Anda di halaman 1dari 12

RENCANA ANGGARAN BIAYA (RAB)

ANALISA BIAYA
(SNI)
DINAS PEKERJAAN UMUM PROVINSI KEPULAUAN RIAU

HARGA SATUAN JUMLAH HARGA (Rp.)


KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

A PENGADAAN PIPA HDPE DN 63 PN 10


1.00000 Supplay/harga pipa loco pabrik m 38,400.00 38,400.00
0.04550 Transportasi Truk pipa (di jakarta dan di Anambas) jam 278,400.00 12,667.20
0.00148 Mobil crane (di jakarta dan di Anambas) jam 511,200.00 757.33
0.00992 Kapal laut (jakarta - Anambas) m3 2,100,000.00 20,837.25
JUMLAH - 38,400.00 34,261.78 72,661.78
KEUNTUNGAN DAN OVER HEAD (15%) 10,899.27
JUMLAH 83,500.00

A PENGADAAN PIPA HDPE DN 90 PN 10


1.00000 Supplay/harga pipa loco pabrik m 77,880.00 77,880.00
0.02300 Transportasi Truk pipa (di jakarta dan di Anambas) jam 278,400.00 6,403.20
0.00303 Mobil crane (di jakarta dan di Anambas) jam 511,200.00 1,549.09
0.02025 Kapal laut (jakarta - Anambas) m3 2,100,000.00 42,525.00
JUMLAH - 77,880.00 50,477.29 128,357.29
KEUNTUNGAN DAN OVER HEAD (15%) 19,253.59
JUMLAH 147,600.00

A Pengadaan Tee PVC DN 110x110 S12-5 (RRJ-all socket) bh


1.00 Bh Tee PVC DN 110x110 S12-5 (RRJ-all socket) 381,960.00 381,960.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 381,960.00 28,211.16 410,171.16
KEUNTUNGAN DAN OVER HEAD (15%) 61,525.67
JUMLAH 471,600.00

A Pengadaan Flange Spigot PVC DN 110 S12-5 (RRJ) bh


1.00 Bh Flange spigot PVC DN 160 S12-5 (RRJ) 222,400.00 222,400.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 222,400.00 28,211.16 250,611.16
KEUNTUNGAN DAN OVER HEAD (15%) 37,591.67
JUMLAH 288,200.00

A Pengadaan Flange Socket PVC DN 90 S12-5 (RRJ) bh


1.00 Bh Flange Socket PVC DN 90 S12-5 (RRJ) 187,400.00 187,400.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 187,400.00 11,416.34 198,816.34
KEUNTUNGAN DAN OVER HEAD (15%) 29,822.45
JUMLAH 228,600.00

A Pengadaan Tee HDPE DN 160 bh


1.00 Bh Tee HDPE DN 160x90 with compression 1,446,440.40 1,446,440.40
0.01531 jam Truk pipa 278,400.00 4,261.38
0.00291 jam Mobil crane 511,200.00 1,489.92
0.02560 m3 Kapal laut 2,100,000.00 53,760.00
JUMLAH - 1,446,440.40 59,511.30 1,505,951.70
KEUNTUNGAN DAN OVER HEAD (15%) 225,892.75
JUMLAH 1,731,800.00

A Pengadaan Tee HDPE DN 110 with compression bh


HARGA SATUAN JUMLAH HARGA (Rp.)
KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

1.00 Bh Tee HDPE DN 110x110 with compression 959,040.00 959,040.00


0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 959,040.00 28,211.16 987,251.16
KEUNTUNGAN DAN OVER HEAD (15%) 148,087.67
JUMLAH 1,135,300.00

A Pengadaan Tee HDPE DN 90 with compression bh


1.00 Bh Tee HDPE DN 90x90 with compression 394,920.00 394,920.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 394,920.00 11,416.34 406,336.34
KEUNTUNGAN DAN OVER HEAD (15%) 60,950.45
JUMLAH 467,200.00

A Pengadaan Clamp Saddle HDPE DN 160 bh


1.00 Bh Clamp Saddle HDPE DN 160x63 179,424.00 179,424.00
0.01531 jam Truk pipa 278,400.00 4,261.38
0.00291 jam Mobil crane 511,200.00 1,489.92
0.02560 m3 Kapal laut 2,100,000.00 53,760.00
JUMLAH - 179,424.00 59,511.30 238,935.30
KEUNTUNGAN DAN OVER HEAD (15%) 35,840.29
JUMLAH 274,700.00

A Pengadaan Stub end flange HDPE DN 160 bh


1.00 Bh Stub end flange HDPE DN 160 1,145,760.00 1,145,760.00
0.01531 jam Truk pipa 278,400.00 4,261.38
0.00291 jam Mobil crane 511,200.00 1,489.92
0.02560 m3 Kapal laut 2,100,000.00 53,760.00
JUMLAH - 1,145,760.00 59,511.30 1,205,271.30
KEUNTUNGAN DAN OVER HEAD (15%) 180,790.69
JUMLAH 1,386,000.00

A Pengadaan Stub end flange HDPE DN 110 bh


1.00 Bh Stub end flange HDPE DN 110 261,960.00 261,960.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 261,960.00 28,211.16 290,171.16
KEUNTUNGAN DAN OVER HEAD (15%) 43,525.67
JUMLAH 333,600.00

A Pengadaan Stub end flange HDPE DN 90 bh


1.00 Bh Stub end flange HDPE DN 90 212,040.00 212,040.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 212,040.00 11,416.34 223,456.34
KEUNTUNGAN DAN OVER HEAD (15%) 33,518.45
JUMLAH 256,900.00

A Pengadaan Compression HDPE DN 63 bh


1.00 Bh Compression HDPE DN 63 57,240.00 57,240.00
0.00214 jam Truk pipa 278,400.00 594.95
0.00027 jam Mobil crane 511,200.00 137.24
0.00238 m3 Kapal laut 2,100,000.00 5,000.94
JUMLAH - 57,240.00 5,733.13 62,973.13
KEUNTUNGAN DAN OVER HEAD (15%) 9,445.97
HARGA SATUAN JUMLAH HARGA (Rp.)
KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

JUMLAH 72,400.00

A Pengadaan Compression HDPE DN 90 bh


1.00 Bh Compression HDPE DN 90 118,680.00 118,680.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 118,680.00 11,416.34 130,096.34
KEUNTUNGAN DAN OVER HEAD (15%) 19,514.45
JUMLAH 149,600.00

A Pengadaan Dop HDPE DN 110 bh


1.00 Bh Dop HDPE DN 110 203,880.00 203,880.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 203,880.00 28,211.16 232,091.16
KEUNTUNGAN DAN OVER HEAD (15%) 34,813.67
JUMLAH 266,900.00

A Pengadaan Dop HDPE DN 90 bh


1.00 Bh Dop HDPE DN 90 69,480.00 69,480.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 69,480.00 11,416.34 80,896.34
KEUNTUNGAN DAN OVER HEAD (15%) 12,134.45
JUMLAH 93,000.00

A Pengadaan MTA HDPE DN 90 bh


1.00 Bh MTA HDPE DN 90 70,200.00 70,200.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 70,200.00 11,416.34 81,616.34
KEUNTUNGAN DAN OVER HEAD (15%) 12,242.45
JUMLAH 93,800.00

A Pengadaan MTA HDPE DN 110 bh


1.00 Bh MTA HDPE DN 110 156,960.00 156,960.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 156,960.00 28,211.16 185,171.16
KEUNTUNGAN DAN OVER HEAD (15%) 27,775.67
JUMLAH 212,900.00

A Pengadaan Bend 90 HDPE DN 90 bh


1.00 Bh Bend HDPE DN 90 132,000.00 132,000.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 132,000.00 11,416.34 143,416.34
KEUNTUNGAN DAN OVER HEAD (15%) 21,512.45
JUMLAH 164,900.00

A Pengadaan BEND 90º dan 45º, HDPE DN 160 bh


1.00 Bh BEND 90 HDPE DN 160 661,920.00 661,920.00
0.01531 jam Truk pipa 278,400.00 4,261.38
0.00291 jam Mobil crane 511,200.00 1,489.92
HARGA SATUAN JUMLAH HARGA (Rp.)
KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

0.02560 m3 Kapal laut 2,100,000.00 53,760.00


JUMLAH - 661,920.00 59,511.30 721,431.30
KEUNTUNGAN DAN OVER HEAD (15%) 108,214.69
JUMLAH 829,600.00

A Pengadaan Reducer 90 HDPE DN 90 bh


1.00 Bh Reducer HDPE DN 90 77,900.00 77,900.00
0.00331 jam Truk pipa 278,400.00 920.53
0.00057 jam Mobil crane 511,200.00 289.81
0.00486 m3 Kapal laut 2,100,000.00 10,206.00
JUMLAH - 77,900.00 11,416.34 89,316.34
KEUNTUNGAN DAN OVER HEAD (15%) 13,397.45
JUMLAH 102,700.00

A Pengadaan Reducer 90 HDPE DN 110 bh


1.00 Bh Reducer HDPE DN 90 221,800.00 221,800.00
0.00741 jam Truk pipa 278,400.00 2,064.33
0.00144 jam Mobil crane 511,200.00 736.83
0.01210 m3 Kapal laut 2,100,000.00 25,410.00
JUMLAH - 221,800.00 28,211.16 250,011.16
KEUNTUNGAN DAN OVER HEAD (15%) 37,501.67
JUMLAH 287,500.00

A Pengadaan Reducer HDPE DN 160 bh


1.00 Bh Reducer HDPE DN 160 292,700.00 292,700.00
0.01531 jam Truk pipa 278,400.00 4,261.38
0.00291 jam Mobil crane 511,200.00 1,489.92
0.02560 m3 Kapal laut 2,100,000.00 53,760.00
JUMLAH - 292,700.00 59,511.30 352,211.30
KEUNTUNGAN DAN OVER HEAD (15%) 52,831.69
JUMLAH 405,000.00

A PENGADAAN PIPA GI DN 100


1.00000 Supplay/harga pipa loco pabrik m 304,500.00 304,500.00
0.01830 Transportasi Truk pipa (di jakarta dan di Anambas) jam 278,400.00 5,094.72
0.00833 Mobil crane (di jakarta dan di Anambas) jam 511,200.00 4,260.00
0.01000 Kapal laut (jakarta - Anambas) m3 2,100,000.00 21,000.00
JUMLAH - 304,500.00 30,354.72 334,854.72
KEUNTUNGAN DAN OVER HEAD (15%) 50,228.21
JUMLAH 385,000.00

A PENGADAAN PIPA GI DN 75
1.00000 Supplay/harga pipa loco pabrik m 252,400.00 252,400.00
0.01373 Transportasi Truk pipa (di jakarta dan di Anambas) jam 278,400.00 3,821.04
0.00625 Mobil crane (di jakarta dan di Anambas) jam 511,200.00 3,195.00
0.00750 Kapal laut (jakarta - Anambas) m3 2,100,000.00 15,750.00
JUMLAH - 252,400.00 22,766.04 275,166.04
KEUNTUNGAN DAN OVER HEAD (15%) 41,274.91
JUMLAH 316,400.00

A Pengadaan Tee GI DN 75x75 bh


1.00 Bh Tee GI DN 75x75 130,900.00 130,900.00
0.01225 jam Truk pipa 292,700.00 3,584.21
0.00233 jam Mobil crane 278,400.00 649.13
JUMLAH - 130,900.00 4,233.34 135,133.34
KEUNTUNGAN DAN OVER HEAD (15%) 20,270.00
JUMLAH 155,400.00

A Pengadaan Bend 90 GI DN 75 bh
1.00 Bh Bend 90 GI DN 75 101,822.00 101,822.00
HARGA SATUAN JUMLAH HARGA (Rp.)
KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

0.0150 jam Truk pipa 292,700.00 4,390.66


0.0029 jam Mobil crane 278,400.00 795.18
JUMLAH - 101,822.00 5,185.84 107,007.84
KEUNTUNGAN DAN OVER HEAD (15%) 16,051.18
JUMLAH 123,000.00

A Pengadaan Flange steel DN 75 bh


1.00 Bh Flange steel DN 75 94,930.00 94,930.00
0.0107 jam Truk pipa 292,700.00 3,136.18
0.0020 jam Mobil crane 278,400.00 567.99
JUMLAH - 94,930.00 3,704.17 98,634.17
KEUNTUNGAN DAN OVER HEAD (15%) 14,795.13
JUMLAH 113,400.00

A Pengadaan Flange steel DN 100 bh


1.00 Bh Flange steel DN 100 163,200.00 163,200.00
0.01531 jam Truk pipa 292,700.00 4,480.26
0.00291 jam Mobil crane 278,400.00 811.41
JUMLAH - 163,200.00 5,291.67 168,491.67
KEUNTUNGAN DAN OVER HEAD (15%) 25,273.75
JUMLAH 193,700.00

A Pengadaan Blind Flange steel DN 100 bh


1.00 Bh Blind Flange steel DN 100 319,800.00 319,800.00
0.01531 jam Truk pipa 292,700.00 4,480.26
0.00291 jam Mobil crane 278,400.00 811.41
JUMLAH - 319,800.00 5,291.67 325,091.67
KEUNTUNGAN DAN OVER HEAD (15%) 48,763.75
JUMLAH 373,800.00

A Pengadaan Giboult Joint DN 100 bh


1.00 Bh Giboult Joint DN 100 459,648.00 459,648.00
0.01 jam Truk pipa 292,700.00 1,991.23
0.001 jam Mobil crane 278,400.00 360.63
JUMLAH - 459,648.00 2,351.86 461,999.86
KEUNTUNGAN DAN OVER HEAD (15%) 69,299.98
JUMLAH 531,200.00

A Pengadaan Giboult Joint DN 150 bh


1.00 Bh Giboult Joint DN 150 900,000.00 900,000.00
0.02 jam Truk pipa 292,700.00 4,480.26
0.00 jam Mobil crane 278,400.00 811.41
JUMLAH - 900,000.00 5,291.67 905,291.67
KEUNTUNGAN DAN OVER HEAD (15%) 135,793.75
JUMLAH 1,041,000.00

A Pengadaan Gate valve DN 150 bh


1.00 Bh Gate valve DN 150 4,920,000.00 4,920,000.00
16.00 bh Mur baud 8,400.00 134,400.00
2.00 bh sleeve/ packing 33,000.00 66,000.00
0.10276 jam Truk pipa 278,400.00 28,607.77
0.02400 jam Mobil crane 511,200.00 12,268.80
0.03600 ton Kapal laut 2,100,000.00 75,600.00
JUMLAH - 5,120,400.00 116,476.57 5,236,876.57
KEUNTUNGAN DAN OVER HEAD (15%) 785,531.49
JUMLAH 6,022,400.00

A Pengadaan Gate valve DN 100


1.00 Bh Gate valve DN 110 m1 2,460,000.00 2,460,000.00
16.00 bh Mur baud 6,600.00 105,600.00
HARGA SATUAN JUMLAH HARGA (Rp.)
KODE ANALISA VOL
(Rp.) UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7

2.00 bh sleeve/ packing 18,000.00 36,000.00


0.07853 jam Truk pipa 278,400.00 21,864.09
0.01467 jam Mobil crane 511,200.00 7,497.60
0.02200 ton Kapal laut 2,100,000.00 46,200.00
JUMLAH - 2,601,600.00 75,561.69 2,677,161.69
KEUNTUNGAN DAN OVER HEAD (15%) 401,574.25
JUMLAH 3,078,700.00

A Pengadaan Gate valve DN 75


1.00 Bh Gate valve DN 110 m1 1,860,000.00 1,860,000.00
16.00 bh Mur baud 4,800.00 76,800.00
2.00 bh sleeve/ packing 15,000.00 30,000.00
0.05917 jam Truk pipa 278,400.00 16,472.39
0.01133 jam Mobil crane 511,200.00 5,793.60
0.01700 ton Kapal laut 2,100,000.00 35,700.00
JUMLAH - 1,966,800.00 57,965.99 2,024,765.99
KEUNTUNGAN DAN OVER HEAD (15%) 303,714.90
JUMLAH 2,328,400.00

A Pengadaan Gate valve DN 50


1.00 Bh Gate valve DN 50 bh 1,100,000.00 1,100,000.00
16.00 bh Mur baud 3,600.00 57,600.00
2.00 bh sleeve/ packing 11,000.00 22,000.00
0.01447 jam Truk pipa 278,400.00 4,029.79
0.00800 jam Mobil crane 511,200.00 4,089.60
0.01200 ton Kapal laut 2,100,000.00 25,200.00
JUMLAH - 1,179,600.00 33,319.39 1,212,919.39
KEUNTUNGAN DAN OVER HEAD (15%) 181,937.91
JUMLAH 1,394,800.00

A Pengadaan Globe valve DN 25


1.00 Bh Gate valve DN 25 bh 650,000.00 650,000.00
0.00724 jam Truk pipa 278,400.00 2,014.89
0.00400 jam Mobil crane 511,200.00 2,044.80
0.00600 ton Kapal laut 2,100,000.00 12,600.00
JUMLAH - 650,000.00 16,659.69 666,659.69
KEUNTUNGAN DAN OVER HEAD (15%) 99,998.95
JUMLAH 766,600.00

A. PENGADAAN AIR VALVE DN 25 BH


1.00 bh Single Air valve CI DN 25 PN 10 all screw 1,260,000.00 1,260,000 1,260,000
0.01447 jam Truk pipa 278,400.00 4,030 4,030
0.00800 jam Mobil crane 511,200.00 4,090 4,090
0.01200 m3 Kapal laut 2,100,000.00 25,200 25,200
JUMLAH 33,319.39 1,293,319.39 - 1,326,638.78
KEUNTUNGAN DAN OVER HEAD (15%) 198,995.82
JUMLAH 1,525,600.00
DAFTAR HARGA SATUAN UPAH DAN PERALATAN

NO U R A I A N VOL SATUAN HARGA (Rp.) KETERANGAN

A UPAH
1 Pekerja 1 OR/HR Rp 80,000.00 Lokasi Pekerjaan
2 Tukang 1 OR/HR Rp 90,000.00 Lokasi Pekerjaan
3 Tukang Las 1 OR/HR Rp 90,000.00 Lokasi Pekerjaan
4 Tukang Las HDPE 1 OR/HR Rp 130,000.00 Lokasi Pekerjaan
5 Kepala tukang 1 OR/HR Rp 120,000.00 Lokasi Pekerjaan
6 Kepala tukang HDPE 1 OR/HR Rp 150,000.00 Lokasi Pekerjaan
7 Mandor 1 OR/HR Rp 110,000.00 Lokasi Pekerjaan
8 Juru Ukur 1 OR/HR Rp 100,000.00 Lokasi Pekerjaan
9 Operator 1 OR/HR Rp 100,000.00 Lokasi Pekerjaan

B MATERIAL

1 Pipa HDPE DN 63 mm PN 10 1 M Rp 38,400.00 Loco pabrik


2 Pipa HDPE DN 90 mm PN 10 1 M Rp 77,880.00 Loco pabrik
3 Pipa HDPE DN 110 mm PN 10 1 M Rp 116,280.00 Loco pabrik

4 Globe Valve CI ND 25 mm all screw 1 Bh Rp 650,000.00 Loco pabrik


5 Gate Valve CI ND 50 mm all flange 1 Bh Rp 1,100,000.00 Loco pabrik
6 Gate Valve CI ND 75 mm all flange 1 Bh Rp 1,860,000.00 Loco pabrik
7 Gate Valve CI ND 100 mm all flange 1 Bh Rp 2,460,000.00 Loco pabrik
8 Gate Valve CI ND 150 mm all flange 1 Bh Rp 4,920,000.00 Loco pabrik
9 Gate Valve CI ND 250 mm all flange 1 Bh Rp 12,720,000.00 Loco pabrik

10 Giboult joint CI ND 100 mm all flange 1 Bh Rp 459,648.00 Loco pabrik


11 Giboult joint CI ND 150 mm all flange 1 Bh Rp 900,000.00 Loco pabrik
12 Giboult joint CI ND 250 mm all flange 1 Bh Rp 2,580,000.00 Loco pabrik

13 Tee HDPE DN 250x250, PE 100, PN 10, SDR 17 1 Bh Rp 2,236,440.00 Loco pabrik


14 Tee HDPE DN 160x90, PE 100, PN 10, SDR 17 1 Bh Rp 1,446,440.40 Loco pabrik
15 Tee HDPE DN 110x110, PE 100, PN 10, SDR 17 1 Bh Rp 834,120.00 Loco pabrik
16 Tee HDPE DN 110x90, PE 100, PN 10, SDR 17 1 Bh Rp 959,040.00 Loco pabrik
17 Tee HDPE DN 90x90, PE 100, PN 10, SDR 17 1 Bh Rp 394,920.00 Loco pabrik
18 Tee HDPE DN 63x63, PE 100, PN 10, SDR 17 1 Bh Rp 131,640.00 Loco pabrik

19 Stub end flange HDPE DN 250 PE 100, PN 10, SDR 17 1 Bh Rp 2,186,760.00 Loco pabrik
(incl. flange/ backing ring DN 160)
20 Stub end flange HDPE DN 160 PE 100, PN 10, SDR 17 1 Bh Rp 1,145,760.00 Loco pabrik
(incl. flange/ backing ring DN 160)
21 Stub end flange HDPE DN 110 PE 100, PN 10, SDR 17 1 Bh Rp 261,960.00 Loco pabrik
(incl. flange/ backing ring DN 110)
22 Stub end flange HDPE DN 90 PE 100, PN 10, SDR 17 1 Bh Rp 212,040.00 Loco pabrik
(incl. flange/ backing ring DN 90)
23 Stub end flange HDPE DN 63 PE 100, PN 10, SDR 17 1 Bh Rp 145,200.00 Loco pabrik
(incl. flange/ backing ring DN 63)

24 Compression HDPE DN 110, PE 100, PN 10, SDR 17 1 Bh Rp 266,160.00 Loco pabrik


25 Compression HDPE DN 90, PE 100, PN 10, SDR 17 1 Bh Rp 118,680.00 Loco pabrik
NO U R A I A N VOL SATUAN HARGA (Rp.) KETERANGAN

26 Compression HDPE DN 63, PE 100, PN 10, SDR 17 1 Bh Rp 57,240.00 Loco pabrik

27 Dop HDPE DN 110, PE 100, PN 10, SDR 17 1 Bh Rp 203,880.00 Loco pabrik


28 Dop HDPE DN 90, PE 100, PN 10, SDR 17 1 Bh Rp 69,480.00 Loco pabrik
29 Dop HDPE DN 63, PE 100, PN 10, SDR 17 1 Bh Rp 31,200.00 Loco pabrik

30 Bend 90 HDPE DN 63, PE 100, PN 10, SDR 17 1 Bh Rp 65,040.00 Loco pabrik


31 Bend 90 HDPE DN 90, PE 100, PN 10, SDR 17 1 Bh Rp 132,000.00 Loco pabrik
32 Bend 90 HDPE DN 110, PE 100, PN 10, SDR 17 1 Bh Rp 297,600.00 Loco pabrik
33 Bend 90 HDPE DN 160, PE 100, PN 10, SDR 17 1 Bh Rp 661,920.00 Loco pabrik
34 Bend 90 HDPE DN 250, PE 100, PN 10, SDR 17 1 Bh Rp 1,441,320.00 Loco pabrik

35 Tee PVC DN 250x160 mm S-12.5 (RRJ-all socket) 1 Bh Rp 2,858,880.00 Loco pabrik


36 Tee PVC DN 160x90 mm S-12.5 (RRJ-all socket) 1 Bh Rp 999,240.00 Loco pabrik
37 Tee PVC DN 160x110 mm S-12.5 (RRJ-all socket) 1 Bh Rp 1,005,480.00 Loco pabrik
38 Tee PVC DN 160x160 mm S-12.5 (RRJ-all socket) 1 Bh Rp 1,017,000.00 Loco pabrik
38 Tee PVC DN 110x90 mm S-12.5 (RRJ-all socket) 1 Bh Rp 375,720.00 Loco pabrik
39 Tee PVC DN 110x110 mm S-12.5 (RRJ-all socket) 1 Bh Rp 381,960.00 Loco pabrik
40 Tee PVC DN 90x90 mm S-12.5 (RRJ-all socket) 1 Bh Rp 218,040.00 Loco pabrik

41 Tee GI DN 75x75 1 Bh Rp 130,900.00 Loco pabrik

41 Reducer PVC DN 160x90 mm S-12.5 (RRJ-all socket) 1 Bh Rp 147,300.00 Loco pabrik


42 Reducer HDPE DN 90x63 mm S-12.5 (all compression) 1 Bh Rp 77,900.00 Loco pabrik
43 Reducer HDPE DN 110x90 mm S-12.5 (all compression) 1 Bh Rp 221,800.00 Loco pabrik
44 Reducer HDPE DN 160x110 mm S-12.5 (all compression) 1 Bh Rp 292,700.00 Loco pabrik

45 Repair socket PVC DN 160 mm, S-12.5 (RRJ-all socket) 1 Bh Rp 100,600.00 Loco pabrik
46 Repair socket PVC DN 250 mm, S-12.5 (RRJ-all socket) 1 Bh Rp 307,500.00 Loco pabrik

47 Flange spigot PVC DN 160 S12-5 (RRJ) 1 Bh Rp 436,200.00 Loco pabrik


48 Flange spigot PVC DN 110 S12-5 (RRJ) 1 Bh Rp 222,400.00 Loco pabrik
49 Flange spigot PVC DN 90 S12-5 (RRJ) 1 Bh Rp 175,400.00 Loco pabrik
50 Flange socket PVC DN 250 S12-5 (RRJ) 1 Bh Rp 723,100.00 Loco pabrik
51 Flange socket PVC DN 110 S12-5 (RRJ) 1 Bh Rp 247,200.00 Loco pabrik
52 Flange socket PVC DN 90 S12-5 (RRJ) 1 Bh Rp 187,400.00 Loco pabrik

53 Flange steel DN 100 1 Bh Rp 163,200.00 Loco pabrik


54 Flange steel DN 75 1 Bh Rp 94,930.00 Loco pabrik

55 Blind Flange steel DN 150 1 Bh Rp 319,800.00 Loco pabrik

56 Straat pot CI Ø6" 1 Bh Rp 370,000.00 Lokasi

57 Mur baud untuk pipa 2" 1 Bh Rp 3,600.00 lokasi


58 Mur baud untuk pipa 3" 1 Bh Rp 4,800.00 lokasi
59 Mur baud untuk pipa 4" 1 Bh Rp 6,600.00 lokasi
60 Mur baud untuk pipa 6" 1 Bh Rp 8,400.00 lokasi
61 Mur baud untuk pipa 10" 1 Bh Rp 13,200.00 lokasi
NO U R A I A N VOL SATUAN HARGA (Rp.) KETERANGAN

62 Sleeve/ packing untuk mur baud pada pipa 2" 1 Bh Rp 11,000.00 lokasi
63 Sleeve/ packing untuk mur baud pada pipa 3" 1 Bh Rp 15,000.00 lokasi
64 Sleeve/ packing untuk mur baud pada pipa 4" 1 Bh Rp 18,000.00 lokasi
65 Sleeve/ packing untuk mur baud pada pipa 6" 1 Bh Rp 33,000.00 lokasi
66 Sleeve/ packing untuk mur baud pada pipa 10" 1 Bh Rp 45,000.00 lokasi

67 Meter air, DN 1/2" (PN 10), brass (bahan kuningan) 1 Bh Rp 420,000.00 lokasi
68 Stop kran, CI DN 1/2" (PN 10) 1 Bh Rp 43,200.00 lokasi
69 Elbow HDPE DN 1/2" 1 Bh Rp 8,040.00 lokasi

70 Male threated adaptor (MTA) HDPE DN 1/2" 1 Bh Rp 3,960.00 lokasi


71 Male threated adaptor (MTA) HDPE DN 63 1 Bh Rp 31,680.00 lokasi
72 Male threated adaptor (MTA) HDPE DN 90 1 Bh Rp 70,200.00 lokasi
73 Male threated adaptor (MTA) HDPE DN 110 1 Bh Rp 156,960.00 lokasi
74 Female threated adaptor HDPE DN 1/2" 1 Bh Rp 4,680.00 lokasi

75 Clamp saddle HDPE DN 2" 1 Bh Rp 42,480.00 lokasi


76 Clamp saddle HDPE DN 3" 1 Bh Rp 91,008.00 lokasi
77 Clamp saddle HDPE DN 110 1 Bh Rp 110,304.00 lokasi
78 Clamp saddle HDPE DN 160x2" 1 Bh Rp 179,424.00 lokasi
79 Clamp saddle HDPE DN 160x4" 1 Bh Rp 179,424.00 lokasi
80 Clamp saddle CI DN 250x2" 1 Bh Rp 510,000.00 lokasi

81 Pipa HDPE DN 1/2" 1 m Rp 6,000.00 pabrik


82 Pipa GI DN 100 mm klas medium 1 m Rp 304,500.00 pabrik
83 Pipa GI DN 75 mm klas medium 1 m Rp 252,400.00 pabrik
84 Pipa GIP DN 50 mm klas medium 1 m Rp 184,080.00 pabrik

85 Ball Valve CI DN 50 PN 10 1 bh Rp 5,424,000.00 lokasi


86 Bend 90, GI DN 50 klas medium 1 bh Rp 66,240.00 lokasi
87 Bend 90, GI DN 75 klas medium 1 bh Rp 101,822.00 lokasi
87 Double nipple GI DN 50 1 bh Rp 48,960.00 lokasi
88 Double nipple GI DN 25 1 bh Rp 30,500.00 lokasi
88 Shock draat GI DN 50 1 bh Rp 39,600.00 lokasi
89 Flange steeel DN 50 1 bh Rp 99,216.00 lokasi
90 Clamp saddle CI PN 10 DN 150x50 1 bh Rp 510,000.00 lokasi
91 Double Air valve, CI DN 50 PN 10 1 bh Rp 2,535,000.00 lokasi
92 Single Air valve, CI DN 25 PN 10 1 bh Rp 1,260,000.00 lokasi

92 Pasir Beton 1 M3 Rp 206,000.00 lokasi


93 Pasir Beton 1 Kg Rp 147.15 lokasi
94 Pasir pasang 1 M3 Rp 206,000.00 lokasi
95 Pasir Urug 1 M3 Rp 153,650.00 lokasi
96 Kerikil 1 M3 Rp 400,903.80 lokasi
97 Kerikil 1 Kg Rp 296.97 lokasi
98 Batu kali 1 M3 Rp 299,250.00 lokasi
99 Kayu Klas II 1 M3 Rp 4,308,990.00 lokasi
100 Kayu Klas III 1 M3 Rp 3,000,000.00 lokasi
101 Plywood 9 mm 1 Lbr Rp 180,000.00 lokasi
102 Kayu dolken 8-10 cm - panjang 4 m 1 Btg Rp 25,560.00 lokasi
NO U R A I A N VOL SATUAN HARGA (Rp.) KETERANGAN

103 Paku Segala ukuran ( Rata - Rata ) 1 Kg Rp 25,000.00 lokasi


104 Paku kayu 1 Kg Rp 25,000.00 lokasi
105 Pelicin sabun cream 1 Kg Rp 10,000.00 lokasi
106 Cat Minyak 1 Kg Rp 65,000.00 lokasi
107 Aspal 1 Kg Rp 14,000.00 lokasi
108 Kayu Bulat Ø 1" (Patok) 1 Btg Rp 7,350.00 lokasi
109 Cement PC (50 kg) 1 Zak Rp 100,000.00 lokasi
110 Cement PC 1 Kg Rp 2,000.00 lokasi
111 Besi beton 1 Kg Rp 16,000.00 lokasi
112 Besi profil 1 Kg Rp 25,000.00 lokasi
113 Kawat beton 1 Kg Rp 25,000.00 lokasi
114 Dyna bolt 1 bh Rp 35,000.00 lokasi
115 Paving blok 1 bh Rp 4,000.00 lokasi
116 Air 1 m3 Rp 2,500.00 lokasi
117 Air 1 lt Rp 2.50 lokasi
118 Solar 1 Ltr Rp 8,600.00 lokasi
119 Pelumas 1 Ltr Rp 10,000.00 lokasi
120 Minyak bekisting/ solar 1 Ltr Rp 15,000.00 lokasi
121 Kawat las 1 Kg Rp 32,000.00 lokasi

PERALATAN
1 Dump truk 8 ton (truk pipa) 1 hari Rp 2,227,200.00 lokasi
2 Dump truk 8 ton (truk pipa) 1 Jam Rp 278,400.00 lokasi
3 Crane 1 hari Rp 4,089,600.00 lokasi
4 Crane 1 Jam Rp 511,200.00 lokasi
5 Genset 20 KVA 1 hari Rp 744,000.00 lokasi
6 Genset 20 KVA 1 Jam Rp 93,000.00 lokasi
7 Water pump 10 lt/dt (pompa dewatering) 1 hari Rp 278,400.00 lokasi
8 Water pump 10 lt/dt (pompa dewatering) 1 Jam Rp 34,800.00 lokasi
9 Jack hammer 1 hari Rp 307,200.00 lokasi
10 Jack hammer 1 Jam Rp 38,400.00 lokasi
11 Mesin las 1 hari Rp 7,389,200.00 lokasi
12 Mesin las 1 jam Rp 923,650.00 lokasi
13 Alat butt welding (mesin las HDPE) 1 bulan Rp 36,000,000.00 lokasi
14 Alat butt welding (mesin las HDPE) 1 jam Rp 150,000.00 lokasi
15 Alat Ukur 1 Jam Rp 120,000.00 lokasi
16 Alat Bantu (tripod, rantai dll) 1 hari Rp 120,000.00 lokasi
17 Alat Bantu (tripod, rantai dll) 1 jam Rp 15,000.00 lokasi
18 Alat Bantu (kunci pipa, acetone, dll) 1 hari Rp 120,000.00 lokasi
19 Alat Bantu (kunci pipa, acetone, dll) 1 Jam Rp 15,000.00 lokasi
20 Sewa Alat Pembelah Aspal 1 Jam Rp 38,400.00 lokasi
21 Kapal laut 1 m3 Rp 2,100,000.00 lokasi
22 Kapal laut 1 ton Rp 2,100,000.00 lokasi
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

#REF! : -

#REF! : -

#REF! : -

#REF! : -
KODE : -
JENIS EKERJAAN : -
PERKIRAAN VOL. PEK. : -
SATUAN PEMBAYARAN : - TOTAL HARGA (Rp.) : -

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Jumlah Harga Tenaga Kerja
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
D (A+B+C) 0.00
E Overhead + Profit ( Contoh 15% ) 15 % x D 0.00
Harga Satuan Pekerjaan per - m3
F (D + E) 0.00