1
Construction Project Management
What is project management?
It is the management processes through which the
Scope (the Works) stipulated in the specification is
completed within the Time and the Cost established
and with the Quality specified
First, the Scope and Quality is defined by the design
drawings and the specifications
Second, the completion Time will be decided through
the demands from ultimate users
Third, acceptable Cost will be established by the
contract between the Employer and the winning
contractor (winning bid)
3
2
5
3
Contractual Requirement- FIDIC 4th
Programme to be Submitted
14.1 The Contractor shall, within the time stated in Part II of these
Conditions after the date of the Letter of Acceptance, submit to the
Engineer for his consent a programme, in such form and detail as
the Engineer shall reasonably prescribe, for the execution of the
Works.
The Contractor shall, whenever required by the Engineer, also
provide in writing for his information a general description of the
arrangements and methods which the Contractor proposes to adopt
for the execution of the Works.
Revised Programme 14.2
If at any time it should appear to the Engineer that the actual
progress of the Works does not conform to the programme to
which consent has been given under Sub-Clause 14.1, the
Contractor shall produce, at the request of the Engineer, a revised
programme showing the modifications to such programme
necessary to ensure completion of the Works within the Time for
Completion. 7
4
Contractual Requirement- FIDIC MDB 2006
(b) each of these stages for work by each nominated
Subcontractor (as defined in Clause 5 [Nominated
Subcontractors],
(c) the sequence and timing of inspections and tests
specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the
Contractor intends to adopt, and of the major stages, in
the execution of the Works, and details showing the
Contractor’s reasonable estimate of the number of each
class of Contractor’s Personnel and of each type of
Contractor’s Equipment, required on the Site for each
major stage. 9
10
5
Schedule Control in International
Construction Contracts
The bases of Contract Administration are found in the
project management processes used for Schedule
Control and Cost Control.
Schedule Control, however, is not just controlling
time, but productivity and work resources
– Using these controls, the actual status of productivity and
work resources can be determined
11
12
6
Schedule Control based on FIDIC 87
International Conditions of Construction Contract(FIDIC).
Clauses related extension of time for completion
– Delays and cost of delay of Drawings. Clause 6 (4)
– Adverse Physical Conditions and Artificial Clause 12
Obstructions.
– Suspension of Work Clause 40
– Possession of Site Clause 42
– Extension of time for completion Clause 44
– Variations and change Clause 51
– etc.
14
7
Correlation between Cost Control, Schedule
Control and Contract Administration
Project Management
Schedule control Schemes
1.Bar Chart
This scheme was found by Henry Gant
during time of the world war II, so it is
called Gant chart
2.Network planning
(C.P.M.;Critical Path Method)
This scheme was found in the USA in
the late 1950s.
16
8
1.Bar chart schedule control Chart
17
1.Bar chart
Garden project
Work items
Planning
design
gardening
18
9
2.C.P.M.;Critical Path Method
19
Terrace
foundation 7
Pond
Planning design Excavation
1 2 3 5 8
2 3
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 2016
10
Network planning method
activity E activity G
3 5 6
activity A activity C
1 2 4
Arrow Diagram
21
22
11
Fundamental knowledge of Arrow
Diagram (2)
A C
1 2 4
A C
1 2 4
12
Fundamental knowledge of Arrow
Diagram (4)
E G
3 5 6
A C
1 2 4
E G
3 5 6
A C
1 2 4
13
CPM.;Critical Path Method
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Demolished Material
Re-movement (The arrow diagram)
4
2
Garden Plants Finishing
Procurement Planting
6 9 1
4 0
Terrace Terrace
Foundation works
7
Pond
Planning Design Excavation
1 2 3 5 8
2 3 27
28
14
Critical Path
The path comprise of the activities which all have ZERO
Total Float.
TF=0 d TF=0 d
7 14 15 21
Task B Task D
8 days 7 days TF=0 d
1 6 22 24
7 14 15 21
Task A Task F
6 days 11 15 3 days
7 10
1 6 Task C Task E 22 24
4 days 5 days
11 14 17 21
TF=4 d TF=6 d
The Longest path(s) through the network
29
15
Fundamental knowledge of the Arrow Diagram
- How to use the floating time -
The vertical dotted line has shows
1 only work sequence but not time
Excavation
2
3 Day
Activity A Activity C
1 2 4
4 days 6 days
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17day
32
16
Changing the schedule
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17day
Activity D needs to bet 4 days
Activity E Activity G
Activity B
3 5 6
5 days 3 days
Activity A Activity C
1 2 4
4 days 6 days
33
Activity A Activity C
1 2 4
4 days 6 days
34
17
Changing the Critical Path Method
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
day
Activity G
Activity E
3 5 6
5 days 3 days
Activity A Activity C
1 2 4
4 days 6 days
35
36
18
Back yard garden project Plan
Pond
housing
A A
Trace
B B
Pond
37
Trace
Pond
38
19
C.P.M.;Critical Path Method
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Demolished Material
Re-movement
4
2
Garden Plants Finishing
Procurement Planting
6 9 1
4 0
Terrace Terrace
Foundation works
7
Pond
Planning Design Excavation
1 2 3 5 8
2 3
39
40
20
Changing the schedule
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Demolished Material
Re-movement
4
2
Garden Plants Finishing
Procurement Planting
6 9 1
4 0
Terrace Terrace
Foundation works
7
Pond
Planning Design Excavation
1 2 3 5 8
2 3
41
Demolished Material
Re-movement
4
2
Garden Plants Finishing
Procurement Planting
6 9 1
4 0
Terrace Terrace
Foundation works
7
Pond
Planning Design Excavation
1 2 3 5 8
2 3
42
21
Project Management system
Time Management: CPM Program (Primavera P3)
43
Manpower allocation
(before)
44
22
Manpower Leveling
(after)
45
Resource Leveling
(before)
(after)
46
23
1) Construction Schedule at Tender
A schedule is attached to the tender document
Construction Schedule at Tender shall be established
based on conditions that tender documents provided
(inquiry package) and are set by the Employer
It shall take account of any changed conditions that are
given to all bidders that are issued after the tender, or
in clarifications with the bidders
It shall not take into account any changed conditions
that are issued after the tender, but may take into
account conditions that change after the contract is
executed and as a result of negotiations
47
2)Contract Schedule
48
24
2)Contract Schedule
3) Master Schedule
After receipt of the notice to proceed, the contractor
shall confirm the actual conditions of the site etc., and
establish a “Master Schedule”.
The Master Schedule shall be established on the same
base as the Contract Schedule.
If the contractor found some matters that it believes are
different than or are a change from the conditions of the
contract, it will notify the employer in writing of such a
change, but the contractor shall not take such conditions
into account in establishing the Master and Contract
Schedules
The Contractor shall prepare a changed schedule to
account for such changes as are necessary and submit
the revised schedule to the employer for his approval
and acceptance with in the time set in the contract.
50
25
4)Detailed Schedule & Method of
Statements
Monthly and/or weekly schedules shall be
established for execution of the works
Those schedules shall be established based on
the master schedule.
It is essential that all schedules shall be
established on the same basis as the
conditions that existed at the tender stage.
51
26
P-53
53
P-54
54
27
Productivity values in construction
Productivity levels are calculated from the work force
level divided by the quantity of work done
55
56
28
Equipment daily report sheet
EQUIPMENT DAILY REPORT
BULLDOZER
BULLDOZER
BULLDOZER
BULLDOZER
BULLDOZER
BULLDOZER
MG1 12G-GRADER
MG2 14G-GRADER
Date / /
SC1 SCRAPER
Section No.
Back Charge Code
NO CD NAME
Day Night
BD2 D-8
BD3 D-7
BD4 D-6
BD5 D-5
BD6 D-4
BD1 D-9
Shift
TOTAL
COST WORK
CODE DESCRIPTION
UNIT
QTY
SUB-CON CONTR.
NO DESCRIPTION
-
HR
-
HR
-
HR
REPORTED BY REMARKS ABBREVIATION
ID - NO. NO : NUMBER OF EQUIPMENT
CHECKED BY HR : WORKING HOURS
ID - NO.
57
29
Schedule control submitted by contractor
59
Construction
Schedule at Contract
tender stage. Schedule Master
Schedul Detailed
e Schedule
Tender
clarification
Commencement
Contract works
Tender Negotiation Signing of
contract
Letter of
acceptance
60
30
Cost Accounting vs. Cost Control
Cost control
Contract
Administration Schedule&Execution Accounting
31
Contract Cost control
Administration
Schedule&Execution Accounting
64
32
Basic Principle of Schedule and Cost Control
Planning Measuring
Compare
Schedules Progress
Explain
Compare
Budgets Incurred Cost
Explain
Controlling
65
33
Project Control: Earned Value
Budget at
Actual Completion
Cumulative values
Cost (BAC)
(AC)
Planned Value (PV)
Data Date
Time
67
Performance Index
Cost Performance Index (CPI)
– CPI = EV / AC
– If CPI < 1: Cost Overrun
– If CPI > 1: Cost Underrun
68
34
Conclusion
The essence of Schedule Control is to establish
schedules and maintaining of schedules based
on the same philosophy from the Schedule at
the Tender to the Detailed Schedule.
Construction Schedules are not just guideline of
execution of works, they are the guideline of
execution of its contract.
69
70
35
Cost Control analysis
Excavation work on the top of the hill shall be
implemented under the following conditions.
71
72
36
Step 1: Target Unit Price
Excavation volume of 100,000 m3
duration of 25 calendar days
Sunday 4days+contingency1day
actual work days: 25-(4+1) = 20days
The target productivity
100,000 m3 /20 days = 5,000m3/day
The total budget for this work is $ 24,000,000.
the target unit price:
$24,000,000/100,000 m3 = $ 240/m3
73
40,000m3
12days
37
Step 2 : Productivity analysis
40,000m3 60,000m3
12 calendar days 18 calendar days
75
76
38
Step 3 : To Date Unit Price
40,000m3
12 days
78
39
Step 5 : Theoretical To Complete Unit Price
40,000m3 60,000m3
12days
40,000m3 60,000m3
12days
80
40
Step 6 : to find out an appropriate
To Complete Unit Price
■ Productivity and Unit Price comparison
■ Target To Date Theo. To Compl.
Productivity 5,000m3/day 4,000 m3/day 6,000m3/day
Unit price $ 240/m3 $ 270/m3 $ 220/m3
81
41
Step 7 : Time extension and additional cost
40,000m3 60,000m3
days 13calendar days – (2+1)+3
83
84
42