3Td Corrigenda & Addenda to PWD (WB), SOR: 2015-16 Volume III: Road & Bridge Works

3rd. ADDENDA & CORRIGENDA


TO THEPWD (WB),SCHEDULE OF RATES- 2015-16
Volume III: Road & Bridge Works
[Effective from 01 12.2015]

Dated: 19thApril, 2016.

CORRIGENDA OF SCHEDULE OF RATES - 2015-16

1. Following Corrections to be made to the Item as shown below:


Item I
Page In place of To be read as
SI.
No.
No.
209 Table Granular Sub· base with Granular sub-base with
3.3·1 Graded Material Unit Quantity Graded Material Unit Quantity
(Table:· 400·1) (Table:· 400·1)

Grading III: cum Grading III: cum


13.2mm chips 0.1920 m3 26.5mm chips 0.4480 m3
11.2mm chips 0.2560 m3 5.6mm chips 0.5760 m3
5.6mm chips 0.5760 m3 Sand 0.2560 m3
Sand 0.2560 m3

Grading IV: cum Grading IV: cum


13.2mm chips 0.1920 m3 26.5mm chips 0.4480 m3
11.2mm chips 0.2560 m3 5.6mm chips 0.5120 m3
5.6mm chips 0.5120 m3 Sand 0.3200 m3
Sand 0.3200 m3
Grading V: cum
Grading V: cum 37.5mm chips 0.2560 m3
37.5mm chips 0.3449 m3 22.4mm chips 0.2560 m3
22.4mm chips 0.2938 m3 11.2mm chips 0.1920 m3
11.2mm chips 0.1277 m3 5.6mm chips 0.3200 m3
5.6mm chips 0.2555 m3 Sand 0.2560 m3
Sand 0.2555 m3

All districts Darjeeling All districtsof Darjeeling


of HillArea WB&Darjee HillArea
Granular Sub-base Granular Sub- lingPlainof
243 4.08 Unit WB&Darjee Unit
with Graded Material lingPlainof base with Graded Slg.Subdivn. Rate
Rate (Rs)
(Table:- 400-1) Slg.Subdivn. Material (Rs) (Rs)
(Rs) (Table:· 400·1

A. PlantMixMethod A. Plant Mix Method


Cum 378.00 437.00 Cum 381.00 432.00
(iii) Grading - III (iii) Grading - III Cum 383.00 438.00
Cum 380.00 444.00
(iv) Grading - IV 447.00 (iv) Grading - IV Cum 391.00 446.00
Cum 395.00
(v) Grading - V (v) Grading - V

B. Mix In Place Method B. Mix In Place


Method

(iii) Grading -III Cum 199.00 249.00 (iii) Grading - III Cum 202.00 243.00
(iv) Grading - IV Cum 200.00 255.00 (iv) Grading -IV Cum 203.00 250.00
(v) Grading - V Cum 215.00 259.00 (v) Grading - V Cum 211.00 257.00

1
• .. .lTd Corrigenda & Addenda to PWD (WB), SOR: 2015-16 Volume III: Road & Bridge Works
Item I
Page
SI. In place of To be read as
No.
No.
294 12.24 Integritytesting of Pile using Low Strain / Sonic Integrity Integrity testing of Pile using Low Strain / Sonic Integrity
Test / Sonic Echo Test method in accordancewith IS Test / Sonic Echo Test method in accordance with IS
14893 ........ all complete as per direction of Engineer-in- 14893 ........ all complete including mobilisation &
charge. demobilisation as per direction of Engineer-in-charge.
All districts ofW.B. & Darjeeling Hill Area
Darjeelingplain or Siliguri Sub
Division Rate~ Rate~ Rate ~
a) Within 50 km. radius from
696.50

Raj-Bhavan
b ) For Rest of South Zone & West 870.60
765.00 765.00 Zone

c) For North Zone 1160.80

2. TABLE NO. 1-2EX-OUTLET PRICES OF BITUMEN (Page 216 of SOR 2015-16) is replaced by the following:

Page 51. No.1 In place of To be read as


Description of item Unit
No. Item
Rates at outlets (f) Rates at outlets (f)
1 2 3 4 5 6
216 TABLE EX-OUTLET PRICES OF BITUMEN: At Haldia At Dhulagarh At Haldia At Dhulagarh
1·2
............................................................................................................................................................................................................ _ .
In.(on NH-6) In.(on NH-6)
.... ..~.:. _ _~i.!~~~~J~~I~).:y~=~9(~9.!~9.q) ~T ?~?~~:.gq :.*.:. _ ?~?'~~:Qq . ***
2 ~i.!~~~~J~~~~~~):Y.~=~9(~9./1qq) MT 33367.00 *** 33367.00 ***
3. _~i.!~.~.~n
(Bulk) :VG-30 (?9.!!.9.)' ~T ?~?~?:gg._._ *** 29642.00 ***
... ........ ~:.. . _~i.!~~~~_(~~~ked):VG-30 (60/70) MT 34328.00 *** 34328.00 ***
5. Bitumen (Bulk) :VG-40 (30/40) MT 30123.00 *** 30123.00 ***

6. Bitumen (Packed) :VG-40 (30/40) MT 34688.00 *** *** ***


• ••• _ ••• _ •••••••••• _ •••• _ _ ••••••••••••••••• •••• • ••••••••••••••••••• H ..

Penetration gr. Bitumen (Packed): MT ***


7. 36223.00 *** 36223.00
(10/20)
......................................................

8. Bituminous Emulsion (Bulk) MS Type MT 26239.00 *** 24035.00 ***


. _ ..
Bituminous Emulsion (Packed) MS
*** 32646.00 *** 32646.00
.............
:.... ..._ Ty.p~ ..
10. CRMB - 55 (Bulk) MT 32430.00 *** 32430.00 ***

11. CRMB - 55 (Packed) MT 38830.00 *** 36146.00 ***

12. CRMB - 60 (Bulk) MT 32850.00 *** 32850.00 ***

13. CRMB - 60 (Packed) MT 39166.00 *** 36566.00 ***

~~-rnA""
(TAPASH~. DEY)
Superintending Engineer
~
~.t._,

(DEBASHIS ROY)
Superintending Engineer
r

'~IDL«(W'''' Alub
(MALAY GHOSH) I~~
Engineer-in-Chief & E. O. Secretary &
Bridge Planning Circle. Planning & Monitoring Circle, Chief Engineer (HQ)
Public Works(Roads) Directorate & Public Works Directorate & Public Works Directorate &
Jt. Convenor of the Combined Schedule Convenor of the Combined Schedule Chairman of the Combined Schedule
Committee of PWD Committee of PWD Committee of PWD

2
3Td Corrigenda & Addenda to PWD (WB), SOR: 2015-16 Volume III : Road & Bridge Works

3rd. ADDENDA & CORRIGENDA


ff !~ TO THEPWD (WB), SCHEDULE OF RATES- 2015-16
~~(,&~ Volume III: Road & Bridge Works
pI 'I~/...), d, [Effective from 01 12.2015]
rr~~\ Dated: 19thApril, 2016.

CORRIGENDA OF SCHEDULE OF RATES - 2015-16

1. Following Corrections to be made to the Item as shown below:


Item I
Page In place of To be read as
SI.
No.
No.
209 Table Granular sub-base with Granular Sub·base with
3.3·1 Graded Material Unit Quantity Graded Material Unit Quantity
(Table:· 400·1) (Table:· 400·1)

Grading III : cum Grading III : cum


13.2mm chips 0.1920 m3 26.5mm chips 0.4480 m3
11.2mm chips 0.2560 m3 5.6mm chips 0.5760 m3
5.6mm chips 0.5760 m3 Sand 0.2560 m3
Sand 0.2560 m3

Grading IV: cum Grading IV: cum


13.2mm chips 0.1920 m3 26.5mm chips 0.4480 m3
11.2mm chips 0.2560 m3 5.6mm chips 0.5120 m3
5.6mm chips 0.5120 m3 Sand 0.3200 m3
Sand 0.3200 m3
Grading V: cum
Grading V: cum 37.5mm chips 0.2560 m3
37.5mm chips 0.3449 m3 22.4mm chips 0.2560 m3
22.4mm chips 0.2938 m3 11.2mm chips 0.1920 m3
11.2mm chips 0.1277 m3 5.6mm chips 0.3200 m3
5.6mm chips 0.2555 m3 Sand 0.2560 m3
Sand 0.2555 m3

All districts
of Darjeeling Granular Sub· All districtsof Darjeeling
Granular Sub-base WB&Darjee HillArea WB&Darjee HillArea
243 4.08 Unit base with Graded Unit
with Graded Material lingPlainof lingPlainof
(Table:- 400·1) Slg.Subdivn. Rate (Rs)
Material Slg.Subdivn. Rate
(Rs) (Table:· 400·1 (Rs) (Rs)

A. PlantMixMethod A. Plant Mix Method


Cum 378.00 437.00 Cum 381.00 432.00
(iii) Grading - III (iii) Grading - III Cum 383.00 438.00
Cum 380.00 444.00
(iv) Grading - IV 447.00 (iv) Grading - IV Cum 391.00 446.00
Cum 395.00
(v) Grading - V (v) Grading - V

B. Mix In Place Method B. Mix In Place


Method

(iii) Grading - III Cum 199.00 249.00 (iii) Grading - III Cum 202.00 243.00
(iv) Grading - IV Cum 200.00 255.00 (iv) Grading -IV Cum 203.00 250.00
(v) Grading - V Cum 215.00 259.00 (v) Grading - V Cum 211.00 257.00

1
3'd Corrigenda & Addenda to PWD (WB), SOR: 2015-16 Volume III: Road & Bridge Works

Item I
Page In place of To be read as
SI.
No.
No.
294 12.24 Integritytesting of Pile using Low Strain I Sonic Integrity Integrity testing of Pile using Low Strain I Sonic Integrity
Test I Sonic Echo Test method in accordancewith IS Test I Sonic Echo Test method in accordance with IS
14893 ........ all complete as per direction of Engineer-in- 14893 ........ all complete including mobilisation &
charge. demobilisationas per direction of Engineer-in-charge.
All districts of W.B. & Darjeeling Hill Area
Darjeelingplainor SiliguriSub
Rate'
DivisionRate ' Rate'
a) Within 50 km. radius from Raj·
696.50
Bhavan
b ) For Rest of South Zone & West 870.60
765.00 765.00 Zone

c) For North Zone 1160.80

2. TABLE NO. 1·2EX·OUTLET PRICES OF BITUMEN (Page 216 of SOR 2015·16) is replaced by the following:

In place of To be read as
Page 51. No.1 Unit
Description of item
No. Item
Rates at outlets n Rates at outlets n
1 2 3 4 5 6
216 TABLE EX·OUTLET PRICES OF BITUMEN: At Haldia At Dhulagarh At Haldia At Dhulagarh
In.(on NH-6) In.(on NH-6)
1·2
1. MT........ ...........••......28681.00 *** 28681.00 ***
...........
~.i~~
.~.~.~
. ...(~~I.~)...:yC}_=~g ..(~q!~qg).......... ~
••••........

MT 33367.00 *** 33367.00 ***


........ ~it~'.:'l~~(~~~~~~) :YC}_=~g(~q/~qq)
2.
3. MT 29642.00 *** 29642.00 ***
........
. ~i!~'.:'l~~(.~~_I~).:y~.=~q.(?glJq) .....................
............_ ..................

4. MT 34328.00 *** 34328.00 ***


~i!~'.:'l~~J~~~~~~):y.~=~q(?qlJq)
Bitumen (Bulk) :VG-40 (30/40) MT 30123.00 *** 30123.00 ***
5.
..............._ ..................

Bitumen (Packed) :VG-40 (30/40) MT 34688.00 *** *** ***


6.
Penetration gr. Bitumen (Packed): MT
7. *** 36223.00 *** 36223.00
(10/20)
Bituminous Emulsion (Bulk) MS Type MT 26239.00 *** 24035.00 ***
8.
Bituminous Emulsion (Packed) MS *** 32646.00 *** 32646.00
9.
Type
........ ..................................... ..
MT 32430.00 *** 32430.00 ***
10. CRMB - 55 (Bulk)
CRMB - 55 (Packed) MT 38830.00 *** 36146.00 ***
11.
MT 32850.00 *** 32850.00 ***
12. CRMB - 60 (Bulk)
CRMB - 60 (Packed) MT 39166.00 *** 36566.00 ***
13.

~~~\I~ ~ 1": ~\"\\\'


1~\0'1)~II.
(TAPASH KR. DEY) (DEBASH S ROY) (MALAY GHOSH) \
Superintending Engineer Superintending Engineer Engineer·in·Chief & E. O. Secretary &
Bridge Planning Circle. Planning & Monitoring Circle, Chief Engineer (HQ)
Public Works(Roads) Directorate& Public Works Directorate& Public Works Directorate&
Jt. Convenor of the Combined Schedule Convenor of the Combined Schedule Chairman of the Combined Schedule
Committee of PWD Committee of PWD Committee of PWD