Anda di halaman 1dari 4

PT.

FAJAR SARANA MANDIRI


JL. TABRANI AHMAD GG. BERDIKARI 1 NO. 1 KECAMATAN PONTIANAK BARAT – KALBAR
TELP. (0561) 773528

REKAPITULASI RENCANA ANGGARAN BIAYA


PEKERJAAN : PEMB RUMAH TINGGAL Komp. SEHA GRAND CITY 3
LUAS BANGUNAN : 36 M2
LUAS TANAH : 150 M2
LOKASI : JL. Raya Sungai Kakap Pal 7 Desa Pal 9

NO JENIS PEKERJAAN SUB JUMLAH

I PEKERJAAN PERSIAPAN Rp 1,000,000.00

II PEKERJAAN PONDASI Rp 6,112,300.00

III PEKERJAAN LANTAI BETON Rp 6,544,750.00

IV PEKERJAAN DINDING,KOLOM & BALOK Rp 7,736,100.00

V PEKERJAAN KAPSPANT & ATAP Rp 11,873,600.00

VI PEKERJAAN PLAFOND & LISTRIK Rp 2,926,000.00

VII PEKERJAAN PINTU,JENDELA & VENTILASI Rp 8,893,000.00

VIII PEKERJAAN PENGUNCI & PENGGANTUNG Rp 500,500.00

IX PEKERJAAN PENGECATAN Rp 1,510,000.00

X PEKERJAAN SANITASI Rp 1,180,000.00

XI PEKERJAAN LAIN - LAIN Rp 3,423,000.00


Rp 51,699,250.00

JUMLAH Rp 51,699,250.00
UPAH TUKANG 36 X 480000 Rp 17,280,000.00
PERENCANAAN 36 X 230000 Rp 8,280,000.00
IMB Rp 2,500,000.00
KAVLING TANAH Rp 48,000,000.00
JUMLAH Rp 127,759,250.00
KEUNTUNGAN PERUSAHAAN 20% Rp 25,551,850.00
TOTAL Rp 153,311,100.00
DIBULATKAN Rp 153,000,000.00

Hormat kami,
PT. FAJAR SARANA MANDIRI

HAMIDI SALIDIN
Direktur
NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH HARGA
SATUAN

IV PEKERJAAN DINDING, KOLOM


& BALOK
IV.1 Dinding batako M2 108.34
_ Batako 8x15x30 btg 2,500.00 1,300.00 3,250,000.00
_ Semen 50 kg zak 14.25 78,000.00 1,111,500.00
_ Pasir m3 1.25 175,000.00 218,750.00
IV.2 Dinding plesteran tebing layar cp 1 : 4 t. 3 cm M2 38.60
_ Semen 50 kg zak 3.22 78,000.00 251,160.00
_ Pasir m3 0.89 175,000.00 155,750.00
_ Kawat ayak m2 15.00 10,000.00 150,000.00
IV.3 Lapis plesteran dinding batako cp 1 : 4 t 1,5 cm M2 216.68
_ Semen 50 kg zak 18.00 65,000.00 1,170,000.00
_ Pasir m3 1.25 100,000.00 125,000.00
IV.4 Kolom & balok praktis M3 1.59
_ Semen 50 kg zak 5.98 78,000.00 466,440.00
_ Pasir m3 0.50 175,000.00 87,500.00
_ Batu 1x2 m3 1.00 750,000.00 750,000.00
SUB JUMLAH 7,736,100.00

V PEKERJAAN KAPSPANT & ATAP


V.1 Kapspant Kayu Kls II m2 36.21 160,000.00 5,793,600.00
V.2 Atap seng metal asoka kpg 98.00 42,000.00 4,116,000.00
V.3 Atap dack beton M3 1.01
_ Semen 50 kg zak 4.20 85,000.00 357,000.00
_ Pasir m3 0.55 200,000.00 110,000.00
_ Batu 1x2 m3 0.82 750,000.00 615,000.00
V.4 Nok metal m1 6.00 37,000.00 222,000.00
V.5 Lisplank papan 1,8x18 kpg 12.00 55,000.00 660,000.00
SUB JUMLAH 11,873,600.00

VI PEKERJAAN PLAFOND & LISTRIK


VI.1 Papan GRC 5 mm kpg 15.00 62,000.00 930,000.00
VI.2 Rangka plafond 4/6 btg 68.00 17,000.00 1,156,000.00
VI.3
VI.4 Paku GRC kg 8.00 10,000.00 80,000.00
VI.5 Stop kontak pcs 3.00 25,000.00 75,000.00
VI.6 Saklar ganda pcs 2.00 25,000.00 50,000.00
VI.7 Saklar tunggal pcs 3.00 25,000.00 75,000.00
VI.8 Lampu sl 18 wat pcs 7.00 30,000.00 210,000.00
VI.9 Skring box pcs 1.00 150,000.00 150,000.00
VI.10 Kabel dll lsm 1.00 200,000.00 200,000.00
SUB JUMLAH 2,926,000.00
RENCANA ANGGARAN BIAYA
( RAB )

PEKERJAAN : PEMB RUMAH TINGGAL Komp. SEHA GRAND CITY 3


LUAS BANGUNAN : 36 m2
LUAS TANAH : 150 M2
LOKASI : JL. Raya Sungai Kakap Pal 7 Desa Pal 9

NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH HARGA


SATUAN

I PEKERJAAN PERSIAPAN
I.1 Pembersihan lsm 1.00 450,000.00 450,000.00
I.2 Pengukuran / Bowplang lsm 1.00 550,000.00 550,000.00
SUB JUMLAH 1,000,000.00

II PEKERJAAN PONDASI M1 38.20


II.1 Cerucuk Ø 10 - 4 m btg 51.00 8,000.00 408,000.00
II.2 Pasir uruk bawah pondasi m3 1.19 125,000.00 148,750.00
II.3 Lt kerja beton Cp. 1 : 3 : 5 M3 1.24
_ Semen 50 kg Zak 2.23 85,000.00 189,550.00
_ Pasir m3 0.3 200,000.00 60,000.00
_ Batu 1 x 2 m3 0.7 750,000.00 525,000.00
II.4 Pondasi lajur beton Cp 1 : 2 : 3 M3 6.83
_ Semen 50 kg Zak 28 85,000.00 2,380,000.00
_ Pasir m3 1.20 200,000.00 240,000.00
_ Batu 1 x 2 m3 2.20 750,000.00 1,650,000.00
II.5 Balok slop beton Cp 1 : 2 : 3 M3 0.52
_ Semen 50 kg Zak 3.00 85,000.00 255,000.00
_ Pasir m3 0.23 200,000.00 46,000.00
_ Batu 1 x 2 m3 0.28 750,000.00 210,000.00
SUB JUMLAH 6,112,300.00

III PEKERJAAN LT. BETON


III.1 Cor lantai T 6 cm Cp 1 : 2 : 3 M3 2.16
_ Semen 50 kg Zak 12.25 85,000.00 1,041,250.00
_ Pasir m3 1.00 200,000.00 200,000.00
_ Batu 1 x 2 m3 1.25 750,000.00 937,500.00
III.2 Lapis keramik 30 x 30 ktk 37.00 70,000.00 2,590,000.00
III.3 Lapis keramik 20 x 20 ktk 2.00 60,000.00 120,000.00
_ Semen 50 kg Zak 6.20 85,000.00 527,000.00
_ Pasir m3 1.32 200,000.00 264,000.00
_ Semen nat kg 1.00 5,000.00 5,000.00
III.4 pasir uruk bawah lantai m3 8.60 100,000.00 860,000.00
SUB JUMLAH 6,544,750.00
NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH HARGA
SATUAN
VII PEKERJAAN PINTU JENDELA & VENTILASI
VII.1 Kusen pintu,jendela & ventilasi m1 45.60 105,000.00 4,788,000.00
VII.4 Pintu panil 0,80 X 2,10 pcs 3.00 950,000.00 2,850,000.00
VII.5 Pintu PVC ( KMWC ) 0,68 X 2,10 pcs 1.00 370,000.00 370,000.00
VII.6 Jendela kaca jungkit 0,70 X 1,22 pcs 1.00 350,000.00 350,000.00
VII.7 Jendela kaca jungkit 0,72 X 0,60 pcs 3.00 150,000.00 450,000.00
VII.8 Ventilasi kaca jungkit 0,72 X 0,42 pcs 1.00 85,000.00 85,000.00
SUB JUMLAH 8,893,000.00
VIII PEKERJAAN PENGUNCI & PENGGANTUNG
VIII.1 Kunci pintu 2 slag pcs 3.00 50,000.00 150,000.00
VIII.2 Engsel pintu 4 " pcs 12.00 8,500.00 102,000.00
VIII.3 Engsel jendela 3 " pcs 10.00 8,500.00 85,000.00
VIII.4 Kait angin pcs 5.00 8,500.00 42,500.00
VIII.5 Handle jendela pcs 5.00 8,200.00 41,000.00
VIII.6 Slot pintu & jendela pcs 10.00 8,000.00 80,000.00
SUB JUMLAH 500,500.00

IX PEKERJAAN PENGECATAN
X.1 Plamur 5 kg klg 1.30 40,000.00 52,000.00
X.2 Cat dasar 5 kg klg 2.00 60,000.00 120,000.00
X.3 Cat tembok 5 kg klg 10.00 87,000.00 870,000.00
X.4 Cat kilat 1 kg klg 6.00 78,000.00 468,000.00
SUB JUMLAH 1,510,000.00

X PEKERJAAN SANITASI
XI.1 Closet jongkok pcs 1.00 150,000.00 150,000.00
XI.2 Bak mandi pcs 1.00 250,000.00 250,000.00
XI.3 Kran air pcs 1.00 15,000.00 15,000.00
XI.4 Flor drain pcs 1.00 15,000.00 15,000.00
XI.5 Berpoot pcs 1.00 550,000.00 550,000.00
XI.6 Pipa air bersih/kotor lsm 1.00 200,000.00 200,000.00
SUB JUMLAH 1,180,000.00
XI PEKERJAAN LAIN-LAIN
XII.1 Papan mal kpg 50.00 20,000.00 1,000,000.00
XII.2 Besi Ø 10 _ 12 btg 15.00 50,000.00 750,000.00
XII.3 Besi Ø 10_ 12 btg 10.00 33,000.00 330,000.00
XII.4 Kawat bendrat kg 3.00 6,000.00 18,000.00
XII.5 Paku 2" 3" kg 5.00 15,000.00 75,000.00
XII.6 Paving Blok lsm 1.00 1,250,000.00 1,250,000.00
SUB JUMLAH 3,423,000.00

Hormat kami,
PT. FAJAR SARANA MANDIRI

HAMIDI SALIDIN
Direktur

Anda mungkin juga menyukai