PHYSICAL PROGRESS
As Per Schedule Actual Progress
Effective
Sino. Description Unit BOQ Quantity Remarks
Rate (Rs) Today Month Season Since Inception Today Month Season Since Inception
1 Clearing & grubbing ha 35,805 245 1.00 1.000 40.65 40.65 Km:74.500 - Km:75.000 (RHS). #VALUE!
5 Embankment - From Borrow cum 251 592,922 270 270.00 93,542.00 93,542.00 Km:69.600 - Km:69.650 (RHS). #VALUE!
FINANCIAL PROGRESS
1 Work Rs. Lacs 4,535,800,240 690,327 690,327 30,887,959 30,887,959
2 Escalation Rs. Lacs
Turnover Rs. Lacs - 4,535,800,240 - - - - 690,327 690,327 30,887,959 30,887,959
Remarks:
2 Km:47 Bhandgaon quarry crusher electrical works in progress. Primary to GSB trail run works in progress.
3 Retainig wall works for HMP / MMM in progress @ Girim Quarry Ch:69.000
Mobilization Status : -
1 Shuttring plates
DAILY PROGRESS REPORT
PROJECT Pune- Solapur, 4- Lane Project, NH-9.
CLIENT PSEPL
PACKAGE PKG 1 Date : 3-Mar-10 Wednesday
CONTRACTOR IJM( India) Infrastructure Ltd. Weather: Dry
PHYSICAL PROGRESS
As Per Schedule Actual Progress
Effective
Sino. Description Unit BOQ Quantity Remarks
Rate (Rs) Today Month Season Since Inception Today Month Season Since Inception
1 Clearing & grubbing ha 35,805 245 0.40 1.400 41.05 41.05 Km:77.500 - Km:77.700 (RHS). #VALUE!
Embankment - From
6 cum 125 422,185 - 901 901 #VALUE!
Excavation
7 Sub grade cum 256 1,074,399 229 2,520.80 12,062.80 12,062.80 Km:65.120 - Km:65.200 (LHS). #VALUE!
8 Median filling cum 260 172,719 #VALUE!
FINANCIAL PROGRESS
1 Work Rs. Lacs 4,535,800,240 852,300 1,542,627 31,740,259 31,740,259
2 Escalation Rs. Lacs
Turnover Rs. Lacs - 4,535,800,240 - - - - 852,300 1,542,627 31,740,259 31,740,259
Remarks:
1 Km:47 Bhandgaon quarry crusher electrical works in progress and Primary to GSB trail run works in progress.
2 Retainig wall works for HMP / MMM in progress @ Girim Quarry Ch:69.000
Mobilization Status : -
1 Shuttring plates
DAILY PROGRESS REPORT
PROJECT Pune- Solapur, 4- Lane Project, NH-9.
CLIENT PSEPL
PACKAGE PKG 1 Date : 4-Mar-10 Thursday
CONTRACTOR IJM( India) Infrastructure Ltd. Weather: Dry
PHYSICAL PROGRESS
As Per Schedule Actual Progress
Effective
Sino. Description Unit BOQ Quantity Remarks
Rate (Rs) Today Month Season Since Inception Today Month Season Since Inception
Embankment - From
6 cum 125 422,185 - 901 901 #VALUE!
Excavation
FINANCIAL PROGRESS
1 Work Rs. Lacs 4,535,800,240 1,200,212 2,742,839 32,940,471 32,940,471
2 Escalation Rs. Lacs
Turnover Rs. Lacs - 4,535,800,240 - - - - 1,200,212 2,742,839 32,940,471 32,940,471
Remarks:
1 Km:47 Bhandgaon quarry crusher electrical works in progress and Primary to GSB trail run works in progress.
2 Retainig wall works for HMP / MMM in progress @ Girim Quarry Ch:69.000
Mobilization Status : -
1 Primary crusher for Girim Quarry (Ch:69.00) has been moblised
DAILY PROGRESS REPORT
PROJECT Pune- Solapur, 4- Lane Project, NH-9.
CLIENT PSEPL
PACKAGE PKG 1 Date : 5-Mar-10 Friday
CONTRACTOR IJM( India) Infrastructure Ltd. Weather: Dry
PHYSICAL PROGRESS
As Per Schedule Actual Progress
Effective
Sino. Description Unit BOQ Quantity Remarks
Rate (Rs) Today Month Season Since Inception Today Month Season Since Inception
7 Sub grade cum 256 1,074,399 1,312.80 5,074.60 14,616.60 14,616.60 Km:66.200 - Km:66.560 (RHS), #VALUE!
Km:66.150 - Km:66.350 (RHS).
8 Median filling cum 260 172,719 #VALUE!
FINANCIAL PROGRESS
1 Work Rs. Lacs 4,535,800,240 514,086 3,256,925 33,454,557 33,454,557
2 Escalation Rs. Lacs
Turnover Rs. Lacs - 4,535,800,240 - - - - 514,086 3,256,925 33,454,557 33,454,557
Remarks:
1 Km:47 Bhandgaon quarry crusher electrical works in progress and Primary to GSB trail run works in progress.
2 Retainig wall works for HMP / MMM @ Girim Quarry Ch:69.000 0.750m out of 4m completed.
3 Pipe bedding laying in progress for culverts @ Ch: 70+164 and Ch: 72+460
Mobilization Status : -
1 Primary crusher for Girim Quarry (Ch:69.00) has been moblised
2 Bins erection for WMM plant completed @ Bhand gaon quarry
3 2 No's Tranisit Mixture( Shwing Sette- 6 cum capacity) has been Moblised to site
DAILY PROGRESS REPORT
PROJECT Pune- Solapur, 4- Lane Project, NH-9.
CLIENT PSEPL
PACKAGE PKG 1 Date : 6-Mar-10 Saturday
CONTRACTOR IJM( India) Infrastructure Ltd. Weather: Dry
PHYSICAL PROGRESS
As Per Schedule Actual Progress
Effective
Sino. Description Unit BOQ Quantity Remarks
Rate (Rs) Today Month Season Since Inception Today Month Season Since Inception
Embankment - From
6 cum 125 422,185 - 901 901 #VALUE!
Excavation
FINANCIAL PROGRESS
1 Work Rs. Lacs 4,535,800,240 775,077 4,032,002 34,229,634 34,229,634
2 Escalation Rs. Lacs
Turnover Rs. Lacs - 4,535,800,240 - - - - 775,077 4,032,002 34,229,634 34,229,634
Remarks:
1 Km: 47 Bhandgaon quarry crusher electrical works Completed and Primary to GSB trail run works in progress.
2 Retainig wall works for HMP / MMM @ Girim Quarry Ch:69.000 1m out of 4m completed.
3 Pipe bedding laying in progress for culverts @ Ch: 70+164 and Ch: 72+460
Mobilization Status : -
1
2