TECHNICAL SPECIFICATION
PTS 20.112
NOVEMBER 1995
PREFACE
PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication,
of PETRONAS OPUs/Divisions.
They are based on the experience acquired during the involvement with the design, construction,
operation and maintenance of processing units and facilities. Where appropriate they are based
on, or reference is made to, national and international standards and codes of practice.
The objective is to set the recommended standard for good technical practice to be applied by
PETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants, chemical
plants, marketing facilities or any other such facility, and thereby to achieve maximum technical
and economic benefit from standardisation.
The information set forth in these publications is provided to users for their consideration and
decision to implement. This is of particular importance where PTS may not cover every
requirement or diversity of condition at each locality. The system of PTS is expected to be
sufficiently flexible to allow individual operating units to adapt the information set forth in PTS to
their own environment and requirements.
When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the
quality of work and the attainment of the required design and engineering standards. In
particular, for those requirements not specifically covered, the Principal will expect them to follow
those design and engineering practices which will achieve the same level of integrity as reflected
in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his
own responsibility, consult the Principal or its technical advisor.
Subject to any particular terms and conditions as may be set forth in specific agreements with
users, PETRONAS disclaims any liability of whatsoever nature for any damage (including injury
or death) suffered by any company or person whomsoever as a result of or in connection with the
use, application or implementation of any PTS, combination of PTS or any part thereof. The
benefit of this disclaimer shall inure in all respects to PETRONAS and/or any company affiliated
to PETRONAS that may issue PTS or require the use of PTS.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual
arrangements, PTS shall not, without the prior written consent of PETRONAS, be disclosed by
users to any company or person whomsoever and the PTS shall be used exclusively for the
purpose they have been provided to the user. They shall be returned after use, including any
copies which shall only be made by users with the express prior written consent of PETRONAS.
The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be held in safe
custody and PETRONAS may at any time require information satisfactory to PETRONAS in order
to ascertain how users implement this requirement.
REVISION REGISTER
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
3 ABBREVIATIONS
4. UNITS/METRICATION
5. MATERIAL SPECIFICATION
5.1 MATERIAL
5.2 CERTIFICATION OF MATERIALS
6. WELDING CONSUMABLES
6.1 ELECTRODES, WIRES AND FLUXES
6.2 CONDITION AND STORAGE
6.3 HEATING AND BAKING REQUIREMENTS
10 FABRICATION
10.1 GENERAL
10.2 ALIGNMENT AND FIT-UPS
10.3 FINISHING OF SURFACES
10.4 PROTECTION OF PIPE ENDS
10.5 REPAIR AND REMEDIAL PROCEDURES
11 QUALITY ASSURANCE
13. DOCUMENTATION
14 REFERENCES
15. APPENDIX I - Table I - Non Destructive Testing
APPENDIX II - Table II - Preheat and PWHT Temperatures
1. SCOPE
This specification governs requirements of welding, fabrication and inspection of process and
utility piping systems fabricated in the shop or in the field.
For non or less critical applications, e.g. low pressure service, some of the requirements of
this specification may be waived or reduced. This will, in individual cases, be subjected to
review and approval by THE COMPANY
2. DEFINITIONS
Throughout this specification, the following definitions apply :
• 'THE COMPANY' means PETRONAS who has placed the contract for construction.
• 'The CONTRACTOR' means the fabricator to whom the contract has been awarded.
• 'The SUBCONTRACTOR' means a fabricator to whom the CONTRACTOR awards any
part of the work.
• 'SHALL' is used to indicate a requirement.
• 'SHOULD' is used to indicate a recommendation.
• 'MAY' is used to indicate one acceptable course of action subject to COMPANY approval.
• "APPROVAL" is a written response from THE COMPANY confirming agreement to the
proposal by the CONTRACTOR.
3. ABBREVIATIONS
AISI American Iron and Steel Institute
ANSI American National Standards Institute
ASME American Society of Mechanical Engineers
API American Petroleum Institute
ASTM American Society For Testing and Materials
ASNT American Society For Non-Destructive Testing
ASNT SNT-TC-1 A Personnel Qualification and Certification in Non-destructive Testing.
AWS American Welding Society
BS British Standard
CEV Carbon Equivalent Value
CSR Company Site Representative
CSWIP Certification Scheme For Welding Inspection Personnel
DAC Distance Amplitude Curve
PTS PETRONAS Technical standard
DIN Deutsches Institute For Normung
DPI Dye Penetrant Inspection
GMAW Gas Metal Arc Welding
GTAW Gas Tungsten Arc Welding
HAZ Heat Affected Zone
IQI Image Quality Indicator
ISO International Organisation For Standardization
MPI Magnetic Particle Inspection
NACE National Association of Corrosion Engineers
NDT Non Destructive Testing
PCN Personnel Certification in NDT
PQR Procedure Qualification Record
PWHT Post Weld Heat Treatment
RT Radiographic Testing
SAW Submerged Arc Welding
SES Standard Engineering Specification
SMAW Shielded Metal Arc Welding
UT Ultrasonic Testing
WPQT Welding Procedure Qualification Test
WPS Welding Procedure Specification
4. UNITS/METRICATION
The Sl system and units of measurement shall be used. Imperial units may be indicated
where necessary e.g. where referenced standards are available only in Imperial units.
5. MATERIAL SPECIFICATION
5.1 MATERIAL
All steel pipes, flanges and fittings, etc. that shall be welded shall comply with the
requirements of PTS 20.081.
6. WELDING CONSUMABLES
7.1 GENERAL
Detailed welding procedures shall be established and qualified in accordance with ASME IX,
Article II and as further required by this Specification. All procedures shall be submitted to
THE COMPANY for review and approval before any welding procedure qualification is
commenced. The procedure test shall be witnessed by THE COMPANY or nominated
representative. All costs connected with the establishment of any welding procedures shall be
borne by the CONTRACTOR.
No fabrication welding shall commence until the appropriate procedure tests have been
completed and approved by THE COMPANY.
Copies of the approved Welding Procedure Specification (WPS) shall be readily available for
reference at any time by the welder or welding operator and THE COMPANY.
Procedures shall be established and qualified for repair welding. Special care shall be taken
when repairing areas suffering from cracking or lack of fusion.
NDT for qualification test pieces shall be delayed for at least 48 hours following the
completion of welding.
7.2 PARAMETERS
• Welding Procedure Specifications (WPS) shall contain the following applicable
parameters with all the explanatory details necessary.
• Material specification of base metals (including P number).
• Welding process, manual, semi-automatic or automatic.
• Wall thickness and diameter range for which the procedure is valid.
• Geometry of welding groove showing allowable tolerances.
• Root gap showing allowable tolerances.
• Welding position and direction.
• Filler metal specification, brand and diameter.
• Filler metal classification.
• Flux specification and brand.
• Gas shielding, flow, mixture and composition (to include back purging).
• Number and sequence of all passes, (indicate stringer or weave beads).
• Welding current range, voltage range and polarity. If pulse welding is used, the pulse
range.
• Travel speed or electrode run out length for each pass and range.
• Heat input range (KJ/mm)
• Preheat and interpass temperatures.
• Postweld heat treatment (PWHT).
• Method of gouging and cleaning.
8.1.7 Retest
If the test joint does not meet the specified requirements, the welder or welding operator may,
at the discretion of THE COMPANY, carry out a new test joint of the same type as the one
rejected and provided the cause of failure is determined and is not attributed to inadequate
training. Failing of both these tests shall result in the disqualification of the welder or welding
operator for a period of one month employed on the work.
8.1.8 Welder Qualification Record
A record of each welder or welding operator qualification test, including a reference to the
corresponding WPS number, the essential variables according to ANSI/ASME IX and the test
results, shall be issued by the CONTRACTOR for each qualification test successfully
completed.
9. PRODUCTION WELDING
9.1 GENERAL
All production welding shall be in accordance with the requirements of ANSI/ASME B31.3 and
this Specification.
No welding shall be carried out before the welding procedure specifications and the
procedure qualification records are completed and approved and the welders have been
qualified.
Preparation and welding of pipe and pipe components shall be in accordance with the
appropriate qualified WPSs. No welding shall be done until as much of the piping system as
will be stiffened thereby has been properly aligned.
Attention shall be given to the necessity of achieving adequate firm support of the pipe
components in both the vertical and horizontal plane.
When alignment is required for two pipe components of an unequal thickness which will be
joined by a butt weld, this shall be done by tapering the thicker component to a 1:4 taper. This
shall be prepared as much as possible by machining in a shop rather than grinding in the
field.
Current return cables of welding equipment shall be connected directly to the pipe on which
the welding work is to be done.
No production welding shall be carried out before, where applicable, a hot-work permit has
been obtained.
9.12 CLEANING
Upon completion of each welding pass, the weld shall be cleaned of spatter, slag and flux
deposits. After welding is completed, adjacent surfaces shall be thoroughly cleaned of all
spatter and deposits.
Only stainless steel wire brushes and grinding disc that have not been used on carbon, low
alloy materials or galvanised steels shall be used for stainless steels.
9.14 PEENING
Peening may be used on intermediate weld layers for control of shrinkage stresses in thick
welds to prevent cracking. Any such operation shall be carefully controlled. No peening shall
be done to the root or surface layer of the weld.
9.15 DISTANCE BETWEEN WELDS
Minimum distance between girth welds shall be the greater of either 50 mm, 4 times the wall
thickness or one half the nominal diameter.
10.0 FABRICATION
10.1 GENERAL
All measures shall be taken to ensure correct positioning and swing of the components to be
welded.
Work shall not be performed when the weather and/or lack of sufficient protection does not
permit satisfactory workmanship or when conditions prevent adequate inspection.
If any fabrication is to be carried out in the vicinity of equipment already installed then, before
such fabrication work commences, adequate protection shall be provided to prevent any
damage from weld spatter, flame cutting droplets etc.
Care shall be taken to avoid overloading, damage or undue deformation in any of the pipe
components at all stages of the work.
The full pipe joint shall not be used, if laminations or split ends were discovered in any pipe.
12.1 GENERAL
The CONTRACTOR shall be responsible for undertaking all the inspection and
non-destructive testing (NDT) required by this specification, and any such activity carried out
by THE COMPANY shall not absolve the CONTRACTOR of this responsibility.
The CONTRACTOR shall maintain a quality control function, responsible for undertaking all of
the inspection and NDT requirements of this specification, which is independent of other
fabrication functions.
The CONTRACTOR shall as part of the Quality Assurance requirements of Section 11 of this
specification, formulate a Quality Control Plan which shall be submitted to THE COMPANY
for approval. The QC Plan shall include detailed procedures for all inspection and NDT
techniques, including proposed report formats and the names and qualifications of inspection
and NDT personnel.
THE COMPANY shall have the right to inspect the fabrication erection of all items covered by
this Specification. Any weld defects, damage due to fit up, arc strikes or other weld features
which THE COMPANY specified as deficient or detrimental to the integrity of the structure
shall not be acceptable.
COMPANY's inspection personnel shall have free access at all times to any part of the
CONTRACTORS' or his SUB-CONTRACTORS' yard and facilities that are concerned with
the Works. They shall be given full co-operation and allowed sufficient time for all inspection
and testing procedures to be properly executed. The CONTRACTOR shall carry out all
necessary cleaning of the area necessary to facilitate inspection and testing.
No testing shall be carried out within 48 hours of completion of welding without COMPANY's
approval.
The CONTRACTOR shall furnish, install and maintain in safe operating condition all
scaffolding, ladders, walkways, adequate lighting, etc. necessary for safe and thorough
inspection. These must conform with local industrial and safety codes.
THE COMPANY shall have the right to inspect the work and any tools or equipment to be
used on the work, at any time and shall have the right to condemn any equipment or work
which does not conform with the Contract documents.
The CONTRACTOR shall inform THE COMPANY at least 48 hours prior to commencing any
work so as to enable THE COMPANY to adequately arrange any inspection and testing
deemed necessary.
When required by the Contract documents, the CONTRACTOR shall provide complete on site
facilities for radiography, ultrasonic, magnetic particle and dye penetrant inspection of welds
including equipment for developing and viewing films and the full time services of qualified
technicians conversant with radiographic and ultrasonic inspection techniques.
Any inspection by THE COMPANY shall not absolve the CONTRACTOR from his
responsibility to exercise such quality assurance procedures as will ensure that the
requirements and intent of this Specification are satisfied.
Final acceptance of Post Weld Heat Treated (PWHT) joints shall be done after PWHT.
NOTES:
1. Partial hydrogen pressure > 7 bar.
2. Ultrasonic examination may be applied if the configuration precludes radiography
3. The indicated percentage of welds to be radiographed shall apply to all welders involved.
4. Small bore nipples to be included.
5. The following film qualities shall be applied:
- For X-ray fine grain may be used, e.g. Agfa D7, Kodak, Industriex AX.
- For J-ray ultra-fine grain film shall be used, e.g. Agfa D4, Kodak Industriex MX.
6. N.A. = Not Applicable.
7. MPI = Magnetic Particle Inspection.
APPENDIX II
NOTES:
1. PWHT is required for CEV > 0.45 or C > 0.23%.
2. Temperature for optimum high-temperature properties.
3. Temperature range in the case of service for H2 or general refinery services.
4. Temperature range for maximum softening.
5. For hydrogen service PWHT is required irrespective of the wall thickness.
6. If ambient temperature is below 5°C, preheat to 40°C is recommended.
7. Low-hydrogen consumables shall be applied.
8. Minimum holding time one hour.
The post-weld heat treatment furnace temperature shall not exceed 300°C at the time of
insertion of the workpiece.
NOTE: NDT for acceptance purposes shall be carried out after final post-weld heat treatment.