SPECIFICATION FOR
PIPING LAYOUT
SPC-0804.02-50.05 REV.D2
TOTAL 16 PAGES
.
AREA CODE OF SITE LOCATION
0804.02
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 2 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
CONTENTS
SECTION
3.0 BOLT AND NUT, VENT, DRAIN AND SAMPLE CONNECTIONS .................... 7
1.0 SCOPE
This Standard covers the requirements for piping design and piping layout.
Excluded are
a) All instrument control piping downstream of the first piping block valve.
Where local plant conditions or space limitations dictate that this Standard
cannot be applied, proposed deviations shall be submitted for
PTT/CONSULTANTS approval.
In pipe tracks and pipe racks hot lines shall be grouped together and expansion
loops shall be nested. The number of expansion loops should be kept to a
minimum, consistent with the stress requirements.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 4 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
Provision shall be made for the flushing of all lines after hydrostatic testing, and
shall normally be done by the use of a removable spool piece or on long lines
with a line size flange and blank at the end of the line.
- Overhead lines for acid, caustic or other corrosive services must not have
flanged joints located above access ways or platforms.
All safety valves inlet lines shall slope and free drain towards the process line
and all flared lines shall slope towards the knockout drums with the minimum
slope as required on PD-10-13240-3515-01.
Underground lines shall have means for testing, draining and flushing.
Branch connections from horizontal air mains shall be taken from the top of the
main.
Piping arrangements shall ensure that installed valves are readily accessible and
easy to operate.
Where valves are secured in position only by being clamped between pipe work
flanges, e.g. wafer valves, the effect of removing the adjoining pipe work shall
be taken into account.
Valves shall not be installed with their stems below the horizontal.
Access shall be provided for valves in ground level pipe tracks, the valves being
suitably grouped as far as practicable.
Valve with extended stems in cold services that may contain liquids shall have
their stems located in a vertically upwards position to ensure that cryogenic
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 5 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
liquids will not come into contact with the stem packing area. Exceptions may
be made for vent/ drain and instrumentation block valves.
2.2 Clearances
Piping systems shall be designed and equipment laid out to provide access by
mobile equipment.
Space shall be left around equipment and piping to facilitate maintenance (tube
bundle removal, cleaning, etc).
2.2.1 Clearance between Pipelines and between Pipe and Concrete and Steel
Constructions
The minimum distance is generally 50mm. When deciding the spacing of the
pipes, the thermal expansion and contraction must be considered.
Clearance between the outside diameter of flange and the outside diameter of
pipe or insulation: 25 mm.
Pipe work shall be carried on overhead pipe racks wherever practicable, and
clear ways provided where necessary to allow the operation of cranes and other
mobile equipment for maintenance purposes.
Battery limit valves, spades and drains may be located in vertical or horizontal,
except for the flare and relief systems. Permanent platform access shall be
provided. Where more than one unit is located within the same process area
battery limit, separate utility headers provided with isolation valves shall be
required for any unit which is not fully integrated.
This pipe work shall run on pipe ways at ground level or in overhead pipe racks.
When above-ground lines and underground lines run parallel to one another, the
above-ground lines shall not be laid directly over the underground lines.
Lines at ground level shall be grouped together, to form grade tracks and shall
be run on supports, to give the lines on the same bottom elevation.
Expansion loops shall be used to absorb excess stresses where the normal pipe
routing is too rigid.
Expansion bellows shall only be used in special cases and shall be subject to
written approval from the PTT/CONSULTANT.
Limited pressure drop conditions may be expected in large vapor lines, heater
transfer lines, re-boiler circuits, pump suctions, safety valve in- and outlet lines,
and gravity flow lines. Such piping to be routed as directly as practical.
All pipe supports, guides, etc, are to be located on the isometrics and piping
plan.
After bolt and nut had been tighten at correct torque (prior to insulate, if
required), they shall be degreased to remove any contaminated fat, grease or oil
by using degreaser then two pack surface tolerant-high solid epoxy ( Jotamastic
87) shall be applied to the bolt and nut at least two layers:
Bolt and nut which serviced at temperature (design temperature) higher than
100 deg C or lower than -10 deg C, CONTRACTOR shall propose other
appropriate paint for such temperature to PTT for prior approval.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 8 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
After painting, uninsulated flange ( size 4” and above )shall be protected with
“CORROSHIELD” flange protection system.
For ease of bolt and nut removal, flange shall not be connected directly to
elbow. A minimum of 5D short pieces shall be provided between flange and
elbow.
All high points of lines shall be vented. Process vents to be indicated on the
piping and instrument diagram.
All vents to be fitted with valves and blind flange, clearance for insulation is to
be considered.
- All low points of lines shall be drained. Drains shall be fitted with valve (s)
and blind flange and have a minimum clearance of 250 mm below the drain.
- Only flanged valve shall be used for amine service or line where Post Weld
Heat Treatment is required.
- Casing vents and drains for pumps in non-volatile services shall be valved
and piped to the pump base plate or into a gutter or sewer.
- Casing vents and drains for pumps in services handling material near the
flash point shall be piped to a cooler and from the cooler to a sewer; or
alternatively piped to an operating line, relief or blow-down line or to a safe
location. Note that where the drain is to a closed system, facilities shall be
provided for installing blinds for test purposes.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 9 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
The effect on the area classification shall be considered when arranging the
position of the sample point.
Sample connection inlet lines, which are tapped from a horizontal main pipeline,
shall be connected from the top of pipe for vapour contents and from the
bottom of pipe for liquid(with isolation valve).
All operational parts of the sampling system shall be easily accessible, including
the primary isolation valve. Sample points shall either be approximately 1 m
above ground level or 1 m above a platform level, which shall be provided with a
stairway access but subject to PTT approval.
Connection between sampling storage with process piping shall be locking dog
mechanism with large contract area used to stem retention stainless steel quick
coupling.
Steam piping shall be designed for complete condensate removal. Drip legs shall
be provided on all steam lines at low points and dead ends.
Branch connections shall be taken off the top of the headers and shall be 1”
minimum size.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 10 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
Block valves shall be installed in the horizontal run of each branch line unless
otherwise shown on Piping and Instrument Diagrams.
Steam traps shall be provided at low points and drip legs of steam lines.
Traps shall be located adjacent to the equipment they serve. They shall be
accessible for maintenance from grade or platform firmly supported. No steam
trap shall be connected to more than one steam line nor to more than one
section of the same line.
Valves shall be located on each side of a steam trap for trap removal on closed
systems. Steam traps discharging to the atmosphere shall have upstream block
valves only.
Utility hose stations shall be installed throughout the process area to provide
water, air and inert gas (normally will be Filtered water, Utility air, Nitrogen).
Demin water and Steam utility may be provided additionally in some utility
station where necessary.
These utility stations shall be located so that working areas at grade, vessels or
structures can be reached with a 15m length of hose.
Utility stations shall be installed such that they remain in service during unit
shutdown.
Two (2) hoses (15 meter length each, ¾” size) and hose rack shall be provided
per each utility station.
Stainless steel quick coupling shall be furnished, hose ends shall be male and
female, station end shall be male.
One utility station shall be provided at each manhole of pressure vessel, tank,
furnace, WHRU.
Utility for vessel man hole shall be provided air and inert gas.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 11 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
Air system piping design shall allow for good drainage. Drain valves and drip
legs shall be provided at the low points of systems. Branch connections shall be
from the top of the header.
Water for eye-washing fountains and emergency showers shall be supplied from
the drinking water system and shall be maintained at suitable constant
temperature. Self-closing valves and self-draining hydrants shall be furnished.
5.0 INSTRUMENTS
Where control valves size are less than line sizes; reducers shall be placed
adjacent to the valve. Concentric reducers shall be used on socket weld and
screwed fittings, eccentric reducers (bottom flat) on butt-weld fittings. Spools or
reducers between flanged block and control valves shall be made long enough to
permit bolt removal.
All control valves shall be accessible and preferably be located at grade level for
operation and maintenance convenience. The actuators shall be installed in a
vertical position in horizontal lines.
Control valve manifolds shall be designed to allow for easy removal of the
control valve. Sufficient clearance shall also be provided above and below the
control valve for removal of the actuator plug.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 12 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
All above requirements shall be applicable to all other automatic valve; e.g.
emergency shut down valve etc.
Horizontal metering runs shall be provided for liquid flow measurement and in all
cases where segmental orifices are used. Vertical runs with downward flow may
be used for steam and condensibles, and upward flow for liquids near their
boiling points.
The level in level gauges shall be visible from grade ladder or a platform and its
associated level control instrument and level switches, where possible. Level
gauges and control instruments shall not penetrate platforms.
Connection for local pressure gauge shall be located so instruments can easily
be read from the grade or platform or ladder.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 13 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
Piping and platforms around columns and vertical vessels shall be arranged so
that, where necessary, there is a clear space for lowering equipment to the
ground.
Piping shall be arranged so that, blinds can be readily installed at vessel nozzles
for maintenance.
Where possible, block valves shall be located directly against the vessel nozzles.
Process and water piping to shell and tube exchangers shall be arranged to
permit easy removal of shell covers, channel covers, channels and bundles.
Adequate clearance shall be allowed for mobile handling equipment. Piping shall
be adequately supported such that bundles can be removed without the use of
additional supports.
Piping should not be routed in air fin areas in such a way that would obstruct
maintenance.
Unless otherwise specified piping header for air cooler shall be arranged as
below.
Note:
When thermal expansion have been taken into account, the headers which
serviced at high temperature or having long distance may be split into two or
more separated symmetrical headers
Inlet piping shall be provided inline strainer with isolation valve and spectacle
blind. Pipe shot spool on that point shall be provided.
SPC-0804.02-50.05
PTT PUBLIC COMPANY LIMITED PAGE: 15 of 16
PIPING LAYOUT ENGINEERING SPECIFICATION REV: D2
Outlet piping shall be provided pipe shot spool with inert gas connection 2 inch
with valve and provide isolated valve with spectacle blind.
Accessibility to remove pipe shot spool like lifting advise equipment and platform
shall be provided.
Suction piping shall slope continuously downward from the knockout vessel to
the compressor inlet. An alternate arrangement depending on compressor
suction valve location, piping shall slope from the valve to compressor suction
inlet on one side from the valve to the knockout vessel on the other side.
Centrifugal compressor piping shall be designed and supported such that the
load on the nozzle is in accordance with that allowed by the compressor
VENDOR.
Piping at pumps and turbines shall be designed to allow for sufficient flexibility
of the equipment nozzles and supported so that the equipment can be
dismantled or removed without adding temporary supports or dismantling valves
and piping other than spool piece or reducers adjacent to the equipment
connections.
Block valves in suction and discharge shall be located as close to the pump
nozzles as possible.