53 247.10
2 58 1.99 230.84
2 35 0.37 25.90
2 123 0.27 66.15
PL-3 2 20 3.50 140.00
2 24 3.50 168.00
2 35 3.77 263.90
2 58 1.99 230.84
2 58 0.37 42.92
2 232 0.27 125.28

TOTAL ML : 1302.00 0.00 2499.00 0.00 3084.75 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 2929.50 0.00 2499.00 0.00 1735.17 0.00
TOTAL VAR : 145 0 278 0 343 0
TOTAL KG 7,163.67
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO C-1 2 18 3.50 126.00
PRIMER PISO est. 2 29 1.85 107.30
06.03.04.03 ACERO GRADO 60 EN COLUMNAS est. 2 29 1.80 104.40
est. 2 29 1.50 87.00
C-1' 6 16 3.50 336.00
est. 6 29 1.85 321.90
est. 6 29 1.80 313.20
est. 6 29 1.30 226.20
C-2 12 18 3.50 756.00
est. 12 29 1.85 643.80
est. 12 29 1.80 626.40
est. 12 29 1.90 661.20
C-3 2 8 3.50 56.00
est. 2 29 1.40 81.20
est. 2 29 1.30 75.40
C-4 4 8 3.50 112.00
est. 4 29 2.00 232.00
est. 4 27 0.37 39.96
C-5 6 6 3.50 126.00
est. 6 29 1.40 243.60
CP-1 2 6 3.50 42.00
est. 2 29 2.00 116.00
CA-1A 4 4 3.50 56.00
est. 4 29 2.00 232.00
CA-2 3 4 3.50 42.00
est. 3 29 2.00 174.00
CB-1 1 6 3.50 21.00
est. 1 29 2.00 58.00
CB-2 3 4 3.50 42.00
est. 3 29 2.00 174.00
SEGUNDO PISO
C-1 2 18 3.50 126.00
est. 2 29 1.85 107.30
est. 2 29 1.80 104.40
est. 2 29 1.50 87.00
C-1' 6 16 3.50 336.00
est. 6 29 1.85 321.90
est. 6 29 1.80 313.20
est. 6 29 1.30 226.20
C-2 12 18 3.50 756.00
est. 12 29 1.85 643.80
est. 12 29 1.80 626.40
est. 12 29 1.90 661.20
C-3 2 8 3.50 56.00
est. 2 29 1.40 81.20
est. 2 29 1.30 75.40
C-4 4 8 3.50 112.00
est. 4 29 2.00 232.00
est. 4 27 0.37 39.96
C-5 6 6 3.50 126.00
est. 6 29 1.40 243.60
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

TERCER PISO
C-1 2 18 3.50 126.00
est. 2 29 1.85 107.30
est. 2 29 1.80 104.40
est. 2 29 1.50 87.00
C-1' 6 16 3.50 336.00
est. 6 29 1.85 321.90
est. 6 29 1.80 313.20
est. 6 29 1.30 226.20
C-2 12 18 3.50 756.00
est. 12 29 1.85 643.80
est. 12 29 1.80 626.40
est. 12 29 1.90 661.20
C-3 2 8 3.50 56.00
est. 2 29 1.40 81.20
est. 2 29 1.30 75.40
C-4 4 8 3.50 112.00
est. 4 29 2.00 232.00
est. 4 27 0.37 39.96
C-5 6 6 3.50 126.00
est. 6 29 1.40 243.60

TOTAL ML : 4536.00 42.00 105.00 56.00 11406.68 638.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 10206.00 65.63 105.00 31.50 6416.26 159.50
TOTAL VAR : 504 5 12 6 1267 71
TOTAL KG 16,983.88
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO

06.03.05.03 ACERO GRADO 60 EN COLUMNAS Y VIGAS DE AMARRE


PRIMER PISO
EJE A CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-2 3 4 3.38 40.50
Est. 3 20 0.65 39.00
EJE B CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE E CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
EJE F CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE H CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 1 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-2 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 3 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 4 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

EJE 5 CA-1 2 4 3.38 27.00


Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 6 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 8 CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00

V-A
EJE 1 vert 1 2 12.39 24.77
est 1 62 0.23 14.24
EJE 3 vert 1 2 2.65 5.30
est 1 13 0.23 3.05
EJE 4 vert 1 2 1.50 3.00
est 1 8 0.23 1.73
EJE 5 vert 1 2 4.53 9.05
est 1 23 0.23 5.20
EJE 6 vert 1 2 4.23 8.45
est 1 21 0.23 4.86
EJE 8 vert 1 2 4.00 8.00
est 1 20 0.23 4.60
EJE A vert 1 2 15.39 30.78
est 1 77 0.23 17.70
EJE B vert 1 2 1.57 3.15
est 1 8 0.23 1.81
EJE E vert 1 2 3.68 7.36
est 1 18 0.23 4.23
EJE F vert 1 2 9.54 19.08
est 1 48 0.23 10.97
EJE G' vert 1 2 2.20 4.40
est 1 11 0.23 2.53
EJE H vert 1 2 13.63 27.26
est 1 68 0.23 15.67
SEGUNDO PISO
EJE A CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE F CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

CA-1 2 4 1.50 12.00


Est. 2 10 0.65 13.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 1 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 2.50 20.00
Est. 2 15 0.65 19.50
CA-2 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 2.50 20.00
Est. 2 15 0.65 19.50
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 4 CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 8 CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00

V-A
EJE 1 vert 1 2 2.55 5.10
est 1 13 0.23 2.93
EJE 4 vert 1 2 1.53 3.05
est 1 8 0.23 1.75
EJE 8 vert 1 2 4.00 8.00
est 1 20 0.23 4.60
EJE A vert 1 2 13.00 26.00
est 1 65 0.23 14.95
EJE F vert 1 2 13.00 26.00
est 1 65 0.23 14.95
TERCER PISO
EJE A CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE B CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
EJE F CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

CA-1 2 4 2.85 22.80


Est. 2 17 0.65 22.10
EJE 1 CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 3.38 27.04
Est. 2 20 0.65 26.00
CA-2 2 4 3.38 27.00
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.04
Est. 2 20 0.65 26.00
CA-1 2 4 3.38 27.00
Est. 2 20 0.65 26.00
EJE 8 CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 2 4 1.50 12.00
Est. 2 10 0.65 13.00
CA-1 1 4 3.38 13.50
Est. 1 20 0.65 13.00

V-A
EJE 1 vert 1 2 8.85 17.70
est 1 44 0.23 10.18
EJE 5 vert 1 2 4.53 9.05
est 1 23 0.23 5.20
EJE 7 vert 1 2 1.25 2.50
est 1 6 0.23 1.44
EJE 8 vert 1 2 4.00 8.00
est 1 20 0.23 4.60
EJE A vert 1 2 13.00 26.00
est 1 65 0.23 14.95
EJE B vert 1 2 5.55 11.10
est 1 28 0.23 6.38
EJE F vert 1 2 3.08 6.16
est 1 15 0.23 3.54
EJE F' vert 1 2 5.20 10.40
est 1 26 0.23 5.98

TOTAL ML : 0.00 0.00 0.00 1995.54 0.00 1,825.15

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25

TOTAL KG : 0.00 0.00 0.00 1122.49 0.00 456.29

TOTAL VAR : 0 0 0 222 0 203


TOTAL KG 1,578.78
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO

06.03.06.03 ACERO GRADO 60 EN VIGAS


BLOCK "B"
PRIMER PISO
eje 1 y 2 VP-101 As(+) 2 2 17.95 71.80
entre eje A-F As(+) 2 1 17.95 35.90
As(+) 2 2 12.55 50.20
As(-) 2 2 17.85 71.40
As(-) 2 1 17.85 35.70
Est. 2 111 1.34 297.48
eje 1 ,2,3 y 4 VP-101 As(+) 4 3 5.40 64.80
entre eje G-H As(-) 4 3 5.30 63.60
Est. 4 31 1.34 166.16
eje 3 VP-101 As(+) 1 2 17.95 35.90
As(+) 1 1 17.95 17.95
As(+) 1 2 14.55 29.10
As(-) 1 3 18.46 55.38
Est. 1 105 1.34 140.70
eje 4,5 y 6 VP-101 As(+) 3 2 7.59 45.54
entre eje A-C As(+) 3 1 7.59 22.77
As(+) 3 2 7.32 43.92
As(-) 3 2 7.45 44.70
As(-) 3 1 7.45 22.35
Est. 3 48 1.34 192.96
eje 4,5 y 6 VP-101 As(+) 3 2 7.09 42.54
entre eje D-F As(+) 3 1 7.09 21.27
As(+) 3 2 6.77 40.62
As(-) 3 2 6.97 41.82
As(-) 3 1 6.97 20.91
Est. 3 42 1.34 168.84
eje 7 VP-101 As(+) 1 2 19.45 38.90
As(+) 1 1 19.45 19.45
As(+) 1 2 14.00 28.00
As(-) 1 3 19.35 58.05
Est. 1 129 1.34 172.86
eje 8 VP-101 As(+) 1 2 17.25 34.50
As(+) 1 1 17.25 17.25
As(+) 1 2 12.55 25.10
As(-) 1 3 17.85 53.55
Est. 1 94 1.34 125.96
eje 9 Y 10 VP-101 As(+) 2 2 7.65 30.60
As(+) 2 1 7.65 15.30
As(+) 2 2 7.25 29.00
As(-) 2 3 7.55 45.30
Est. 2 43 1.34 115.24
EJE 9' VP-101 As(+) 1 2 2.95 5.90
As(+) 1 1 2.95 2.95
As(+) 1 2 2.54 5.08
As(-) 1 3 2.95 8.85
Est. 1 15 1.34 20.10
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

EJE 5 VS-103 As(+) 1 2 1.60 3.20


As(-) 1 2 1.60 3.20
Est. 1 10 1.00 10.00
EJE 6 VS-103 As(+) 1 2 1.80 3.60
As(-) 1 2 1.80 3.60
Est. 1 11 1.00 11.00
EJE 9' y 9'' VB-101 As(+) 2 2 4.70 18.80
As(-) 2 2 4.70 18.80
Est. 2 36 0.80 57.60
EJE A' VB-102 As(+) 2 2 3.66 14.64
As 2 4 3.66 29.28
As(-) 2 2 3.66 14.64
Est. 2 23 1.40 64.40
EJE A y F VS-101 As(+) 2 3 26.30 157.80
As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-101 As(+) 2 3 26.30 157.80
As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-102 As(+) 2 2 6.09 24.36
As(-) 2 2 6.09 24.36
Est. 2 40 1.50 120.00
EJE C y D VCH-101 As(t) 4 10 3.23 129.20
Est. 4 24 3.23 310.08
EJE C y D VB-101 As(t) 2 4 15.01 120.08
Est. 2 121 3.23 781.66
EJE G y H VS-101 As(+) 2 2 11.27 45.08
As(-) 2 2 11.87 47.48
Est. 2 77 1.04 160.16
EJE G' VP-101 As(+) 1 2 4.28 8.56
As(-) 1 2 4.18 8.36
Est. 1 28 1.34 37.52
EJE G' VS-103 As(+) 1 2 3.95 7.90
As(-) 1 2 3.95 7.90
Est. 1 2 1.00 2.00
SEGUNDO PISO
eje 1 y 2 VP-101 As(+) 2 2 19.45 77.80
entre eje A-F As(+) 2 1 19.45 38.90
As(+) 2 2 14.05 56.20
As(-) 2 2 19.35 77.40
As(-) 2 1 19.35 38.70
Est. 2 128 1.34 343.04
eje 3 VP-101 As(+) 1 2 20.25 40.50
As(+) 1 1 20.25 20.25
As(+) 1 2 15.45 30.90
As(-) 1 3 19.35 58.05
Est. 1 115 1.34 154.10
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

eje 4,5 y 6 VP-101 As(+) 3 2 7.59 45.54


entre eje A-C As(+) 3 1 7.59 22.77
As(+) 3 2 7.32 43.92
As(-) 3 3 7.45 67.05
Est. 3 48 1.34 192.96
eje 4,5 y 6 VP-101 As(+) 3 2 7.09 42.54
entre eje D-F As(+) 3 1 7.09 21.27
As(+) 3 2 6.77 40.62
As(-) 3 3 6.97 62.73
Est. 3 42 1.34 168.84
eje 7 VP-101 As(+) 1 2 19.45 38.90
As(+) 1 1 19.45 19.45
As(+) 1 2 14.00 28.00
As(-) 1 3 19.35 58.05
Est. 1 129 1.34 172.86
eje 8 VP-101 As(+) 1 2 17.25 34.50
As(+) 1 1 17.25 17.25
As(+) 1 2 12.55 25.10
As(-) 1 3 17.85 53.55
Est. 1 94 1.34 125.96
eje 9 Y 10 VP-101 As(+) 2 2 7.65 30.60
As(+) 2 1 7.65 15.30
As(+) 2 2 7.25 29.00
As(-) 2 3 7.55 45.30
Est. 2 43 1.34 115.24
EJE 9' VP-101 As(+) 1 2 2.95 5.90
As(+) 1 1 2.95 2.95
As(+) 1 2 2.54 5.08
As(-) 1 3 2.95 8.85
Est. 1 15 1.34 20.10
EJE 9' y 9'' VB-101 As(+) 2 2 4.70 18.80
As(-) 2 2 4.70 18.80
Est. 2 36 0.80 57.60
EJE A' VB-102 As(+) 2 2 3.66 14.64
As 2 4 3.66 29.28
As(-) 2 2 3.66 14.64
Est. 2 23 1.40 64.40
EJE A y F VS-101 As(+) 2 3 26.30 157.80
As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-101 As(+) 2 3 26.30 157.80
As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-102 As(+) 2 2 6.09 24.36
As(-) 2 2 6.09 24.36
Est. 2 40 1.50 120.00
EJE C y D VCH-101 As(t) 4 10 3.23 129.20
Est. 4 24 1.90 182.40
EJE C y D VB-101 As(t) 2 4 15.01 120.08
Est. 2 121 0.80 193.60
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

TERCER PISO
eje 1 y 2 VP-101 As(+) 2 2 19.45 77.80
entre eje A-F As(+) 2 1 19.45 38.90
As(+) 2 2 14.05 56.20
As(-) 2 2 19.35 77.40
As(-) 2 1 19.35 38.70
Est. 2 128 1.34 343.04
eje 3 VP-101 As(+) 1 2 20.25 40.50
As(+) 1 1 20.25 20.25
As(+) 1 2 15.45 30.90
As(-) 1 3 19.35 58.05
Est. 1 115 1.34 154.10
eje 4,5 y 6 VP-101 As(+) 3 2 7.59 45.54
entre eje A-C As(+) 3 1 7.59 22.77
As(+) 3 2 7.32 43.92
As(-) 3 3 7.45 67.05
Est. 3 48 1.34 192.96
eje 4,5 y 6 VP-101 As(+) 3 2 7.09 42.54
entre eje D-F As(+) 3 1 7.09 21.27
As(+) 3 2 6.77 40.62
As(-) 3 3 6.97 62.73
Est. 3 42 1.34 168.84
eje 7 VP-101 As(+) 1 2 19.45 38.90
As(+) 1 1 19.45 19.45
As(+) 1 2 14.00 28.00
As(-) 1 3 19.35 58.05
Est. 1 129 1.34 172.86
eje 8 VP-101 As(+) 1 2 17.25 34.50
As(+) 1 1 17.25 17.25
As(+) 1 2 12.55 25.10
As(-) 1 3 17.85 53.55
Est. 1 94 1.34 125.96
eje 9 Y 10 VP-101 As(+) 2 2 7.65 30.60
As(+) 2 1 7.65 15.30
As(+) 2 2 7.25 29.00
As(-) 2 3 7.55 45.30
Est. 2 43 1.34 115.24
EJE 9' VP-101 As(+) 1 2 2.95 5.90
As(+) 1 1 2.95 2.95
As(+) 1 2 2.54 5.08
As(-) 1 3 2.95 8.85
Est. 1 15 1.34 20.10
EJE 9' y 9'' VB-101 As(+) 2 2 4.70 18.80
As(-) 2 2 4.70 18.80
Est. 2 36 0.80 57.60
EJE A' VB-102 As(+) 2 2 3.66 14.64
As 2 4 3.66 29.28
As(-) 2 2 3.66 14.64
Est. 2 23 1.40 64.40
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

EJE A y F VS-101 As(+) 2 3 26.30 157.80


As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-101 As(+) 2 3 26.30 157.80
As(-) 2 3 26.87 161.22
Est. 2 166 1.04 345.28
EJE B y E VS-102 As(+) 2 2 6.09 24.36
As(-) 2 2 6.09 24.36
Est. 2 40 1.50 120.00
EJE C y D VCH-101 As(t) 4 10 3.23 129.20
Est. 4 24 1.90 182.40
EJE C y D VB-101 As(t) 2 4 15.01 120.08
Est. 2 121 0.80 193.60

TOTAL ML : 0.00 1547.51 5159.72 230.04 0.00 8459.60 389.00

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25

TOTAL KG : 0.00 3481.90 8062.06 230.04 0.00 4,758.53 97.25

TOTAL VAR : 0 172 573 26 0 940 43


TOTAL KG 16,629.78
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES
06.03 OBRAS DE CONCRETO ARMADO

06.03.07.03 ACERO GRADO 60 EN LOSA ALIGERADA BLOCK "B"

PRIMER PISO
ENTRE EJES A-B Sup. 1 11 12.48 137.28
Sup. 1 11 5.50 60.50
Inf. 1 11 26.03 286.33
ENTRE EJES B-E Sup. 2 4 5.50 44.00
Sup. 2 4 2.50 20.00
Inf. 2 4 14.34 114.72
ENTRE EJES E-F Sup. 1 12 5.50 66.00
Sup. 1 12 12.48 149.76
Inf. 1 12 26.03 312.36
ENTRE EJES G-H Sup. 1 12 7.48 89.76
Inf. 1 12 10.81 129.72
ENTRE EJES G-H Sup. 1 9 1.12 10.08
ENTRE 5 Y 6 Inf. 1 9 1.12 10.08
ENTRE EJES G-H Sup. 1 1 3.95 3.95
ENTRE 6 Y 7 Inf. 1 1 3.95 3.95
SEGUNDO PISO
ENTRE EJES A-B Sup. 1 11 12.48 137.28
Sup. 1 11 5.50 60.50
Inf. 1 11 26.03 286.33
ENTRE EJES B-E Sup. 2 4 5.50 44.00
Sup. 2 4 2.50 20.00
Inf. 2 4 14.34 114.72
ENTRE EJES E-F Sup. 1 12 5.50 66.00
Sup. 1 12 12.48 149.76
Inf. 1 12 26.03 312.36
ENTRE EJES G-H Sup. 1 1 5.50 5.50
Sup. 1 1 8.45 8.45
Inf. 1 1 18.86 18.86
TERCER PISO
ENTRE EJES A-B Sup. 1 11 12.48 137.28
Sup. 1 11 5.50 60.50
Inf. 1 11 26.03 286.33
ENTRE EJES B-E Sup. 2 4 5.50 44.00
Sup. 2 4 2.50 20.00
Inf. 2 4 14.34 114.72
ENTRE EJES E-F Sup. 1 12 5.50 66.00
Sup. 1 12 12.48 149.76
Inf. 1 12 26.03 312.36
ENTRE EJES G-H Sup. 1 1 5.50 5.50
Sup. 1 1 8.45 8.45
Inf. 1 1 18.86 18.86

TOTAL ML : 0.00 0.00 522.50 3335.45 28.06 0.00 0.00

COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25


TOTAL KG : 0.00 0.00 816.41 3335.45 15.78 0.00 0.00

TOTAL VAR : 0 0 58 371 3 0 0

TOTAL KG 4,167.64
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

06.03 OBRAS DE CONCRETO ARMADO

06.03.08.03 ACERO GRADO 60 EN LOSA MACIZA

PRIMER PISO
ENTRE EJES B-C, D-E H Sup. 2 7 12.59 176.26
(entre ejes 1-8) H Inf. 2 7 11.71 163.94
ENTRE EJES B-C, D-E H Sup. 2 10 6.43 128.60
(entre ejes 9-10) H Inf. 2 10 6.43 128.60
ENTRE EJES C-D H Sup. 1 15 4.38 65.70
(entre ejes 2-3) H Inf. 1 15 4.38 65.70
ENTRE EJES C-D H Sup. 1 10 3.30 33.00
(entre ejes 7-8) H Inf. 1 10 3.30 33.00
ENTRE EJES C-D H Sup. 2 10 2.33 46.50
(entre ejes 9-10) H Inf. 2 10 2.33 46.50
ENTRE EJES 2-3 V Sup. 1 19 6.86 128.63
(entre ejes B-E) V Inf. 1 19 6.86 128.63
ENTRE EJES 7-8 V Sup. 1 13 6.86 90.90
(entre ejes B-E) V Inf. 1 13 6.86 90.90
ENTRE EJES 9-10 V Sup. 2 9 6.77 116.78
(entre ejes B-E) V Inf. 2 9 6.77 116.78
ENTRE EJES 1-2 V Sup. 2 7 2.00 28.00
(entre ejes B-C Y D-E) V Inf. 2 7 2.00 28.00
ENTRE EJES 9-10 V Sup. 2 10 2.55 49.73
(entre ejes B-C Y D-E) V Inf. 2 10 2.55 49.73
SEGUNDO PISO
ENTRE EJES B-C, D-E H Sup. 2 7 12.59 176.26
(entre ejes 1-8) H Inf. 2 7 11.71 163.94
ENTRE EJES B-C, D-E H Sup. 2 10 6.43 128.60
(entre ejes 9-10) H Inf. 2 10 6.43 128.60
ENTRE EJES C-D H Sup. 1 15 4.38 65.70
(entre ejes 2-3) H Inf. 1 15 4.38 65.70
ENTRE EJES C-D H Sup. 1 10 3.30 33.00
(entre ejes 7-8) H Inf. 1 10 3.30 33.00
ENTRE EJES C-D H Sup. 2 10 2.33 46.50
(entre ejes 9-10) H Inf. 2 10 2.33 46.50
ENTRE EJES 2-3 V Sup. 1 19 6.86 128.63
(entre ejes B-E) V Inf. 1 19 6.86 128.63
ENTRE EJES 7-8 V Sup. 1 13 6.86 90.90
(entre ejes B-E) V Inf. 1 13 6.86 90.90
ENTRE EJES 9-10 V Sup. 2 9 6.77 116.78
(entre ejes B-E) V Inf. 2 9 6.77 116.78
ENTRE EJES 1-2 V Sup. 2 7 2.00 28.00
(entre ejes B-C Y D-E) V Inf. 2 7 2.00 28.00
ENTRE EJES 9-10 V Sup. 2 10 2.55 49.73
(entre ejes B-C Y D-E) V Inf. 2 10 2.55 49.73
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

TERCER PISO
ENTRE EJES B-C, D-E H Sup. 2 7 12.59 176.26
(entre ejes 1-8) H Inf. 2 7 11.71 163.94
ENTRE EJES B-C, D-E H Sup. 2 10 6.43 128.60
(entre ejes 9-10) H Inf. 2 10 6.43 128.60
ENTRE EJES C-D H Sup. 1 15 4.38 65.70
(entre ejes 2-3) H Inf. 1 15 4.38 65.70
ENTRE EJES C-D H Sup. 1 10 3.30 33.00
(entre ejes 7-8) H Inf. 1 10 3.30 33.00
ENTRE EJES C-D H Sup. 2 10 2.33 46.50
(entre ejes 9-10) H Inf. 2 10 2.33 46.50
ENTRE EJES 2-3 V Sup. 1 19 6.86 128.63
(entre ejes B-E) V Inf. 1 19 6.86 128.63
ENTRE EJES 7-8 V Sup. 1 13 6.86 90.90
(entre ejes B-E) V Inf. 1 13 6.86 90.90
ENTRE EJES 9-10 V Sup. 2 9 6.77 116.78
(entre ejes B-E) V Inf. 2 9 6.77 116.78
ENTRE EJES 1-2 V Sup. 2 7 2.00 28.00
(entre ejes B-C Y D-E) V Inf. 2 7 2.00 28.00
ENTRE EJES 9-10 V Sup. 2 10 2.55 49.73
(entre ejes B-C Y D-E) V Inf. 2 10 2.55 49.73

TOTAL ML : 0.00 5147.57 0.00 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 0.00 5147.57 0.00 0.00
TOTAL VAR : 0 572 0
TOTAL KG 5,147.57
DESCRIPCION TIPO # CANT L Ø 1" Ø 3/4" Ø 5/8" Ø 1/2" Ø 3/8" Est. 3/8" Est. 1/4"
VECES

06.03 OBRAS DE CONCRETO ARMADO

06.03.09.03 ACERO ESTRUCTURAL F'Y=4200 KG/CM2

PRIMER PISO
mesa de partes losa 1 4 1.74 6.84
losa 1 13 0.44 5.54
pedestal 1 8 0.90 7.08
pedestal 1 14 0.44 6.16
CUARTO PISO
vestidor varones losa 1 4 2.37 9.32
losa 1 17 0.44 7.39
pedestal 1 8 0.90 7.08
pedestal 1 14 0.44 6.16
vestidor damas losa 1 4 2.54 9.99
losa 1 18 0.44 7.89
pedestal 1 8 0.90 7.08
pedestal 1 14 0.44 6.16
cafetería losa 2 4 3.04 23.91
losa 2 21 0.44 18.71
pedestal 2 8 0.90 14.16
pedestal 2 14 0.44 12.32

TOTAL ML : 0.00 0.00 155.81 0.00


COEFICIENTE : 4.00 2.25 1.56 1.00 0.56 0.56 0.25
TOTAL KG : 0.00 0.00 87.64 0.00
TOTAL VAR : 0 0 17
TOTAL KG 87.64