net/publication/290958306
CITATIONS READS
34 2,245
4 authors, including:
Marko Starbek
University of Ljubljana
43 PUBLICATIONS 397 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
P2-0270: Production systems, laser technologies and material welding - PLAS View project
All content following this page was uploaded by Janez Kušar on 02 December 2016.
The market requires that companies continuously reduce their product and process development
time and costs, in order not to lose their competitive advantage on the global market. Short product and
process development time in combination with low costs and achievement of required quality can be
obtained only by integrating project management methods with concurrent engineering elements.
Project management of orders combined with concurrent engineering elements allows for
considerable reduction of development time, reduction of costs, and provides for a higher quality of
order/product [1].
Order planning phase is very important in integrated product/process development. In the
traditional product/process development, on average only 3% of total order development time is used for
planning, while at the concurrent concept this time increases to about 20% [2].
The company which has decided for the integrated product/process development as a mode of its
operation, first has to carry out organization and information redesign of its business process, as well as
to make system and operation project management guidelines.
The paper presents an example of project management implementation in a company, the
emphasis being on the development of planning procedure and project management of orders, as well as
design of a project dossier.
© 2008 Journal of Mechanical Engineering. All rights reserved.
Keywords: project management, orders management, project management office, dossier,
cuncurrent engineering
*
Corr. Author's Address: University of Ljubljana, Faculty of Mechanical Engineering, Aškerčeva 6, Ljubljana,
588
Slovenia, janez.kusar@fs.uni-lj.si
Strojniški vestnik - Journal of Mechanical Engineering 54(2008)9, 588-606
Resource
Portfolio
Portfolio
Project
Goals
Asset
FUNCTION RESPONSIBILITY
and managers of functional units),
• project information system administrator
(information support for projects and PMO),
• project process analyst (planning and
...
1.3. Creation of System- and Operational experience obtained during tender preparation are
Guidelines for Project Management of Orders an important source of information for the
implementation project preparation.
Studies have shown that a company, which Order management project therefore has to
has decided to use project management of orders, be carried out in two phases:
has to develop system- and operational guidelines Phase 1: Planning and management of a tender.
(Figure 5), which have to be harmonized with Phase 2: Planning and management of
other system- and operational guidelines of the implementation project.
company.
For each project it is necessary to set up a 1.4.1 Planning and Management of Making a
project dossier – a data warehouse of all Tender for an Order
data/documents produced in the project lifetime.
For easier survey, the project dossier is divided A tender is made on the basis of customer
into folders with documents related to a particular inquiry or internal initiative in an organizational
process type (Figure 6). The project dossier has to unit of the company. Company management
be accessible to all project participants via the should check whether the proposal is in
intranet. accordance with objectives and strategies of the
company. If it is, then the company management
1.4. Method for Planning and Project orders that a tender be made and appoints an ad
Management of Orders hoc project team, which (on the basis of customer
requirements and market analyses) obtains as
The studies on introduction of project much input data as possible and examines the
management of orders in companies have shown history and experience on similar, reference
that the order management process has to be dealt projects.
with in a holistic manner. The data and
Figure 5: Overview of system- and operational guidelines for project management of orders
The course of making a tender is presented in By signing the contract the foundations are
Figure 7. made for planning and management of the
Ad hoc project team is usually managed implementation project.
by the marketing-department representative. Its
members are from development, technology, 1.4.2 Planning and Management of
manufacturing and, when necessary, from other Implementation Project of an Order
departments of the company. The future project
manager is also a member of the ad hoc project Planning and management of the
team. The result of work of the ad hoc project implementation project of an order consists of a
team is an estimate of the economic justification logical sequence of all the activities needed for
and feasibility of the project, including risk the preparation and implementation of the project,
analysis. If the estimated economic justification as well as the documents resulting from
and feasibility of the project are promising, the individual activities.
tender is made in accordance with the customer Planning and management of the
requirements. The tender contains technical and implementation project of an order for new
financial data, as well as data on deadlines – the product development is similar to execution of a
Gantt chart of the project tender. previously developed product, the difference
If the tender is successful, a contract is being in individual activities.
signed, which defines: project deliverables, Project manager and project team are
quality, deadline with milestones, costs and responsible for the execution of planning and
method of payment, supervision and report on the managing of implementation project.
course of the project.
ACTIVITY PROJECT DOSSIER - DOCUMENTS
In
accordance with NO
the company's
goal?
Project proposition
YES
FEASIBILITY STUDY, Cost and feasibility
Working PROJECT COST EVALUATION, evaluation
direction PROJECT RISKS
YES
NO NO
Accepted Supplementing Breaking off the bidding
the bidding
YES
SIGNING THE CONTRACT
points for the project - tender documentation; risk analysis with measures, communication
general and specific objectives of the project; plan and plan for management of changes,
strategies for meeting the deadlines; scope of the • basic plan of implementation project activities.
project; data on project manager, his deputy and Work breakdown structure (WBS)
project team members; data on other project represents a structured breakdown of the whole
participants: suppliers, sub-contractors, customer, project [8], [10] and [14] into smaller and
control; reference project; feasibility study; the manageable tasks. WBS is important in terms of
way of ensuring the required resources; the management of time, costs and risks of the
investment dynamics and ROI data; pre- project [15]. WBS defines the scope of the project
calculation; milestones: external and internal; and all the activities necessary for project
general risk assessment; the way of monitoring objectives completion.
the project and reporting to the contracting WBS of the implementation project
authority and to the customer. (Figure 9) consists of four main groups of tasks:
definition of project objective, planning the
1.4.2.2 Planning of Implementation project, implementation and monitoring of the
Project of an Order project, and completion of the project.
The tasks listed comprise activities for all
Planning the implementation project is a phases of the implementation project.
responsibility of the project team, which has to The "Implementation and monitoring of
make: the project" task is – on the basis of the assembly
• work breakdown structure of the structure of the product – divided into groups of
implementation project – WBS, parts, sub-groups and parts (PtBS – part
• organization breakdown structure of the breakdown structure).
implementation project – OBS, The tasks defined within PtBS can be
• responsibility assignment matrix, performed sequentially or parallelly [5].
• network diagram of the implementation project, Planning and manufacturing of
• proposal of the plan of the implementation components is treated in a process manner (PsBS
project: schedule, plan of resources and costs, – processes breakdown structure) (Figure 9).
Tasks (packages of activities) can be
performed sequentially or parallelly [5].
Product and
Technology
Consultants
Marketing
process
Suppliers
Auditors
Finance
Quality
Supply
development
Sales
phases (WBS)
WBS
1.4.2.4 Completion of the Project The company management found that for
introduction of project management into the
After the project has been completed, the company, the employees do not have the required
project manager and project team members knowledge. In collaboration with the Centre of
perform project evaluation, which includes: excellence for modern automation technologies
analysis of objectives achieved, deviations of on the Faculty of Mechanical Engineering in
time, resources, costs, risk analysis and important Ljubljana several seminars and workshops have
conclusions for future projects. The project board been organized, where the employees obtained
confirms the project evaluation. the required knowledge on project management,
Project is completed when a total project teamwork, creativity, communications and
dossier has been elaborated; it comprises full concurrent engineering. The seminar participants
tested their newly obtained knowledge in solving company's intranet; all project participants can
actual problems in their company. obtain the project-related data on that site.
2.2. Organization and Information Setup 2.3. Creation of System- and Operational
Guidelines
In the past, the company was organized
according to the functional principle. Based on an Company management organized the
analysis of a suitable company organizational creation of system- and operational guidelines.
form, the company management selected a Project team, responsible for project management
balanced matrix company organization. The implementation in the company, made project
decision was based on the fact that project management rules, where project management
decision-making is equally divided between the system was defined, as well as a procedure for
project manager (regarding project management project planning and management, and the
and achievement of goals) and heads of company content of a project dossier. The project
functional units (for carrying out project activities management rules were adjusted to the company
and ensuring product quality). quality management rules. As an aid to project
A product and service project board was managers and project team members, a project
appointed, managed by the company executive management handbook was made, which
director and consisting of project managers and contained practical guidelines and templates of all
functional unit heads. documents appearing in folders and project
A PMO was established for organizational dossier. For execution of individual processes
and technical project management support. It was (bid, product and process development and
managed by the project management assistant to validation, test manufacturing) operational
the executive director and it consisted of project guidelines have been used that had already been
management administrator, project control made for the company quality management
analyst, administrator and all professional project system, so they have been just harmonized with
managers. the project management rules.
Responsibilities (OBS)
Industrialization
Development
Management
Project team
Cooperation
Production
Marketing
Suppliers
& design
Purchase
Quality
Product and process development
phases (WBS)
Project preparing S P S I I
Develop ment and design of product S I P S S I
Develop ment and design of process S S P S I I I I
Qualification of product and process I S S S P S S S S
Serial p roduction and project completion P S
Afterwards, team members formed a After the network diagram had been made,
project OBS (Figure 15); they included into it the project team members defined duration of
those functional units of the company, which each activity they allocated the required resources
would provide resources for the implementation and defined the data required for cost analysis.
of activities, as well as external suppliers and sub- MS Project software was used for time-,
contractors. Responsibilities assignment matrix resources- and cost analysis. A period of 644 days
was made for easier coordination between project would be required for project implementation
management and functional-units management using the As-Is process.
(Figure 16). The responsibilities were presented During the risk analysis all project
by symbols (P – primary, S – secondary, I – activities were checked, risk types were defined,
informational responsibility). risk levels were calculated and preventive and
During project planning, the creation of a corrective measures were defined if necessary.
project network diagram was the most difficult The output of the project team was a
and most critical task for the project team. Only proposal of the implementation project plan with
the network diagram that realistically and risk analysis. It was sent to the project board for
logically defines dependencies between project confirmation. After the project has been
activities can serve as a useful tool for further confirmed its implementation could begin.
planning and management of project After the order implementation project had
implementation. Project team members made been made in accordance with the existing
activity card (label) for every activity. Then they implementation process, the project team began
logically connected activities into a network designing an implementation project plan, which
activity diagram (Figure 17). In this process they would, as far as possible, include elements of
defined the As-Is order implementation project concurrent engineering.
process as precisely as possible.
Fig. 17. Part of network diagram for car pedal component (sequential engineering)
Fig. 18. Part of network diagram for car pedal component (concurrent engineering)
It is obvious that by incorporating
Procedure for designing implementation
concurrent engineering elements, the project
project plan is similar as in a classical project
implementation changes because its processes
implementation, with the following important
overlap (APQP) and the network diagram
differences:
structure changes, too – the goal is to achieve as
1. It is necessary to ensure as much as possible
high concurrency as possible. Because of a partial
concurrency of process implementation,
overlapping of interdependent activities, their
defined by the APQP methodology [21].
execution time may even extend – without
2. It is necessary to find which activities within
extending the project duration time. Incorporation
processes can be executed concurrently, so that
of concurrent engineering elements does not
maximum overlapping is achieved, and to
influence the WBS and OBS project structures
define the values of partial dependencies
(Figure 18).
between network diagram activities.
The process overlapping and partial
3. It is necessary to define concurrent engineering
dependencies between project activities require a
loops.
high level of collaboration between the holders of
4. It is necessary to form teams (sub-teams) for
responsibilities and operators of activities, so it is
implementation of concurrent engineering
necessary to introduce concurrent engineering
loops.
loops [1] and [2], as shown in Figure 19.
Fig. 19. Concurrent engineering loops during product and process development for car pedal component
Three concurrent engineering loops were risk. Nevertheless, they decided to implement this
defined for the car pedal component project: project in a new, more demanding way. They
• product development loop were aware that they have insufficient knowledge
• process development loop of concurrent engineering, so they asked the
• qualification of the product and process loop. experts of the Centre of excellence for modern
technologies on the Faculty of Mechanical
Within an individual loop, various Engineering in Ljubljana for technical assistance.
activities are being carried out concurrently by
resources from various functional units and by 2.4.3 Implementation and Monitoring of the
external contractors. To ensure on-line Project
information exchange between operators of
various activities, sub-teams are formed within According to the project plan, the project
the project team for implementation of concurrent manager sends (in electronic form – using MS
engineering loops (Figure 20). Outlook) to team members and functional unit
heads the information about activities that should
start with a special document containing data on
planned activities, their duration and the planned
date of beginning and completion. The same
document has fields for entering dates of actual
beginning and completion of activities.
A project team member from a particular
functional unit is responsible for monitoring the
implementation of activities and for current
reporting on status of activities to the project
manager, while functional unit head is
responsible for the implementation of activities
within the prescribed deadline and for
achievement of the required quality. Reports on
the implementation of activities are made once a
week.
Project manager promptly stores the actual
data into the MS Project software.
Project team makes a weekly snapshot of
Fig.20. Team structures of concurrent project status. It finds out which activities have
engineering loops been finished completely and which have been
Loop teams consist of representatives finished just partially. On the basis of these data a
(operators) from those functional units, which calculation of the current project status is made.
concurrently carry out activities of an individual By comparing it with the initial plan, the team
concurrent engineering loop. members find which activities are delayed, which
Loop teams do not have permanent are carried out according to the plan and which
members – they change depending on the loop for are carried out faster. Also important are the
which the team is responsible or depending on the analyses of critical activities, critical paths and
activities that will be carried out within this loop. the costs incurred so far. Problems and risks are
After all changes had been made, the identified (so called "status indicators" are an aid
project implementation time was reduced from to the team members); they can be overcome by
644 to 419 days, which is 35% reduction of triggering an appropriate action plan made during
project duration. risk analysis, and additional measures can be
The company management was aware that taken if necessary.
project implementation on the basis of concurrent Project manager and team members are
engineering elements is a very demanding process responsible for the implementation of measures.
and its implementation is associated with a high If a measure exceeds their competences, they
forward it to the project board or to the company After the project has been completed, the
management. Project manager continuously keeps company management dissolved the project team
records of measure results. and appoints the sales department for execution
Weekly results on current situation of post-contract obligations.
snapshot are published on the project
management portal, listed by the whole project 2.5. Establishment of Multi-project
activities and separately by activities allocated to Environment
individual functional units of the company.
Project manager reports on the project After the analyses of the first results of
status and on the measures taken at the project planning and management of the test project, the
board meeting, where the project status is being company management decided that all new
harmonized with other current projects. projects should be managed using the described
An analysis of all current projects, procedure (one year later, more than 30 projects
especially in terms of the used resources and have been planned and managed in this way).
costs, is prepared by the PMO. PMO is responsible for project
According to the contract, the project coordination, especially for the use of common
status data are sent to the customer, who thus has resources and cost management.
an accurate overview of the project status and Every week PMO sends a report on
problems, and can participate in their solution. cumulative status of all projects to the company
management; the projects are classified in three
2.4.4 Completion of the Project categories:
• carried out according to the plan,
Project is completed when all the project • carried out according to the plan with some
activities have been carried out and the objectives discrepancies that are manageable,
met. When the project has been completed, the • critical, whose discrepancies are difficult to
project team made evaluation of project control or even beyond control.
including: In each individual case the company
• Meeting the deadlines and financial limits: management acts according to its strategy.
project was completed within the agreed
deadline and within the approved costs. 3 CONCLUSION
• Use of internal and external resources: there
were great difficulties with internal resources This paper deals with market-oriented and
associated with coordination of their value-added projects and services, especially
involvement in other projects. cyclically repeated projects, i.e. projects of
• Quality of project management and project implementing a previously developed
deliverables: was in accordance with project project/service in a specific form, in accordance
management rules and with the customer's with the customer's requirements, and projects
expectations, which was confirmed by two related to new product/process development,
audits made by a reviser authorized by the which are afterwards submitted to a mass
customer. production.
• Overview of the planned and performed risk Introduction of project management into a
measures: there were many more preventive company, as a mode of business process
and corrective measures prepared than actually operation, is a demanding task, because it
used. requires changes in the integration and focus of
• Experience obtained that is important for company functional units to the goals of the
similar future projects: regular meetings of company. It is important that project objectives
project team. Project team members have to be have higher priorities than functional unit
well prepared for a meeting – this is a priorities, and that project-friendly environment is
precondition for short end effective meetings. created in a company.
Likewise all other project dossier It is proposed that project management be
documentation, the final report was also introduced in the company in four steps.
published on the project management portal.
Before introducing project management The market requires as short delivery time
into a company, the employees have to be trained as possible and the highest possible quality, so it
to use new knowledge, methods and techniques is necessary to extend the order/service project
required for project management – and change planning and management methods with
their way of thinking: from focus to the company concurrent engineering elements. Concurrent
goals, the employees have to focus to the engineering is based on teamwork, track and loop
customer/market goals ("customer is the king" process of implementation and incorporation of
principle). Project management requires concurrent engineering tools. IT and
continuous and on-line exchange of information, communication support are required for
so it is important that employees learn to incorporation of concurrent engineering elements
communicate in a way of giving and receiving the (ERP, PDM and PLM systems).
right information, at the right time and related to The proposed methodology of project
the task they perform. In practice, a problem of management implementation, as well as planning
hiding information within the functional unit (or and management of products/services was tested
within an individual person) can still be found. It in a company, which is a development supplier of
is therefore important that the company components for automotive industry. On the basis
establishes a knowledge management system. of the proposed methodology of project planning
Success of introduction of project and management for products/services, the
management also depends on organizational and company management decided to create two
informational changes. Authors of this paper versions of a project plan.
propose that a transition from a functional to a The results have shown that the version of
balanced-matrix organization be made, with a project implementation, extended with concurrent
possibility of further transition to a project-type engineering elements, has some essential
organization. Our proposal can be justified by the advantages: shorter delivery time, higher quality,
fact that in this case an important advantage of somewhat lower costs, simultaneous elimination
functional units is retained. In these units of errors already in the concurrent engineering
specialist knowledge is concentrated, employees loops and not in later phases as in the sequential
have permanent training available and they get to engineering. In spite of a higher risk, associated
know modern trends in their field of speciality. with the implementation of a project in this way,
Members of functional units participate in the company management decided to test the
projects temporarily and during that time they proposed new method and carry out the project in
give their maximum contribution to a successful a new way. The customer agreed with that.
project implementation. Working in projects, they Insufficient capability and willingness of
gain experience, which they later transfer back to project participants for on-time, continuous and
their functional units. accurate communication and exchange of data
It is important that (especially in early and information turned out to be the main
phases – during project and process development) problem during project implementation.
the best and most qualified personnel is involved, Nevertheless, the results achieved have
so that decisions are made as fast as possible and been encouraging, so further research will be
optimal from the quality and cost point of view. focused mainly on the definition of criteria for
In the company there are several projects formation of concurrent engineering loop teams,
running concurrently (even several dozens), so it their internal and external information integration,
is essential to set up a PMO, which supports the and to methods for effective personal and
projects and provides management of the whole technical communication.
company project portfolio.
Project management procedures have been 4 REFERENCES
formalized by making system and operational
guidelines for project management, where [1] Kušar J., Duhovnik J., Grum J., Starbek,
procedures for the implementation of individual M. How to reduce new product
project phases and the contents of required development time. Robot. comput.-integr.
documents, which make a project dossier, are manuf., 2004,vol. 20, no. 1, p. 1-15.
defined precisely.
[2] Prasad B. Concurrent Engineering [11] Bridges D., Crawford K. How to startu
Fundamentals, Integrated Product and pand rollout a project office,
Process Organization, 1996, vol. I, http://www.systemcorp.com/framesite/do
Prentice Hall PTR, New Jersey wnloads/startup_frame.html, 2. sept. 2002
[3] Kendall I.G., Rollins C.S. Advanced [12] Block T.R., Frame J.D. Today's Project
Project Portfolio Management and the Office: Gauging Attitudes, PM Network,
PMO, J. Ross Publishing, Inc., 2003. August 2001.
[4] Fleischer M., Liker K.J. Concurrent [13] Duhovnik, J., Starbek, M., Dwivedi, S.N.,
Engineering Effectiveness: Integrating Prasad, B. Development of innovative
Product Development Across products in a small and medium size
Organisations, Hanser Garden enterprise. Int. j. comput. appl. technol.,
Publications, Cincinnati, 1997. 2003, vol. 17, no. 4, p. 187-201.
[5] Kušar J., Rihar L., Kisiček K., Starbek M. [14] Badiru B. A. Project Management in
Experiences at Project Management Office Manufacturing and High Technology
Implementation. Project network of Operations, John Wiley & Sons, Inc., New
Slovenia, 2004, vol. 7, no. 4, p. 42-46 (In York, 1996.
Slovene) [15] Engineer J.S. Progressive Manufacturing,
[6] Schlicksupp. H. Creative Search for Ideas J. Ross Publishing, Inc., 2005.
in a Company. Watter der Gruyter, Berlin [16] Turner J.R. The Handbook of project –
- New York, 1977 (In German) based management, The McGaww-Hill
[7] Cappels M. T. Financially Focused Project Compnies, 1993.
Management, J. Ross Publishing, Inc., [17] Brezovar A. Process orientated
2004. organisation of production in virtual
[8] PMBOK Guide, A guide to the project enterprices, PhD Thesis, University of
management body of knowledge, 3rd ed., Ljubljana, 2005 (In Slovenian).
Newtown Square: Project Management [18] Goodpasture C.J. Quantitative methods in
Institute, 2004. project management, J. Ross Publishing,
[9] Meredith R.J., Mantel J.S. Project Inc., 2004.
Management, A Managerial Approach [19] Risk management guide for DOD
(fifth edition), John Wiley &vSons, Inc., acquisition sixth edition, Department of
2003. defence, USA, 2006.
[10] Badiru B. A. Project management tools for [20] Michalski J.V., King G.D. Six sigma tools
engineering and management navigator, Productivity press, New York,
professionals, Industrial Engineering 2003.
Press, Instiute of Industrial Engineers, [21] Stamatis D.H. Advanced Quality Planning,
Norcross, Georgia, 1991. Productivity, Inc, USA, 2001.