Abstract

S no Particular Unit Qty Indian Amount


Rate
A Concrete

1 pile Cum 139.887 25000 3497175


2 pile cap Cum 68.75 14000 962500
3 pier Cum 233.145 14000 3264030
4 pier cap Cum 132 14000 1848000
5 trapeziodal section Cum 63.25 14000 885500

6 support beam Cum 39.6 14000 554400


7 slab Cum 200 14000 2800000
Total 13811605

B Steel MT 140.26112 60000 8415667.2

C For Liner, 6668181.66


shuttering , all
equipments and
tools and tackles
etc

Total 28895453.86

Area of Bridge Sqm 80 10 800

Rate / 36119.31733
Sqm

Note It does not include preparing access to the project site ,


installation of crane , barge etc

It does not include labour camp construction


It does not include electrical costs , DG set cost
Measurement Sheet

S NO ITEM UNIT NOS LENGTH BREADTH HEIGHT

A Concrete
1 PILE Cum 44 0.63585 5
2 PILE CAP Cum 11 2.5 2.5 1
3 PIER Cum 11 1.76625 12
4 PIER CAP Cum 33 2 2 1
5 TRAPEZOIDAL Cum 11 10 1.5 1
SECTION

6 SUPPORT BEAM Cum 33 8 0.3 0.5


7 SLAB Cum 10 8 10 0.25

Total

B Steel KG

MT

C Shuttering
Pier Sqm 11 104
Quantity Considerations

139.887 pile dia 0.9


68.75 pier dia 1.5
233.145
132
63.25

39.6
200

876.632

140261.12

140.26112

1144