CONTRACT NO : LOCATION: Wood Yard Line 7 CONTRACTOR : PT. Mitra Mahajaya Mandiri
PO 9000372606 MONTH : 1 DAY : 21 DATE : December 27, 2018
WEATHER SHINE DRIZZLE HEAVY VERY HEAVY FROM TO REMARKS
AM √ 7:00 AM 12:00 PM
PM √ 13:00 PM 21:00 PM
WORKING TIME : 14 Hours REMARKS :
START : 7:00 AM FINISH : 21:00 PM
SUPERVISORY STAFF NO LABOUR FORCE NO MACHINERY NO MACHINERY NO
Site Manager 1 Welder 11
Supervisor 1 Fitter 3
QA/QC 1 Semi Skill 6
HSE 1 Scaffolder 3
Helper 5
Warehouse Keeper 1
Electrical 1
TOTAL 4 TOTAL 30 TOTAL TOTAL
None
SITE INSTRUCTION :
None
None
VISITOR/S TO SITE :
None
NOTE :
None