COTIZACIÓN DE INSTALACIÓN DE TUBERÍA PVC- SAP PARA RED, PUESTA A TIERRA Y ELÉCTRICA
COSTO DIRECTO
GASTOS GENERALES (2%)
UTILIDAD (2%)
SUB TOTAL
IGV (18%)
TOTAL
L
UESTA A TIERRA Y ELÉCTRICA
MATERIALES
METRADO P.U TOTAL
1 2,300.00 2300.00
10 12.35 123.50
27 11.12 300.11
1 35.00 35.00
1 45.00 45.00
4 43.00 172.00
100 16.00 1600.00
88 15.00 1320.00
1 40.00 40.00
1 225.00 225.00
1 205.00 205.00
1 1,000.00 1000.00
1 2,600.00 2600.00
1 600.00 600.00
1 350.00 350.00
2 940.00 1880.00
S/. 12,795.61
S/. 255.91
S/. 255.91
S/. 13,307.43
S/. 2,395.34
S/. 15,702.77