Anda di halaman 1dari 12

SITE DAILY REPORT

PT. MITRA MAHAJAYA MANDIRI

PROJECT : Barking Drum Shell WY Line #7 (Diameter 5480 mm x 20785 mm)

CONTRACT NO : LOCATION: Wood Yard Line 7 CONTRACTOR : PT. Mitra Mahajaya Mandiri
PO 9000372606 MONTH : 1 DAY : 21 DATE : December 27, 2018
WEATHER SHINE DRIZZLE HEAVY VERY HEAVY FROM TO REMARKS
AM √ 7:00 AM 12:00 PM
PM √ 13:00 PM 21:00 PM
WORKING TIME : 14 Hours REMARKS :
START : 7:00 AM FINISH : 21:00 PM
SUPERVISORY STAFF NO LABOUR FORCE NO MACHINERY NO MACHINERY NO
Site Manager 1 Welder 11
Supervisor 1 Fitter 3
QA/QC 1 Semi Skill 6
HSE 1 Scaffolder 3
Helper 5
Warehouse Keeper 1
Electrical 1
TOTAL 4 TOTAL 30 TOTAL TOTAL

PROGRESS OF WORK AT SITE

Description Status Report No.


1. Welding Support Ring Part No.9 On-Going -
2. Welding Joint CWL-2 (Shell 1 to Shell 2) Outside On-Going -
3. Fit-up Shell 4B to 3B On-Going -
4. Inspection Fit-up Shell 4B to 3B On-Going -
5. Inspection Dimensional Shell 4B to 3B (Alignment) On-Going -
6. Install Temporary Lifting Lugs on Shell 4A (2 Part) On-Going -
7. Install Temporary Lifting Lugs on Shell 3C (2 Part) On-Going -
8. Install Temporary Lifting Lugs on Shell 3A (2 Part) On-Going -
Documentary Photo
Documentary Photo
MATERIAL :

MATERIAL IN / OUT DESCRIPTION FROM


- - -
- - -
- - -
- - -

DRAWING / DOCUMENT RECEIVED:

None

SITE INSTRUCTION :

None

ARCHITECT & ENGINEER'S INSTRUCTION :

None

VISITOR/S TO SITE :

None

NOTE :

None

Prepared By (Contractor): Checked By (Contractor): Verified By (Client / Consultant):

Signature : Signature : Signature :

Name : Name : Name :


Date : Date : Date :

Anda mungkin juga menyukai