ABSTRACT
ORDER:
The Chief Engineer (R&B) MDR in his letter read above, has stated that
proposed Inner Ring Road to Kuppam town is 10.45 kms length, which comprise 4
Arms. The Arm-I (North side) for a length of 2.40 Km is named as Linked road, for
which Land acquisition process is completed and the construction work is in
progress. The Arm – IV (East side) length of 3.05 Km is a part of the existing NH-
219 and no development is required. For the balance two arms – Arm – II (West
side - 2.40 Km) & Arm –III (South side -2.60 Km) the Stage-I activities i.e., Land
Acquisition & shifting of utilities for both the Arms are in brisk progress. Hence the
Chief Engineer (R&B) MDR has requested to accord Administrative sanction for the
two said two arms i.e., Arm-II and Arm-III under PLAN MDR.
4) The amount sanctioned in para (2) above, shall be met from the Head of
Account “ 5054 Capital outlay on Roads and Bridges - 04 District and Other Roads –
MH.337 Road Works–GH.11 State Development Schemes – SH (09) Major District
Roads –530 Major Works - 531 Other Expenditure”.
5) The Chief Engineer (R&B) MDR, AP shall take further necessary action
accordingly.
6) This order issues with the concurrence of Finance Dept vide their
U.O.No.17023/76/FMU-TR&B/2018, dt.25.05.2018
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
To
The Chief Engineer (R&B), MDR, A.P., Vijayawada.
Copy to:
The Director of Treasuries Accounts, A.P., Vijayawada.
The Pay and Accounts Office, AP., Chittoor District.
The Director of Works and Accounts, AP, Vijayawada.
The Finance (FMU.TR&B) Dept.
The P.S. to Hon’ble M (R&B)
The P.S. to Spl.Chief Secretary, TR&B Dept.
Sf/Sc
// FORWARDED :: BY ORDER //
SECTION OFFICER