Anda di halaman 1dari 10

IEEE Power Engineering Society

Transmission and Distribution


Committee
3152 IEEE Transactions on Power Apparatus and Systems, Vol. PAS-104, No. 11, November 1985
DISRlBUrIOKIA VARENTION OF DISTRIBUTIt(N
SYSTEM RELIABILITY IDICES
R. Billinton, Fellow IEE E. Wojczynski
Power Systems Research Group Manitoba Hydro
University of Saskatchewan Winnipeg, Manitoba
Saskatoon, Saskatchewan Canada
Canada
ABSTRACT with a utility's criteria of acceptable
performance) [6].
Reliability analyses are mainly concerned with the 4) the validation of reliability models and the
mean values of reliability measures, however, the applicability of reliability data [4,5,10,11,12],
distributional variation about the mean is becoming as outage data is often insufficient and
increasingly important as a supplemental measure. inadequate. The index probability distributions
This paper presents the results of a series of can be useful in estimating the errors resulting
simulations studying the distributional variation from inaccurate data. Confidence intervals could
associated with indices for simple distribution be comuted. This type of study is even more
systems. Distributions for the Load Point Failure applicable in generation reliability studies.
Rate, Load Point Outage Duration, Load Point Annual 5) the determination of customer costs of
Interruption Time, SAIDI, SAIFI, and CAIDI are interruptions using non-linear cost functions.
presented and discussed.
Probability distributions provide a practical
IT1DUCTION vehicle to describe the variation of reliability
measures about their means. The approach taken in
Conventiona1 reliability analyses are normally this study to determine these distributions was to
only concerned with the expected or average value of perform probabilistic (Monte Carlo) simulations of
the particular measure of reliability. Little typical radial distribution systems. Monte Carlo
consideration has been given in the past to the simulation is a widely applied technique and as it has
variation of that measure about its mean. For been described fully elsewhere [13 ,14, 151, an
example, when the frequency of failures at a load explanation is not provided here.
point is predicted, only the average value of that An alternative approach is to analyse actual
quantity is typically calculated. The probability interruption data for distributional information. A
that the load point will suffer a specified number of number of such studies have been published
failures in a year is not normally calculated. [4,6,10,11,121. Mlost of these are studies of outages
Similarly, the expected values of the duration indices of components such as lines rather than studies of
are determined but the probabilities of various load point interruptions. Load point index
durations are not calculated. The mnean values are distributions are dependent not only on combinations
extremely useful and are the primary indices of load oE component outages but also on system configurations
point adequacy. There is, however, an increaesd and restoration activities. With the increasing
awareness of the need for information related to the mphasis that utilities are placing on data
variation of the reliability measures around their collection, it is possible that in the near future
means [1,2,3,4,5,6] This information can prove
. more statistical data on load point interruptions will
useful in studies involving: be available. Not only can simulation studies provide
useful information before comprehensive historical
1) the probability of the interr'uptions being longer data is available but they can provide information
than the Critical Service Loss Duration Time or that would not otherwise be possible to obtain. For
some othher time of interest [4,7,8,9]. This example, simulations can provide information
information is especially useful in the design of concerning the effects of very specific system
distribution systems for industrial customers with configurations. Furthermore, simulations can deal
critical processes or conercial customers with with predictive reliability indices not just
very non-linear costing functions. performance indices. Their advantages become obvious
2) the probability of a certain number of failures when making use of distributional studies of
occurring in a particular year [2,3,10,11,12] performance data such as the one by Koval and Erbland
(perhaps determine annoyance factor).
to [6]. The paper provides quite useful information and
3) the comparison of performance indices of different an illustration of the distributional tendencies.
years or different systems to determine the Such as aproach however is not a good means to study
probability of their having a different average the effects of specific characteristics such as manual
value. Such a comparison would assist plaanners to sectionalizing capabilities. The reliability of
judge whether differences in indices indicate real specific designs for a line can not be analyzed by
changes in performance or are due to statistical performance data studies but could be anal]yzed using
variation. (eg. the SAIDI, SAIFI, and CAIDI of a predictive reliability indices and simulations.
system could be compared on a year-to-year basil Studies exanining the di stributions associated
for significant variation or could be compared with the basic reliability indices indicate that the
load point failure rate is approximately Poisson
85 Wi 229-0 A paper recommended and approved
;istributed [2,3]. The failure rate probabilities can
be readily obtained using the mean load point failure
by the IEEE Transmission and Distribution Committee rate, since the Poisson distribution is a
of the IEEE Powqer Engineering Society for presenta- single-parameter function. This information can be
tion at the IEEE/PES 1985 Winter Meeting, New York,
calculated directly using the Poisson equation [2,31
New York, February 3 - 8, 1985. Manuscript submit-
or from a set of published graphs [16].
ted August 23, 1984; made available for printing It has been noted that if the restoration times
December 12, 1984. can be assumed to be exponentially distributed, the
load point outage duration is approximately gamma
Jistributed and the desired probability information
caa be readily calcuilated [2,3]. There are, however,

0018-9510/85/1100-3152$01.00O1985 IEEE
3153
many distribution systems for which the ganma
distribution does not adequately describe the load
point outage duration. These systems are ones in
which some of the restoration t.imes may be better
described by non-exponential distributions, eg.
log-normal repair or manual sectionalizing times.
Studies carried out at the Univrersity of Saskatchewan
indicate that when the restoration times are assumed
to be non-exponential then the interruption duration Load
can not generally be represented by a gana ', 2miles Point
distribution [3,16,17]. In this case, obtaining the ~-~- ---- --- B
desired probability information is more difficult.
Distributions for the Annual Load Point Outage Time,
SAIDI, SAIFI, and CAIDI indices can also not readily I mile
be represented by common distributions. This paper
presents example distributions resulting from studies
of a sample radial system.
DISTRIBUTION SYSTE RELIABILITY ASSESSMENT Load
A C
Reliability assessment in distribution systems is
concerned with system performance at the customer end, F'igure 1. Simple Radial Configuration.
ie. at the load points. The basic indices normally
used to predict the reliability of a distribution utilizing the following basic equations:
system are: Average Load Point Failure Rate, Average
Load Point Outage Duration, and Average Annual Load A EXi failures/yr.
Point Outage Time. These indices are used to predict EX 1
future system performance. Utilities also calculate EA. r.
service performance indices to describe statistically r
s
=- i
-- hours/failure
the past performance of the system. The performance
indices - System Average Interruption Duration Index
(SAIDI), System Average Interruption Frequency Index
(SAIFI), Customer Average Interruption Duration Index Us = As .rs hours/year
(CAIDI), and others [3,18] - can also be calculated This procedure [18] is shown in Table I.
directly from the three basic predictive indices. An
example calculation of reliability and performance Sunmmarizing the results.
indices is presented for the example radial system
shown in Figure 1. Table II
In this base case configuration, all switches are Case 1 Indices
rormally closed and the customer load points A, B, C
are supplied from the primary main by fused laterals. A B C
The feeder breaker and the substation supply bus are
ass umed to be fully reliable. The individual
component data are as follows: X - failures/year 1.35 1.1 0.885
r - hours/failure 1.15 1.86 2.41
Primary main 0.10 failure/circuit mile/yr U - hours/year 1.55 2.05 2.05
3.0 hrs. average repair time
Primary lateral 0.25 failures/circuit/mile/yr There are many configurations particularly in
1.0 hrs. average repair time rural locations which have a topology similar to that
shown in Figure 1. The results shown in Table II can
Manual sectionalizing time for any switching action = be used to obtain the standard performance indices.
0.5 hrs. Assume that there are 250, 100 ahd 50 customers
The simplest approach is to perform a failure res,pectively at load points A, B and C, giving a total
modes and effect analysis [18] in a table form A:-Jt 400 customers in the system.

Table .I
Case 1 (Base Case) Calculatio'ns
LoDad Point A Load Point 1B ___
Load Point C
Component X r Ar X r Ar A r Ar

f/yr_ hrs hrsZy fZyK_ hrs _hrszyE f/yK hrs hrs/yr

Primary Main
2 m section 0.2 3.0 0.6 0.2 3.0 0.6 0.2 3.0 0.6
3 m section 0.3 0.5 0.15 0.3 3.0 0.9 0.3 3.0 0.9
1 m section 0.1 0.5 0.05 0.1 0.5 0.05 0.1 3.0 0.3

Primary Lateral
3 m section 0.75 1.0 0.75 - - -

2 m section - 0.5 1.0 0.5


1 m section -__ 0.25 1.0 0.25
1.35. 1.15 1.55 1.1 1.86 2.05 0.85 2.41 2.05
3154

Annual Customer Interruptions - describe the Poisson distribution, ie. the expected
annual failure rate. Since this value is the index
(250) (1.35) + (100) (1.1) + (50) (0.85) = 490] normally calculated, the distributional information
can be obtained from the Poisson distribution equation
System Average Interruption Frequency Index = with minimal extra effort.
SAIFI Figure 2 depicts the distributions associated with
the failure rates of load points A, B and C for Case
total number of customer interruptions 1. The distributions are noticeably different for the
total number of customers served three load points. At load point A, years with one
failure occur most frequently while at load point C,
SAIFI = 490 = 1.23 years with no failures occur most frequently.
400 Concurrent with an increase in the average failure
rate, the shape of the distribution varies
Customer Interruption Duration = significantly and the individual failure rate
probabilities increase in a non-linear fashion.
(250) (1.55) + (200) (2.05) + (50) (2.05) = 695
Load Point Outage Duration Distributions
System Average Interruption Duration Index = SAIDI
Patton [21 noted that if the repair and other
sum of customer interruption durations restoration times can be assumed to be exponentially
total number of customers served distributed, the load point outage duration can be
approximated by a gamna distribution [2]. This is
SAIDI = 695 = 1.74 confirmed by the studies described in this paper.
400 Figure 3 shows the simulation results for the
outage durations of load points A, B and C for Cases
Customer Average Interruption Duration Index = 1, 2 and 4 when the restoration times are assumed to
CAIDI be exponentially distributed. These distributions can
also be reasonably described by the gamma distribution
sum of customer interruption durations (Chi-square level of significance - .05). As can be
total number of customer interruptions seen, the general shape of the distributions does not
vary. Although the gamna distribution can take on
CAIDI = 695 = 1.42 many different shapes, when it is the result of
490 combinations of exponential distributions, the shape
is always of this general form. The ganma
Similar calculations are presented in Reference 16 distribution becomes more or less spread out, or more
for the following operating assumptions: peaked, depending on the average outage durations and
1) Base Case (As in Figure 1) the average restoration durations. If it can be
2) Base Case with alternate supply available assumed that the restoration times are exponentially
3) Base Case with alternate supply conditional distributed, the resulting outage duration
load transfer probability of .5 distribution can be assumed to be of the forms in
4) Base Case with solidly connected laterals Figure 3 and the outage duration probabilities can be
5) Base Case with probability of successful readily calculated from the gamrna distribution.
lateral fault clearing = 0.9. Patton describes a relatively simple approach for
These case number designations are used later in this calculating the ganna distributed duration
paper to illustrate the distributional effects. probabilities using only the average outage durations
and failure frequencies of the load points and
PROBAABILISTIC SIMULATION PROGRAM contributing sections [2].
In many practical systems, the restoration times
A program was developed at the University of cannot be assumed to be exponentially distributed. It
Saskatchewan to simulate the performance of any is often unrealistic to assume that the probability of
N-section radial distribution system with loads a repair or restoration increases as the duration
connected to laterals or directly to the primary mains approaches zero. Restoration times may be better
[17]. Any combination of exponential, normal, described by non-exponential distr ibutions, eg.
log-normal, and gamma distributions can be used to log-normal repair times. The studies carried out
sinulate the failure, repair, manual sectionalizing, indicate that when the restoration times are assumed
alternate supply and fuse times. Costs of each to be non-exponential, the load point outage duration
interruption can be calculated from 1 minute, 20 cannot generally be represented by a ganma
minute, 1 hour, 4 hour and 8 hour cost data. The distribution. The remainder of this section will
program outputs for each load point: the mean, discuss the resulting distributions and how they vary
standard deviation, and distribution histogram of the with certain factors.
annual interruption time, interruption duration, It should be emphasized that the average values of
annual intorruption frequency, and annual interruption the load point outage duration indices are not
cost. It provides similar outputs for the entire affected by what the underlying distributions are. A
system, in terms of SAIFI, SAIDI, CAIDI, cost per set of averages such as those calculated for the
interruption, and annual interruption cost. Studies example system can have any set of distributions
were performed on the 6 section example system of associated with it.
Figure 1 and on a larger 18 section system. The durations associated with repairs and other
restoration activities may often be weJll described by
Distribution of Load Point Failure Rate 1og-normal or other similarily skewed distributions.
Figure 4 shows the simulation results for the outage
The studies indicate that the load point failure durations when repair times are assumed to be
rate is reasonably described by the Poisson log-normally distributed with a standard deviation
distribution with a Chi-squared level of significance equal to one third of the mean. These distributions
= .1 [3,16, 17]. This result is in agreement with of the load point outage durations have a radically
theoretical considerations and a previous study b., d,,! £erent shape than those a^ssumng expnential
Patton [2]. Only one parameter is required to r>- ;toration times (Figure 3) . In Case 1, the form of
3155

combination of those at A and C.


The backfeeding in Case 2 reduces the number of
failures with three hour repairs at load point C. The
CAS E second mode in the distribution is eliminated. The
3 mode resulting from the lateral repairs is now more
FAILURES/YEAR
pronounced for both load points B and C. When the
AVERAGE
* 1.345

laterals are connected solidly to the mains as in Case


SIMUJLATED RESULT
4, the first mode is even more pronounced for all
three load points. The predominant cause of outages
are failures on the primary laterals resulting in one
hour average repairs.
A visual inspection of the distributions in Figure
4 indicates that the distributions are so different
from those of Figure 3 that attempts to predict the
duration probabilities using the gamma distribution in
these cases of non-exponential restoration times could
O 1 3 4 S 6 7 lead to large errors. Similar results have been
2A RRESUS/YEAR obtained from simulations that assumed restoration
activities are garma and normal distributed. This
.4 indication is verified by goodness of fit testing
;
CASE 1
~~~~~~LOADPOINT B
(level of significance = .01) and by example
calculations [3].
The study results indicate that no known
distributions can universally describe the outage
duration distributions. Studies of outage duration
distributions for entire regions and service areas
confirm the reasonableness of this conclusion and the
distributions depicted in Figure 4 [4,6].
~o~~ ~ ~ ~ ~ ~ ~ As already discussed, varying the means of the
restoration times can significantly affect the shape
of the outage duration distributions. If the
underlying distributions are assumed to be similar to
the lognormal or gamma distributions, the effect is
greater. When the different components all have
restoration times with averages near to each other and
close to the origin, the distribution tends to
FAI LURES/YEAR resemble the exponential. As the differences between
the averages increases, the resemblance decreases.
The distribution may even be multimodal.
The distributions vary with the associated
standard deviations as well as with the component
means. Figure 5 shows outage durations for the sample
.4 4 _ 7 ~~~~~~~LOAD
POINT C
system with the assumptions that the standard
deviations for the repair times are equal to m (MMTR),
m/2, m/3, and m/6. When the standard deviations are
relatively large, the contributing distributions
overlap with the result that the outage duration
distribution is almost a monotonically decreasing
function. As the standard deviations decrease, the
contributing distributions become apparent and the
distribution definitely multimodal.
The sizes of the primary main or lateral sections
L L _ affect the mean, standard deviation, and possibly the
type of the ccrponent restoration distribution. The
load point outage duration distributions are then
indirectly affected by these factors in the ways
discussed above. It is possible that the number of
sections in the system affects the individual
O l ~2
~ 3 4 5 b 7
component restoration distributions. A more likely
FAILURES/REAR possibility is that the larger number of contributing
distributions may tend to overlap more and to obscure
Figure 2 Load Point Failure Rate Distributions - modal tendencies that might be apparent in smaller
Exponentially Distributed Restoration systems. This tendency is most pronounced if the
Activities. restoration activities of the different system
sections are dissimilar.
the distribution of load point A appears to be Simulations were performed for an 18 section
decreasing with duration except for a peak a couple of system similar to the example system but with 9 load
bars wide. This peak is attributable to the large points. Figure 6 plots the outage duration
number of repairs of 1 hour average duration which are probabilities for the first, middle, and last load
made on the first primary lateral. Due to it being points of the 18 section system. Visual and
further down the line, load point C has a larger statistical comparisons (Chi-Square level of
numer of repairs of three hour average duration. significance = .05) indicate that the outage duration
These repairs to the mains in combination with repairs distributions resulting from the assumption of
to the third lateral result in a bimdal distribution lognormal distributed repair times are significantly
with peaks of durations just less than one and three different from those resulting from an assumption of
hours
long. Load point B has a distribution that is a exponential distributed repair time. This confirms
3156

.351 .35 1- distributed restoration


times resulted in annual
.30 .30
interruption time
distributions that contain a
CASE 1 CASE 2 CASE 4
LOAD POINT A
sharp peak for the interval
LOAD POINT A
.25
LOAD POINT A
AVERAGE-1.1709 HRS. AVERAGE-1. 1707 HRS. .25 AVERAGE-0.9411 HRS. indicating the number of
years with no failures. The
distributions are steadily
.20
r.20 decreasing ones with long
-3 tails. The distributions
.: .15 go C . 15 are not of the exponential
*s
C;
I=
or gamma form.
The simulations that
.10 .10 assumed lognormal
distributions for the repair
.054 .05
times and exponential
distributions for the other
times also resulted in
0 distributions with a sharp
U 1 2
OUTACE DURATION IN
3 4
XJhOURS
5 1 2 3 4
OUTAGE DURATION IN HOURS peak for the no failure
.30 .30 interval. Inspection of the
annual interruption time
distributions of all the
.25 .25 other Case 1, six section
CASE 1 CASE 2 CASE 4
LOAD POINT B LOAD POINT B LOAD POINT B system simulations reveals
.20
AVERAGE-1.8739 HRS. AVERAGE-1.5363 HRS.
.20
AVERAGE1.L4416 HRS. that the number of years
with zero hours of
J interruption is independent
;; 15
.2
0 < .15 of the form and standard
0*
: co
deviation of the restoration
10
10
time distributions. This
.
independence occurs because
the number of years with
.05 zero interruption time is
dominated by the failure
ll
rate distributions which
1 4 5
0
determine the number of
years in which no failures
.0 2 3

OUTAGE DURATION IN HOllRS


30 .30 1 occur.
CAS E 1 CASE 2 CASE 4 The lognormal
LOAD POINT C LOAD PONTM C LOAD POINT C
AVERAGE-1.6350 HRS.
simulations did not result
AVERAGE=2.4151 HRS. AVERAGE=1.2597 HRS. .251
in steadily decreasing
distributions but in
20 distributions with multiple
I,-
modes. The multiple
-0 modality is more prcninent
:;,
:
2: Is5
co
when the restoration times
0 are assumed to have small
10 .10 standard deviations. With
standard deviations equal to
the means, the zero failure
.05 peak and a second mode
31) before 1.2 hours are
observable. With standard
1 2 3 4 S 0 1 2 3 4 5 1 2 3 4 5 deviations equal to 1/6
OlJTAGE DlURATION IN IIOURS OllTAGE DURPUl I!l IN IIOIIRS OUlTAI(T IIUJRATION IN HOURS means, the zero failure peak
and modes about 1.0, 2.0,
Figure 3 Load Point Outage Duration Distributions - 3.0, and 6.0 hours are evident. The peaks of certain
Exponentially Distributed Restoration duration (ie 2 and 6 hours) are related to years in
Activities. which more than one interruption occurs and the
restoration times are multiples of the dominent modes.
the conclusion drawn for the smaller 6 section system
that the outage duration distributions cannot in Distribution of SAIDI, SAIFI, CAIDI
general be described by the gania distribution
ccmputed fran the carponent average repair times. System performance indices and load point
reliability indices are not normally carpared or
Distribution of Load Point Annual Interruption Time simultaneously calculated. Performance and
reliability indices are in reality related by the fact
The annual interruption time distribution is that both are based on a cmmon set of data. The
dependent on both the failure rate and outage duration distributions of both indices are dependent on the
distributions. Because of this, it is even more distributions of the cmponent failure rates and the
difficult to describe the interruption time restoration activities. The SAIFI and SAIDI average
distributions by known functions. Figure 7 depicts indices are independent of the underlying
distributions resulting from simulations of the six distributions but the CAIDI average index is
section example system. distributionally dependent (17).
The simulations that assumed exponentially Figure 8 depicts distributions resulting fran
3157

.30 .30
likely that there would be
at least oneinterruption.
CASE 1
LOAD POINT A
CASE 2
LOAD POINT A
CASE 4
LOAD POINT A The SAIFI distributions
.2S AVERAGE.1.1668 HRS. .25 AVERAGE.1.1560 HAS. AVERAGE.0.9252 HRS. are identical for the
,_I
exponential, log-normal S.D.
.20 .20 = m, and S.D. = m/6
simulations because SAIFI is
only dependent on the
is -.15 component failure time
4 distributions which do not
.10 .10 .I
vary with the simulations
runs and on the number of
customers served at each
.05 .OS load point. The irregular
variation of the
distribution shape is
related to the small number
0

0 1 2 3 4 5 I 3 4 S
of load points and the
2

OUTAGE DURATION IN iOURS OU1 AGE DURATION IN HOURS OUTAGE DURATION IN HOURS
.30 .30 resulting discrete weighting
CASE 1 CASE 2
LOAD POINT B
CASE 4
LOAD POINT B
by the number of customers
LOAD POINT B
AVERAGEal.5084 HRS. AVERAGE-1.4010 HRS. factor. As for the SAIDI
.25 AVERAGE-1.8772 HRS. .25$ .25
distributionss, in large
systems the probability of
.201 .20 SAIFI equalling zero
diminishes with the
distribution less resembling
.%.is
15
-. is
an exponential one and more
40 go one with a mode about the
.10 .1 average.
The CAIDI distributions

tl
are non-linearily related to
.05.
both the failure and
restoration times. This
0 0
1f
results in a somewhat
1 2 3 4 S D 1 2 3 4
OIuTAGE DURATION IN HOURS
similar modal distribution
OUTAGE DURATION IN HOURS
for the three simulations.
.30 The exponential and
CASE 1 CASE 2 CASE 4
LOAD POINT C
lognormal S.D. = m
LOAD POINT C
AVERAGE-2.4096 HRS. .2S
LOAD POINT C
AVERAGE.1.2455 HRS. AVERAGE=1.5825 HRS. simulation distributions are
more similar than the
lognormal S.D. = mV6
.20 .2( simulation distribution.
This and other comparisons
.- indicate that the standard
deviations of the underlying
.15
an
co co
CL.
1'
distributions can affect the
.10 .1 shape of the final index
distribution as much or more
.0s5
than the actual form chosen
.05
for the underlying
distributions. For large
0
0
systems, the CAIDI
0 1 2 3 4
OUTAGE DURATION IN HOURS
5 0 1 2 3 4
OUTAGE DURATION IN HOURS
distribution also tends to
OUTAGE DURATION IN HOURS "tighten up"' around the
,u'en .
;.ure 4 Load Point Outage Duration Distributions -
Pepair Times Lognormally Distributed (SD CXTLUSIC
1/3 Mean) Other Times Exponentially
Distributed. The means of the reliability and system
performance indices are and will continue to be the
simulations of the 6 section example systen. The main indice characteristic but the indice
SAIDI distribution is dependent on the distributions will increasingly be utilized as
distributions of the restoration times. The number of supplementary measures. The Load Point Failure Rate
customers at each load point and the average failure distribution can be assumed to be Poisson distributed
rates are weighting factors that are independent of with the distributional information easily obtainable
the associated distributions. The SAIDI distributions from the Poisson equation. The Load Point Outage
of Figure 8 are similar to the Annual Interruption Duration distribution can be assumed to be Gamma
Time distributions of Figure 7. This is because SAIDI distributed when it is possible to assume that
is a linear combination of annual interruption times. restoration activities are exponentially distributed.
In a large system, the resemblance tends to decrease Otherwise the duration distributions must be obtained
because of the averaging effect of the large number of by simulations or other means. The Load Point Annual
load points which are aggregated. In this small Interruption Time, CAIDI, SAIFI, and SAIDI
system, the number of years with a SAIDI equal to zero distributions cannot in general be described by any
is relatively high (ie. P [SAIDI 0] is high). This = known distribution and must be found by simulations or
might be expected in a small or moderate size system. other means.
In the case of a large system or region it is -very Distributional information obtained from
3158

.30 LOAD POINT A LOAD POINT A .30 LOAD POINT A


S.D. (r)= S.D. (r) =mf/2 S.D. (r=1)=m/2 .30 LOAD POINT A
AVERAGE=1 .1743 AVERAGE=1. 1698 (=3)/3
S ,D r.- S. D. (r)=m/6
S.D. (ra)= .6183 S.D.(rS)=1 .1166 AVERACE=1 .1682 AVRRAGE=1.1657
.25 .25 S.D. (ra)=1 .0236 S.D. (r8)=.8954
.25

.20. .20 1
.20

q .15 .15
N .15

,,.
.10 .10 K .10

4 .0.5o
.05 I'
.°S
0
1 Z 3' 4 -3 1 2 3 4 5' 0
OUTAGE DURATION IN HOURS OUTAGE DURATION IN HOURS 1 2 3 4' 5
OUTAGE DLRATION IN HOURS

LOAD POINT C .25 LOAD POINT C


S.D. (r)=m/2 LOAD POINT C
S.D.(r)=a S .D.(ral )=A/2 LOAD POINT C
AVEIAGE=2.3979 A VEAGE=2.4098 S.D.(r)=v/6
S .D .(r-3) =013
S.D. (r8)=2.6414 AVERAGE=2.4141
S.D. (r8)=1 .5637 AYERAGE=2.4118
.20 .20 S.D.(r )=1.2618 .20
S.D.(r,)=1.0054

f"; .15
i .15
H

I
1
X .10

.05
.05

0 -rF

OUTAGE DURTION IN HOURS 1 2 3 4 5


OUTAGE DURATION IN HOURS

Figure 5 Load Point Outage Duration Distributions As Approach", IEEE TPAS-102, No. 6, June 1983, pp.
A Function of Ccmponent Standard Deviations 1486-1493.
- Repair Times Lognormally Distributed, Case 6. Koval, D., Erbland, M., "Distribution Reliability
1. Assessment Using a Proprietory Statistical
Package", CEA Distribution System Planning,
simnulation studies such as these shown in this paper Conference #1, October 1983.
complement actual data on index variation collected 7. IEEE Cnittee Report,"Report on Reliability
for similar load points over a number of years. Survey of Industrial Plants, Part II: Cost of
Together they provide additional valuable information Power Outages, Plant Restart Time, Ctitical
on system and load point reliability. Service Loss Duration Time, and Type of Loads Lost
Versus Time of Power Outages", IEEE Transactionis
on Industry Applications, Vol. IA-10, No. 2, pp.
236-241, March/April, 1974.
1. Koval,, D.O., and Billinton, R., "Statistical and 8. Power Systems Reliability Subcomlittee Report,
Analytical Evaluation of the Duration and Cost of P.E. Gannon, "Cost of Electrical Interruptions in
Consumers Interruptions",, IEEE/PES Paper No. A79 Commercial Buildings", IEEE 1975 I&CPS Conference,
057-1, Winter Meeting, February 1979. pp. 123-129, 1975.
2. Patton, A.D., "Probability Distribution of 9. Wojczynski, E., Billinton, R., and Wacker, G.,
Transmission and Distribution Reliability "Interruption Cost tMethodology and Results - A
Performance Indices", 1979 Reliability Conference Canadian Ccxnercial and Small Industrial Survey",
for the Electric Power Industry, pp. 120-123, IEEE SM 390-2 1983.
1979. 10. Beaurecueil, P.S., "Southern California Edison
3. Billinton, R., Wojczynski,, E., and Rodych, V., Company Transmission Line Outages Statistical
"Probability Distributions Associated with Analysis",, Reliability Conference for the Electric
Distribution System Reliability Indices", 1980 Power Industry, pp. 27-38, 1980.
Reliability Conference for the Electric Power 11. Fond, C.C., and Le Reverend, B.K., "CaTputerized
Meeting, 1980. Statistical Analysis of Transmission System Outage
4. Koval, D.O., and Erbland, M.J., "Statistical Data", Reliability Conference for the Electric
Analysis of the Duration of Outages", CEA Power Industry, pp. 39-46, 1980.
Transactions, presented at Fall Meeting, Winipeg, 12. Polena, R.J., 11345 kV Line Outage Data Analysis
1980. for System Planning Application", Reliability
5. Sahinoglu, M., Longnecker, M., Ringer, L., Singh, Conference for the Electric Power Industry, op.
C., Ayoub, A., "Probability Distribution Functions 45-49, 1981.
for Generation Reliability Indices - Analytical
3159

.35

.30 LOAD POINT A .30 WOAD POINT A


EXPONWTAL REPAIR LOGNORMAL REPAIR
S.D.(r)- J9 S.D. (r)../2
AVRA9.8 90 AVERAGE=-.8427
.25 .25

.20 .20

N .15 I .15

.10 .10

.05
o .05

0 0
1 2 3 4 5 1 2 3 4 5
OUTAGE DURATION IN HOURS OUTAGE DURATION IN HOURS
.30

W2IAD POINT N
E2DCPONTMAL REPAIR .25
*25 WAD POINT E
WOGNORMAL REPAIR
S.D. (r)-m S.D. (r)=m/2
AVERACE=1.895 AVERAGE=l.909
.20 .20

k . 15 > . 15

.10 .10
.°S

.05
o .05o

0 0
1 2 3 4 5
OUTAGE DURATION IN HOURS OUTAGE DURATION IN HOURS
.30 .30

.25 I WAD POINT I 25 LOAD POINT I


EXPONENTIL1 REPAIR
5

LOGNORMAL REPAIR
S.D. (r)=m S.D. (r)=u/2
AVERAGE=2.727 AVERAGE=2.761
.20 .20

1>4
4 .15 F .15

A .10 A .10

.05 .05

1 2 3 4 5 0 1 2 3 4
OUTAGE DURATION IN HOURS OUTAGE DURATION IN HOURS

Figure 6 Outage Duration Distributions For An 18 Section System - Case 1.

13. Shannon, R., Systens Simulation; The Art and 17. Wojczynski, R., "Application of Reliabilit Worth
Science, Prentice-Hall Inc., New Jersey, 1975. in Power System Planning", M.Sc. Thesis,
14. Singh, C., and Billinton, R., System Reliability University of Saskatchewan, January 1984.
Modelling and Evaluation, Hutchinson and Campany, 18. Billinton, R., Allan, R.N., "Reliability
London, 1977. Evaluation of Power Systems", Pitman Publishers
15. Billinton , R., Hamud, G.A., Jamali, M.M., Ltd. 1984.
"Reliability Evaluation Using Monte Carlo
Simulation",, CEA Transactions, Spring 1979.
16. Billinton, R., Wojczynski, E.,, Godfrey, M.,
"Practical Calculations of Distribution System
Reliability Indices and Their Probability
Distributions", CEA Transactions, 1981.
3160

.30 .30 .30

.25 LOAD POINT A .25 LOAD POINT A


EXPORNIISAL 100AI0 LOGNORMAL REPAIR
.25 LOAD POINT A
S.D.0(or). S .D. (r) -- I0GNORMAL REPAIR
AVM=AR= 1.576 AVER4CE=1. 50 (0r)/6
SA.DO.
.20 .20 AVERAGE=1 .568
.20

>-
g .15
.15
I FX *
I .10I .10 I°3 l1

.0

AIINAL INlTRRUPTION TIOE IN HOURS

.60 .60 .60

.30 LOAD POIINT C .S0 LOAD POINT C .50 LOAD POINT C


EXPONENTIAL REPAIR LOGNORMAL REPAIR DOGNORMAL REPAIR
S.D.(r)o( S.D.(1r5= S.D. (r)00/6
AVERACE=2.077 AVOERAG=2.061
.40 .40 .40 A01AG:S'2.075

l .30 j .30
l .30
A. .20 .20
A A .20

.10 .10 .10

0 0
A z 3 4 S 6 7 S 0 1 2 3 6 5 6 (7 0 1 2 3 4 S A ?
ANNUAL INTEIuOION TIME II NOURS A1NUAL INIT11UPTIOR TIME IN HDt0S
A
ANNUAL INTERRUPIION TIME Il HDURS

Figure 7 Distribution of Annual Interruption Tines - Case 1.

I
.30 .30

.25
I EPOINENTIAL REPAIR .2 !5 EXPONENTIAL REPAIR .25 EXPOENTUI REP0I0
_S.'D.(r)-a 0.1D(r).a S.D.(r)..
AVERAGE=1.762 AVER00=1 .224 AVERACE=1 .332
.20
S.DI.(SA.DI).2.318
.21 0
S.D.(SAIPI)=.974
.20
S.D. (CAIDi0=1.199

N .15 5 .15
3-
13

I .10 0 .10

.05 .00 .05

0
0.3 1.0 1.5
SAIDI- HDRS/CUMOIERN CADI- HDURSAINlTUoTION
.30 .30 .30

.25 lONORRAL REPAIR .25 iDCNORltAL REPAiIR


S.D.1(r)
_ AVER0E=1.761
.25 S.D. (r)--
AVERAGE=1.346 Figure 8 Distribution of System
S.D.(OSAIDI.)2.292 S.D.(CAII)=l .257 Performance Indices Case 1.
.20 .20 .20

I3 .15 rt .15

1 .10

.05
,, .15 .05
i .10

0
0 1 2 3 O 0 015 1.0 1.5
SAIDI- iV01S/a=00RME1 SAIFI- INTERRUPTIONS/CUSTOME:R C1ID1. HDURS/IIPIrRRUPTION
.10
,Wv Tr .30

.25 ICNORMAL REPAIR .25 10S0.1D1.(r) 006 .23


2 LOGNORMAL1*1
S.D (r) ./6
REPAIR

S.D. (r)-u/6
AVERA0 R=1.757 A0ERA1E01.224 A0E0AG016=.333
S.D.(SAIDI).1.729 .20
S.D.(SAIPI).97?4
.20
S.D.(CAIDI ).589

1 A~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
N .15
3 *iS .15

.10
I.10

.05 .05
.05

°S

1 2 3 0 10 0.5 1.5

S11DI- i0URS0/CJIoMER INTEoRRUPTIONSR SI/OOT ERo CAIRO- H00010/IIIT1I UPTION

Anda mungkin juga menyukai