MUROS TERRAMESH

TRAMO:
62+700 A 65+700

GAVION GAVION GAVION


TRAMO DE MURO CODIGO GAVION CON GAVION CON GAVION CON COLA COLA COLA GEOTEXTIL
COLA1X1X4 COLA 1X1X5 COLA 1X1X6 (m2)
0.5X1X4 0.5X1X5 0.5X1X6
62+815.00 62+900.00 MT-01 305 70 653
64+122.00 64+233.00 TA73 274 50 30 40 841.4
Err:509 64+025.00 MT-03 215 90 578
63+610.00 63+630.00 TA71 80 143
63+305.00 63+325.00 TA70 45 50 20 20 255
63+245.00 63+255.00 MT-06 15 50 5 10 179
Total (m2) 2649.4
Total (m3) 934 150 125 160
Total Piezas 934 150 250 320
1x1x4 1x1x5 0.5x1x4 0.5x1x5
COMPUTO METRICO - MURO TERRAMES
1 m2 0.5 m2
Seccion m2 CORTE
Cota Cota de Dist. al eje de Cola de 4 m Cola de 5 m Cola de 6 m Cola de 4 m Cola de 5 m Area (m2)
62+815.00 62+905.00 Terminada fundacion via
62+815.00 5.00 2187.50 2184.50 6.20 3 8.96
62+820.00 5.00 2187.50 2184.50 6.20 3 7.235
62+825.00 5.00 2187.50 2184.50 6.20 3 3.802
62+830.00 5.00 2187.50 2184.50 6.20 3 1.498
62+835.00 5.00 2187.50 2183.50 6.20 4 4.744
62+840.00 5.00 2187.50 2183.50 6.20 4 3.919
62+845.00 5.00 2187.50 2183.50 6.20 4 2.194
62+850.00 5.00 2187.50 2183.50 6.20 4 1.047
62+855.00 5.00 2187.50 2183.50 6.20 4 0.193
62+860.00 5.00 2187.50 2182.50 6.20 3 2 3.434
62+865.00 5.00 2182.50 2187.50 6.20 3 2 2.722
62+870.00 5.00 2187.00 2182.00 6.20 3 2 4.462
62+875.00 5.00 2187.00 2182.00 6.20 3 2 5.054
62+880.00 5.00 2187.00 2182.00 6.20 3 2 8.092
62+885.00 5.00 2187.00 2182.00 6.20 3 2 11.535
62+890.00 5.00 2187.00 2182.00 6.20 3 2 11.465
62+895.00 5.00 2187.00 2183.00 6.20 4 8.79
62+900.00 5.00 4 10.381
Piezas 305 1x1x1x4 0 140 0.5x1x1x4
Subtotal (m3) 305 0 70
Total (m3) 375
O TERRAMESH MT-01
CANTIDADES
CORTE RELLENO GEOTEXTIL
Volumen Vol. Acum. Volumen Vol. Acum. Area Acum.
Area (m2) L (m) Area (m2)
(m3) (m3) (m3) (m3) (m2)
40.49 40.49 8.531 42.9475 42.9475 5.4 27 27
27.59 68.08 8.648 43.435 86.38 5.4 27 54
13.25 81.33 8.726 43.645 130.03 5.4 27 81
15.61 96.94 8.732 51.255 181.28 5.4 27 108
21.66 118.59 11.77 58.9125 240.20 7 35 143
15.28 133.88 11.795 58.7875 298.98 7 35 178
8.10 141.98 11.72 58.47 357.45 7 35 213
3.10 145.08 11.668 58.24 415.69 7 35 248
9.07 154.15 11.628 66.3075 482.00 7 35 283
15.39 169.54 14.895 74.0775 556.08 9.8 49 332
17.96 187.50 14.736 76.3125 632.39 9.8 49 381
23.79 211.29 15.789 78.3675 710.76 9.8 49 430
32.87 244.15 15.558 77.015 787.77 9.8 49 479
49.07 293.22 15.248 75.545 863.32 9.8 49 528
57.50 350.72 14.97 73.9 937.22 9.8 49 577
50.64 401.36 14.59 64.305 1001.52 9.8 49 626
47.93 449.28 11.132 54.6375 1056.16 5.4 27 653
25.95 475.24 10.723 26.8075 1082.97 0 653

475.24 1082.9675 653


COMPUTO METRICO - MURO TERRAMES
1 m2 0.5 m2
Seccion m2 CORTE
Cota Cota de Altura Cola de 4 m Cola de 5 m Cola de 6 m Cola de 4 m Cola de 5 m Area (m2)
64+122.00 64+230.00 Terminada fundacion
64+122.00 8.00 2182.00 3.00 3 8.664
64+130.00 5.00 2180.00 5.00 3 2 6.132
64+135.00 5.00 2180.00 5.00 3 2 8.831
64+140.00 5.00 2181.00 4.00 4 7.704
64+145.00 5.00 2181.00 4.00 4 8.999
64+150.00 5.00 2182.00 3.00 3 6.156
64+155.00 5.00 2182.00 3.00 3 6.559
64+160.00 5.00 2182.00 3.00 3 7.306
64+165.00 5.00 2182.00 3.00 3 7.988
64+170.00 5.00 2182.00 3.00 3 8.878
64+175.00 5.00 2182.00 3.00 3 9.806
64+180.00 5.00 2182.00 3.00 3 9.879
64+185.00 5.00 2180.00 5.00 3 2 11.66
64+190.00 5.00 2179.00 6.00 4 2 9.981
64+195.00 5.00 2178.00 7.00 5 2 10.35
64+200.00 5.00 2178.00 7.00 5 2 9.235
64+205.00 5.00 2179.00 6.00 4 2 13.245
64+210.00 5.00 2181.00 4.00 4 10.123
64+215.00 5.00 2181.00 4.00 4 11.08
64+220.00 5.00 2181.00 4.00 4 9.271
64+225.00 8.00 2182.00 3.00 3 8.252
64+233.00 10.263
Piezas 274 50 0 60 80
Subtotal (m3) 274 50 0 30 40
Total (m3) 324
O TERRAMESH MT-02
CANTIDADES
CORTE RELLENO GEOTEXTIL
Volumen Vol. Acum. Volumen Vol. Acum. Area Acum.
Area (m2) L (m) Area (m2)
(m3) (m3) (m3) (m3) (m2)
59.18 59.18 9.876 101.308 101.308 5.4 43.2 43.2
37.41 96.59 15.451 76.47 177.78 9.8 49 92.2
41.34 137.93 15.137 67.09 244.87 9.8 49 141.2
41.76 179.69 11.699 58.3375 303.21 7 35 176.2
37.89 217.57 11.636 50.175 353.38 7 35 211.2
31.79 249.36 8.434 42.1525 395.53 5.4 27 238.2
34.66 284.02 8.427 41.95 437.48 5.4 27 265.2
38.24 322.26 8.353 41.8125 479.30 5.4 27 292.2
42.17 364.42 8.372 41.7475 521.04 5.4 27 319.2
46.71 411.13 8.327 41.72 562.76 5.4 27 346.2
49.21 460.35 8.361 41.74 604.50 5.4 27 373.2
53.85 514.19 8.335 57.42 661.92 5.4 27 400.2
54.10 568.30 14.633 89.325 751.25 9.8 49 449.2
50.83 619.12 21.097 121.625 872.87 11.4 57 506.2
48.96 668.09 27.553 138.0425 1010.92 13 65 571.2
56.20 724.29 27.664 122.4425 1133.36 13 65 636.2
58.42 782.71 21.313 82.9075 1216.27 11.4 57 693.2
25.31 808.01 11.85 29.625 1245.89 7 35 728.2
27.70 835.71 11.952 29.88 1275.77 7 35 763.2
23.18 858.89 12.113 30.2825 1306.05 7 35 798.2
33.01 891.90 9.085 36.34 1342.39 5.4 43.2 841.4
9.14

891.90 1342.393 841.4


COMPUTO METRICO
63+970 a 64+030 (MT 03)

1 m2 0.5 m2
Seccion m2 CORTE
Cota de Volumen
63+970.00 64+030.00 Altura Cola de 4 m Cola de 5 m Cola de 6 m Cola de 4 m Cola de 5 m Area (m2)
fundacion (m3)
63+970.00 5.00 2180.00 3.00 15 9.611 60.22
63+975.00 5.00 2180.00 6.00 20 10 14.475 48.21
63+980.00 5.00 2181.00 6.00 20 10 4.808 24.75
63+985.00 5.00 2181.00 6.00 20 10 5.092 36.76
63+990.00 5.00 2182.00 6.00 20 10 9.611 44.94
63+995.00 5.00 2182.00 6.00 20 10 8.364 42.63
64+000.00 5.00 2182.00 6.00 20 10 8.686 36.05
64+005.00 5.00 2182.00 5.00 15 10 5.734 28.00
64+010.00 5.00 2182.00 5.00 15 10 5.466 29.23
64+015.00 5.00 2182.00 5.00 15 10 6.224 27.83
64+020.00 5.00 2182.00 4.00 20 4.907 28.40
64+025.00 5.00 2180.00 3.00 15 6.454 32.27
64+030.00 5.00 6.454
Piezas 215 0 0 0 180
Subtotal (m3) 215 0 0 0 90
Total (m3) 215 90
MPUTO METRICO
970 a 64+030 (MT 03)

CANTIDADES
CORTE RELLENO GEOTEXTIL
Vol. Acum. Volumen Vol. Acum. Area Acum.
Area (m2) Area (m2) Area (m2)
(m3) (m3) (m3) (m2)
60.22 9.981 80.405 80.41 5.4 27 27
108.42 22.181 109.9025 190.31 11.4 57 84
133.17 21.78 107.87 298.18 11.4 57 141
169.93 21.368 78.3725 376.55 11.4 57 198
214.87 9.981 76.08 452.63 11.4 57 255
257.49 20.451 100.985 553.62 11.4 57 312
293.54 19.943 90.49 644.11 11.4 57 369
321.54 16.253 79.895 724.00 9.8 49 418
350.77 15.705 77.6475 801.65 9.8 49 467
378.60 15.354 67.92 869.57 9.8 49 516
407.00 11.814 50.875 920.44 7 35 551
439.27 8.536 42.68 963.12 5.4 27 578
8.536

439.27 963.1225 578


COMPU
1 m2
Seccion m2
Cota Cota de Altura Cola de 4 m Cola de 5 m Cola de 6 m
63+967.00 64+230.00 Terminada fundacion
63+610.00 5.00 2182.00 3.00 15
63+615.00 5.00 2180.00 3.00 15
63+620.00 5.00 2180.00 4.00 20
63+625.00 5.00 2181.00 3.00 15
63+630.00 5.00 2181.00 3.00 15
Piezas 80 0 0
Subtotal (m3) 80 0 0
Total (m3) 80
COMPUTO METRICO
0.5 m2 CANTIDADES
eccion m2 CORTE RELLENO
Volumen Vol. Acum. Volumen Vol. Acum.
Cola de 4 m Cola de 5 m Area (m2) Area (m2)
(m3) (m3) (m3) (m3)
0.00 0.00 0 0
0.00 0.00 0 0.00
0.00 0.00 0 0.00
0.00 0.00 0 0.00
#REF! #REF! #REF! #REF!
0 0
0 0
0 #REF! #REF!
GEOTEXTIL 3 4 5 6 7
Area Acum.
Area (m2) Area (m2) (m2) 5.4 7.0 9.8 11.4 13.0
5.4 27 27 3.00
5.4 27 54 3.00
7 35 89 4.00
5.4 27 116 3.00
5.4 27 143 3.00

143
157.3
8

14.6
COMPU
1 m2
Seccion m2
Cota Cota de Altura Cola de 4 m Cola de 5 m Cola de 6 m
63+967.00 64+230.00 Terminada fundacion
63+305.00 5.00 2182.00 3.00 15
63+310.00 5.00 2180.00 5.00 15
63+315.00 5.00 2180.00 7.00 25
63+320.00 5.00 2181.00 7.00 25
63+325.00 5.00 2181.00 5.00 15

Piezas 45 50 0
Subtotal (m3) 45 50 0
Total (m3) 95
COMPUTO METRICO
0.5 m2 CANTIDADES
eccion m2 CORTE RELLENO
Volumen Vol. Acum. Volumen Vol. Acum.
Cola de 4 m Cola de 5 m Area (m2) Area (m2)
(m3) (m3) (m3) (m3)
0.00 0.00 0 0
2 0.00 0.00 0 0.00
2 0.00 0.00 0 0.00
2 0.00 0.00 0 0.00
2 #REF! #REF! #REF! #REF!

40 40
20 20
40 #REF! #REF!
GEOTEXTIL 3 4 5 6 7
Area Acum.
Area (m2) Area (m2) (m2) 5.4 7.0 9.8 11.4 13.0
5.4 27 27 3.00
9.8 49 76 5.00
13 65 141 7.00
13 65 206 7.00
9.8 49 255 5.00
0.00

255
280.5
8

14.6
COMPU
1 m2
Seccion m2
Cota Cota de Altura Cola de 4 m Cola de 5 m Cola de 6 m
63+967.00 64+230.00 Terminada fundacion
63+245.00 5.00 2182.00 5.00 15
63+250.00 5.00 2180.00 7.00 25
63+255.00 5.00 2180.00 7.00 25

Piezas 15 50 0
Subtotal (m3) 15 50 0
Total (m3) 65
COMPUTO METRICO
0.5 m2 CANTIDADES
eccion m2 CORTE RELLENO
Volumen Vol. Acum. Volumen Vol. Acum.
Cola de 4 m Cola de 5 m Area (m2) Area (m2)
(m3) (m3) (m3) (m3)
10 0.00 0.00 0 0
10 0.00 0.00 0 0.00
10 0.00 0.00 0 0.00
0.00 0.00 0 0.00
#REF! #REF! #REF! #REF!

10 20
5 10
15 #REF! #REF!
GEOTEXTIL 3 4 5 6 7
Area Acum.
Area (m2) Area (m2) (m2) 5.4 7.0 9.8 11.4 13.0
9.8 49 49 5.00
13 65 114 7.00
13 65 179 7.00
0 179 0.00
0 179 0.00

179
196.9