SCIENCE IT
Comparison Chart
BASIS FOR
NPV IRR
COMPARISON
Definition of NPV
When the present value of the all the future cash flows generated from a
project is added together (whether they are positive or negative) the result
obtained will be the Net Present Value or NPV. The concept is having great
importance in the field of finance and investment for taking important
decisions relating to cash flows generating over multiple years. NPV
constitutes shareholder’s wealth maximization which is the main purpose of
the Financial Management.
NPV shows the actual benefit received over and above from the investment
made in the particular project for the time and risk. Here, one rule of thumb is
followed, accept the project with positive NPV and reject the project with
negative NPV. However, if the NPV is zero, then that will be a situation of
indifference i.e. the total cost and profits of either option will be equal. The
calculation of NPV can be done in the following way:
Definition of IRR
IRR for a project is the discount rate at which the present value of expected net
cash inflows equates the cash outlays. To put simply, discounted cash inflows
are equal to discounted cash outflows. It can be explained with the following
ratio, (Cash inflows / Cash outflows) = 1.
In this method, the cash inflows and outflows are given. The calculation of the
discount rate, i.e. IRR, is to be made by trial and error method.
The decision rule related to the IRR criterion is: Accept the project in which the
IRR is greater than the required rate of return (cut off rate) because in that
case, the project will reap the surplus over and above the cut-off rate will be
obtained. Reject the project in which the cut-off rate is greater than IRR, as the
project, will incur losses. Moreover, if the IRR and Cut off rate are equal, then
this will be a point of indifference for the company. So, it is at the discretion of
the company, to accept or reject the investment proposal.
4. Decision making is easy in NPV but not in the IRR. An example can
explain this, In the case of positive NPV, the project is
recommended. However, IRR = 15%, Cost of Capital < 15%, the
project can be accepted, but if the Cost of Capital is equal to 19%,
which is higher than 15%, the project will be subject to rejection.
6. When the timing of cash flows differs, the IRR will be negative, or
it will show multiple IRR which will cause confusion. This is not in
the case of NPV.
7. When the amount of initial investment is high, the NPV will always
show large cash inflows while IRR will represent the profitability
of the project irrespective of the initial invest. So, the IRR will show
better results.
Conclusion
Net Present Value and Internal Rate of Return both are the methods of
discounted cash flows, in this way we can say that both considers the time
value of money. Similarly, the two methods, considers all cash flows over the
life of the project.
During the computation of Net Present Value, the discount rate is assumed to
be known, and it remains constant. But, while calculating IRR, the NPV fixed
at ‘0’ and the rate which fulfills such a condition is known as IRR.
Leave a Reply
Your email address will not be published. Required fields are marked *
Comment
Name *
Email *
Website
POST COMMENT
TOP 5 DIFFERENCES
RELATED DIFFERENCES
Key Differences
2,381 likes